ARTICLE - Project Implementtion Methods
ARTICLE - Project Implementtion Methods
Vinay Jain
Project Formulation & Management | II Sem. M Plan | UTD, CSVTU Bhilai
April, 2020
PROJECT IMPLEMENTATION METHODS
The Project implementation is a process whereby " project
inputs are converted in to project outputs". May be looked at
as
- Ernesto A Frenco
To implement a project means to carry out activities proposed in the application form with
the aim to achieve project objectives and deliver results and outputs. Its success depends on
many internal and external factors. Some of the most important ones are a very well organised
project team and effective monitoring of project progress and related expenditures.
Project Operation - This is practical management of a project. Here, project inputs are
transformed into project outputs for achieving immediate project objectives
PROJECT IMPLEMENTATION METHODS
The project implementation methods include
1. Gantt Chart
2. Critical path Method (CPM) or Network Analysis
3. Project Evaluation and Review Techniques PERT
4. Risk Management Strategies
5. Budgeting process
6. Work break down methods
7. Resource Histograms
8. Report (Project Initiation Document)
9. Project Management Software and Systems
10. Earned Value Management (EVM)
Gantt Charts
GANTT CHARTS
Week number
Week 0 1 2 3 4 13 14 15 16 17 18 19 20
Project
activities
Design Plan
Actual
Integration Plan
Actual
Testing Plan
Going live Plan
Training Plan
Gantt charts are a poor time management tools when projects are lengthy and complex.
There often exists in large projects a high interdependency between various tasks e.g. some
activities cannot start, until others have been completed first, therefore many activities are
interrelated. Gantt charts in these circumstances are less desirable because they do not
display or indicate interdependencies. Network (or critical path) analysis can display more
logically the sequence and timing of each activity, they communicate interdependency and a
more effective time management tool for large and complex projects.
Elapsed time (or estimated time) to complete the project can be calculated.
Highlights those activities which are ‘critical activities’ e.g. those tasks which must be
completed within their planned time, otherwise the elapsed time (or estimated time) of
the project will not be achieved.
Enables more effective resource planning, resources can be diverted away from ‘non-
critical’ to ‘critical activities’ e.g. staff could be moved from one task to another, should
problems of overrunning occur on critical activities. This does assume that resources
moved are directly substitutable between tasks.
Highlights ‘float times’ for all activities e.g. the amount of time an activity or task can
slip past its planned completion time, without delaying the elapsed time (or estimated
time) of the project. All critical activities have a float time of zero, because each must
be completed within their planned completion time, otherwise the elapsed time of the
project won’t be achieved.
3. Arrange activities in the most efficient sequence of events and estimate the
elapsed time of the project
The technique of PERT helps gives better time estimation for a project, by accounting for the
uncertainty when predicting task durations. As an illustration, the project manager could
estimate the worse, best and most probable duration of time for each activity and then
determine an ‘average’ completion time. This can be undertaken by assigning probabilities
to the three estimates and calculating an ‘expected value’. The average time of each activity
would then be used to configure the elapsed time of the project.
Resources can be planned and allocated from using it e.g. staff planning
The complexity of the diagram will increase as more activities are included Key
uncertainties often exist when estimating the duration for activities, therefore can be a
poor prediction for elapsed time.
RISK MANAGEMENT
Risk is the chance or probability of something that may or may not occur;
it is something which can be quantified (using standard deviation).
In a project environment there is always a risk or chance that adverse conditions occur, which
could cause the project to fail, or fail to meet its planned objectives e.g. time, cost and quality.
A project manager or a project board should consider the different tasks, activities and work
to accomplish project deliverables, and consider any risk that an actual outcome could differ
to an expected outcome. The financial and non-financial effects of each risk should be well
documented, each risk perhaps classified into groups for better understanding of its
implications. Models such as PEST or SLEPT analysis and other derivatives help to analyse
different types of risk
e.g. social, legal, economic, political and technological risk. Risk management processes can
also help to identify those risks that are controllable and uncontrollable, once each risk has
been identified and the scale or impact of each clearly understood, appropriate risk
management strategies can be implemented in order to control each risk. This will be an on-
going activity throughout the various stages of the project.
A process of managing risk
1. Risk committee set up to address risk issues identified e.g. regular risk audits, to identify
and estimate the likelihood and consequences.
2. Risk register kept which documents:
a. All identified risks ‘ranked and prioritised’.
b. Significance and consequence of each risk reported.
c. Assigned responsibilities to individuals to manage different risks identified e.g. for
greater accountability.
d. Documentation of measures and actions to be taken for each risk, in the event that it
does occur e.g. risk management strategies.
3. Existing processes for risk management reviewed and refined over time e.g. continuous
improvement.
A budget is a forecast or quantified plan of action. A quantified financial plan of action which
itemizes a projects income and expenditure allocated e.g. a list of all planned income and
expenses. Budgetary planning creates a budget as part of the planning process for the project.
