Substation - Design and Construction
Substation - Design and Construction
CE-019-ST-0007
1
20/03/2020
Disclaimer: This document is developed solely and specifically for use on Melbourne metropolitan tram network managed by Yarra Trams. It is not suitable for any other purpose. You must not
use or adapt it or rely upon it in any way unless you are authorised in writing to do so by Yarra Trams. If this document forms part of a contract with Yarra Trams, this document constitutes a
“Policy and Procedure” for the purposes of that contract. This document is uncontrolled when printed or downloaded.Users should exercise their own skill and care or seek professional advice
in the use of the document. This document may not be current. Current standards are available for download internally from CDMS or from https://yarratrams.com.au/standards.
Infrastructure – Network Power – Substation – Design
and Construction
Table of Contents
1 PURPOSE..................................................................................................................................................... 3
2 SCOPE ......................................................................................................................................................... 3
3 COMPLIANCE .............................................................................................................................................. 4
4 DC SUBSTATION REQUIREMENTS .............................................................................................................. 5
4.1 General principals............................................................................................................................... 5
4.2 Functional requirements .................................................................................................................... 7
4.3 Electrical performance requirements .............................................................................................. 13
4.4 Service performance requirements ................................................................................................. 14
4.5 Design requirements ........................................................................................................................ 16
4.6 Construction requirements .............................................................................................................. 26
4.7 Reliability, Availability, Maintainability and Safety (RAMS) requirements ...................................... 28
4.8 Documentation requirements.......................................................................................................... 29
5 DIAGRAMS AND GUIDANCE ..................................................................................................................... 33
5.1 Single line diagram of a DC traction substation ............................................................................... 33
6 RELATED LEGISLATION & DOCUMENTS ................................................................................................... 34
DOCUMENT VERSION CONTROL ...................................................................................................................... 36
APPENDIX A – GLOSSARY ................................................................................................................................. 37
APPENDIX B – TENDER REQUIREMENTS .......................................................................................................... 40
APPENDIX C – INNOVATION ............................................................................................................................. 42
APPENDIX D – ECO-FRIENDLY DESIGN ............................................................................................................. 43
APPENDIX E – ASSET NAMING CONVENTIONS ................................................................................................ 44
E1 Substations .............................................................................................................................................. 44
E2 Electrical sections .................................................................................................................................... 45
E3 Feeder cables........................................................................................................................................... 45
E4 Substation equipment ............................................................................................................................. 46
APPENDIX F – DC REACTORS AND HARMONIC FILTERS ................................................................................... 47
1 PURPOSE
The purpose of this standard is to specify the minimum requirements for design, construction, integration,
commissioning and through life support of DC traction substations, which are to be installed on the Yarra
Trams network.
The configuration, ratings and any other project specific equipment details shall be provided by Yarra Trams
in the accompanying Scope of Works document.
2 SCOPE
The scope of this standard encompasses requirements for all new DC traction substations.
This standard does not apply retrospectively to existing DC traction substations on the Yarra Trams network.
However, this standard is applicable if an existing DC traction substation is being altered, modified or
replaced.
The scope of this document includes:
• All equipment which is located within the property limit of the DC traction substation;
• The 750 V DC positive system which includes the positive feeder cables, conduits and pits from
the DC traction substation up to and including the cable termination at the interface with either
the overhead wiring system (e.g. an overhead switch or feeder tap to trolley) or an existing cable
termination (e.g. a pillar box or existing cable pit); and
• The DC negative return system which includes the negative feeder cables and buses, conduits
and pits from the substation up to and including the rail bonds.
The scope of this document does not include:
• Positive feeder cable supports and protection (armour) at the point of termination as well as
overhead switches and pillar boxes; and
• Remote negative cables (aerial or underground).
The requirements in this standard have been derived from the following sources:
• International and Australian Standards listed in section 6: Related legislation and documents
• Local subject matter experts within Yarra Trams and suppliers to Yarra Trams.
• PSU-2.6-SP-A-0001 rev 1.2 - General Design Requirements;
• PSU-2.6-SP-A-0016 rev 1.2 – DC Reactor and Harmonic Filter Specification;
• VRIOGS 010.3: Railway Traction Substation Design Standard Revision A 08/09/2009; and
• VRIOGS 010.4: Railway Traction Substation Construction Standard Revision A 08/09/2009.
The scope items outlined in Table 1, which were previously included in one or more of the above superseded
documents, are excluded from this standard and have been addressed in other Yarra Trams documents as
appropriate:
This standard applies to any party who is involved in the specification, design, construction, integration
and through life support of DC traction substations for Yarra Trams.
3 COMPLIANCE
Any party who is involved in the specification, design, construction, installation, test or commissioning of DC
traction substations for Yarra Trams shall fully comply with this standard.
Deviation from this standard is only permitted when a deviation or waiver has been formally requested and
approved by the Engineering Design Authority at Yarra Trams.
The Yarra Trams Engineering Change Management Procedure (CE-021-PR-0020) shall be followed in all
circumstances where change is proposed to this standard.
‘Shall’ statements are mandatory in the context of compliance with requirements stipulated in this standard.
‘Should’ statements are considerations in the context of compliance with requirements stipulated in this
standard.
‘Information’ statements provide additional content for clarification purposes only and are not requirements
in the context of compliance with this standard.
‘So far as is reasonably practicable’ statements must at a minimum result in the provision of a technical risk
assessment including proposed list of design controls to demonstrate compliance to this standard.
