5 Fall!2008
5 Fall!2008
5 Fall!2008
Fall 2008
www.on-sitemag.com
Rail’s
Light rail transit gathers steam
In this issue:
Growth in Edmonton LRT
Canada Line meets Olympian
challenge in Vancouver
Calgary’s C-Train set for growth
5 Comment
Make nice: If you think keeping good relations
with the public is optional, think again.
7 News
Calgary cuts construction fees
17
Safety tools for construction
Streu named VP at LMS
Northern Crane acquires Parkland Crane
Lefaivre is new Stantec CFO
Non-residential building costs climb in Calgary
Drug testing mandatory for union workers in B.C.
Temporary foreign workers a focus in Alberta
Finning acquires two Alberta rental stores
Code green for B.C.
Thomas names Kasha as dealer
www.on-sitemag.com
Fax: (416) 764-1733
COMMENT
By Jim Barnes
EDITORIAL
Editor: James A. Barnes
(416) 764-1612
[email protected]
Art Director: Melissa Crook
(416) 764-1545
Making nice
M
[email protected]
ore than two thirds of respondents to a recent survey in
BUSINESS WCN’s sister publication, Backfill (our electronic newsletter),
Publisher: Peter Leonard said that the public is getting more hostile. They said that
(416) 764-1510 incidents of confrontation, complaint, vandalism and so on have
[email protected]
been on the rise over the past five years.
Account Manager: Tracy Ryan
416-764-1557 How many respondents thought the public’s attitudes toward
[email protected] construction had improved? Zero.
Account Manager: David Skene When people complain, they usually do it to the municipality. Earlier
416-764-1590 in the year, Calgary decided it had had enough. Calgary sometimes
[email protected]
seems like one big, 24-hour construction site, and in 2007 it got some
Sales & Marketing Coordinator: Kim Rossiter
(416) 764-1787 3,000 noise complaints, a 15 per cent increase from the year before.
[email protected] In response to these issues, it introduced a new, voluntary code
Circulation: Bibi Khan of conduct that it is asking contractors to sign. The Construction and
(416) 764-1450 Demolition Site Management Code of Practice involves tasks like
[email protected]
keeping the neighbourhood informed about your work, logging your
Publications mail agreement no. 40070230 response to complaints and controlling noise, lighting and cleanliness.
REGISTRATION NO. 10811
Return undeliverable address BLOCKS to: I am sure some of you have virtually collapsed in laughter by this
ON-SITE
CIRCULATION DEPT. P.O. BOX 720, STN K point. The city itself euphemistically notes that “Industry associations
Toronto, Ontario M4P 3J6
On-Site, established 1957, is published 7 times a year by Rogers continued to indicate general non-support for the code.” Nobody
Publishing Limited, a division of Rogers Media Inc.
Rogers Publishing Limited wants the additional costs and red tape, especially for something as
One Mount Pleasant Road
Toronto, Ontario, M4Y 2Y5.
Subscription inquiries Toronto only: (416) 932-5071 9 a.m. to
fickle as public goodwill.
6 p.m. EST weekdays. Outside Toronto subscription inquiries: But think about it for a moment. When municipal governments
1-866-236-0608 Fax: 416-932-1620
Mail: On-Site, Circulation Dept. P.O. Box 720 STN K,
Toronto, Ontario M4P 3J6 look at the public, they see voters. If they see a way to make hay with
E-mail: [email protected]
Subscription price per year: $79.00 CDN; Outside Canada per year voters without too much expenditure on their part, they are quite
$135.00 US; Single copy price: $13.00 Single copy & Directory
Sales: Bebe Jardine 416-764-3858 tempted do it. There may not be such a code of conduct in your city yet,
E-mail: [email protected] 9 a.m. to 5 p.m. EST
weekdays Fax: 416-764-3938 and the Calgary code may be voluntary today, but that might change.
Mail: On-Site, Circulation Dept. One Mount Pleasant Road, 7th
Floor, Toronto, ON M4Y 2Y5 Printed in Canada. Contractors’ relations with the public are on a downward trend.
