Lecture 4
Lecture 4
Evaluation
[MPM6133]
Lecture 4
4 November 2021
INTRODUCTION
3
Techniques
5
Advantages of Scheduling Techniques
• Help management decide how to use its resources to achieve time and
cost goals.
• Provide visibility & enable management to control “one-of-a-kind”
programs.
• Help management evaluate alternatives, & facilitate “what if ”
exercises
• Provide a basis for obtaining facts for decision-making.
• Help to determine manpower, material, and capital requirements, as
well as to provide a means for checking progress.
• Provide the basic structure for reporting information.
• Reveal interdependencies of activities.
• Identify the longest path or critical paths.
• Aid in scheduling risk analysis.
6
Program/Project Evaluation & Review
Technique (PERT)
7
Drawing the project network (AOA)
8
Coming Up!!
✓PERT
Program/Project Evaluation & Review
Technique (PERT)
◼ Pessimistic Time (tp ) - the longest time that an activity might require.
This time assumes that everything will not go according to plan and
maximum difficulties will develop.
◼ Most Likely Time (tm ) - the completion time having the highest
probability. Note that this time is different from the expected time
◼ Optimistic Time (to ) - generally the shortest time in which the activity
can be completed. It is common practice to specify optimistic times to be
three standard deviations from the mean so that there is approximately
a 1% chance that the activity will be completed within the optimistic
time.
10
BETA PROBABILITY DISTRIBUTION WITH
THREE TIME ESTIMATES
11
Program/Project Evaluation & Review
Technique (PERT)
12
EXAMPLE
Under strict deadline from her bosses, Williams needs to be sure that installation
of the filtering system progresses smoothly and on time.
Milwaukee Paper has identified the eight activities that need to be performed in
order for the project to be completed. When the project begins, two activities
can be simultaneously started: building the internal components for the device
(activity A) and the modifications necessary for the floor and roof (activity B).
The construction of the collection stack (activity C) can begin when the
internal components are completed. Pouring the concrete floor and
installation of the frame (activity D) can be started as soon as the internal
components are completed and the roof and floor have been modified.
14
EXAMPLE
After the collection stack has been constructed, two activities can begin:
building the high-temperature burner (activity E) and installing the pollution
control system (activity F).
The air pollution device can be installed (activity G) after the concrete floor
has been poured, the frame has been installed, and the high-temperature
burner has been built. Finally, after the control system and pollution device
have been installed, the system can be inspected and tested (activity H).
15
PERT : EXAMPLE
PERT : EXAMPLE
PERT : EXAMPLE
NEED TO CALCULATE
19
EXPECTED TIMES AND VARIANCES
20
Probability of Project Completion
21
Ship being built at the Hyundai shipyard,
Asia’s largest shipbuilder, in Korea.
22
VARIANCE & STANDARD DEVIATION FOR
MILWAUKEE PAPER
23
PROBABILITY OF COMPLETING A PROJECT ON TIME
Find the probability that her project will be finished on or before the
16-week Earth Day deadline.
We needs to determine the appropriate area under the
normal curve. This is the area to the left of the 16th week.
where Z is the number of standard deviations the due date or target date lies
from the mean or expected date.
24
PROBABILITY OF COMPLETING A
PROJECT ON TIME
25
PROBABILITY OF COMPLETING A PROJECT ON TIME
26
PROBABILITY OF 99% COMPLETING A PROJECT
✓ We wants to find the due date that gives her company’s project a 99%
chance of on-time completion.
27
PROBABILITY OF COMPLETING A
PROJECT ON TIME
28
PROBABILITY OF 99% COMPLETING A PROJECT
29
Cost-Time Trade-Offs and Project Crashing
31
Crashing Project Steps:
32