KLRCA SFC Without-Quantities
KLRCA SFC Without-Quantities
KLRCA SFC Without-Quantities
[Without Quantities]
2017 Edition
Issued by
First published: 2017
Bangunan Sulaiman,
Jalan Sultan Hishamuddin,
50000 Kuala Lumpur
Malaysia
www.klrca.org
ISBN: 978-983-42603-3-0
ARTICLES OF AGREEMENT
PRELIMINARY RECITALS
ARTICLES
Article 1 Contractor’s Obligations 2
Article 2 Contract Documents 2
Article 3 Contract Sum 2
Article 4 Architect 3
Article 5 Engineer 3
Article 6 Quantity Surveyor 3
Article 7 Specialist Consultant 4
Article 8 Definitions 4
Article 9 Meanings 10
ATTESTATION/SIGNATORIES OF THE PARTIES 11
THE CONDITIONS OF CONTRACT
1.0 Contractor’s General Obligations 12
1.1 Completion of Works in Accordance with the Contract 12
1.2 Site Operations, Temporary Works and Methods of Construction 12
1.3 Contractor’s Design, Responsibilities and Design Guarantee Bond 12
1.4 Discrepancy or Divergence between Contract Documents 13
1.5 Safety Procedures 13
1.6 Access to Site and Rights of Way 14
1.7 Avoidance of Interference 14
1.8 Suitability and Maintenance of Access Route 14
1.9 Protection of the Environment 15
1.10 Progress Reports 15
2.0 Architect’s Power and Architect’s Instructions 16
2.1 Architect’s Power 16
2.2 Architect’s Representative 16
2.3 Architect’s Power to Delegate 16
2.4 Architect’s Instructions 16
2.5 Failure of Contractor to Comply with Architect’s Instruction 17
2.6 Dispute as to Architect’s Power to Issue Instructions 17
2.7 Delayed Instructions 18
3.0 Contract and Other Documents 18
3.1 Custody and Care of the Documents 18
3.2 Copies of Documents 18
3.3 Further Drawings or Details 19
3.4 Contractor to Provide Works Programme 19
3.5 Work Programme Not Part of or Incorporated into the Contract Documents 19
3.6 Submission and Approval of Works Programme 20
3.7 Limitation of Use of Documents 20
3.8 As-built Drawings, etc. 20
ARTICLES OF AGREEMENT
Between
…………………………………………………………………..... ………………………...….
of (or whose registered office is situated at) ………………………………………..………
……………………………………………..……….………………...………………
………………………………………………………… (hereinafter called the “Employer”)
of the first part;
And
…………………………………………………………………...…….……………………….
of (or whose registered office is situated at) ………………………………………..…
……………………………………………......…….………………………………………
…………………………………………..…………………….........................................
(hereinafter called the “Contractor”) of the second part.
WHEREAS
D. The Employer has accepted the Tender by the Contractor for the execution and
completion of the Works in accordance with the Contract.
Article 1
Contractor’s Obligations
In consideration of the payments to be made by the Employer to the Contractor as
mentioned in this Contract, the Contractor covenants with the Employer to execute and
complete the Works in conformity with the provisions of the Contract.
Article 2
Contract Documents
The following documents shall be deemed to form, and be read and construed as part of
the Contract Documents:
Article 3
Contract Sum
The Employer will pay the Contractor the sum of ………………………………………
…………………………………………… (RM………………………………..) or such other
sum as shall become payable hereunder at the times and in the manner prescribed by the
Contract (hereinafter called the “Contract Sum”).
Article 5
Engineer
The term ‘Engineer’ in the Contract means:
(c) …………………………………………………………………………………………………
of .................................................................................................................................
.....................................................................................................................................
...................................................……………………………………………………………
or in the event of his death or ceasing to be the Engineer for the purpose of this Contract,
such other Person as the Employer shall nominate and appoint within twenty-eight (28)
Days therefrom. The Engineer shall perform the duties expected of his profession. The
Architect may from time to time delegate such duties and authority of the Architect to the
Engineer as the Architect deems fit.
Article 6
Quantity Surveyor
The term ‘Quantity Surveyor’ in the Contract means ……………………………………….
…………………………………………….................................................................................
Article 7
Specialist Consultant
The term ‘Specialist Consultant’ in the Contract means:
(a) ……………………………………………………………...................................................
of .................................................................................................................................
.....................................................................................................................................
...................................................……………………………………………………………
(b) …………………………………………………………………………………………………
of .................................................................................................................................