Any party who is involved in the specification, design, construction, installation, test or commissioning of DC
traction substations for Yarra Trams shall complete and return a statement of compliance for this standard.
Assessment of compliance shall be provided for each requirement, defined by one of three permissible
responses:
• Compliant;
• Partially compliant; or
• Non-compliant.
4 DC SUBSTATION REQUIREMENTS
4.1 General principals
4.1.1 Design principles
4.1.1.1 All design activity shall be undertaken by engineers with engineering design competency accepted
and delegated by Yarra Trams in accordance with the Engineering Design Authority Procedure (CE-
021-PR-0019).
4.1.1.2 The Designer shall identify discrepancies in referenced documentation and seek clarification from
Yarra Trams, as required.
Statement of compliance and deviation procedure
Information: As outlined in APPENDIX B – TENDER REQUIREMENTS of this standard and each equipment
specification, the Designer shall return a statement of compliance.
Yarra Trams recognises that it may not always be practicable to fully comply with all standards and
specifications at all times. In some conditions, a better outcome could be achieved for Yarra Trams through
an alternative approach. In such circumstances, an approval of deviation to the standard or specification shall
be sought. An approved deviation from the standard or specification is required before procurement,
implementation or construction. Deviation is only permitted when a deviation or waiver has been formally
requested and approved by the Engineering Design Authority at Yarra Trams. The deviation procedures below
shall be followed. The deviation procedures for ‘standards’ and ‘specifications’ are different and are clarified
below.
Deviation procedure for standards
4.1.1.3 The Designer shall follow the Deviation from Standards Procedure (CE-021-PR-0004).
Deviation procedure for specifications
4.1.1.4 The Designer shall:
• Return a statement of compliance to the specification, with the deviations highlighted;
• Submit the statement of compliance to the specification, with the deviations highlighted,
through the Engineering Change Management System; and
• Receive notification of approval or rejection through the Engineering Change Management
System.
4.1.4 Safety
4.1.4.1 The Designer shall comply with the requirements of Safety in Design (SS-021-PR-0001).
4.1.4.2 The Designer shall ensure that the design of the substation and its equipment incorporates safety
to humans for all aspects of the equipment life cycle.
4.1.4.3 The Designer shall consider the safety in design prompts in Table 2:
Table 2: Safety in design - Prompts
Guideword Prompts
Dual supply LV auxiliary supplies;
Foreign voltage On running rails;
On the overhead wiring system;
Fail-safe system Damage to equipment;
Human injury;
Inadvertent operation of critical equipment;
Interlocks;
SCADA logic;
Component reliability Known/unknown reliability;
Unpredictable failure modes;
Proven in service;
4.1.4.4 The following safety principles shall be followed in the design and operation of the substation:
• The system design shall require positive actions to be taken in a prescribed manner to either
begin or continue system operation;
• The safety of the system in the normal automatic operating mode shall not depend on the
correctness of actions or procedures used by operating personnel;
• There shall be no single-point failures in the system that can result in an unacceptable or
undesirable hazard condition;
• If one failure combines with a second failure, which can cause an unacceptable or undesirable
hazard condition, the first failure shall be detected and the system shall achieve a known safe
state before a second failure can occur;
• Software faults shall not cause an unacceptable or undesirable hazard condition;
• Interlocking shall be included in the design of equipment to prevent incorrect operation of
equipment and inadvertent access to hazardous environments within the substation (see
section 4.5.5); and
• The design shall ensure that isolated sections of an installation cannot be inadvertently
energised from parallel connected secondary sources (for example auxiliary transformers is
supplied from the star secondary winding of the rectifier transformer).
4.2.1 General
4.2.1.1 The DC traction substation shall contain the following major subsystems:
• Incoming high voltage power supply system;
• Rectification system;
• 750 V DC positive system;
• DC negative return system;
• Earthing system;
• Electrolysis mitigation system;
4.2.3.3 In multiple rectifier unit substations, it shall not be possible to close both HV supply circuit breakers
and the HV tie circuit breaker together and thus connect the two incoming HV AC supplies. However
the outputs of the rectifiers may be connected to the same 750 V DC bus.
Information: The Yarra Trams preference is to have a tie breaker between the incoming high voltage feeder
breakers. The designer should consult with the electricity supply authority to determine the authorised
configuration of the HV switchboard. If a tie breaker is allowed, it should not be possible to close both HV
supply circuit breakers and the HV tie circuit breaker together and thus connect the two incoming HV AC
supplies. The HV tie-breaker interlocking scheme should be approved by the electricity supply authority. The
outputs of the rectifiers may be connected to the same 750 V DC bus.
• Interfaces with the rectification system, control system, DC negative system and substation
earthing system.
4.2.4.2 The 750 V DC positive system shall comply with the Yarra Trams specifications for the following
components:
• 750 V DC Switchgear and Control;
• External Isolator;
• Transducer and Measurement Devices;
• Cables; and
• Outdoor Cable Pits.
Information: Unless stated otherwise, the Designer shall not be responsible for providing protection settings
for the 750 V DC positive system because these are highly dependent on tram operational requirements and
the overhead system configuration. Yarra Trams will provide the protection settings.
cables or connections shall still allow the normal designed return traction current to flow without causing
further damage.
• Buildings; and
• Outdoor Cable Pits.
4.3.1.10 The equipment shall be capable of carrying the short circuit current when a direct bolted short
circuit is applied across the positive and negative DC bus for the time required for the AC
overcurrent protection to effectively clear the fault, or 200ms, whichever is the longest.
