Valve Inspection
Valve Inspection
Valve Inspection
process is:
Design code
Purchase order specification
Purchaser's standards
Approved drawings
API 598
API 6D
API 594
ASME / ANSI B16.5
API 600, 602, 603, 604
The list of documents normally is agreed upon in the Pre-Inspection meeting, which is
held several weeks before the actual commencement of the inspection work.
The parties that participate in this meeting are the manufacturer, purchaser and third
party inspection agency representatives.
This is already explained in the Inspection and Test Plan for Valve article.
These are the list of documents that are normally agreed upon to be presented to the
inspector:
The first actual inspection work in the valve is the materials inspection. The original or
authenticated copies of mill certificates of material normally are available at the
manufacturer's premises.
Certificate No.
Heat or cast No.
Chemical composition.
Mechanical properties.
Heat treated condition.
NDE applied and results.
Surface finish
This covers body stem material, shell material, trim materials, gland materials, anti-
friction materials, ball, wedge or flap materials, operating components, support material,
well end, flanges and any other specified component.
Then the inspector witnesses the materials identification on the certificates against the
materials marking. It is also necessary to check these with the valve drawing datasheet,
material list and other specifications as appropriate.
Visual inspection for surface finish and probable defects is done and dimensional
compliance with specification need to be controlled, as well.
When third party inspector carries out the material inspection, then provides the
inspection visit report (IVR), the report contains the following items:
Confirmation of satisfactory document review
Record of the endorsement of certification reviewed/witnessed
Record of all non-conformities
Record of any tests witnessed and the result
When the valve material inspection is carried out, and the results were satisfactory
or non-conformities were closed by remedial action, then the valve manufacturer will
start fabrication.
The third party inspector checks the following points on the valve based on the
inspection and test plan (ITP), which has already been agreed upon between the
purchaser and the valve manufacturer.
The inspection scope is determined in the ITP. Some purchasers prefer to have
stringent controls and assign the TPI for more “hold or witness points” for inspection and
test activities, and some others prefer less “hold or witness points” and assign the TPI
much more work in the “review document.”
This depends in the inspection budget, which purchasers assign for inspection. Much
more inspection will have a much larger cost and less risk, and conversely, less
inspection will have less cost but more risks.
The third party inspector carries out visual and dimensional check to ensure compliance
with WPS and specification. Where specified, weld bevels need to be examined by MT
or PT after grinding/machining.
Edges and weld bevels need to be clean, dry and free from surface
defects, laminations, cracks, voids, notches, etc.
These are causes for rejection unless suitable/satisfactory remedial action can be
taken. Welding repairs to bevels are not permitted, without approval from the client.
Inspectors need report excessive or serious defects.
Following items are taken into account when third party inspector making inspection on
the valve welding:
Third party inspector carries out dimensional check and PWHT control as specified.
When PWHT has been completed then portable hardness measurement may be used
to establish hardness of material, heat affected zone or welds, as may be specified.
To verify that the model and various features and components comply with the
purchase order description and valve specification and drawings as applicable.
To verify that the dimensions of valves, flanges, flange drilling, bore, stem,
threading, wall thickness and any other dimensions, as applicable, comply with
the requirements of the specification and other.
Witnessing required pressure tests.
Witnessing functional test of actuator on valve, when actuators are specified.
Radiographic examination and other NDE in accordance with the applicable
references noted above.
when required by the contract or purchase order, the third party inspector witnesses low
pressure air test and pays attention to the following points:
The third party inspector checks all previous items have been accepted by authorised
bodies and witness hydrostatic test and verify following points:
After depressurisation, valve components are drained and dried to meet specified
requirements.
Stamping of Inspection authority stamps, are carried out in approved area, as
required by client/code.
Stamps used need to be low stress type.
Application of desiccant/preservative need to be as directed in client's
specification.
All valves need to be checked for cleanliness and dryness by third party inspector.
Nozzle, outlets, flanged or butt welded, saddle, bracket locations and orientations
against assembly drawings are controlled and operation of valve indicator and correct
functioning also be checked.
The third party inspector checks the content in accordance with the approved drawings
and specifications and make sure it is stamped in accordance with the code
requirements.
Surface preparation for painting is checked for the following points, according to
specification by third party inspector:
Third Party Inspection for Valve - Spare Parts, Loose Items and Accessories
Spare parts, loose items and accessories are checked visually for their dimensions,
materials, workmanship and quantity, according to the purchase order specification.
TThe third party inspector provides an Inspection Visit Report (IVR) after each
visit, as well as a final report summarizing the activities carried out during the
valve production in accordance with the contract requirements and circulated
within the time limits specified in the contract.
The report is in the format required by the client and clearly indicates final acceptance
or rejection of the valve.