This publication is for informational purposes only. The content It’s in your interest to keep the public happy (or at least, not unhappy).
and “expert” advice presented are not intended as a substitute for
informed professional engineering advice. You should not act on You may or may not sign a formal code of conduct, but ignoring public
information contained in this publication without seeking specific
advice from qualified engineering professionals.
We acknowledge the financial support of the
hostility to your work won’t take you very far.
Government of Canada, through the In fact, ignore it long enough and you may eventually face onerous,
Publications Assistance Program (PAP) towards our mailing costs.
Want to purchase multiple copies of articles that have appeared in mandatory municipal regulations about noise and site maintenance.
On-Site? Contact Peter Leonard, Publisher.
Rogers Media Inc. President and CEO, Anthony P. Viner
Rogers Publishing Limited President and CEO, Brian Segal
Senior Vice Presidents Marc Blondeau, Michael J. Fox, John Milne
Vice Presidents: Immee Chee Wah, Patrick Renard
Vice President, Consumer Marketing Tracey McKinley
Contents © 2007 by Rogers Publishing Limited, may not be reprinted
without permission.
On-Site receives unsolicited materials (including letters to the
editor, press releases, promotional items and images) from time to
time. On-Site, its affiliates and assignees may use, reproduce, publish,
re-publish, distribute, store and archive such unsolicited submis-
sions in whole or in part in any form or medium whatsoever, without
compensation of any sort.
MEMBERS OF
Canadian Canadian
Association Construction
of Equipment Association
Distributors
will continue to be associated with the “The quarterly increase was mostly
firm in a consulting role. the result of higher labour and fuel
Lefaivre joined Stantec in 1990 as an costs, as well as material price increases,
accounting manager. in particular steel,” according to
Lefaivre “helped navigate our StatsCan.
company through a number of complex
projects including the successful rollout Drug testing
of our enterprise system,” noted Tony In what was officially described
Franceschini, president and C.E.O. as a “Joint News Release,” two major
Stantec provides professional players in the B.C. construction labour
consulting services in planning, engi- sector announced agreement on a non-
neering, architecture, interior design, invasive drug and alcohol policy
landscape architecture, surveying, for jobsites—believed to be the first
environmental sciences, project man- in Canada.
agement, and project economics for Following years of debate in the
infrastructure and facilities projects. industry, the Construction Labour
Relations Association (CLRA) and the
Non-res costs climb in Calgary Bargaining Council of British Columbia
Despite a softening in inflation, Building Trades Unions (BCBCBTU)
Calgary continue to have the highest announced that the Drug and Alcohol A clear head is essential for jobsite safety.
non-residential cost increases in the Policy will boost worker safety and
provide treatment and rehabilitation
to workers who have drug or alcohol detecting, eliminating and treating
problems. substance abuse which stands to impair
The policy, developed by unions and performance on the job,” said Clyde
employers during the negotiations for Scollan, president of the CLRA. “Any
the current standard agreement, applies worker who tests positive for drugs is
to all union construction workers in B.C. immediately taken off the job.”
Testing may be performed on workers Under the terms of the policy,
who are involved in accidents or “near workers who test positive can’t return
misses,” or are otherwise suspected of to work until a doctor who specializes
impairment on the job. in substance abuse issues is satisfied
Testing may also be carried out on the employee can return to the job
employees before starting work on a site safely.
new project; however, these tests are Workplace drug testing has proved
voluntary under the policy. to be contentious legal issue in the past
The two organizations emphasized and has been a particular concern of
that the policy does not address what various human-rights organizations.
workers do on their own time. “We opted
The Bow is one of Calgary’s exciting projects. for a non-invasive testing policy, which is TFWs a focus in Alberta
designed to measure possible current im- There were nearly 22,400 temporary
country, according to information from pairment on the job, not what you did last foreign workers (TFWs) in Alberta in
Statistics Canada. Alberta occupies the week,” said Mark Olsen, president of the 2006, more than double the 11,000 total
same position among the provinces. BCBCBTU. The test covers alcohol, as well from 2003. As TFWs come to occupy
An 8.7 per cent increase was re- as nine other drugs including marijuana. a more important position in the
corded in Calgary in non-residential “Construction work is dangerous Alberta economy, increasing attention
construction costs in the second quarter, enough without the added perils of is being given to their smooth entry
according to the report. Edmonton was having impaired workers on the jobsite,” to the industry.