4.4.1.2 The Designer shall prevent condensation in situations where equipment performance may be
compromised by its presence. Prevention methods may include, for example, special design of the
building or housing, suitable ventilation and heating of the substation or use of dehumidifying
equipment. External conduits and pits should be segregated form substation environments and
should not allow excessive moisture to enter the substation environment.
4.4.3 Noise
4.4.3.1 Unless stated otherwise, the Designer shall submit a Noise Report which provides evidence of
compliance and includes at least the following:
• Design considerations and plan for compliance;
• Noise level measurements on site prior to construction works commencing; and
• Noise level measurements on site upon completion of commissioning of the electrical
equipment.
Inside the DC traction substation
4.4.3.2 Noise levels inside the substation shall comply with all requirements of the Occupational Health
and Safety Act. In particular, the noise levels shall comply with the WorkSafe Victoria Compliance
code: Noise.
4.4.3.3 In addition to the industry defined limits, Yarra Trams have defined a reduced noise exposure level:
The noise exposure level inside a DC traction substation shall not exceed 75 dB(A) averaged over
an eight-hour period.
Outside the DC traction substation
4.4.3.4 Noise levels outside the substation shall comply with all requirements of the Environment
Protection Authority Victoria. In particular, the noise levels shall comply with the State Environment
Protection Policy (Control of Noise from Commerce, Industry and Trade) No. N-1.
• EN 50121-5.
4.4.4.3 All equipment and subsystems within a DC traction substation and the DC traction substation itself
shall comply with the following standards, regarding exposure limits for electromagnetic fields:
• Victorian Traction Industry Electrical Safety Rules (The Orange Book);
• ICNIRP Guidelines: Guidelines for limiting exposure to time-varying electric and magnetic fields
(1 Hz to 100 kHz); and
• ICNIRP Guidelines: Guidelines for limiting exposure to electric fields induced by movement of
the human body in a static magnetic field and by time-varying magnetic fields below 1 Hz.
Rated short
Rated
duration Minimum Minimum Non-
Highest lightning Ground
Nominal voltage, power phase-to- phase-to- flashover
voltage, impulse safety
Un frequency earth phase distance,
Um withstand clearance
[r.m.s] withstand clearance clearance N
[kV r.m.s] voltage, Up [mm]
voltage, Ud [mm] [mm] [mm]
[kV peak]
[kV r.m.s]
230 V / 400 V AC D D D D D D D
or;
240 V / 415 V AC
6.6 kV AC 7.2 20 60 90 105 100 2440
11 kV AC 12 28 95 160 185 175 2440
22 kV AC 24 50 150 280 325 310 2440
D: To be determined by the Designer.
4.5.2.2 The Designer is fully responsible for providing suitable insulations levels for the equipment and shall
verify the values in Table 4 and Table 5.
4.5.2.3 The nominal voltage of 6.6 kV is included for completeness but is a non-preferred voltage for new
installations. If the substation supply nominal voltage is 6.6 kV, the design of all HV AC equipment
shall allow the substation supply nominal voltage to be increased to 11 kV at a later date. The
applicable HV AC equipment includes, but is not limited to:
• HV AC switchgear and control;
• HV AC power cables;
• Metering equipment;
• Rectifier transformer; and
• Auxiliary transformer (if connected to HV AC).
4.5.2.4 Safety clearances for operational purposes and maintenance work shall be in accordance with Table
3.1 of AS 2067 and the Electrical Infrastructure Safety Rules (known as the Yellow Book) (IN-002-
ST-0002).
Document Number: CE-019-ST-0007 Document Author: Allen Tam
Version: 1 Document Authoriser: Greg Williams
Date Published: 20/03/2020 Doc ID: CDMS-313846386-5008
Page 17 of 47
Uncontrolled when printed
Infrastructure – Network Power – Substation – Design
and Construction
4.5.2.5 In accordance with clause 3.2 of AS 2067, the choice of the insulation levels should consider the
method of neutral earthing in the system and the characteristics and locations of overvoltage
limiting devices to be installed.
Information: If the Designer can prove to Yarra Trams that lower insulation levels can be achieved through
appropriate choice of surge protection, the rated lightning impulse withstand voltage requirements in Table
4 may be relaxed.
• The design shall provide for the connection of a substation main earth bar to the outside earth
grid. There shall be some means to visually and electrically confirm the connection of the
substation main earth bar to the external earth grid. The disconnection point for testing shall be
at the main earth bar. In accordance with clause B1.1 (f) of AS 2067, facilities should be provided
to test earth electrodes without disconnection of the earthing system from the energized
substation;
• The design shall provide for connection of earth grid to building reinforcing bars; and
• The Designer shall conduct all six field tests listed in clause 8.8 of AS 2067.
4.5.3.4 Unless stated otherwise, the Yarra Trams earthing system shall be separate from the Distribution
Network Service Provider earthing system.
4.5.3.5 In the Melbourne tram network, the 750 V DC system is unearthed, while the high voltage and low
voltage AC systems are earthed. Unless stated otherwise, the frame of 750 V DC cubicles and 750
V DC cable trays shall be connected to earth in accordance with Figure 1. The insulating material,
installed between the frame of 750 V DC cubicles and earth or the 750 V DC cable trays and earth,
shall provide an isolation resistance of at least 1 MΩ.
Information: Some older substation designs may have 750 V DC cubicles and/or cable trays bonded to the
negative return system, in contrast to Figure 1. The Designer shall pay careful attention to such installations
and shall consult Yarra Trams to discuss the 750 V DC cubicle and cable tray earthing and bonding principle.
