Manpower Loading Sample

This document outlines the manpower and equipment breakdown for a 3-month project to install skyroofs and solar panels at the Isuzu AutopRT Manufacturing Corporation facility. It involves 7 staff members for project management and administration and 37 operation workers including installers, welders, and helpers. The project also requires various tools such as electric jigsaws, drills, wrenches, and electrical equipment to complete the installation work over the 3 month period.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
320 views2 pages

Manpower Loading Sample

This document outlines the manpower and equipment breakdown for a 3-month project to install skyroofs and solar panels at the Isuzu AutopRT Manufacturing Corporation facility. It involves 7 staff members for project management and administration and 37 operation workers including installers, welders, and helpers. The project also requires various tools such as electric jigsaws, drills, wrenches, and electrical equipment to complete the installation work over the 3 month period.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

PROJECT : Isuzu AutopRT Manufacturing Corporation

LOCATION :II 4024 North Main Ave. Ph3 Laguna Technopark Biñan Laguna
SCOPE : Installation of Skyroof and Soalar Panel

ITEM NO. MANPOWER BREAKDOWN Month1 Month2 Month3


1 Project Manager 1 1 1 1 1 1 1 1 1 1 1 1
2 Project In-Charge 1 1 1 1 1 1 1 1 1 1 1 1
3 QA/QC 1 1 1 1 1 1 1 1 1 1 1 1
4 Safety Officer 1 1 1 1 1 1 1 1 1 1 1 1
5 Admin Officer 1 1 1 1 1 1 1 1 1 1 1 1
6 Foreman 1 1 1 1 1 1 1 1 1 1 1 1
7 Warehouseman 1 1 1 1 1 1 1 1 1 1 1 1
Total Number Of Staff 7 7 7 7 7 7 7 7 7 7 7 7
8 Installer 6 6 6 6 6 6 6 6 6 6 6 6
9 Welder 15 15 15 15 15 15 15 15 15 15 15 15
10 Helper 10 10 10 10 10 10 10 10 10 10 10 10
11 Electrical 6 6 6 6 6 6 6 6 6 6 6 6
Total Number Of Operation 37 37 37 37 37 37 37 37 37 37 37 37

Prepared By: Noted:

Alcantara, Abheazear D. Harold L. Legaspi


PIC / Fravinz Enterprises Inc. PM /Fravinz Enterprises Inc.
PROJECT : Isuzu AutopRT Manufacturing Corporation
LOCATION :II 4024 North Main Ave. Ph3 Laguna Technopark Biñan Laguna
SCOPE : Installation of Skyroof and Soalar Panel

ITEM NO. Tool And Equipemtn Month1 Month2 Month3


1 electric jigsaw
2 angle grinder
3 drill machine
4 pliers
5 cutting pliers
6 plat screw
7 star screw
8 hammer
9 .wrench 6mm to 14mm
10 .tester
11 electrical tape
12 drill bit set
14 cable tye
15 libel

Prepared By: Noted:

Alcantara, Abheazear D. Harold L. Legaspi


PIC / Fravinz Enterprises Inc. PM /Fravinz Enterprises Inc.