in second place nationally, with a cost noted Olsen. Many TFW-related issues are not
increase of 6.5 per cent. The national “Our plan provides consistent, currently being addressed, notes the
figure was a more modest three per cent. fair and manageable procedures for Alberta government. The list includes
Among the changes: been eliminated, and the attic-space assemblies. The amount of insulation
• A new Part 10 has been added to insulation increased from RSI 7.7 to RSI is derived from ASHRAE 90.1-2004.
the code that reflects the two, added ob- 9.0 in the colder parts of the province. • All other buildings (primarily
jectives of water and energy efficiency. • Achievement of an EnerGuide Rat- Part 3) must comply with the ASHRAE
• The Part 9 thermal insulation ing System rating of 77 is an acceptable 90.1-2004 standard.
table has been relocated to Part 10 solution that provides an alternative to • The requirements of the existing
and its scope expanded to include compliance with the insulation table for Water Conservation Plumbing Regulation
four-storey residential buildings. As residential buildings. have been relocated to Part 10 of the
well, the allowance to use R14 instead • Non-residential, Part 9 buildings Building Code and are now applicable
of R20 insulation for natural gas-heated must now provide thermal insulation in province-wide.
buildings in the Lower Mainland has wall, roof and suspended-floor
Western building permits soften increase in value of building permits to Of the 34 census metropolitan ar-
$2.7 billion came as stronger industrial eas tracked in the research, 18 recorded
While Canada as a whole eked out a construction intentions offset declines in growth in the value of building permits.
1.8-per cent rebound in July building per- commercial and institutional permits. The step into negative territory did
mit values after a decline of 5.3 per cent in Weakness in commercial buildings not seem to earn much reaction from
June, Alberta and B.C. didn’t make it to the was recorded in B.C. and Ontario, while industry leaders, who both expected
party—recording declines of 3.9 per cent declines in the value of institutional some softening and felt that the con-
and 19 per cent respectively. permits were recorded in Alberta, Ontario struction economies in Alberta and B.C.
A report on construction intentions and Quebec. still continue at a torrid pace.
from Statistics Canada showed that growth
to $6.4 billion in permits nationally in July
was largely attributable to multi-family
dwelling permits in Central Canada and
strong industrial construction intentions
in Saskatchewan.
In the residential sector, the value of
building permits rose 2.7 per cent to $3.7
billion, mainly due to an increase in the
value of multi-family dwelling permits in
Ontario, Quebec and Manitoba.
In the industrial/commercial/institu-
tional (ICI) sector, the slight 0.6 per cent
Actual SAAR
Aug-07 Aug-08 Jul-07 Jul-08
Final Prelim. % change Final Prelim. % change
Canada, all areas 20,868 18,396 -11.8% 186,500 211,000 13.1%
Canada, rural areas 3,667 2,525 -31.1% 25,100 25,100 -0.0%
Canada, urban centres* 17,201 15,871 -7.7% 161,400 185,900 15.2%
Canada, singles, urban centres 8,526 6,406 -24.9% 69,800 71,200 2.0%
Canada, multiples, urban centres 8,675 9,465 9.1% 91,600 114,700 25.2%
Atlantic region, urban centres 1,071 783 -26.9% 8,700 7,700 -11.5%
Quebec, urban centres 3,221 2,869 -10.9% 41,200 37,600 -8.7%
Ontario, urban centres 5,721 7,768 35.8% 47,800 86,500 81.0%
Prairie region, urban centres 4,447 2,034 -54.3% 30,600 23,700 -22.5%
British Columbia, urban centres 2,741 2,417 -11.8% 33,100 30,400 -8.2%
The
• No construction project today could
be run like the CPR of the early days, which con-
stantly teetered on the edge of bankruptcy and plunged
the Canadian government deeply into debt.