750 V DC cubicle
earth
Figure 1: 750 V DC system earthing principle (Adapted from EN 50123-7-1 Figure 4a)
4.5.3.6 The Designer shall ensure that at all times, personnel in the vicinity of all substation equipment are
adequately protected from hazardous step and touch potentials and that there is sufficient physical
separation between equipment that is earthed and equipment that is connected to the 750 V DC
negative system so that substation personnel cannot inadvertently make contact with both types
of equipment at the same time.
Frame leakage protection relay
4.5.3.7 In accordance with Figure 1Figure 1, frame leakage protection relay(s) shall be provided and
connected between the following:
Document Number: CE-019-ST-0007 Document Author: Allen Tam
Version: 1 Document Authoriser: Greg Williams
Date Published: 20/03/2020 Doc ID: CDMS-313846386-5008
Page 19 of 47
Uncontrolled when printed
Infrastructure – Network Power – Substation – Design
and Construction
4.5.4 Protection
General requirements
4.5.4.1 Unless stated otherwise, the protection system shall comply with the requirements of the
equipment specifications and the following standards:
• HV AC protection system: AS 2067 and AS 3851; and
• 750 V DC protection system: EN 50123-1, EN 50123-2, EN 50123-7-1.
4.5.4.2 At all times, the primary consideration for the protection system shall be to protect persons
exposed to the traction power system (e.g. substation staff or members of the public). A secondary
consideration is to protect electrical equipment and a final consideration is to minimise delays to
operations.
4.5.4.3 Unless stated otherwise, in consultation with Yarra Trams, the Designer shall provide suitable
protection settings for all protective devices in the substation except those devices related to the
protection of the outgoing 750 V DC positive feeder cables (i.e. the normal scope shall include
settings for incoming high voltage supply, low voltage auxiliary supply, battery charger, rectification
system, 750 V DC rectifier and bus tie circuit breakers, 750 V DC positive bus, but excludes 750 V
DC feeder circuit breakers and the associated protection relays). The protection settings shall not
interfere with the design output capability of the substation.
4.5.4.4 The Designer shall be responsible for meeting the protection coordination requirements of the
relevant Distribution Network Service Provider with respect to the incoming high voltage supply.
4.5.4.5 All protection wiring between equipment shall be hardwired.
4.5.4.6 Where an earthing design relies on fault clearing times and equipment maintenance requirements
the designer shall clearly define the requirements for incorporation into operational and
maintenance systems.
Information: The specific behaviour of the protection system will depend on the system configuration and
other requirements defined in the specifications and Scope of Works. In particular, the specifications and/or
Scope of Works shall nominate which equipment failure scenarios allow automatic restoration of power
Document Number: CE-019-ST-0007 Document Author: Allen Tam
Version: 1 Document Authoriser: Greg Williams
Date Published: 20/03/2020 Doc ID: CDMS-313846386-5008
Page 20 of 47
Uncontrolled when printed
Infrastructure – Network Power – Substation – Design
and Construction
(auto-reclose) and the conditions under which power may be restored. However, the general application of
these requirements is outlined in the two protection coordination scenarios presented in Figure 2.
In Figure 2 – Scenario 1, there is a fault on one of the rectifiers (e.g. a diode failure). In this situation, the HV
rectifier circuit breaker 1 and the DC rectifier circuit breaker 1 should trip to isolate the fault from the AC and
DC systems. If the HV bus tie circuit breaker is closed, then it should also trip to prevent the fault being fed via
the second-high voltage supply. If it is not possible to back feed from the auxiliary transformer, this is the
minimum required to isolate the fault. Unless there is a failure in one of these circuit breakers, the remaining
AC and DC circuit breakers should remain closed which means that the equipment outage is limited to the
failed rectifier and both the 750 V DC positive bus and second rectifier remain unaffected.
In Figure 2 – Scenario 2, there is a fault on one of the outgoing 750 V DC feeder cables. In this situation,
because of the proximity of the fault to the substation, it may not be possible to discriminate between this
fault and a 750 V DC bus fault. In this case, if it is not practicable to achieve fault discrimination on the DC
system, it is acceptable for all the DC circuit breakers to trip thereby isolating the 750 V DC bus temporarily.
If it is practicable, the AC protection should not operate unless there is a failure in one of the DC rectifier circuit
breakers. Once the bus has been isolated, if the specifications or Scope of Works allow power to be restored
automatically (i.e. auto reclose), each circuit breaker will attempt to close and the circuit breaker with the
Document Number: CE-019-ST-0007 Document Author: Allen Tam
Version: 1 Document Authoriser: Greg Williams
Date Published: 20/03/2020 Doc ID: CDMS-313846386-5008
Page 21 of 47
Uncontrolled when printed
Infrastructure – Network Power – Substation – Design
and Construction
faulty cable will fail to close. This behaviour interrupts tram operations momentarily, and then limits the
equipment taken out of service to the faulty DC feeder cable so that the remainder of the system can continue
operating normally.
Lightning and surge protection
4.5.4.7 Unless stated otherwise, the lightning and surge protection system shall comply with the
equipment specifications, the requirements of Table 4 and the following standards:
• AC surge protection system: AS 2067, AS 1768 (lightning protection for buildings), AS 1307.2 (AC
surge protection devices); and
• 750 V DC surge protection system: EN 50124-1, EN 50124-2, EN 50526-1.