.....................................................................................................................................
...................................................……………………………………………………………
(c) …………………………………………………………………………………………………
of .................................................................................................................................
.....................................................................................................................................
...................................................……………………………………………………………
or in the event of his death or ceasing to be the Specialist Consultant for the purpose of this
Contract, such other Person as the Employer shall nominate and appoint within twenty-
eight (28) Days therefrom. The Specialist Consultant shall perform the duties expected of
his profession. The Architect may from time to time delegate such duties and authority of
the Architect to the Specialist Consultant as the Architect deems fit.
Article 8
Definitions
In the Contract Documents, the following words and expressions shall have the meanings
hereby assigned to them, except where the context otherwise requires:
8.2 Appropriate Authority means any statutory authority having jurisdiction over the
Works;
8.4 Architect’s Instruction means an instruction issued by the Architect under Clause
2.0;
8.6 As-Built Drawings means as-built drawings for works designed (including alternative
design) by the Contractor and/or Nominated Sub-Contractor and any other as-built
drawings required to be provided as specified in the Contract Documents;
8.7 Certificate of Extension of Time means the certificate issued under Clause 23.0;
8.8 Certificate of Making Good Defects means the certificate issued under
Clause 15.5;
8.9 Certificate of Non-Completion means the certificate issued under Clause 22.1;
8.10 Certificate of Partial Possession means the certificate issued under Clause 16.1;
8.11 Certificate of Sectional Completion means the certificate issued under Clause 21.3;
8.12 CIPAA means Construction Industry Payment and Adjudication Act 2012 [Act 746];
8.13 Clause means the clauses and sub-clauses (as the case may be) in the Conditions
of the Contract;
8.14 Completion Date means the date(s) for completion of the Works stated in the
Appendix under Clauses 21.1 and 21.2 or the last extended date granted under
Clause 23.0;
8.15 Conditions means the Conditions of the Contract, including all revisions, amendments
and/or amplifications as may be agreed by the Parties and incorporated as part of
these Conditions of Contract;
8.17 Consultant means the Engineer, Quantity Surveyor and/or Specialist Consultant as
appropriate;
8.20 Contract Sum means the sum stated in Letter of Acceptance and in Article 3 or
such other sum as shall become payable hereunder at the times and in the manner
prescribed by the Contract;
8.21 Contractor means the Party named in the second part of the Articles of Agreement
and includes the Contractor’s legal successors or personal representatives or any
Person to whom the rights and obligations of the Contractor have been transferred
with the agreement of the Employer;
8.22 Contractor’s All Risks Insurance (‘CAR Insurance’) means an insurance policy
which provides cover against any physical loss or damage to work executed
and materials and goods under a standard CAR Insurance policy. The minimum
insurance risks are specified in Clauses 19.0 or 20, and the insurance shall have the
appropriate endorsements. Any additional insurance risks in addition to those stated
in these Conditions that are required to be covered under the CAR Insurance shall
be stated in the Contract Bills;
8.23 Date of Commencement means the date(s) fixed and stated in the Appendix under
Clauses 21.1 and 21.2;
8.24 Day means calendar day including the weekly day of rest but excluding gazette
holidays applicable to the location where the Works is carried out;
8.25 Defects means defects, shrinkages or other faults due to materials or workmanship
not in accordance with the Contract, and/or due to any faulty design (if any) undertaken
by the Contractor, Nominated Sub-Contractor and Nominated Supplier;
8.26 Defects Liability Period means the period stated in the Appendix under
Clause 15.3;
8.27 Employer means the Party named in the first part of the Articles of Agreement and
includes the Employer’s legal successors or personal representatives or any Person
to whom the rights and obligations of the Employer have been transferred with the
agreement of the Contractor;
8.28 Engineer means the Person named in Article 5 and shall be a professional Engineer
or any other form of practice registered under the Registration of Engineers Act 1967
and approved by the Board of Engineers, Malaysia;
8.31 Final Account means the documents showing the adjustment of the Contract Sum
issued under Clause 30.10;
8.32 Final Certificate means the final certificate issued by the Architect under Clauses
30.13 and 30.14;
Force Majeure may include, but is not limited to, exceptional events or circumstances of
the kind listed below, so long as conditions in Article 8.33(a) to (d) above are satisfied:
(i) war, hostilities (whether war be declared or not), invasion, act of foreign enemies;
(ii) rebellion, terrorism, revolution, insurrection, military or usurped power, or civil
war;
(iii) riot, commotion, disorder, strike or lockout by Persons other than the personnel,
servants, agents, and employees of the Contractor and Sub-Contractors;
(iv) munitions of war, explosive materials, ionizing radiation or contamination by
radio-activity, except as may be attributable to the Contractor’s use of such
munitions, explosives, radiation or radio-activity, and
(v) natural catastrophe such as earthquakes, hurricane, typhoon or volcanic
activity.
