The document outlines a project plan for constructing a 2-storey HEPA building on the campus of University Malaysia Perlis from July 2021 to June 2023 with a total cost of RM13.9 million. It includes 26 main tasks such as site preparation, earthworks, building the foundation, ground floor, and other construction elements over the 570 day period. Preliminary works will take place from July 2021 to June 2023 costing RM2.5 million. The main building works from September 2021 to March 2023 will cost RM5 million.

Uploaded by

Syed Syedamirul
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
111 views24 pages

CPM Idp

The document outlines a project plan for constructing a 2-storey HEPA building on the campus of University Malaysia Perlis from July 2021 to June 2023 with a total cost of RM13.9 million. It includes 26 main tasks such as site preparation, earthworks, building the foundation, ground floor, and other construction elements over the 570 day period. Preliminary works will take place from July 2021 to June 2023 costing RM2.5 million. The main building works from September 2021 to March 2023 will cost RM5 million.

Uploaded by

Syed Syedamirul
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 24

ID Task Name Duration Start Finish Cost Predecessors

M A M
1 UNIVERISTY MALAYSIA PERLIS(UNIMAP) 2 570 days Wed 7/4/21 Tue 13/6/23 RM13,900,000.00
STOREY HEPA BUILDING IN CAMPUS PAUH
PUTRA, UNIVERSITY MALYSIA
PERLIS(UNIMAP)
2 START PROJECT 0 days Wed 7/4/21 Wed 7/4/21 RM0.00 7/4
3 SITE POSSESSION AND COMMENCEMENT 0 days Wed 7/4/21 Wed 7/4/21 RM0.00 7/4
DATE
4 1.0 PRELIMINARIES AND TURNKEY 570 days Wed 7/4/21 Tue 13/6/23 RM2,500,000.00
ELEMENTS
5 Location& Access to site 60 days Wed 7/4/21 Tue 29/6/21 RM40,000.00
6 Registration of all the project to CIBD 90 days Wed 7/4/21 Tue 10/8/21 RM20,000.00
7 Contract Documents 25 days Wed 7/4/21 Tue 11/5/21 RM9,000.00
8 Setting Out By Licensed Surveyor 70 days Wed 7/4/21 Tue 13/7/21 RM12,000.00
9 Insurances (CAR / SOCSO) 70 days Wed 7/4/21 Tue 13/7/21 RM400,000.00
10 Law, Regulation& Requirement 570 days Wed 7/4/21 Tue 13/6/23 RM130,000.00
11 Site Establishment 570 days Wed 7/4/21 Tue 13/6/23 RM67,000.00
12 Sanitary Facilities& Accommodation 570 days Wed 7/4/21 Tue 13/6/23 RM190,000.00
13 Telephone/Photostate/Fax/Internet/Lighting
570 days Wed 7/4/21 Tue 13/6/23 RM21,000.00
14 water supply 570 days Wed 7/4/21 Tue 13/6/23 RM12,000.00
15 project signboard 24 days Fri 9/4/21 Wed 12/5/21 RM12,000.00
16 contract administration 570 days Wed 7/4/21 Tue 13/6/23 RM34,000.00
17 approval for site clearing 31 days Wed 7/4/21 Wed 19/5/21 RM50,000.00
18 mobiliztion of equipment 360 days Mon 12/4/21 Fri 26/8/22 RM450,000.00
19 construction material order 120 days Wed 21/4/21 Tue 5/10/21 RM410,000.00