4.5.4.8 Lightning and surge protection shall be provided for all equipment that is exposed to the risk of
lightning or surges (but multiple items of equipment might be protected by one device as part of a
zoned system). The need for protection against lightning surges is essential unless the location
provides an inherent zone of protection from lightning surges.
4.5.4.9 Lightning and surge protection systems shall present a low risk to workers in the event of a nearby
or distant lightning strike. As a result, the safety of personnel working on or near the surge
protective equipment shall be considered when designing the layout of the surge protective
equipment or the route for earth conductors.
4.5.4.10 Surge protected wiring shall be segregated from non-surge protected wiring to prevent coupling of
surges between the wiring. Earth wires are to be considered as non-surge protected wiring. The
amount of segregation shall be suitable for the expected level of surge on the non-protected wiring.
4.5.4.11 When considering lightning and surge protection, the equipment selection principles shall be as
follows:
• shall be fit for purpose;
• shall match the insulation coordination requirements and the detailed equipment specifications
for all equipment supplying the surge zone; and
• surges shall be kept within the tolerances of the equipment being protected.
4.5.4.12 All entry points for surges shall be considered. Lightning and/or surges occur, enter, or are induced
into the system through one or several of the following:
• HV AC system;
• LV AC system;
• 750 V DC system;
• DC negative system;
• Communication lines;
• Earth grid; and
• Electrolysis system.
4.5.5 Interlocking
4.5.5.1 For the purpose of this standard and the substation equipment specifications, interlocking shall be
defined as an electrical, electronic or mechanical device or system which prevents an element from
changing state due to the state(s) of another element(s), and vice versa. Figure 3 provides an
example of the interlocking principles for an earth switch in withdrawable HV AC switchgear. The
following definitions shall apply:
HVCB = Racked in
S0
ES = Open
Figure 3: Interlocking – General principles and worked example– High voltage earth switch
4.5.7.2 The equipment SCADA indication shall be provided by means of dedicated and electrically isolated
normally open and normally closed auxiliary contacts of switchgear, and on and off contact of
indication relays.
4.5.7.3 The SCADA control will be provided from a Remote Terminal Unit (RTU) located in the SCADA
cubicle.
4.5.7.4 The minimum equipment SCADA control and indication requirements are outlined in each
equipment specification. Figure 4 outlines how to interpret these requirements in each
specification and applicable definitions.
TBC
4.5.7.5 The substation shall not be a fully digital substation according to IEC 61850. The substation shall
adhere to Yarra Trams’ current philosophy which includes a combination of hardwired and digital
connections between equipment, according to the following principles:
• Hardwired connections use: Protection functionality between equipment, interlocking
functionality between equipment, ‘critical’ SCADA indication and all equipment SCADA control;
and
• Digital connections use: ‘Non-critical’ SCADA indication.
4.5.7.6 For digital SCADA points, the following communication protocols are supported by Yarra Trams and
are listed in order of preference:
• DNP3.0 TCP/IP;
• Modbus TCP/IP; and
• Modbus Serial (only applicable for legacy systems).
4.5.7.7 As outlined in section 4.8 of this document, the Designer shall submit the following documentation
to Yarra Trams to facilitate the SCADA integration and commissioning:
• SCADA and communications system overview drawing: This drawing would include details such
as, but not limited to, all network connected devices and the network topology.
• SCADA equipment interconnection design and drawings:
Document Number: CE-019-ST-0007 Document Author: Allen Tam
Version: 1 Document Authoriser: Greg Williams
Date Published: 20/03/2020 Doc ID: CDMS-313846386-5008
Page 24 of 47
Uncontrolled when printed
Infrastructure – Network Power – Substation – Design
and Construction
• SCADA points description excel sheet: Yarra Trams shall provide an excel template to the
Designer which describes the ‘Standard’ SCADA configuration.
4.5.9 Efficiency
4.5.9.1 In accordance with APPENDIX D – ECO-FRIENDLY DESIGN, the Designer shall consider the substation
energy efficiency. The energy efficiency is defined as the ratio of the 750 V DC output power to the
HV AC input power. The target substation energy efficiency, as a function of the DC output current
of the substation rectifier(s), is given in Table 6.
Table 6: Target substation energy efficiency
• Grouping arrangement of equipment (i.e. similar or related items should be grouped together
and ordered in a logical sequence from input to output with a minimum number of crossovers);
• Sufficient clearances from equipment to building walls, fences and other equipment for
installation, maintenance, inspection and removal requirements;
• Maintenance of consumable equipment and fittings should avoid the use of ladders or lifting
devices; and
• Operation of all switchgear from ground level without the need to work off platforms.
Information: Yarra Trams are in the process of developing a standard DC traction substation design
equipment layout, which will be made available on PTV DMS.
4.5.10.2 Requirements for the building and equipment layout are given in the Building Specification (IN-021-
ST-0006).
4.6.2 Noise
4.6.2.1 The Designer shall comply with all requirements of the Environment Protection Authority Victoria.
4.6.3 Residents
4.6.3.1 The Designer shall notify residents of all work to occur during construction and potential impacts
including, but not limited to:
• Noise level during construction;
• Impact on traffic flow;
• Safety of commuters;
• Councils in the case of council trees or trees under environmental protection schemes; and
• Impact on any bushes/trees in the vicinity.
operation and reactive maintenance of any in service equipment while the construction is
occurring. Construction plans are to be maintained on site and kept up to date on progress.