8.34 Interim Certificate means the progress payment certificate issued by the Architect
under Clauses 30.1 and 30.2;
8.35 KLRCA means Kuala Lumpur Regional Centre For Arbitration, or its successor;
8.36 Letter of Acceptance [or Letter of Award] means the letter of acceptance of the
Contractor’s Tender issued by or on behalf of the Employer;
8.37 Limit of Liquidated Damages means the amount as stated in the Appendix under
Clause 22.1(a);
8.38 Limit of Retention Fund means the amount as stated in the Appendix under Clause
30.5;
8.42 Nominated Supplier means a supplier nominated by the Architect and approved by
the Employer under Clause 28.0;
8.43 Party (or party) means the Employer or the Contractor, as the context requires;
8.44 Performance Bond means the bond required to be provided by the Contractor as a
security for the due performance of the contract under Clause 37.0;
8.45 Period of Honouring Certificates means the period for honouring certificates stated
in the Appendix under Clause 30.1;
8.46 Person (or person) means a natural person, sole proprietorship, firm (partnership)
or body corporate;
8.48 Prime Cost Sums (‘P.C. Sums’) means the sums provided in the Contract for
works or services to be executed by Nominated Sub-Contractor and Nominated
Supplier or for materials and goods which cannot be determined or detailed at the
time;
8.50 Quantity Surveyor means the Person named in Article 6 and shall be a Registered
Quantity Surveyor or any other form of practice registered under the Quantity
Surveyors Act 1967 and approved by the Board of Quantity Surveyors, Malaysia;
8.51 Retention Fund [or Retention Money or Retention Monies] means the sum
retained in accordance with Clause 30.5;
8.52 Schedules means the document(s) entitled schedules, completed by the Contractor
and submitted as part of the Tender and included in the Contract. Such document
may include the Bill of Quantities, data, lists, and schedule of rates and/or prices.
8.53 Schedule of Rates means any documents however entitled or described comprised
in the Schedules and which is intended to be used for the purpose of valuing
Variations;
8.55 Site means the Site designated as such in the Articles of Agreement and includes
the land or other places on, under, in or through which the Works are to be executed
and any other land or places provided by the Employer as may be specifically stated
in the Contract Documents as forming part of the Site;
8.56 Site Agent means the Person appointed under Clause 8.1;
8.57 Site Staff means the Person appointed under Clause 10.1;
8.58 Specialist Consultant means the Person named in Article 7 and such Person shall
be a Specialist Consultant appointed by the Employer for a designated scope of
professional work;
8.59 Specification means the document entitled specification, as included in the Contract,
and any additions and modifications to the specification in accordance with the
Contract. Such document specifies the Works;
8.61 Time Impact Events means any one of the Non-Employer’s Events and Employer’s
Events set out in Clause 23.8;
8.62 Tender means the Form of Tender, which was completed by the Contractor for the
Works, and all other documents which the Contractor submitted with the Form of
Tender, as included in the Contract;
8.64 Variation means changes made to the Works as defined in Clause 11.1;
8.65 Works means the Works referred to in the Articles of Agreement and are the whole
of the materials, labour, plant and other things necessary and requisite for the proper
execution of the Contract as shown on the Contract Drawings and described by or
referred to in the Employer’s Requirements, Specification, the Contract Bills and the
Conditions, and include any changes made to these works in accordance with the
Conditions;
8.66 Works Programme means the works programme described in the Contract
Documents and in Clause 3.4.
(a) words of one gender include the other gender, and words indicating Persons or Parties
include corporation and other legal entities;
(b) a reference to any Act of Parliament and its subsidiary legislations is deemed to include
references to any subsequent amendments, consolidation or replacement of the Acts
and the subsidiary legislations;
(c) words importing the singular also include the plural and vice versa where the context
requires; and
(d) where any word or phrase is given a defined meaning, any other grammatical form of
that word or phrase has a corresponding meaning.
Signature ..................................................
Name ........................................................
Signature ..................................................
Name ........................................................