Budgetary control compares the budgeted results as a ‘yardstick’ or target, in comparison to
actual results, in order to quantify any variances or deviations from the project plan. This
process at regular intervals throughout a project can be used to take control action and bring
actual results in line with the plans.
Budgets may help in authorising expenditure, communicating objectives and
plans, controlling operations, coordinating activities, evaluating performance,
planning and rewarding performance.
I Integration or coordination
M Motivation
E Evaluation
The purpose of work breakdown structure (WBS) is to help plan effectively for a project by
breaking key tasks or activities down in to more manageable and smaller units of work.
WBS produces a detailed list of tasks to be performed for a project, helping to deliver better
costing, scheduling and resource planning for a project.
Cost breakdown structure (CBS) lists every item classified and its expenditure for the project
in order to get a more detailed estimate of cost or expenditure.
• Staff hours for each task or activity assigned x staff hourly rates per hour
• Staff hours for each task or activity assigned x overhead rates per hour
• Equipment, financing or resources more accurately planned for given more detail of the
tasks to undertake
During a project, financial control can be achieved by actual expenditure being tracked against
each budget allocated for the different tasks assigned. Regular progress can be monitored
using budget or time sheets, and control action taken if appropriate e.g. the process of
exception reporting.
Can help sequence and schedule the timing of different events to improve effectiveness
of how time is allocated e.g. the most efficient sequence of accomplishing activities can
be understood.
Improves resource planning and the efficiency of how resources are consumed e.g.
accurate forecasts for project staffing to save cost.
Can be used as a basis of financial ‘exception reporting’ e.g. actual v budget cost
allowances, and also forecast more accurately the project costs.
Can be used for risk management e.g. to identify risks, and used as an on- going process
for monitoring risks for a project.
A resource histogram is a column (or bar) chart that shows the number of resources assigned
to a project over time. Resource histograms normally presented as bar charts, can be an
effective tool for resource planning and coordinating project staff.
Milestones are a completion of major interim goals for a project e.g. the key stages of a
project from initiation to closure.
Gates are significant events or major objectives that have been accomplished at various
stages of a project. They assess the key completion or quality of work achieved. Gates are
smaller milestones, but well defined into the project management process, a firm deliverable
that can be realised and achieved.
The problem of following gates or milestones, unlike driving from one place to another, is
that the project road signs are not that clear and often can move.
Illustration of a histogram
Project H requires the following types of staff over the next 5 days
Staff type and number Day 1 Day 2 Day 3 Day 4 Day 5
required
3 3 1 1 1
Analyst
Programmer 0 2 3 2 1
Testers 0 0 0 2 2
Total 3 5 4 5 4
1 2 3 4 5 Days
REPORTS
A project planning document (PPD) will normally consist of a project technical and resource
plan at the beginning of a project and used as a reference tool throughout the project.
Contents of a PPD
• Project resource plans
• Quality policies and quality control procedures
• The terms of reference e.g. definition of projects purpose, scope and objectives with
any relevant background information
• Network (critical path) analysis e.g. time estimates and elapsed time identified
• Work breakdown structure and forecasts for expenditure
• Risk analysis undertaken and recommendations
• Timetable for meetings and deadlines
• Organisational team structure and contacts
Progress (or exception reports) can be used to monitor and control the project. This allows
the project board or project manager to identify cost, scheduling or quality related problems
earlier, and view the current status of progress.
The post completion (PC) report would be produced at the closing or completion stage of a
project. This report will summarise project results achieved and used for the purpose of
terminating or ‘signing off’ the project.
Contents of a PC report
Project management software on the market today includes Lotus Notes / Domino or
Microsoft Outlook / Exchange. These fairly comprehensive and integrated packages provide
project applications for timesheets, expense reports, resource management, job costing, help
desk services, time reporting and much more.
Budgeting and controlling cost. Project software will help plan and control project
expenditure more effectively and improve communication of financial reporting. After
budgeted data has been input, actual costs and estimated costs to complete the project can
be tracked, any material exceptions instantly reported. e.g. actual v budget expenditure.
Work breakdown structure. Project software can help assist with planning and
coordination of project staff by breaking tasks or activities down in to more manageable and
smaller units of work or activities to be completed. Automatic schedules of work can be
printed off and used to delegate tasks to different staff within the project team.
Risk management. Project software will help manage the sheer complexity of managing
funds, equipment, staff and other stakeholders to achieve project objectives. Good for ‘What
if’ analysis, the project manager can change different variables e.g. the duration of activities
or cost allowances, in order to understand any fundamental impact this would have on the
project.
Greater accuracy and ease of updating and reprinting reports. Improves the efficiency of
how data is gathered, summarised and communicated.
Earned Value Management (EVM) is a project management system that combines schedule
and cost performance to answer the key question, “What did we get for our money spent?”.
EVM is a measurable performance system which provides quantitative data for project
decision making and control, it is a systematic project management process used to identify
project variances or ‘exceptions’ by the comparison of worked performed and work planned.
It is a measurable system for project scope, scheduling and cost in a single integrated system,
providing an early warning for performance problems.