4.6.8 Training
4.6.8.1 The Designer shall train allocated Yarra Trams representatives in all aspects of the new electrical
installation. All operational, technical, safety and environmental aspects of the new installation
shall be covered during the training. The technical training shall involve going through the as
constructed drawings, operator instructions and a site visit.
4.6.8.2 The Designer shall run two training sessions on different days (per substation), to accommodate
the availability of Yarra Trams representatives.
4.6.8.3 Training shall be completed before the substation is placed into service.
4.6.8.4 Where ever possible the equipment operation will be aligned to existing operating systems within
Yarra Trams.
Description Requirement
Operational availability1, Ao ≥ 0.99
Design life2 ≥ 30 years
1
Operational availability is the probability that an item will operate satisfactorily at a given point in time when
used in an actual or realistic operating and support environment. It includes, but is not limited to:
• Undetected fault down time;
• Administrative down time;
• Logistics down time;
• Preventive maintenance down time; and
• Corrective maintenance down time.
Operational availability is a measure which extends the definition of availability to elements controlled by
project managers, manufacturers and logistics companies. Elements may include the quantity and proximity
of spares, tools and maintenance staff availability. In accordance with EN 61703, operational availability shall
be defined by the expression:
Ao = MUT / (MUT + MDT)
2The design life of electronic devices shall be ≥ 15 years.
Information: Definition and detailed guidance on mathematical treatment of RAMS terms is given in EN
61703.
4.7.1.3 Unless stated otherwise, the Designer shall submit a RAMS Report which provides evidence of
compliance. The report shall at least include the following:
• Consideration of how the operating conditions outlined in section 4.4.1 affect the RAMS of the
substation;
• Details of the maintenance regimes required to achieve the reliability requirements stated; and
• Consideration of how electronic devices will be replaced at the end of their design life (e.g. 15
years) to ensure the design life of the substation (e.g. 30 years).
4.7.1.4 The following substation specific definitions shall apply:
• For a dual rectifier substation, the substation is only considered to be in down time when both
rectifiers are at fault;
• The design shall nominate and ensure maximum reliability for redundant systems;
• The design phase shall consider the following reliability objectives:
o MTBF higher than 12,000 hours for the substation.
o MTBF higher than 50,000 hours for each cubicle/panel.
4.7.1.5 The types of maintenance to support the substation are:
• Preventive maintenance; and
• Corrective maintenance.
Document Number: CE-019-ST-0007 Document Author: Allen Tam
Version: 1 Document Authoriser: Greg Williams
Date Published: 20/03/2020 Doc ID: CDMS-313846386-5008
Page 28 of 47
Uncontrolled when printed
Infrastructure – Network Power – Substation – Design
and Construction
4.7.1.6 Preventive maintenance tasks shall be detailed in the Technical Maintenance Plan of the
substation.
4.7.1.7 The Designer shall request information from Yarra Trams as necessary to calculate the substation
operational availability. Information requests may include:
• MTR values for equipment;
• MAD values for maintenance; or
• Maintenance staff availability;
Information: A Line-Replaceable Unit (LRU) is a part of a system that is designed to be replaced quickly at an
operating location (e.g. a diode or a snubber in a rectifier cubicle). The Yarra Trams LRU MTR values are ‘30
minutes for an LRU whose weight is lower than 20 kg’ and ‘4 hours for an LRU whose weight is higher than
20 kg’.
Project completion
Detailed design
Documentation
energisation)
Preliminary
Systems
design
design
Statement of compliance
Substation single-line diagram ✓ ✓ ✓1
Substation equipment layout and ✓ ✓ ✓1
schedule layout
The detailed configuration of ✓ ✓ ✓1
electrical equipment to be installed
(e.g. number of rectifiers,
transformers, circuit breakers,
feeder panels, battery charger, etc)
Document Number: CE-019-ST-0007 Document Author: Allen Tam
Version: 1 Document Authoriser: Greg Williams
Date Published: 20/03/2020 Doc ID: CDMS-313846386-5008
Page 29 of 47
Uncontrolled when printed
Infrastructure – Network Power – Substation – Design
and Construction
Commissioning (prior to
Project completion
Detailed design
Documentation
energisation)
Preliminary
Systems
design
design
Electrolysis mitigation requirements ✓ ✓ ✓1
Substation integration design
Full details of equipment selection ✓ ✓1
and bill of materials
Main and auxiliary circuit diagrams ✓ ✓1
Equipment interconnection design ✓ ✓1
and drawings
SCADA and communications system ✓ ✓1
overview drawing
SCADA equipment interconnection ✓ ✓1
design and drawings
SCADA points description excel sheet ✓ ✓1
Equipment earthing and bonding ✓ ✓1
connections, design and drawings
Negative, earthing and electrolysis ✓ ✓1
busbars design and drawings
Protection and control system design ✓ ✓1
and drawings
Interlocking system design and
drawings
Cable and wiring schedules ✓ ✓
Design reports
General report (including Equipment ✓ ✓
rating calculations, technical
specifications for the substation and
each individual item of equipment)
Protection report (including fault ✓ ✓
calculations, protection
coordination)
Noise report (see clause 4.4.3.1) ✓
EMC report (see clause 4.4.4.1) ✓
Earthing report (see clause 4.5.3.2) ✓ ✓
RAMS report (see clause 4.7.1.3)
Testing and commissioning
Commissioning (prior to
Project completion
Detailed design
Documentation
energisation)
Preliminary
Systems
design
design
Test and commissioning plans ✓2 ✓ ✓
Application for approval to place ✓ ✓
electrical installation into service
Certificate of electrical safety ✓ ✓
Installation, operation and ✓ 2
✓
maintenance manual(s)
Operation manual(s) ✓2 ✓
Maintenance manual(s) ✓ 2
✓
Technical maintenance plan ✓2 ✓
Calibration certificates (type test ✓
certificates, NATA certification of
metering equipment, factory and
commissioning test overcurrent
calibration charts for the full range of
all settings for each DC circuit
breaker supplied);
4.8.1.2 The Designer shall be solely responsible for the creation, supply and certification of all new
drawings and modifications to existing drawings where necessary.