Safety Procedures
1.5 The Contractor shall:
1.5(a) comply with all applicable safety regulations;
Avoidance of Interference
1.7 1.7(a) The Contractor shall not interfere unnecessarily or improperly with:
1.7(a)(i) the convenience of the public, or
1.7(a)(ii) the access to and use and occupation of all roads and
footpaths, irrespective of whether they are public or in the
possession of the Employer or of others.
1.7(b) The Contractor shall indemnify and hold the Employer harmless
against and from all damages, losses and expenses (including legal
fees and expenses) resulting from any such unnecessary or improper
interference.
Progress Reports
1.10 1.10(a) Unless otherwise instructed by the Architect, monthly progress reports
shall be prepared by the Contractor and submitted to the Architect in
six (6) copies. The first report shall cover the period up to the end of
the first calendar month following the Date of Commencement. Reports
shall be submitted monthly thereafter, each within seven (7) Days after
the last day of the period to which it relates. Reporting shall continue
until the issuance of the Certificate of Practical Completion.
1.10(b) Each report shall include but not limited to:
1.10(b)(i) charts and detailed descriptions of progress, including each
stage of design (if any), procurement, manufacture, delivery
to Site, construction, erection, testing and commissioning,
and including these stages for work by each Nominated
Sub-Contractor,
1.10(b)(ii) photographs showing the status of manufacture and of
progress on the Site,
1.10(b)(iii) for the manufacture of each main item of goods, materials
and parts for the Works, the name of the manufacturer,
manufacture location, percentage progress; and the actual
or expected dates of commencement of manufacture,
Contractor’s inspections, tests and shipment and arrival at
the Site,
1.10(b)(iv) the details of Contractor’s personnel, workmen, plant,
materials, plant and equipment mobilised for the execution
of the Works,
1.10(b)(v) list of notices given for any claim for extension of time and
loss and/or expense under the Contract,
1.10(b)(vi) safety statistics, including details of any hazardous
incidents and activities relating to the environment aspects
and public relations, and
Architect’s Power
2.1 The power of the Architect shall be that stated in or necessarily to be implied
from the Contract. Except as expressly stated in the Contract, the Architect
shall have no power to relieve the Contractor of any of his obligations under the
Contract.
Architect’s Representative
2.2 The Architect may appoint in writing any suitably qualified Person to be the
Architect’s Representative. The Architect’s Representative shall be responsible
to the Architect and shall carry out such duties and exercise such power as may
be delegated to him by the Architect under Clause 2.3.
Architect’s Instructions
2.4 2.4(a) Instructions given by the Architect shall be in writing. For the avoidance
of doubts, a drawing issued by the Architect, or recorded minutes of
any meeting, shall not be considered as an Architect’s Instruction
Delayed Instructions
2.7 2.7(a) The Contractor shall give written notice to the Architect whenever the
Works are likely to be delayed or disrupted if any necessary instruction
is not issued to the Contractor within a reasonable time. The notice
shall include details of the necessary instruction, details of why and by
when it should be issued, and details of the nature and amount of the
delay or disruption likely to be suffered if the issuance of the instruction
is delayed.
2.7(b) If the Contractor suffers delay and/or incurs loss and expense as a result
of a failure of the Architect to issue the notified instruction within the time
required or within a time which is reasonable, the Contractor may apply
for an extension of time under Clause 23.0 and for loss and expense
under Clause 24.0. However, if and to the extent that the Architect’s
failure was caused by any negligence, omission, default and/or breach
of contract by the Contractor or his Nominated Sub-Contractors, the
Contractor shall not be entitled to such extension of time or loss or
expense.
Copies of Documents
3.2 Immediately after the execution of this Contract, the Architect shall without charge
to the Contractor provide him with:
3.2(a) one (1) signed original copy of the Contract Documents;
Setting Out
5.1 5.1(a) The Contractor shall set out the Works in relation to original points,
lines and levels of reference specified in the Contract or notified by the
Architect, and ensure that the positioning of all parts of the Works is
correct.
5.1(b) The Contractor shall provide the necessary instruments, equipment
and labour required for setting out the Works, and provide every
assistance and similar facilities to the Architect for checking the setting
out.
5.1(c) The inspection, assistance and/or approval by the Architect and/or the
Consultant shall not in any way relieve the Contractor of his responsibility
for the accuracy of the setting out.