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp
Summary Manual Summary Rollup Progress
Date: Sat 24/4/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Name Duration Start Finish Cost Predecessors
M A M
20 testing laboratory 50 days Wed 7/7/21 Tue 14/9/21 RM89,000.00
21 first aid kit 570 days Wed 7/4/21 Tue 13/6/23 RM21,000.00
22 site security 570 days Wed 7/4/21 Tue 13/6/23 RM50,000.00
23 temporary site office 560 days Wed 7/4/21 Tue 30/5/23 RM93,000.00
24 temporary road 570 days Wed 7/4/21 Tue 13/6/23 RM300,000.00
25 store 570 days Wed 7/4/21 Tue 13/6/23 RM90,000.00
26 2.0 EARTHWORK 102 days Mon 12/4/21 Tue 31/8/21 RM500,000.00
27 site investigation 7 days Mon 12/4/21 Tue 20/4/21 RM96,000.00
28 excavation 10 days Wed 21/4/21 Tue 4/5/21 RM92,000.00 27
29 cut 30 days Wed 5/5/21 Tue 15/6/21 RM87,000.00 28
30 fill 30 days Wed 16/6/21 Tue 27/7/21 RM79,000.00 29
31 temporary drainage 15 days Wed 28/7/21 Tue 17/8/21 RM33,000.00 30
32 Testing 5 days Wed 18/8/21 Tue 24/8/21 RM30,000.00 31
33 Site Cleaning 5 days Wed 25/8/21 Tue 31/8/21 RM52,000.00 32
34 Silt Fence 5 days Thu 12/8/21 Wed 18/8/21 RM31,000.00
35 3.0 MAIN BUILDING WORKS 411 days Wed 1/9/21 Wed 29/3/23 RM5,000,000.00 26
36 2 STOREY BUILDING 411 days Wed 1/9/21 Wed 29/3/23 RM5,000,000.00
37 3.1 Work below lowest floor 45 days Wed 1/9/21 Tue 2/11/21 RM1,158,000.00
38 Pad footing foundation 45 days Wed 1/9/21 Tue 2/11/21 RM1,090,000.00
39 Excavation 25 days Wed 1/9/21 Tue 5/10/21 RM400,000.00
40 Formwork 20 days Wed 6/10/21 Tue 2/11/21 RM210,000.00 39
41 Reinforcement 20 days Wed 1/9/21 Tue 28/9/21 RM360,000.00
42 Concreting 5 days Wed 29/9/21 Tue 5/10/21 RM120,000.00 41

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp
Summary Manual Summary Rollup Progress
Date: Sat 24/4/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task Name Duration Start Finish Cost Predecessors
M A M
43 Stump 5 days Wed 6/10/21 Tue 12/10/21 RM45,000.00 42
44 Apron and Perimeter Drain 10 days Mon 4/10/21 Fri 15/10/21 RM23,000.00
45 3.2 Ground Floor 176 days Wed 3/11/21 Wed 6/7/22 RM1,070,000.00 37
46 Ground Beam 30 days Wed 3/11/21 Tue 14/12/21 RM209,000.00
47 Reinforcement 20 days Wed 3/11/21 Tue 30/11/21 RM81,000.00
48 Formwork 20 days Wed 3/11/21 Tue 30/11/21 RM50,000.00
49 Concreting 10 days Wed 1/12/21 Tue 14/12/21 RM78,000.00 48
50 Ground Slab 30 days Wed 15/12/21 Tue 25/1/22 RM236,000.00 46
51 Reinforcement 20 days Wed 15/12/21 Tue 11/1/22 RM102,000.00
52 Formwork 20 days Wed 15/12/21 Tue 11/1/22 RM42,000.00
53 Concreting 10 days Wed 12/1/22 Tue 25/1/22 RM92,000.00 52
54 Ground Coloumn 25 days Wed 26/1/22 Tue 1/3/22 RM211,000.00 50
55 Reinforcement 20 days Wed 26/1/22 Tue 22/2/22 RM72,000.00
56 Formwork 20 days Wed 26/1/22 Tue 22/2/22 RM45,000.00
57 Concreting 5 days Wed 23/2/22 Tue 1/3/22 RM94,000.00 56
58 Staircase Construction 12 days Wed 2/3/22 Thu 17/3/22 RM61,000.00 54
59 Reinforcement 8 days Wed 2/3/22 Fri 11/3/22 RM21,000.00
60 Formwork 7 days Wed 2/3/22 Thu 10/3/22 RM16,000.00
61 Concreting 5 days Fri 11/3/22 Thu 17/3/22 RM24,000.00 60
62 Ramp Construction 11 days Fri 18/3/22 Fri 1/4/22 RM43,000.00 58
63 Reinforcement 11 days Fri 18/3/22 Fri 1/4/22 RM15,000.00
64 Formwork 8 days Fri 18/3/22 Tue 29/3/22 RM9,000.00
65 Concreting 3 days Wed 30/3/22 Fri 1/4/22 RM19,000.00 64

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp
Summary Manual Summary Rollup Progress
Date: Sat 24/4/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
ID Task Name Duration Start Finish Cost Predecessors
M A M
66 External wall & Internal Wall 45 days Mon 4/4/22 Fri 3/6/22 RM74,000.00 62
67 Bricklaying 30 days Mon 4/4/22 Fri 13/5/22 RM61,000.00
68 Plastering 15 days Mon 16/5/22 Fri 3/6/22 RM13,000.00 67
69 Doors & Windows 23 days Mon 6/6/22 Wed 6/7/22 RM236,000.00 66
70 Installation of Door frames 15 days Mon 6/6/22 Fri 24/6/22 RM40,000.00
71 Installation of Window frames 15 days Mon 6/6/22 Fri 24/6/22 RM48,000.00

