Set of Flashcards PSPO I 3
Set of Flashcards PSPO I 3
FLASHCARDS
PSPO I
Practice for Professional Scrum Product Owner Certification (Scrum Guide 2017)
265 3 53 4
Details ³
spo_i?flipperMode=true&flipMode=false&max=30&q=) 8 (/box/20201228_pspo_i?flipperMode=false&flipMode=false&max=30&q=)
In order to make investment decisions, the Product Owner is likely to look at the Total Cost of ß
Ownership (TCO) of the product being built. What costs will a Product Owner take into account?
The money spent on development of the product, often a fixed cost per Sprint multiplied by the Sprints required ß
All investments required to conceive, develop, operate and maintain the product
Competitive research ß
Customer feedback
Product vision
In the middle of the Sprint, the customer decides that there are 2 new features she wants. The ß
Product Owner should...
Help manage and increase the velocity of the Development Team's work so they may add the requirements to the ß
end of the Sprint.
Ask the Scrum Master to help integrate the requirements with the Development Team.
In the Sprint Planning meeting, the Product Owner and the Development Team were unable to ß
reach a clear understanding about the highest order Product-Backlog items. Because of this, the
Development Team couldn't figure out how many Product Backlog items it could forecast for the
upcoming Sprint. They were able to agree on a Sprint Goal, however. Which of the following two
actions should the Scrum Master support?
Cancel the Sprint. Send the entire team to an advanced Scrum training and then start a new Sprint. ß
Forecast the most likely Product Backlog items to meet the goal and create a Sprint Backlog based on a likely initial
design and plan. Once the time-box for the Sprint Planning meeting is over, start the Sprint and continue to analyze, decompose,
and create additional functionality during the Sprint.
Continue the Sprint Planning meeting past its time-box until an adequate number of Product Backlog items are well
enough understood for the Development Team to make a complete forecast. Then start the Sprint.
Discuss in the upcoming Sprint Retrospective why this happened and what changes will make it less likely to recur.
Ask everyone to take as much time as needed to analyze the Product Backlog first, and then reconvene another Sprint
Planning meeting.
It is mandatory for the Product Owner to monitor and share progress of Product Backlog ß
through...
A Gantt chart
Any projective practice based on trends of work completed and upcoming work
It is mandatory that the product increment be released to production at the end of each Sprint. ß
True ß
False
Items on the Product Backlog tend to be... ß
It depends
Learning turns into 'validated learning' when assumptions and goals can be assessed through ß
results. What is a key way for a Product Owner to apply validated learning?
Release an Increment to the market to learn about the business assumptions built into the product. ß
Accept an Increment at the Sprint review to learn about the forecast of functionality that was developed.
Set the Sprint Goal before selecting Product Backlog items at Sprint Planning to learn about a Development Team's
productivity.
Multiple Scrum Teams working on the same product or system all select work from the same ß
Product Backlog.
True ß
False
It is optional. Attendance is only required when the Product Owner gets invited by the Scrum Master. ß
It is mandatory. The Sprint Retrospective is an opportunity for the Scrum Team to assess its performance and improve
itself.
It is not allowed. The Sprint Retrospective is an opportunity for the Development Team to inspect itself.
One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily ß
Scrum?
A shared understanding of the most important work to be undertaken next to achieve the best possible progress ß
toward the Sprint goal.
An updated Scrum board to make Sprint progress transparent for the stakeholders.
An update of completed tasks and of the remaining work so the Scrum Master can plan the next day.
A status report for the upper management indicating what each individual has done, will be doing, and what is impeding
him/her.
Product Owners must specify complete acceptance criteria for product Backlog item before the ß
team can select the item in Sprint Planning.
True ß
False
Scrum has a role called "Project Manager". ß
True ß
False
True ß
False
Scrum is based on empirical process control theory. All of its artifacts must be transparent to ß
ensure sufficient accuracy of inspection. Select two ways to maintain the product backlog to
maximize its transparency?
Product backlog items should hold no more than 8 points of work, which is the average in the range of acceptable sizes of
1,2,3,5,8, and 13.
Product backlog is only updated at a release planning meeting with the stakeholders and the release train engineers
present.
Product backlog is only updated at the Sprint Review, when both the Scrum team and the stakeholders are available .
Product backlog items are sized appropriately, i.e. not bigger than a sprint and with preference for several doable items
in a sprint.