Definition of Variation
11.1 The term “Variation” means the change, alteration or modification of the design,
quality or quantity of the Works as described by or referred to in the Contract
Documents including:
11.1(a) the addition, omission or substitution of any work,
11.1(b) the alteration of the kind or standard of any materials and goods to be
used in the Works,
11.1(c) the removal from the Site of any work executed or materials and goods
brought thereon by the Contractor for the purposes of the Works other
than work, materials and goods which are not in accordance with the
Contract,
11.1(d) any changes to the provisions in the Contract with regard to:
11.1(d)(i) any limitation of working hours,
11.1(d)(ii) working space;
11.1(d)(iii) access to or utilisation of any specific part of the Site, and
11.1(d)(iv) the execution and completion of the work in any specific
order,
but shall exclude any changes to the Works intended to rectify any negligence,
omission, default and/or breach of contract by the Contractor whereby such
changes shall be executed by the Contractor entirely at his own cost.
Issue of Variation
11.4 The Architect may issue instructions in writing requiring a Variation at any
time before the issuance of the Certificate of Compliance and Completion.
Thereafter, any Architect’s Instruction requiring a Variation must be necessitated
by the Contractor’s obligation to correct defects in the Works or obligations
or compliance with the requirements of any Appropriate Authority and Service
Provider.
Valuation of Variations
11.6 All Variations shall be measured and valued by the Architect and the relevant
Consultant. Where any recording of site information and/or site measurements
are carried out at the Site, the Contractor shall provide the Architect and the
relevant Consultant with such assistance as may be necessary to take notes and
measurements. The Contractor shall be given the opportunity to be present to
take such notes and measurements as he may require.
Valuation Rules
11.7 The valuation of Variations and of work executed by the Contractor for which a
Provisional Quantity is included in the Contract and the expenditure of Provisional
Sums (other than for work for which a tender had been accepted under Clauses
27.13 and 28.13) shall, unless otherwise agreed, be made in accordance with the
following rules:
11.7(a) where work is of similar character to the work as specified in the
Contract, is executed under similar conditions, and does not significantly
change the quantity as set out in the Contract, the rates and prices in
the Schedule of Rates shall determine the valuation;
11.7(b) where work is of a similar character to the work set out in the Contract
but is not executed under similar conditions or, is executed under
similar conditions but there is a significant change in the quantity of
work carried out, the rates and prices in the Schedules shall be the
basis for determining the valuation which shall include a fair adjustment
of the rates to take into account such difference;
11.7(c) where work is of a different character to the work as set out in the
Contract, the valuation shall be at fair market rates and prices determined
by the Architect;
11.7(d) where work cannot be properly measured and valued in accordance
with Clauses 11.7(a), 11.7(b) or 11.7(c), the Contractor shall be allowed:
11.7(d)(i) the daywork rates in the Schedules, or
11.7(d)(ii) where there are no such daywork rates in the Schedules,
the actual cost to the Contractor of his materials, additional
construction plant and scaffolding, transport and labour
for the work concerned, plus fifteen (15) percent, which
percentage shall include the use of all tools, standing
plant, standing scaffolding, supervision, overheads and
profit.
In either case, the Contractor shall provide the vouchers specifying
the time spent on a daily basis in carrying out the works, the workers’
names and designation, the materials, additional construction plant,
scaffolding and transport used which shall be signed by the Site Agent
Lump Sum
13.1 13.1(a) The Contract Sum shall be on a fixed firm lump sum basis and shall not
be adjusted or altered in any way whatsoever, other than in accordance
with the express provisions of the Contract. Unless otherwise expressly
provided, the Contract Sum is deemed to include all ancillary and other
works and expenditure, which may or may not have been specifically
mentioned or described in the Contract Documents, but which are
indispensably or contingently necessary to be carried out to bring the
Works to completion or to overcome difficulties before completion in
accordance with the Contract.
Additional Risks
20.2 Any additional risks or endorsement in addition to those stated in Clause 20.1
which may be required to be covered under the required insurance(s) shall be
specified in the Contract Bills. If the Contractor desires to have any additional
Suspension of Work
21.4 21.4(a) The Architect may at any time by way of an Architect’s Instruction instruct
the Contractor to suspend progress of part or all of the Works. During
such suspension, the Contractor remains responsible for the works and
shall protect, store and secure the Works against any deterioration, loss
or damage. The Architect may also notify the cause for the suspension. If
and to the extent that the cause is notified and is the responsibility of the
Contractor, the following Clauses 21.4(b) and 21.4(c) shall not apply.