• LRT projects go through an unending suite of consultations
and approvals, not to mention detailed design. The CPR faced
no such delays. The rail line was built at maximum speed in a
straight line no matter what was in the way… including Black-
A
s populations boom in Western Canadian foot territory and the Rocky Mountains (through which there
cities and sustainability becomes the order was no known pass when construction started).
of the day, Alberta and B.C. are hard at work • Traffic management was not an issue for the CPR, but
on light-rail transit—with major system expansions underway contractors working on the LRTs must cope with tens of thou-
or planned in Vancouver, Edmonton and Calgary. These are sands of cars a day, often in urban areas.
spectacular projects. • Labour was an issue, too. LRT workers are well-trained,
A challenging question about LRT construction recently reasonably paid and in much shorter supply than the 12,000
came from Naomi Lakritz, a columnist in a Calgary newspaper. CPR workers—some of whom were virtually slaves. Safety was
She asked why it was taking three years to extend the C-Train a non-issue; the death toll in building the CPR was horrifying.
line in Calgary four km. when the Canadian Pacific Railway Safety is stringent on the LRT projects and accidents of any
was built from Ontario to B.C. in just four years. Ian Norris, kind are rare.
Calgary’s director of transportation infrastructure, made a • Finally, the construction quality is completely dissimilar.
valiant effort to respond, but somehow his point of view failed Some parts of the CPR had to be repaired practically immediately
to impress Lakritz. after the line was opened, whereas no such surprises are expected
We can’t say whether LRT expansion in Calgary is happening from the LRTs.
as fast as it should, but the answer to Lakritz’s broader question The answer to the question has to be that the LRTs are care-
touches both on modern concerns in construction and the fully planned, budgeted, designed and built business projects.
unique place in Canadian history held by the CPR. The CPR was the “National Dream” of the 19th century. They
• First of all, the objectives of the projects were totally both run on rails, but that’s where the similarity ends.
different. For the Canada of the late 1800s, the CPR railway was You have to wonder what a modern contractor would do
like the Apollo program. It was an urgent national priority that with a job like “Just lay track west as fast as you can, whatever
transcended politics and cost. B.C.’s entry to Confederation was it costs, and don’t stop for anything.”
contingent on quick completion of this rail line, and Canada’s We take a look at the status of current LRT projects in Alberta
future was literally at stake. LRT expansion, of course, is a and B.C.—models of careful and professional construction—over
much more sedate and fiscally responsible kind of project— the next few pages.
and that’s a different kind of vision.
V
ancouver has a two-decade-plus history of light-rail was created to manage the Canada Line overall. There is a
transit (LRT) construction, dating back to completion 35-year concession agreement between InTransitBC and the
of the Expo Line in time for the Expo 86 World’s Fair. Canada Line Rapid Transit Co., which represents the public
Its current total of nearly 50 km. of track makes SkyTrain the side of the P3. They represent all government funding agencies
world’s longest automated LRT system. and the greater Vancouver transit authority. So InTransitBC
Another global event is driving the deadlines for the current has a very large presence on this project.”
LRT project. The Canada Line will be operational well before
the 2010 Winter Olympics. Originally called the Richmond- Heavy traffic
Airport-Vancouver (RAV) Line, the 19-km. long system will be The project has offered many major challenges, says Crombie,
an automated, rail-based system operated by the South Coast some of them centred around building elevated guideways
British Columbia Transportation Authority (Translink). As the through parts of Vancouver and Richmond. “We’re building 19
original name suggests, it will connect Vancouver with central km. of transit system, including tunnels and elevated guideways,
Richmond and the Vancouver Airport, massively increasing through busy urban areas. Stations in downtown Vancouver
the city’s transit capacity. Construction began in November, require opening at least a block of downtown Vancouver in
2005 and the line is scheduled to open November 30, 2009. three different locations,” he says. “We have a cut-and-cover
RAV Project Management (RAVCO), a subsidiary of TransLink, tunnel along the Cambie corridor and an elevated guideway
provides governance of the Canada Line. The line is being built down Number Three Road in Richmond.”
by SNC-Lavalin, which will operate it for 35 years. In 2009 the line “At the peak of the project, about 1,800 people were work-
should carry 100,000 passengers a day and 142,000 by 2021. ing—which doesn’t necessarily include all the suppliers and
“InTransitBC has a contract to design, build and operate people peripherally associated with it,” he notes.
the Canada Line and to partially finance it,” explains Steve One of the real challenges is traffic management. “One
Crombie, vice-president of public affairs. “Technically, IntransitBC goal we and the cities of Vancouver and Richmond had was
Photo: SNC-Lavalin
to keep traffic flowing. We built a tunnel along Cambie Street this kind of machine before, and it had never been used in B.C.
while maintaining north/south traffic and cross streets.” There were about 40 people on that crew.”
