Critical Path Project Template

This document outlines a critical path method (CPM) schedule for a project with a start date of 1/11/2015 and finish date of 2/6/2015. It lists 8 tasks (A through G) with their predecessors, optimistic, most likely and pessimistic durations, and early and late start and finish dates. A Gantt chart is included to visualize the critical path.

Uploaded by

Nizwa Khalifa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
53 views2 pages

Critical Path Project Template

This document outlines a critical path method (CPM) schedule for a project with a start date of 1/11/2015 and finish date of 2/6/2015. It lists 8 tasks (A through G) with their predecessors, optimistic, most likely and pessimistic durations, and early and late start and finish dates. A Gantt chart is included to visualize the critical path.

Uploaded by

Nizwa Khalifa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Critical Path Method

Start Date Days to Completion


1/11/2015 20.00
Finish Date
2/6/2015
Times (in Days)

[42]

ID Task Name Predecessors O M P Duration ES EF LS LF Slack


(Enter one ID per cell) (min) (most likely) (max) (exp. time)
10 Start 0.00 0.00 0.00 0.00 0.00 0.00
20 Task A 10 2 4 6 4.00 0.00 4.00 0.00 4.00 0.00
30 Task B 10 3 5 9 5.67 0.00 5.67 3.67 9.33 3.67
40 Task C 20 4 5 7 5.33 4.00 9.33 4.00 9.33 0.00
50 Task D 20 4 6 10 6.67 4.00 10.67 8.33 15.00 4.33
60 Task E 30 40 4 5 7 5.33 9.33 14.67 9.33 14.67 0.00
70 Task F 50 3 4 8 5.00 10.67 15.67 15.00 20.00 4.33
80 Task G 60 3 5 8 5.33 14.67 20.00 14.67 20.00 0.00
90 Finish 70 80 0.00 20.00 20.00 20.00 20.00 0.00

Days: -5 0 5 10 15 20 25
9
Critical Flexible Slack Events
8
Start
7
Task A

Task B 6

Task C 5

Task D 4

Task E 3

Task F
2
Task G
1
Finish
0
Weeks:

http://www.vertex42.com/ExcelTemplates/critical-path-method.html
Holidays to Exclude from Working Days

Date Non-Working Days


1/1/2009 New Year's Day
1/1/2011
12/25/2009 Christmas
12/25/2010