QSEV KT MCQ Question RS
QSEV KT MCQ Question RS
QSEV KT MCQ Question RS
Answer: Option A
Answer: Option D
Answer: Option C
6. The following item of earth work is not measured separately.
(A) Brick work
(B) Site clearance
(C) Plastering work
(D) concrete work
Answer: Option B
Answer: Option D
Module -02
Answer: Option C
Answer: Option A
Answer: Option B
12. 6. For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is
(A) 0.90 m3
(B) 0.94 m3
(C) 0.98 m3
(D) 1.00 m3
Answer: Option B
Answer: Option A
Answer: Option A
Answer: Option B
Module -03
16. Referring of given figure, pick up the correct statement from the following:
17.
(A) The total length of centre line is 23.2 m
(B) Length of long wall out-to-out is 8.80 m
(C) Length of short walls in-to-in is 5.20 m
(D) The total length of centre line is 21.2 m
Answer: Option A
Answer: Option B
Answer: Option A
20. Pick up the item of work not included in the plinth area estimate
(A) Wall thickness
(B) Room area
(C) W.C. area
(D) Courtyard area
Answer: Option D
21. What is the Standard Lead distance
(a) 30m
(b) 20m
(c) 10m
(d) 40m
Ans - A
22. What is Lift
(a) Horizontal Distance
(b) Vertical distance
(c) Oblique Distance
(d) Angular distance
Ans- B
23. What is Standard Distance of Lift
(a) 1.5 m
(b) 2m
(c) 3m
(d) 4m
Ans - A
Ans- A
Module -04
24. If the formation level of a highway has a uniform gradient for a particular length, and the ground is
also having a longitudinal slope, the earthwork may be calculated by
(A) Mid-section formula
(B) Center Line Methods
(C) Long wall short wall methods
(D) Rate Analysis Methods
Answer: Option A
Answer: Option A
26. The correct Prismoidal formula for volume is
(A) D [first area + last area + Ʃ Even area + 2 Ʃ odd areas]
(B) D/3 [first area + last area + 4 Ʃ Even area + 2 Ʃ odd areas]
(C) D/3 [first area + last area + 2 Ʃ Even area + 4 Ʃ odd areas]
(D) D/6 [first area + last area + 2 ∑ Even area + 4 ∑ odd areas]
Answer: Option B
27. Formula for Mean Area method for finding out the quantity
(a) (A1+A2+A3) / 2
(b) (A1+A2) / 3
(c) (A1+A2) / 2
(d) (A1+A2+A3) / 4
Ans – C
28. Which of Following Prismoidal formula is correct for Less no. of chain age
(a) L/6 (A1+A2+4Am )
(b) L/4 (A1+A2+4Am )
(c) L/3 (A1+A2+4Am )
(d) L/6 (A1+A2+2Am )
Ans – A
29. Formula for findint he Depth of Earth work
(a) G.L.- F.L.
(b) F.L. – G.L.
(c) R.L. – F.L.
(d) R.L. – G.L.
Ans – B
30. Trapezoidal formula for Earthwork
(a) L/3(First Area + Last Area +2( Remaining Area )
(b) L/2(First Area + Last Area +2( Remaining Area )
(c) L/4(First Area + Last Area +4( Remaining Area )
(d) L/6(First Area + Last Area +2( Remaining Area )
Ans - B
31. Formula for finding the Next chainage F.L.
(a) F.L. of Previous Chainage +/- (1/ Gradient )x Chainage Difference
(b) F.L. of Current Chainage +/- (1/ Gradient )x Chainage Difference
(c) F.L. of Previous to previous Chainage +/- (1/ Gradient )x Chainage Difference
(d) F.L. of Previous Chainage +/- (1/ Gradient )x Chainage Level
Ans – A
Module -05
32. A voluntary arrangement between two or more parties that is enforceable by law as a binding
legal agreement is known as __________
(a) Job
(b) Loan
(c) Contract
(d) Mutual fund
Ans- C
33. Which tender allows anyone to submit a tender to supply the goods or services that are
required?
(a) Selective tendering
(b) Framework tendering
(c) Open tendering
(d) Close tendering
Ans- C
38. _____________ is the technique of estimating or determining the fair price or value
of a property such as a building, a factory, other engineering structures of various
types.
(a) Depreciation
(b) capital value
(c) valuation
(d) taxation
Ans- C
39. An old building has been purchased by a person at a cost of Rs.30000/- excluding
the cost of the land. Calculate the amount of annual sinking fund at 4% interest
assuming the future lie of the building as 20 years and the scrap value of the building
as 10% of the cost of purchase.
(a) Rs.979.7
(b) Rs.4387.20
(c) Rs.107.20
(d) Rs.907.20
Ans- D
40. A property fetches a net annual income of Rs.900 deducting all outgoings. Workout
the capitalized value of the property if the rate of interest is 6% per annum.
a) Rs.67003.00
b) Rs.189003.00
c) Rs.45603.00
d) Rs.15003.00
Ans- D