Construction methods were pretty standard, says Crombie, As a P3, the Canada Line project requires relationship
apart from tunnelling. “The company that did the bored tunnel building, “because we deal with not only the private sector and
brought their own crew and trained local people. Otherwise, contractors but also various levels of government and public
construction methods were standard.” bodies. Cooperation and trust among parties is vital. They
Crombie credits flexible project management with helping don’t necessarily exist on a typical project. Managing relationships
to accelerate the project. For example, dramatic success with has gone well on this project.”
a cut-and-cover tunnel near Queen Elizabeth Park was used “Flexibility, innovation and creativity have allowed us to
in the Cambie business area, where another approach had work well within a tight schedule. We’re contractually required
been contemplated. “We were going to do the tunnel down the to have trains in revenue service by November 30, 2008. We
middle of Cambie, using a very large gantry crane, and have hope to have the line up and running earlier, which would be
traffic flowing in two lanes on either side of the excavation. But a major feat.”
we recognized that the method for the cut-and cover we used
near Queen Elizabeth Park was so efficient that we knew we “We’re building 19 km. of transit system,
could speed things up by changing the construction method.”
It meant more intensive traffic disruption for a shorter period including tunnels and elevated guideways,
of time. “We finished that area four months early by making a
judgment and changing methodology. The project manage- through busy urban areas.”
ment system is astute at finding new ways of doing things and
adapting,” says Crombie. Roger Woodhead is technical director of SNC Lavalin,
which has the contract to design and build the Canada Line.
People issues They are a one-third partner with InTransitBC.
According to Crombie, there hasn’t been a problem attract- Some problems stemmed from managing such a large group
ing labour, partly because this is the biggest transportation of people, he says. “There are many layers in the organization—
infrastructure project in Canada. “I think people take pride in with innumerable chances for miscommunication. We’re man-
working on a project like this. Also, a multi-year project means aging a group that includes stakeholders and contractors and
fairly steady employment.” engineers with diverse skills.”
Most of the trades are from B.C. but many of the rebar “You need a skilled management team who communicate
workers came from Quebec, notes Crombie. “We had foreign well with each other and get along. One advantage is that SNC
bored-tunnelers from an Italian company called Seli, which Lavalin plays a big role; we don’t have partners and can make
specializes in tunnel boring. They had people who had run quick decisions.”
America,” says Woodhead. and this would have caused schedule problems—there are
some critical rooms in that station that we need to operate
Small innovations helped speed up the work. “One was the system. We actually moved those rooms out of the station
special formwork for the cut-and-cover tunnels. We could into the cut-and-cover tunnel, so we could build those rooms
pour the walls and the roofs in one pour. It’s been done before, while the tunnel-boring machine was still working. That’s one
but maybe not in Vancouver.” change we made during construction, and there are many others,
As well, he notes, “This is the first bored tunnel in Vancouver. because our management system is so flexible.”
The bridge over the North Arm of the Fraser River also reflected
innovation. The river is an active marine way that is under the Experience counts
flight path of the Vancouver National Airport. “It’s the first extra- Ron Fettback, general superintendent of Western Pacific
dosed bridge built in North America,” says Woodhead. Enterprises (WPE), is in charge of building projects and oversees
“The cables are attached low because of the flight path. That labour and work contracts. He says the firm’s experience on
means the slope of the cables is quite shallow. Where in a nor- systems like the Expo Line and the Millennium Line gave them
mal, cable-stayed bridge, the cables tend to slope at about 45 the expertise needed for the Canada Line. “We haven’t had any
deg. so they help lift the bridge up. In this case, the cables are challenges that were unexpected,” he says.