21.4(b) If the Contractor suffers delay and/or incurs loss and/or expense from
complying with the Architect’s Instruction under Clause 21.4(a) and/or
from resuming the work, the Contractor shall be entitled to claim for an
extension of time under Clause 23.0 and/or loss and/or expense under
Clause 24.0.
21.4(c) If the suspension under Clause 21.4(a) has continued for more than the
Period of Delay, then the Contractor may:
21.4(c)(i) by giving notice to the Architect, treat the suspension as
an omission under Clause 11.0 of the affected part of the
Works; or
21.4(c)(ii) if the suspension affects the whole or substantial part of the
Works, the Contractor may be entitled to determine his own
employment under Clause 26.0.
21.4(d) The Contractor shall not be entitled to an extension of time or payment of
any loss and/or expense incurred in making good the consequences of
the Contractor’s faulty design (if applicable), workmanship or materials,
or of the Contractor’s failure to protect, store or secure in accordance
with Clause 21.4(a).
Contemporary Records
24A.2 Clause 24.2 shall apply to any claim made by the Contractor under Clause 24A.1(a).
Defaults by Contractor
25.1 The Employer may determine the employment of the Contractor under the
Contract if the Contractor makes default in one or more of the following instances:
25.1(a) without reasonable cause, fails to commence the Works for more than
fourteen (14) Days from the Date of Commencement or any other
extended date allowed in accordance with the relevant provisions of
the Contract,
25.1(b) without reasonable cause, wholly or substantially suspends the carrying
out of the Works before Practical Completion of the Works,
Defaults by Employer
26.1 The Contractor may determine his own employment if:
26.1(a) the Employer fails or neglects to pay the Contractor the amount due on
any certificate (less any deduction, set off and/or Liquidated Damages
to which the Employer is entitled to make under these Conditions),
within the Period of Honouring Certificates,
26.1(b) the Employer improperly or fraudulently interferes with or influences
or obstructs the issue of any certificate by the Architect, or there is
fraudulent collusion between the Employer and the Architect,
26.1(c) the Employer fails to nominate a succeeding Architect, Consultant or
Specialist Consultant in accordance with Articles 4, 5, 6 and 7, or
26.1(d) before the date of Practical Completion, the carrying out of the whole
or substantially the whole of the uncompleted Works is suspended for
a continuous period of time exceeding the Period of Delay stated in the
Appendix by reason of:
26.1(d)(i) Architect’s Instruction issued by the Architect under Clause
1.4, 21.1 or 21.4 unless the instruction is issued to rectify
any negligence, omission, default and/or breach of contract
by the Contractor, Nominated Sub-Contractor or Nominated
Supplier,
26.1(d)(ii) the Contractor not having received in due time necessary
Architect’s Instruction (including those for or in regard to
the expenditure of P.C. Sums and Provisional Sums, further
drawings, details, levels or any other information) for which
he had specifically applied in writing to the Architect. The
Contractor’s application must be submitted to the Architect
in sufficient time before the commencement of construction
of the affected works, to enable the Architect to issue the
necessary Architect’s Instruction within a period which
would not materially affect the progress of the affected
works, having regard to the Completion Date. Provided
always that the Architect’s Instruction was not required as
a result of any negligence, omission, default and/or breach
of contract by the Contractor and/or Nominated Sub-
Contractor and/or Nominated Supplier,
26.1(d)(iii) delay on the part of craftsmen, tradesmen or others
employed or engaged by the Employer in executing work
not forming part of this Contract or their failure to execute
such work, provided always that the Contractor has
given reasonable access and assistance to enable such
craftsmen, tradesmen or others employed or engaged by
the Employer to execute their works and has provided true
and accurate site conditions and reasonable timelines for
such works to be completed by them, or
Objection to Nomination
27.3 The Contractor shall not be under any obligation to employ a nominated
Person as his Nominated Sub-Contractor against whom the Contractor raises
reasonable objection by notice to the Architect. Such notice of objection shall
be given as soon as practicable, but not later than ten (10) Days from the date
of notification of the nomination, with supporting particulars. An objection shall
be deemed reasonable if it arises from (among other things) any of the following
matters:
27.3(a) the nominated Person does not agree to enter into a sub-contract based
upon the terms and conditions of the Malaysian Standard Form of
Building Sub-Contract, or other form of sub-contract which is approved
by the Architect and the Employer, or
27.3(b) there are reasons to believe that the nominated Person does not have
sufficient competence, resources or financial strength, unless the
Employer agrees in writing to indemnify the Contractor against and
from the consequences in respect thereof.