Scrum is based on empirical process control theory. All of its artifacts must be transparent to ß
ensure sufficient accuracy of inspection. Which two measures ensur that the product backlog is
transparent?
The product Backlog is ordered. ß
The product Backlog only has work for the next 2 sprints.
True ß
False
Scrum requires that the product owner must use which of the following items? ß
Burndown chart
Refactoring
When calculated and estimated, the total amount of technical debt shows exactly how long until the Product Owner ß
can release the Increment.
It leads to false assumptions about the current state of the system, specifically of an Increment being releasable at the
end of a Sprint.
As development progresses and code is added, the system becomes more difficult to stabilize, which results in future
work being slowed down in unpredictable ways.
It enhances transparency for the Product Owner as a Development Team is not allowed to do additional feature
development in a Sprint as long as there is technical debt.
Select two ways to maintain the product backlog to maximize its transparency. ß
Product backlog items are sized appropriately, not bigger than a sprint and a preference for several do-able items in ß
a sprint.
Product Backlog is only updated at the Sprint Review, when both the scrum team and the stakeholders are available.
Product backlog is only updated at a release planning meeting with stakeholders and the release train engineers present.
Six teams new to Scrum will build a new product. What would you strive for? ß
There should be six Product Owners, one for each Scrum Team.
True ß
False
Sprint burndown charts are an efficient tracking tool because they show... ß
How many hours have been worked by each Development Team member.
True ß
False
The "cone of uncertainty" can be used to do what? ß
Determine whether to cut quality, similar to the "Iron Triangle" of Software Development.
The CEO asks the Development Team to add a "very important" item to a Sprint that is in ß
progress. What should the Development Team do?
Inform the Product Owner so he/she can work with the CEO.
Add the item to the current Sprint and drop an item of equal size.
The Daily Scrum is an event that happens every day. What would be three key concerns if the ß
frequency were to be lowered to every two or three days?
Impediments are raised and resolved more slowly. ß
Too much work is spent updating the Scrum board before the meeting.
The Scrum Master loses the ability to update the Gantt chart properly.
The Development Team finds out during the Sprint that they aren't likely to build everything ß
they forecasted. What would you expect the Product Owner to do?
Re-work the selected Sprint Backlog items with the Development Team to meet the Sprint Goal
The Development Team informs the Scrum Master that the IT manager has asked them for a ß
status report during the Sprint. The Scrum Master will...
Talk to the IT manager and inform him that progress in Scrum comes from inspecting increments at the Sprint ß
review.
Ask the product owner to send the unit manager the report.
Tell the development team to fix a report into their Sprint backlog.
The Development Team is accountable for releasing the most valuable product possible. ß
True ß
False
Show 32
(/REGISTER/INDEX) (/INFO/CONTACT)
Y REGISTER V CONTACT & FEEDBACK
W (HTTP://FACEBOOK.COM/CARD2BRAIN) X (HTTP://TWITTER.COM/CARD2BRAIN)
) (HTTP://INSTAGRAM.COM/CARD2BRAIN)
Partners
(/partner/paulemile_mueller) (/partner/akad)
VISCOM BWZ BRUGG
Lernkarten für grafische Berufs- und
Berufe Weiterbildungszentrum
(/partner/viscom) (/partner/bwz_brugg)
Show all
LIBRARY (/LIBRARY)
Natural Sciences (/library/category.naturalscience)
Languages (/library/category.languages)
Society (/library/category.society)
Economics, Financial (/library/category.economy)
Humanities (/library/category.humanities)
Fun (/library/category.fun)
Competition (/library/category.contest)
INFO (/INFO)
What is card2brain.ch? (/info)
Teachers (/info/teacher)
Companies (/info/enterprise)
Frequently Asked Questions (http://feedback.card2brain.ch/knowledgebase)
Prices (/pricing)
SUBSCRIPTIONS (/REGISTER/INDEX)
Features (/features/index)
For schools (/register/educational)
For companies (/register/corporate)
Group discounts (/about/abos)
PARTNER (/PARTNER/INDEX)
Premium Partner (/partner/premium)
Educational Partners (/partner/edu)
BLOG (HTTP://BLOG.CARD2BRAIN.CH)
LOGIN (/LOGIN/AUTH)
Register (/register/index)
GTC (/about/rights) | Data privacy (/about/policy) | Copyright (/faq/copyright) | Legal info (/about/impressum) | Team (/about/team) |
Contact (/info/contact)