72 Installation of Doors 8 days Mon 27/6/22 Wed 6/7/22 RM70,000.00 70


73 Installation of Windows 8 days Mon 27/6/22 Wed 6/7/22 RM78,000.00 71
74 3.3 First Floor 161 days Thu 7/7/22 Thu 16/2/23 RM967,000.00 45
75 First Floor Beam 30 days Thu 7/7/22 Wed 17/8/22 RM202,000.00
76 Reinforcement 20 days Thu 7/7/22 Wed 3/8/22 RM72,000.00
77 Formwork 20 days Thu 7/7/22 Wed 3/8/22 RM49,000.00
78 Concreting 10 days Thu 4/8/22 Wed 17/8/22 RM81,000.00 77
79 First Floor Slab 32 days Thu 18/8/22 Fri 30/9/22 RM213,000.00 75
80 Reinforcement 20 days Thu 18/8/22 Wed 14/9/22 RM90,000.00
81 Formwork 20 days Mon 22/8/22 Fri 16/9/22 RM32,000.00
82 Concreting 10 days Mon 19/9/22 Fri 30/9/22 RM91,000.00 81
83 First Floor Colomn 32 days Mon 3/10/22 Tue 15/11/22 RM183,000.00 79
84 Reinforcement 20 days Mon 3/10/22 Fri 28/10/22 RM72,000.00
85 Formwork 20 days Wed 5/10/22 Tue 1/11/22 RM42,000.00
86 Concreting 10 days Wed 2/11/22 Tue 15/11/22 RM69,000.00 85
87 External wall & Internal Wall 35 days Wed 16/11/22 Tue 3/1/23 RM90,000.00 83
88 Bricklaying 20 days Wed 16/11/22 Tue 13/12/22 RM61,000.00
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp
Summary Manual Summary Rollup Progress
Date: Sat 24/4/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
ID Task Name Duration Start Finish Cost Predecessors
M A M
89 Plastering 15 days Wed 14/12/22 Tue 3/1/23 RM29,000.00 88
90 Doors & Windows 32 days Wed 4/1/23 Thu 16/2/23 RM279,000.00 87
91 Installation of Door frames 11 days Wed 4/1/23 Wed 18/1/23 RM49,000.00
92 Installation of Window frames 11 days Fri 20/1/23 Fri 3/2/23 RM58,000.00