Objection to Nomination
28.3 The Contractor shall not be under any obligation to employ a nominated Person
as his Nominated Supplier against whom the Contractor raises reasonable
objection by notice to the Architect. Such notice of objection shall be given as
soon as practicable, but not later than ten (10) Days from the date of notification
of the nomination, with supporting particulars. An objection shall be deemed
reasonable if it arises from (among other things) any of the following matters:
28.3(a) the nominated Person does not agree to enter into a sub-contract
based upon the terms and conditions approved by the Architect and the
Employer, or
28.3(b) unless the Employer agrees in writing to indemnify the Contractor
against and from the consequences in respect of the matter:
28.3(a)(i) there are reasons to believe that the nominated Person
does not have sufficient competence, resources or financial
strength to meet its obligations under the supply sub-
contract,
28.3(a)(ii) the nominated Person does not accept to indemnify the
Contractor against and from any negligence or misuse of
goods or materials by the nominated Person, his agents
and employees, or
28.3(a)(iii) the nominated Person does not accept to enter into a
sub-contract which specifies that for the goods or materials
to be supplied (including design, if any), the nominated
Person shall undertake to the Contractor such obligations
and liabilities as will enable the Contractor to discharge his
obligations and liabilities under the Contract; and indemnify
the Contractor against and from all obligations and liabilities
arising under or in connection with the Contract and from
the consequences of any failure by the nominated Person
to perform these obligations or to fulfill these liabilities.
30.0 Payment
Set-Off by Employer
30.4 Unless otherwise expressly provided in these Conditions, the Employer shall not
be entitled to withhold or deduct any amount certified as due under any payment
Retention Fund
30.5 The Employer may retain the percentage of the total value of the work,
materials and goods referred to in Clause 30.2 which is stated in the Appendix
as Percentage of Certified Value Retained. When the sum of the amounts so
retained equals the amount stated in the Appendix as Limit of Retention Fund
or that amount as reduced in pursuance of Clauses 16.1(f), 16.1(g), 27.7 and/
or 28.7, as the case may be, then no further amounts shall be retained by virtue
of this Clause.
Final Account
30.10 30.10(a) Within six (6) Months after Practical Completion of the Works, the
Contractor shall submit to the Architect and Consultant, all documents
necessary for preparing the Final Account, including all documents
relating to the accounts of Nominated Sub-Contractors and Nominated
Suppliers (whether previously submitted or not). Such documents
shall contain all the latest construction drawings and details (bound
together), details of all quantities, operation manuals, rates and prices
and any adjustment of the Contract Sum and any additional payment
or compensation claimed by the Contractor under the Contract together
with any explanation and supporting vouchers, documents and
calculations, which may be necessary to enable the Final Account to be
prepared by the Architect.
30.10(b) If the Architect is of the opinion that the documents and particulars
submitted by the Contractor pursuant to Clause 30.10(a) are insufficient
for his evaluation and preparation of the Final Account, the Architect
shall within thirty (30) Days from the date of receipt of the Contractor’s
said documents and particulars, inform him of any deficiency or
insufficiency in his submission and require such further documents and
particulars within thirty (30) Days thereof or such further time as may be
stated by the Architect in writing.
30.10(c) In the event the Contractor fails to submit the requested documents
particulars under Clause 30.10(b), the Architect shall nevertheless
complete and issue the Final Account based on the information
available to him within the period to complete the Final Account as
stated in the Appendix.
30.10(d) On completion of the Final Account, the Architect shall then send a
copy of the document to the Employer and Contractor.
30.10(e) If the Parties agree with the Final Account presented by the Architect,
then the Final Account shall become conclusive [other than any
outstanding items to be resolved separately between the Employer
and the Contractor under Clauses 30.11(b)(i) and 30.11(b)(ii)], except
where the Final Account is erroneous by reason of:
30.10(e)(i) fraud, dishonesty or fraudulent concealment relating to the
Works, or
30.10(e)(ii) any arithmetical errors in any computation.
30.10(f) If either Party disputes the Final Account, then the following provisions
shall apply:
30.10(f)(i) the Party disputing the final account shall by written notice
to the other Party (with a copy to the Architect) setting out
any disagreement thereof complete with particulars within
thirty (30) Days of the date of receipt of the Final Account
from the Architect,
Notices of Determination
31.2 Provided always that such notice shall not be given:
31.2(a) before the expiration of twenty-eight (28) Days from the date on which
the order is given for general mobilisation as aforesaid; or
31.2(b) after Practical Completion of the Works unless the Works or any part
thereof have sustained war damage as defined in Clause 32.3.
