2. To identify and maintain the proper precedence relationship between activities those
are not connected by event, we introduce
(a). Parallel Activity
(b). Dummy Activity
(c). Sequential Activity
(d). None of the above
7. Two of the first steps of OR process encompass the actual use of OR techniques. These
steps are
(a). Model Construction and Model Solution
(b). Observation and Implementation
(c). Definition of the problem and Model Solution
(d). Model Solution and Implementation of results
8. Let FS = Free Slack, TS = Total Slack, INDS = Independent Slack, then which relation
is true
(a). TS ≤ FS
(b). INDS ≤ FS
(c). FS ≤ TS
(d). Both (b) & (c)
9. Best possible time estimate that a given activity would take under normal conditions
which often exist, is called
(a). Most Likely time estimate
(b). Pessimistic time estimate
(c). Smallest time estimate
(d). None of the above
► Backward pass
► No time, no resources
► None of these
If an activity consumes no time and no resources then this activity is called __________.
► dummy activity
► sequential activity
► critical activity
► cyclic activity
► Holding cost
► Set up cost
► Item cost
► Redundancy
► Cycling
► Looping
► Merging
► Redundancy
► Dangling
► Cycling
► Dummy
► Distribution of fertilizer
► PERT
► 12
►2
►4
► 144
For an activity if optimistic time, most likely time estimate and pessimistic time
estimate are 3, 6 and 15 respectively then expected time is
►4
►3
►7
► 20
► Zero
► Minimum
► Maximum
► Average
Activity definition refers to the process of parsing a project into a number of individual
tasks which must be completed ___________ the deliverables can be considered
completed. Activity definitions rely on a number of specific input processes.
► before
► after
A forward pass is used to determine and calculate the ________________ dates, through
utilization of a previously specified start date.
5
B
3
7
► Yes.
► No.
Total cost per period = Item cost + Order cost + Holding cost + _____________.
► Shortage cost
K Z ( )
Where K is called service factor.
2
►
2
►
2
3
►
3
2
►