93 Installation of Doors 9 days Thu 19/1/23 Tue 31/1/23 RM70,000.00 91


94 Installation of Windows 9 days Mon 6/2/23 Thu 16/2/23 RM102,000.00 92
95 3.4 Roof Construction 61 days Wed 4/1/23 Wed 29/3/23 RM1,805,000.00 87
96 Roof Beam 32 days Wed 4/1/23 Thu 16/2/23 RM247,000.00 89
97 Reinforcement 20 days Wed 4/1/23 Tue 31/1/23 RM98,000.00
98 Formwork 20 days Fri 6/1/23 Thu 2/2/23 RM57,000.00
99 Concreting 10 days Fri 3/2/23 Thu 16/2/23 RM92,000.00 98
100 Roof Trusses System 15 days Fri 17/2/23 Thu 9/3/23 RM110,000.00 96
101 Steel Roof truss 15 days Fri 17/2/23 Thu 9/3/23 RM110,000.00
102 Roof Structure & Finishes 11 days Fri 10/3/23 Fri 24/3/23 RM70,000.00 100
103 Gutter 10 days Fri 10/3/23 Thu 23/3/23 RM38,000.00
104 Waterproofing 10 days Mon 13/3/23 Fri 24/3/23 RM32,000.00
105 External Floor Finishes 11 days Wed 4/1/23 Wed 18/1/23 RM180,000.00
106 Internal Floor Finishes 11 days Fri 6/1/23 Fri 20/1/23 RM240,000.00
107 External wall Finishes 12 days Wed 4/1/23 Thu 19/1/23 RM112,000.00
108 Internal Wall Finishes 12 days Wed 4/1/23 Thu 19/1/23 RM190,000.00
109 External Ceiling Finishes 9 days Wed 4/1/23 Mon 16/1/23 RM256,000.00
110 Internal Ceiling Finishes 9 days Wed 4/1/23 Mon 16/1/23 RM240,000.00
111 Sanitary Fittings and Accessories 3 days Mon 27/3/23 Wed 29/3/23 RM160,000.00 104
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp
Summary Manual Summary Rollup Progress
Date: Sat 24/4/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
ID Task Name Duration Start Finish Cost Predecessors
M A M
112 End of HEPA Building 0 days Wed 29/3/23 Wed 29/3/23 RM0.00 111
113 4.0 External Works 255 days Wed 21/4/21 Tue 12/4/22 RM1,000,000.00
114 4.1 Drainage systems 163 days Wed 21/4/21 Fri 3/12/21 RM300,000.00
115 Roadside Drain 30 days Wed 21/4/21 Tue 1/6/21 RM180,000.00
116 Apron and Perimeter Drain 30 days Mon 25/10/21 Fri 3/12/21 RM120,000.00
117 4.2 Pavement, Roadwork & carpark 92 days Mon 6/12/21 Tue 12/4/22 RM499,400.00 114
118 Pavement 65 days Mon 6/12/21 Fri 4/3/22 RM320,000.00
119 Sub-Grade 10 days Mon 6/12/21 Fri 17/12/21 RM40,000.00
120 Sub Base 10 days Mon 20/12/21 Fri 31/12/21 RM40,000.00 119
121 Base Course 10 days Mon 3/1/22 Fri 14/1/22 RM40,000.00 120
122 Prime Coat 5 days Mon 17/1/22 Fri 21/1/22 RM40,000.00 121
123 Binder Course 10 days Mon 24/1/22 Fri 4/2/22 RM40,000.00 122
124 Tack Coat 5 days Mon 7/2/22 Fri 11/2/22 RM40,000.00 123
125 Surface Course 10 days Mon 14/2/22 Fri 25/2/22 RM40,000.00 124
126 Seal Coat 5 days Mon 28/2/22 Fri 4/3/22 RM40,000.00 125
127 Road Furniture 10 days Mon 7/3/22 Fri 18/3/22 RM46,000.00 126
128 Guard rail 10 days Mon 21/3/22 Fri 1/4/22 RM80,000.00 127
129 Road Marking 7 days Mon 4/4/22 Tue 12/4/22 RM23,400.00 128
130 Scupper Drain 7 days Mon 21/3/22 Tue 29/3/22 RM30,000.00
131 4.3 Connection to Water Reticulation 35 days Wed 21/4/21 Tue 8/6/21 RM75,600.00
132 ms pipe 20 days Wed 21/4/21 Tue 18/5/21 RM50,000.00
133 Fittings 10 days Wed 19/5/21 Tue 1/6/21 RM20,000.00 132
134 Testing 5 days Wed 2/6/21 Tue 8/6/21 RM5,600.00 133

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp
Summary Manual Summary Rollup Progress
Date: Sat 24/4/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6
ID Task Name Duration Start Finish Cost Predecessors
M A M
135 4.4 Pipeline 40 days Wed 9/6/21 Tue 3/8/21 RM125,000.00 131
136 HDPE Pipe 15 days Wed 9/6/21 Tue 29/6/21 RM53,000.00
137 Reinforced Concrete Manholes 15 days Wed 30/6/21 Tue 20/7/21 RM40,000.00 136
138 Testing 5 days Wed 21/7/21 Tue 27/7/21 RM20,000.00 137
139 Maintenance 5 days Wed 28/7/21 Tue 3/8/21 RM12,000.00 138
140 End of External works 0 days Tue 3/8/21 Tue 3/8/21 RM0.00 139
141 5.0 MECHANICAL WORKS 30 days Fri 17/2/23 Thu 30/3/23 RM1,500,000.00 74
142 Sanitary Plumbing 30 days Fri 17/2/23 Thu 30/3/23 RM380,000.00
143 Air Conditioning & Ventillation System 25 days Mon 20/2/23 Fri 24/3/23 RM720,000.00
144 Fire Protection System 25 days Fri 17/2/23 Thu 23/3/23 RM400,000.00
145 6.0 ELECTRICAL WORKS 45 days Fri 31/3/23 Thu 1/6/23 RM2,000,000.00 141
146 6.1 Internal Electrical Installation 20 days Fri 31/3/23 Thu 27/4/23 RM1,060,000.00
147 Structured Cable System 20 days Fri 31/3/23 Thu 27/4/23 RM130,000.00
148 Installation Electrical Cable & Sockets 10 days Mon 3/4/23 Fri 14/4/23 RM230,000.00