If the Contractor for reasons beyond his control is prevented from executing or
completing the protective works to which the said instruction relates within three
(3) Months from the date on which the instructions were issued, he may abandon
such work.
34.0 Arbitration
Powers of Arbitrator
34.2 The Arbitrator shall, without prejudice to the generality of his powers, have power:
34.2(a) to rectify the Contract so that it accurately reflects the true agreement
made by the Employer and the Contractor,
34.2(b) to direct such measurements and/or valuations as may in his opinion be
desirable in order to determine the rights of the Parties,
Commencement of Arbitration
34.3 34.3(a) Unless otherwise agreed in writing by the Parties, such arbitration
shall be commenced after the Practical Completion or alleged Practical
Completion of the Works, or determination or alleged determination of
the Contractor’s employment under the Contractor, or termination or
alleged termination of the Contract under the law, or abandonment or
alleged abandonment of the Works except on:
34.3(a)(i) the question of whether or not the issuance of an instruction
is empowered by these Conditions,
34.3(a)(ii) any dispute or difference under Clauses 31.0 or 32.0,
34.3(a)(iii) whether or not a certificate has been improperly withheld or
otherwise not in accordance with these Conditions, or
34.3(a)(iv) whether or not a payment to which the Contractor may claim
to be entitled has been properly withheld in accordance
with these Conditions.
34.3(b) The obligations of the Parties and the Architect shall not be altered by
reason of any arbitration being conducted during the progress of the
Works.
Architect as Witness
34.4 Nothing shall disqualify the Architect from being called as a witness and giving
evidence before the arbitrator(s) on any matter whatsoever relevant to the dispute
referred to arbitration.
Written Communication
36.3 All written communication shall be sent to the address stated in the Articles of
Agreement unless otherwise notified in writing.
39.0 Waiver
Waiver
39.1 Unless otherwise provided, no failure or delay on the part of either Party to
exercise any right or remedy under this Contract shall be construed or operate
as a waiver thereto nor shall any single or partial exercise of any right or remedy
be construed as waiver of any other rights or remedies provided in this Contract.
Such rights and remedies are cumulative and not exclusive of any rights or
remedies provided by the law.
Clause
Defects Liability Period [if none is stated is 15.3 ………………………………..
twelve (12) Months from the day stated in
the Certificate of Practical Completion of the
Works]
Insurance cover for accidental bodily injury 19.1 RM …………………………..
to or illness of third-parties (whether fatal (Details)
or not), accidental loss of or damage to
property (the aggregate liability of the
insurers shall be limited by twice the limit of
indemnity caused by any one occurrence)
[if none stated the insured liability shall be
not less than RM1 million]
Amount of Insurance Cover for Works, 20.0 RM …………………………..
Materials and Goods [if none stated is the (Details)
Contract Sum as stated in the Articles plus
15%]
Insuring Party 20.0 Contractor/Employer*
(delete as may be
appropriate)
Insurance deductible amount [if none 19.1 and, RM ……………………….....
stated shall be not more than RM50,000 an 20.0
occurrence]
Period of Honouring Certificates [if none 30.1, 30.6 & 30.14 ……………………………….....
stated is twenty-one (21) Days from the
date of presentation of the required Tax
Invoice with the relevant Certificate (if
the Contractor is a taxable person under
the Goods and Services Act 2014), or
the date of issuance of the relevant
Certificate (if the Contractor is not a
taxable person under the Goods and
Services Act 2014), as the case may be]
Percentage of Value of materials and 30.2 ……………………………….....
goods included in the Certificate [if none
stated is 100%]
Percentage of Certified Value Retained [if 30.5 ……………………………….....
none stated is 10% of the value of work
executed and materials on site included
in the certificate subject to the Limit of
Retention Fund]
Limit of Retention Fund [if none stated is 30.5 RM …………………………......
5% of the Contract Sum]
Period to complete the Final Account [ if 30.10(c) ……………………………….....
none stated shall be twelve (12) Months
from the date of Practical Completion]
Amount of Performance Bond / 37.0 RM …………………………......
Performance Guarantee Sum [if none
stated is 5% of the Contract Sum]
(*) – This is to be used when there are different Completion Dates for identified Sections