much flatter—they post-tension the bridge, more than lift it.” Most of WPE’s work is on communiciation cabling, but
Woodhead credits local experience with helping advance Fettback says they also built the Richmond maintenance and
the project quickly. “There’s an experienced Vancouver workforce operations facility and installed the electrical alarm. Training is
that has built rapid-transit systems before. On the elevated guide- an ongoing focus at WPE. “All of our crane operators and such Photo: SNC-Lavalin
by Don Buchanan
I
n Edmonton, during the “construction season” of 2008— The City of Edmonton hired Edmonton-based Stantec as
otherwise known as summer—the spotlight shone brightly managing consultant to oversee the contractors engaged by
on a wide range of construction contractors, who jointly the City and to lead the planning and design of the South LRT
withstood the heat and generally made significant and timely Extension. “As the managing consultant we have overseen the
progress on many aspects of the $673-million South LRT Ex- work of more than 50 design firms, engineering consultants
tension project. and construction contractors on different aspects of this
“This project is the largest infrastructure project ever led project,” said Rob Fewings, Stantec’s South LRT Extension
by the city of Edmonton and is a major step forward in increasing project manager.
ridership and the practicality of the city’s LRT system,” said Brad
Griffith, design and construction director for the city’s Transit Risk management
Projects Branch. “The fact that most parts of this southern line Fewings noted that effective risk management has been a
have to be built by going around or through existing road- top priority on the project. “We hold regular risk management
ways and infrastructure makes it inherently more costly and sessions and categorize risks on a priority basis. In general,
complicated, especially compared to the existing northbound the biggest hurdle for most of the contracted firms and con-
leg, which was built on an existing railway right-of-way in struction companies has been the chronic labour shortage—
advance of the 1978 Commonwealth Games.” but other issues are in the mix, such as inflation, scheduling
issues, rerouting of traffic, and dealing with citizen concerns
“To ensure we received a sufficient before and during construction.”
number of competitive bids on some of the The South LRT Extension project runs approximately 7.5
km. southward from the existing Health Sciences station on the
tendered work, we had to break out the main University of Alberta campus to 23rd Ave. near the high-
work into smaller bid packages.” density Century Park development. The South LRT Extension
includes four new LRT stations and is expected to trigger a dou-
“Doing the work over the last few years in Alberta’s boom bling in daily ridership on the system.
economy has also been a huge challenge,” stated Griffith. “As The first two stations to open will be the McKernan/Belgravia
the project owner, we’ve been faced with labour shortages, station, located about one km. south of the main University of
inflationary pressures and, at times, a shortage of contractors. Alberta campus, and the South Campus station, located an-
To ensure we received a sufficient number of competitive bids other two km. further south near some important university
on some of the tendered work, we had to break out the work athletic facilities and several provincial government office
into smaller bid packages.” complexes. These stations are on track to open in the spring
Costs grow
Griffith noted that the original budget for the South LRT
Extension allowed for eight per cent inflation per annum, but
given the major boom in 2006 and 2007, costs on the project
were higher than budgeted. “Cost increases were relatively
minimal for some components of the work, such as signalling,
while costs for roadwork and excavation rose by up to 40 per
cent, so our cost increases averaged out at about 20 per cent
per year for 2006 and 2007.”
As one means of managing overall project costs, Griffith
said that the construction of two LRT stations on the southern
line was tendered as construction-management contracts,
instead of design-bid-build contracts. “This process was fol-
lowed for the Southgate and Century Park stations and we
Roadwork and excavation
engaged PCL Construction Management Inc. as the construction costs grew by 20 per cent.
manager for this work. They have done a great job in tendering
and overseeing the subcontracted work on those two stations,”
says Griffith. that were ordered to ensure sufficient carrying capacity on the
PCL Construction Management Inc. was also engaged expanded LRT system. Each car can hold up to 160 people and
as the construction manager for expansion work on the D.L. LRT trains will run with up to five cars at a time.