149 Installation Electrical & ICT Works 10 days Tue 4/4/23 Mon 17/4/23 RM670,000.00
150 Testing 5 days Tue 18/4/23 Mon 24/4/23 RM30,000.00 149
151 6.2 Electrical Infrastructure Works 25 days Thu 27/4/23 Thu 1/6/23 RM940,000.00 146
152 High Voltage Installation 20 days Fri 28/4/23 Thu 25/5/23 RM640,000.00
153 External Loose Tube Cabling 5 days Fri 26/5/23 Thu 1/6/23 RM300,000.00 152
154 End of Electical Works 0 days Thu 27/4/23 Thu 27/4/23 RM0.00
155 7.0 Landscaping Works 25 days Fri 31/3/23 Thu 4/5/23 RM500,000.00 141
156 Soft Landscape 25 days Fri 31/3/23 Thu 4/5/23 RM250,000.00
157 Hard Landscape 25 days Fri 31/3/23 Thu 4/5/23 RM250,000.00
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp
Summary Manual Summary Rollup Progress
Date: Sat 24/4/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 7
ID Task Name Duration Start Finish Cost Predecessors
M A M
158 8.0 Prime Cost Sum & Provisional Sums 570 days Wed 7/4/21 Tue 13/6/23 RM900,000.00 2
159 Prime Cost sum 0 days Wed 7/4/21 Wed 7/4/21 RM0.00 7/4
160 Provisional Sums 0 days Wed 7/4/21 Wed 7/4/21 RM900,000.00 7/4
161 Contribution to authorities 0 days Wed 7/4/21 Wed 7/4/21 RM0.00 7/4
162 Hand over 0 days Wed 7/4/21 Wed 7/4/21 RM0.00 7/4

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp
Summary Manual Summary Rollup Progress
Date: Sat 24/4/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 8
Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023
M J J A S O N D J F M A M J J A S O N D J F M A M J J

7/4
7/4

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp
Summary Manual Summary Rollup Progress
Date: Sat 24/4/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 9
Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023
M J J A S O N D J F M A M J J A S O N D J F M A M J J

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp
Summary Manual Summary Rollup Progress
Date: Sat 24/4/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 10
Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023
M J J A S O N D J F M A M J J A S O N D J F M A M J J

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp
Summary Manual Summary Rollup Progress
Date: Sat 24/4/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 11
Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023
M J J A S O N D J F M A M J J A S O N D J F M A M J J

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp
Summary Manual Summary Rollup Progress
Date: Sat 24/4/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 12
Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023
M J J A S O N D J F M A M J J A S O N D J F M A M J J

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp
Summary Manual Summary Rollup Progress
Date: Sat 24/4/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 13
Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023
M J J A S O N D J F M A M J J A S O N D J F M A M J J
29/3

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp
Summary Manual Summary Rollup Progress
Date: Sat 24/4/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 14
Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023
M J J A S O N D J F M A M J J A S O N D J F M A M J J

3/8

27/4

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp
Summary Manual Summary Rollup Progress
Date: Sat 24/4/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 15
Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023
M J J A S O N D J F M A M J J A S O N D J F M A M J J

7/4
7/4
7/4
7/4

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp
Summary Manual Summary Rollup Progress
Date: Sat 24/4/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 16
Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025
J A S O N D J F M A M J J A S O N D J F M A M J J A S

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp
Summary Manual Summary Rollup Progress
Date: Sat 24/4/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 17
Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025
J A S O N D J F M A M J J A S O N D J F M A M J J A S

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp
Summary Manual Summary Rollup Progress
Date: Sat 24/4/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 18
Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025
J A S O N D J F M A M J J A S O N D J F M A M J J A S

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp
Summary Manual Summary Rollup Progress
Date: Sat 24/4/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 19
Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025
J A S O N D J F M A M J J A S O N D J F M A M J J A S

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp
Summary Manual Summary Rollup Progress
Date: Sat 24/4/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 20
Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025
J A S O N D J F M A M J J A S O N D J F M A M J J A S

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp
Summary Manual Summary Rollup Progress
Date: Sat 24/4/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 21
Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025
J A S O N D J F M A M J J A S O N D J F M A M J J A S

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp
Summary Manual Summary Rollup Progress
Date: Sat 24/4/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 22
Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025
J A S O N D J F M A M J J A S O N D J F M A M J J A S

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp
Summary Manual Summary Rollup Progress
Date: Sat 24/4/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 23
Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025
J A S O N D J F M A M J J A S O N D J F M A M J J A S

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project cpm idp