Method Statement

This document provides a method statement for constructing an 800mm diameter reinforced concrete carrier pipe tunnel between two shafts using pipe jacking. It details the construction sequence, required equipment and materials, and safety issues to be addressed during construction.

Uploaded by

Murali Cs
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
17 views

Method Statement

This document provides a method statement for constructing an 800mm diameter reinforced concrete carrier pipe tunnel between two shafts using pipe jacking. It details the construction sequence, required equipment and materials, and safety issues to be addressed during construction.

Uploaded by

Murali Cs
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Method Statement for Airport way finding signage at Muscat

International Airport
Introduction
This method statement covers the carrier pipe Drive at Sewri Railway Crossing between shaft
no 1 to 2.The 800mm Diameter R.C.C pipe drive will start from shaft no 1 to 2
The approximate tunnel length is 80 meter. Drive will be in the gradient of 1:760
The proposed invert level of the tunnel at the entry to shaft no 1 is 23.823m
The proposed invert level of the tunnel the exit from shaft no 2 is 23.722m

The annulus between the casing pipe and the carrier pipe will be 240 mm .

Construction Method and Sequence


After complete the casing pipe drive, need to clean inside of the pipe for pour the M30 grade
concrete. It will be the base of carrier pipe.
The base concrete should be minimum 600mm width and 120mm height at center, and it
should be throughout the full length of casing pipe.
After complete the first carrier pipe drive, need to hold the pipe with locking cylinder for
connecting the second one. It will continue up to the end of the pipe jacking.
Fixing steel bars on top of pipes for holding them (c-Shape bars, 12mm dia 500mm long) to
prevent the separation of pipes during the drive
After complete the drive, both the end of annulus space should be closed by bricks and will
keep 2” diameter hole for fix the grouting pipe at both ends and also keep 2” diameter holes at
inside the alternative carrier pipes for the grouting.
Annulus space in between casing pipe and carrier pipe should be filled with cement grouting.
Grouting pump will use for the same.
After complete the grouting, all the concerned machineries should be removed from the shaft
and start the preparations for Manhole Construction.
Method Statement for Airport way finding signage at Muscat
International Airport

Equipment and materials


 800 mm R.C.C pipes (NP3class)
 Pipe Jacking Frame
 Control cabin
 Launch seal and thrust wall arrangement
 12t Hydra
 Grouting pump
 DG 500KVA and 45 KVA
 Cement
 Rubber ring
 Locking cylinder with power pack
 Steel bars (12 mm dia)

Safety Issues
The following safety issues will be addressed during the construction of the work

 Confined space working


 Monitoring of air quality/ventilation
 All personnel to be made fully aware the safety implications of working with in shaft
and tunnel environment
 Lifting operations to be properly planned, monitored and implemented
 All personnel to be fully qualified to perform their duties
 All equipment to be certified as required
 All personnel to be receive adequate training where necessary
 All personnel to be attend shift start safety briefing
 Oil and storage regime to be strictly controlled