MacDonald light rail vehicle (LRV) maintenance facility, located
in the City’s north end. The expanded facility will be used to Cooperation
maintain the city’s growing fleet of LRVs, including 37 new cars Roger Dootson, vice-president of PCL Construction Man-
agement Inc., noted that in addition to the three construction-
management contracts, PCL also won five other contracts on
South LRT: Construction Features different portions of the LRT South Extension project. “The
• Four LRT stations: McKernan/Belgravia, South total value of work being done by PCL is about $230 million.
Campus, Southgate and Century Park. Transit centres For each part of the work that we are doing, we have had great
(for buses) will be associated with South Campus, cooperation from the city and the various departments, par-
Southgate and Century Park Stations. ticularly the traffic-operations group and the transit depart-
• The McKernan/Belgravia station features a pe- ment. Given all of the transit and traffic issues, such as revised
destrian underpass, under 114 St. at 76 Ave. This facilitates bus stops, traffic detours and lane closures, we couldn’t have
pedestrian safety for local residents and children attend- kept things on schedule this summer without this proactive
ing a nearby elementary-junior high school. approach from the city’s departments.”
• Two LRT underpasses—a 114-m. tunnel under Dootson also noted that the PCL team has had to work
Belgravia Road, and a 90-m. underpass beneath the closely with utility companies, the city and design personnel
southbound lanes of 111 St. to bring the LRT into the to deal with challenges relating to existing utility installations.
median, south of 61 Ave. “In some cases, we had to adapt as we went and redesigned
• A one-way bridge (“busway”) connecting buses from around existing utility installations to ensure they were functional
the South Campus Transit Centre to Fox Dr., facilitating within the new LRT system.”
commuter access to Edmonton’s west end. Public safety issues and workplace safety have also been
• A bridge over Whitemud Dr. for the LRT, just south prominent concerns on this project, added Dootson. “For ex-
of the Southgate station. ample, when building a pedway over a major roadway at the
• 37 new LRVs (Light Rail Vehicles) have been ordered. Southgate station site, we ensured that all of the critical lifts
The first car arrived in May 2008. of the steel structure components took place at night, under
• A fully landscaped multi-use recreation trail follows carefully supervised conditions. We have stringent policies
the entire length of track. and procedures for these special events and we want to ensure
that workers and the public are safe at all times.”
the formwork designer. “For a pour rate of, say, one metre an and more precise.” However, Aecon had not used this technology
hour, you would know the maximum pressure reached and on a project of this size before.
can design the formwork accordingly.” Doka’s Framax S Xlife panels were combined with Dokaflex
SCC is a different story. “You have to design as if it’s go- tables and supported by Staxo 100 towers. The towers, designed
ing to be full liquid head—as if you’ve got, say, five metres of in a table configuration, could readily be transported, set up
hydrostatic pressure. The only way to work around that and and reused. When the towers are stripped, they are wheeled
see how the preassure developes is to monitor it as you pour,” out of the tunnel and picked up the same way tables are lifted,
explains Pereira. “SCC can have somewhat of an unpredictable with lifting straps. The towers are then set to the new position
pressure envolope.” for the next pour and the walls are stripped and set up in the
new location.
C
algary’s C-Train LRT system has the highest volume
of any such system in North America, estimated at
271,100 boardings per weekday in the fourth quarter of
2007. Expansion would seem to be in the cards, and the city
has announced a design-build project called the West LRT to
all interested parties.
The West LRT line will expand the City’s Light Rail Transit
(LRT) service into southwest Calgary. Construction is slated
to begin in early 2010 and the new C-Train line is expected to
open in December 2012.
In November 2007, Calgary city council approved $700
million to fund the project. Preliminary design-engineering
work is being carried out by Calgary-based Hatch Mott Mac-
Donald (HMM). Early design work took place between February
and May 2008 and the proposed alignment for the new line
was approved by Council in June 2008. Contracts for C-Train expansion
“The next step is to issue a Request for Qualifications,” will be awarded in 2009.
explained Ryan Murray, communications advisor for the West
NO.
On-Site MAGAZINE
One Mount Pleasant Road 7th Floor, Toronto ON, M4Y 2Y5 Fax: 416.764.1748
Publisher reserves the right to determine qualification & limit distribution.