4.8.1.3 All drawings shall be technically and functionally correct, accurately reflecting the installed
equipment and associated circuits.
4.8.1.4 Documentation of the design of equipment, assemblies or installations shall be supplied to Yarra
Trams at each design step for review and approval, as part of the gate process. The main purpose
of the review and approval gate processes is to determine that the design is compliant with the
technical standards and specifications.
Installation, operation and maintenance manuals:
4.8.1.5 The Designer shall provide installation, operation and maintenance manuals for all substation
equipment. The manuals shall at least include a description of all the servicing activities, the
overhaul instructions, adjustments procedures, changing components for repairs, fault finding
procedures, any software programs (where a PLC/IED is utilized), a complete set of as-built
drawings and a comprehensible spare parts list for the electrical equipment.
Technical maintenance plan:
4.8.1.6 The Designer shall be solely responsible for the creation, supply and certification of the technical
maintenance plan for a new substation and the modifications to existing substation technical
maintenance plans where necessary (e.g. replacing a single piece of equipment in a substation).
The technical maintenance plan shall at least include:
• A summarised maintenance policy for the equipment;
Document Number: CE-019-ST-0007 Document Author: Allen Tam
Version: 1 Document Authoriser: Greg Williams
Date Published: 20/03/2020 Doc ID: CDMS-313846386-5008
Page 31 of 47
Uncontrolled when printed
Infrastructure – Network Power – Substation – Design
and Construction
Figure 5: Typical single line diagram of the DC traction substation – Single rectifier substation (LV auxiliary supply option 1)
Document Number: CE-019-ST-0007 Document Author: Allen Tam
Version: 1 Document Authoriser: Greg Williams
Date Published: 20/03/2020 Doc ID: CDMS-313846386-5008
Page 33 of 47
Uncontrolled when printed
Infrastructure – Network Power – Substation – Design
and Construction
APPENDIX A – GLOSSARY
Table 11: Glossary - Words
Word Definition
Application for approval to Internal Yarra Trams document to be submitted prior to energisation.
place electrical installation
into service
Contact wire Overhead cable used to transmit electrical energy from the substations to the
trams and in direct contact with the pantograph of each tram.
Control voltage See “Reliable auxiliary supply”. The terms “Control voltage” and “Reliable
auxiliary supply” are used interchangeably.
Corrective maintenance Maintenance carried out after fault detection to effect restoration.
Demand “Demand” means the active power or apparent power consumed at point of
common coupling integrated over fifteen or thirty minute period.
Designer The party who is fully responsible for the suitability and compliance of the
design of the DC traction substation and all its equipment and subsystems.
Design life The period of time during which the item/system is designed to work within its
parameters. It is the length of time between placement into service and
disposal of the item/system.
Feeder Panel The term “Panel” or “Feeder Panel” means any enclosed assembly comprising
a DC feeder circuit breaker, together with any associated protection and
control equipment for the purpose of operating trams.
Life cycle Series of identifiable stages through which an item or system goes, from its
conception to disposal.
Panel See “Feeder Panel”.
Preventive maintenance Maintenance carried out to mitigate degradation and reduce the probability of
failure.
Reliable auxiliary supply Supply voltage of closing and opening devices and of auxiliary and control
circuits.
Scope of Works The Scope of Works is a key document that defines the specific project-related
requirements such as the configuration and rating of equipment to be installed.
It prevails over all the specifications.
Specifications Set of documents that define the general requirements applicable to each item
of equipment or subsystem to be installed within a DC traction substation.
Substation An electrical installation equipped to transform and rectify HV AC supplies
before distributing it through 750 V DC circuit breakers to the overhead system.
Tie station An electrical installation not equipped to transform and rectify HV AC supplies
but equipped with 750 V DC circuit breakers to distribute traction power
through the overhead system.
Trolley wire See “Contact wire”.
Table 12: Glossary - Abbreviations
Abbreviation Definition
AC Alternating Current
Document Number: CE-019-ST-0007 Document Author: Allen Tam
Version: 1 Document Authoriser: Greg Williams
Date Published: 20/03/2020 Doc ID: CDMS-313846386-5008
Page 37 of 47
Uncontrolled when printed
Infrastructure – Network Power – Substation – Design
and Construction
Abbreviation Definition
DC Direct Current
DNSP Distribution Network Service Provider
ECM Engineering Change Management (internal Yarra Trams abbreviation)
EMC Electromagnetic Compatibility
EMS Engineering Management System (internal Yarra Trams abbreviation)
EPD Environmental Product Declaration
ES Earth Switch
HV “High Voltage” means a nominal voltage exceeding 1000 V AC or exceeding
1500 V DC
IED Intelligent Electronic Device
IP Ingress Protection Rating (or International Protection Rating)
LCA Life Cycle Assessment
LCC Life Cycle Cost
LRU Line-Replaceable Unit
LV “Low Voltage” means a nominal voltage exceeding 50 V AC / 120 V DC but not
exceeding 1000 V AC / 1500 V DC
MAD Mean Administrative Delay
MDT Mean Down Time
MRT Mean Repair Time
MTBF Mean (operating) Time Between Failures (for repairable items)
MTR Mean Time to Repair
MUT Mean Up Time
NATA National Association of Testing Authorities, Australia
NSS Negative Shorting Switch
OHW Overhead Wiring
PCB Polychlorinated Biphenyl
POC Power and Operations Centre
PLC Programmable Logic Controller
PPE Personal Protective Equipment
PTV Public Transport of Victoria
RMS Root Mean Square
RTU Remote Terminal Unit
SCADA Supervisory Control and Data Acquisition
Term used to describe a system of remote control and indication of substation
equipment. SCADA systems involve one or more Control rooms,
communication systems and substation-based Remote Terminal Units
SF6 Sulphur Hexafluoride
To Be Confirmed. These requirements may be included in later versions of the
TBC
standard.
