JSP For SS 9013 No. JSP#04 Cutting and Bending of Steel Reinforcement Bars
JSP For SS 9013 No. JSP#04 Cutting and Bending of Steel Reinforcement Bars
JSP For SS 9013 No. JSP#04 Cutting and Bending of Steel Reinforcement Bars
JOB/TASK
TYPE:
Cutting and bending of steel reinforcement bars DATE: 13-11-2022
JOB SAFETY PROCEDURE LINXON
COMPILED BY: Eng. Ahmed Tosson DATE: 13-11-2022
N0: RA-04
Name Designation Signature Name Designation Signature
HIRA Eng. Ahmed Tosson Site Manager SS9013 Mr. Najmul Hasan HSE Officer
TEAM
Eng. Ibrahim Al-Harbi Site Manager SS9007
Date Signature Date 15 Signature
Reviewed by: Mr. Hayat Ur Rehman 11-11-22 Approved by: Eng. M. Irfan -14-2022
: : : :
P.P.E. REQUIRED ☐ Helmet, ☐ Safety Goggles, ☐ Safety Shoes, ☐ Coverall, ☐ Respiratory Musk, ☐ Ear Protection, ☐ Full body Harness, ☐ Hand Protection, ☐ Arc Flash Protection,
FOR TASK: ☐ Others To be Specify: __________________________, ☐ Others To be Specify: _______FACE SHEILD___________________
JOB SAFE PROCEDURE ANALYSIS
LIST ALL STEPS IN PERFORMING HAZARDS DANGER / RISK
STEP PREVENTATIVE CONTROLS REQUIRED TO MINIMIZE /
THIS TASK IN EACH STEP, WHAT COULD CAUSE INJURY, LOSS, (INJURIES, DAMAGE, ILLNESS,
No. DAMAGE INTERRUPTION, OR POLLUTION? POLLUTION, ETC)
ELIMINATE HAZARD
(IN SEQUENCE)
complete.
Ensure that specific type of work permit for certain activities is
being used.
1.2. Attaching all the required Incompetent assigned personnel. Lack of Supervision All the involved personnel dealing with all the required documents
documents such as a related Unidentified or incomplete hazards Unidentified Hazards shall be qualified, competent and trained.
checklist, risk assessment, and risk information. leading to an Accident. A safe work practice shall be identified to reduce the possibilities of
method statement and other Lack of productivity accident/incident.
forms necessary to fulfill the Ensure that all required supporting documents shall be available as
request. per PTW requirements.
All the required related documents as identified to be attached in
PTW shall be reviewed and evaluated by issuer and receiver to
ensure that all hazard and risk is identified and complete.
1.3. Verifying the site condition as Open areas, protruding sharp objects, Lack of Supervision The workplace shall be pre-checked, free from any obstruction and
per requirements mentioned in falling objects limited illuminations Unidentified Hazards in safe good working condition prior to a combined verification
the application of Permit to and other construction hazards may leading to an Accident. visit.
Work by both the Permit cause accidents during the Lack of productivity All Issuer and receiver must be aware of the hazard present in the
Receiver and Permit Issuer. verification visit. area and must be familiar with the ingress and egress of the
Unfamiliarity with access to the project site.
areas.
1.4. Issuance of approved Permit to Untrained personnel. Lack of Supervision Permit Issuer and Receiver must be qualified, trained and
Work from Permit Issuer to Incomplete information on Permit to Unidentified Hazards competent.
Permit Receiver. work. leading to an Accident. Permit Issuer shall ensure that the site was visited to ensure that
Lack of productivity workplace hazards and risk are adequately identified and
mitigating measure shall be established.
Permit Issuer and Receiver shall ensure that all the information
required in the permit to work are reviewed, completed and
signed.
1.5. Verifying the approved Permit to Inadequate coordination and area Lack of Supervision Permit to Work shall be displayed at the worksite
Work by the assigned SEC control protocol. Unidentified Hazards Permit Receiver shall not leave the area for the whole duration of
Consultant. Unauthorized work to be performed leading to an Accident. permit to work.
within a defined location and Lack of productivity Work shall not proceed without the presence of approved PTW and
boundary. the Permit Receiver overseeing the activity.
Permit Receiver shall account all workers under his Permit to Work
• pinch/crash points Establish systems so workers are rotated away from tasks to
resulting hand injuries minimize the duration of continual exertion, repetitive motions,
and awkward postures. Design a job rotation.
Use appropriate hand protection to avoid hand and finger injuries.
2.4 Verify tagging for tools and Struck with a sharp and hard object. • Muscular injuries (back Ensure that all workers are provided with all the required Personal
equipment base from color code Defective tools and equipment. pain, strain, fractures) protective equipment for minimum and general requirements.
matrix. • pinch/crash points Close supervision required supervisor and foreman must be
resulting hand injuries present at the site.