WCN ADVERTISERS’ INDEX & WEBSITES
Lower Mainland Steel................... www.lmsgroup.ca.......................6, 34 The WCN Advertisers’ Index is provided as a free service
Mack................................................. www.macktrucks.com...................13 to our advertisers.
Changed conditions
W hat’s going on at the Seymour-Capilano Filtration Project
(SCFP)?
I’ve been following the Seymour-Cap epic and most of the
associated projects for seven years. I’ve published some half-
dozen articles, attended two moving St. Barbara celebrations
and have a genuine fondness for the project. BB claimed that rock conditions were causing safety issues.
St. Barbara—the patron saint of those who work under- MV’s consultants issued a plan to address these concerns, but
ground or with explosives—is commonly celebrated in Europe. BB rejected it, countering with a “pay as you go” option. In re-
Bilfinger Berger (BB), a European contractor, built a modest sponse, MV terminated their right to work.
shrine in her honour at the bottom of the shaft and celebrated Today some $38-million worth of equipment is sitting idle;
her day annually. MV has seized one of the tunnel-boring machines under the
It’s an interesting project. Explosive compaction was used terms of the contract (the other is leased); and BB is suing MV
downstream of an operating dam, the capacity of the Seymour for $22 million.
UV disinfection plant is the largest in the world, the filtration How will the work proceed? Submissions for “Expressions
capacity the largest in Canada, green-roof technology is planned of Interest and Statement of Qualifications” closed in August.
for the filtration plant and clear wells and the twin tunnels are MV hopes to pre-qualify three contractors. Déjà vu. Since the
the largest civil tunneling project in B.C. in decades. job is about half done and the original duration was four years,
The $600-million undertaking includes a pumping station I suppose it would be fair to allow two more years—but I doubt
(one of Canada’s largest) and energy-recovery plant at Capilano the bids to complete the work will be anywhere near $99 million
with twin, 7.1-km., 3.8-m. dia. tunnels that will eventually carry in this market.
untreated water from the Capilano reservoir to be treated at Meanwhile an interim contractor has 30 workers maintaining
Seymour and then returned. Over and above the $600 million, the pumps so that the tunnel doesn’t flood and destroy the
three dams that hold back Metro Vancouver’s (MV) water supply electrical components of all the gear that may not see the light
have undergone major upgrades. of day for years to come. It will be many more years before MV
So why has Seymour-Cap been shut down? or BB is vindicated.
In a nutshell, the wheels that pushed this project started Ironically, MV has started a campaign to get people off bottled
turning in 1984 when the City of Vancouver determined that water and the City of Vancouver is talking about an outright
the Canadian drinking-water standards were not consistently ban. In fairness, the filtration plant is on schedule and filtered
being met in its water supply. The pH level was often low, non- water from the Seymour reservoir will be available for wider
pathogenic bacteria were present and the turbidity was often distribution during periods of high turbidity.
higher than the standards. With a dispute-resolution that was attractive to the contractor,
In 2003, three of eight pre-qualified contractors bid on you have to ask how this could have been avoided.
the tunnels. BB was the winning bid at $99 million, the next- Two years ago, someone involved in the project noted that
higher bid was $186 million and the highest was $237 million. “changed geology is normal; the difficulty is who pays for it.”
BB wanted to enter the North American market, it liked the I would counter that with the most profound pearl of wisdom
terms of the contract, and—I remember this well—it liked the I’ve ever heard in my years of business writing: “there’s no such
dispute-resolution mechanism, so they bid aggressively. The thing as changed conditions—only what we choose to find out
engineer’s estimate wasn’t divulged. about the existing conditions.”
The tunnels were to be bored over four years, starting and Sadly, the most valuable lesson to come out of this won’t be
finishing in the fall of 2004 and 2008 respectively. Difficulties about tunneling and it might even be something we already
with sinking the 640-m. entry shaft put BB behind schedule know—you get what you pay for.u
from the get-go, but during my visit in late 2006, they were still
confident they’d make the deadline.
Fast-forward to January 2008, 4.1 km. into the raw-water Tonia Jurbin is a regular contributor to WCN. She is based in
tunnel and 3.8 km. into the treated tunnel—and it’s over! Greater Vancouver. Contact editor@on-sitemag.