Document Number: CE-019-ST-0007 Document Author: Allen Tam
Version: 1 Document Authoriser: Greg Williams
Date Published: 20/03/2020 Doc ID: CDMS-313846386-5008
Page 38 of 47
Uncontrolled when printed
Infrastructure – Network Power – Substation – Design
and Construction
Abbreviation Definition
TDU Thyristor Drainage Unit
TMP Technical Maintenance Plan
VLD Voltage Limiting Device
VRIOG The Victorian Rail Industry Operators’ Group comprising the following
members:
VicTrack
V/Line Passenger
Metro Trains Melbourne
Yarra Trams
Australian Rail Track Corporation
Public Transport Division of the Department of Transport
TPS Traction Power System. Assets required to supply, switch and protect the 750
V DC supplies to electrified trams.
VEC Victorian Electrolysis Committee
Description Requirement
Substation system level design1
1
Refer to the Yarra Trams Standard, Infrastructure - Network Power - Traction Power – Design and
Construction CE-021-ST-0037) for details.
Statement of compliance
The Designer shall return a statement of compliance to this standard. The Yarra Trams statement of
compliance template, which shall be used for the substation standard and equipment specifications, is
embedded below.
Statement of
Compliance Template.xlsx
• Environment Friendliness.
APPENDIX C – INNOVATION
Innovative solutions such as energy efficiency solutions should be highly considered.
Examples of innovative solutions are:
• Integrated transformer rectifier (rectifier transformer and rectifier converter combined into a
single unit);
• Controlled rectifier(s);
• Wayside energy storage system(s);
• Inverter(s) connected in parallel with the rectifier(s); and
• 4-quadrant rectifier(s) entirely controlled.
If such solutions are used, they shall be compliant with the relevant reference documents listed in section 6.
These solutions shall be proven in-service, rather than untried principles or equipment.
Cardinal
Street name
Station
complex
Albert Park Danks
Street & Danks St Sub
N N N Y(DS) N N DS DS-SS
Victoria Station
Avenue
E2 Electrical sections
The electrical section naming convention shall adhere to the following rules:
• If the electrical section is only connected to one substation, the electrical section name shall be
‘Substation name Panel number’. E.g. XX1
• If the electrical section is connected to two substations, the electrical section name shall be
‘Substation 1 name Panel number. Substation 2 name Panel number’, as shown in Table 15.
‘Substation 1’ is defined as the substation which is located closest to Melbourne’s General Post
Office and ‘Substation 2’ is defined as the substation which is located furthest from Melbourne’s
General Post Office. E.g. XX1.YY2
Table 15: Asset naming conventions: Electrical sections
Option XX 1 . YY 2
Position 1 2 . 3 4
E3 Feeder cables
The feeder cable naming convention shall adhere to the following rules:
• If the feeder cable is connected between the substation and the nearest point of connection to
the section (usually a tap to a trolley), the feeder cable name shall be as shown in Table 16. E.g.
SY 5 0.6 U.G.
• If the feeder cable is connected between the nearest point of connection to the section (usually
a tap to a trolley) and the electrical section, the feeder cable name shall be as shown in Table
17. E.g. XX1.YY2 0.6 O.H.
Table 16: Asset naming conventions: Feeder cables (1)
Position 1 2 3 4
Position 1 2 3
E4 Substation equipment
Unless stated otherwise, the substation equipment naming convention shall adhere to the descriptions
provided in Table 18.
Table 18: Asset naming conventions: Substation equipment
Designation Description
+AT_ Auxiliary transformer
+CLD Current Limiting Device
+DA_ DC feeder
+DB_ DC rectifier breaker
+DC_ DC auxiliary feeder
+EMC Electrolysis mitigation cubicle
+FIP Fire indicator panel
+G0_ Generator plug box
+IP_ External isolator
+KA_ SCADA panel
+L0_ HV switchgear
+LA_ Negative cubicle
+MET Metering cubicle
+SA_ LV switchboard
+T0_ Rectifier transformer
+VA_ Rectifier converter
+VCC VicTrack communications cubicle
VESDA Very early smoke detection apparatus
+VLD Voltage limiting device
+ZA_ Battery and battery charger
NOTE: The symbol “_” is used where the general equipment designation should be incrementally increased
according to the number of equivalent units in the substation. E.g. “+DA_” is the general equipment
designation for DC feeder panels. For a substation with three DC feeder panels, the equipment
designations would be “+DA1”, “+DA2” and “+DA3” respectively.