Ensure all tools are inspected properly and color code shall be
• Physical Injury from slip,
applied.
trip & fall
Any defective tools found shall be removed from service, and
marked with a defective tag.
3. Cutting and bending of steel reinforcement bars (Fabrication)
3.1 Check and inspect tools and Inspection and maintenance not • Serious accident that may The machine shall be inspected on a periodic basis and shall also be
equipment condition prior to done. result to severe injury or visually inspected daily prior to each use.
use. Look for any signs of cracks, Improper grounding of property damage Daily inspection record should be readily available in the
deformation, and any form of cutting/bending machine. • Accident resulting Injury to fabrication area.
damages. Damaged electrical cables around the Ensure proper grounding is provided and an electrical source is
personnel and property
equipment. protected with GFCI.
damage of adjacent structure
Unorganized materials and access. Call the attention of certified electrician to replace damaged cables
Area congestion.
or appurtenances and ensure that new cable was properly arranged & managed to
prevent tripping from the users.
Remove unnecessary materials and equipment on the affected
areas.
Designated access shall be free from any obstruction.
Designate a location for unloading of materials and to be stored
only on a designated storage area.
All materials location and storage shall be barricaded and provided
with adequate signage.
3.2 Reinforcement steel shall be Operator misuse of cutting / bending • Serious accident that may Only trained workers on machine use shall be authorized to
accurately fabricated to the machine. result to severe injury or operate and maintain the equipment.
dimensions and shapes shown in Incompetent personnel / Lack of property damage Workers should understand the purpose and function of all
the Contract Documents. training for cutting/bending machine controls on the machine, should know how to stop the equipment
OHS Forms Procedure Reference Revision Number Revision Date
Page |4 JOB SAFE PROCEDURE OHS-PR-09-03-F07 (A) 0 MAY 2021
HAZARD IDENTIFICATION & RISK ASSESSMENT (HIRA)
OHS-PR-09-03-F07 (A) JOB SAFE PROCEDURE
High noise pollution fatality. Unplug the Grinder from electrical source when changing disc.
Spark With less RPM, disc will Insert the earplug, wear ear muff when work for prolong period of
Eye damage due to spark shatter/ scatter and cause time , apply job rotation system.
Fumes and dust injury Wear double protection safety glass and face shield to protect the
Fire due to high spark Pinch injury and hand face. Cover the area with fire blanket to protect the other worker.
injury can occur with Wear cartridge mask and provide local ventilation
sudden start of grinder. Clear all area from combustible and flammable material. Cover the
Hair impairment and loss grinding area with fire blanket, assigned the fire watch place fire
of hearing sense extinguisher.
Serious eye injury when
spark hit the eye
Fumes and dust cause
asthma and lung disease
Fire may erupt when sparks
lying on combustible and
flammable liquid.
fractures) Conduct toolbox meeting to discuss all the hazard of the activity
● Pinch/crash points Close supervision by the Engineer, Supervisor or Foreman must be
resulting hand injuries. observed.
5. Closing of Permit to Work
5.1 Returning of the Permit to Work Inadequate communication. Significant property and Permit Receiver & Issuer shall ensure that housekeeping is done
to Permit Issuer for closing. Untrained personnel. appurtenances damage before, during and after the work.
Governmental violation All waste materials generated from the work shall be properly
Environmental complaint disposed and shall not be left unattended at the worksite.
Accident resulting serious Electrical equipment shall be properly secured, distribution board
injury or death to worker closed and padlocked.
All materials used at the site such as chemicals, flammable and
combustible materials shall be stored at the designated storage at
the end of each day.
5.2 Verifying the site condition as Poor housekeeping. Significant property and Permit Receiver shall ensure that housekeeping is done before,
per requirements mentioned in Undisposed waste materials. appurtenances damage during and after the work.
the closing of Permit to Work by Unaccounted workers. Governmental violation All waste materials generated from the work shall be properly
both the Permit Issuer and Unsecured electrical equipment Environmental complaint disposed and shall not be left unattended at the worksite.
Permit Receiver. /energized equipment. Loss of production Electrical equipment shall be properly secured, distribution board
Poor storage of chemical, flammable Accident resulting serious closed and padlocked.
and combustible materials and etc. injury or death to worker All materials used at the site such as chemicals, flammable and
Unattended unsafe condition. Significant cost due to combustible materials shall be stored at the designated storage at
Unfamiliarity with access to the areas damages. the end of each day.
and the present construction hazard. Mobile equipment shall properly park on a designated equipment
laydown.
Ensure that all workers are accounted and there was no
incident/accident occurred which is not reported.
All Issuer and receiver must be aware of the hazard present in the
area and must be familiar with the ingress and egress of the
project site.
5.3 Signing/clearing of the Permit to Inadequate communication. Accident resulting serious Work permit issuer and receiver must be qualified, trained and
Work by the Permit Issuer upon Untrained personnel. injury or death to worker competent.
verification of site condition and Proper communication should be observed.