Causes of Claims On Road Projects - A Case Study in Ethiopia
Causes of Claims On Road Projects - A Case Study in Ethiopia
Causes of Claims On Road Projects - A Case Study in Ethiopia
A THESIS SUBMITTED TO
ADDIS ABABA UNIVERSITY
FACULITY OF TECHNOLOGY-SOUTH
DEPARTMENT OF
CONSTRUCTION TECHNOLOGY AND MANAGEMENT
IN PARTIAL FULFILMENT OF
THE REQUIRMENT FOR THE DEGREE OF BSc IN
CONSTRUCTION TECHNOLOGY AND MANAGEMENT
AUGUST 2006
APPROVED BY BOARD OF EXAMINER:
____________________
____________________
ADVISOR
____________________
______________________
EXAMINER
Causes of Claims on Road Projects in Ethiopia
A THESIS SUBMITTED TO
ADDIS ABABA UNIVERSITY
FACULITY OF TECHNOLOGY-SOUTH
DEPARTMENT OF
CONSTRUCTION TECHNOLOGY AND MANAGEMENT
IN PARTIAL FULFILMENT OF
THE REQUIRMENT FOR THE DEGREE OF BSc IN
CONSTRUCTION TECHNOLOGY AND MANAGEMENT
AUGUST 2006
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 I
Causes of Claims on Road Projects in Ethiopia
ABSTRACT
The study has two main sections: the first part is an overview and
discussions of concepts and contextual practices of claims. In the
second part, a case study and questionnaires are made primarily to
assess the causes of claims in Ethiopian road projects. In addition, this
study (especially the survey questionnaires) also assesses the current
practices of the construction firms and clients in mitigating and/or
administering claims.
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 II
Causes of Claims on Road Projects in Ethiopia
ACKNOWLEDGMENTS
We wish to express our gratitude to those who made this thesis work of
great success. We are greatly thankful to our advisor Ato Ismael
Ibrahim from MH Engineering for his continuous supervision and
support. We also would like to thank Dr. Wubishet Jekale Mengesha for
his invaluable support in providing documents and guidance through
out the whole process; without him it would have been very difficult to
prepare this thesis.
Our special appreciation goes to all engineers in contract administration
division and workers of legal service division documentation department
of the Ethiopian Road Authority/ERA/ for their assistance in providing
documents. We would also like to thank all those who were kind enough
to give replies to our survey questioners scarifying their precious time.
Abebe Nigussie
Fentahun Fekadu
Kidanemariam Tesfaye
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 III
Causes of Claims on Road Projects in Ethiopia
ABSTRACT........................................................................................... II
ACKNOWLEDGMENTS........................................................................III
LISTS OF ACRONYMS.........................................................................VI
PART ONE - INTRODUCTION AND METHODOLOGY
1. Introduction..................................................................................... 1
1.1 Background ....................................................................................................... 2
1.2 Aim and Objective ........................................................................................... 4
1.3. The study Scope and Limitations ............................................................. 4
1.4 Problem Identification.................................................................................... 5
2. Methodology .................................................................................... 7
2.1. Study methodology ........................................................................................ 7
2.2. Study strategy ................................................................................................. 7
2.3. Orientation of the survey questionnaires............................................... 8
PART TWO - LITRATURE REVIEW
1 Claim Perspective............................................................................ 10
1.1 Definitions .............................................................................. 11
1.2 Valid claims ............................................................................ 12
1.3 Contents of a claim ................................................................. 12
1.4 Classification of claims ............................................................ 13
1.5 Impacts of claims .................................................................... 14
2. Causes of claims .................................................................................................. 15
2.1 Principal causes of claims ....................................................... 15
2.2 Remedial rights ....................................................................... 24
3 Provisions of standard conditions of contracts on claims ................. 25
3.1 MoWUD, 1994 provisions on claims ....................................................... 25
3.2 FIDIC, 1987 provisions on claims............................................................ 28
3.3 Standard bidding document for the procurement of works............ 31
by PPA, 2006 .......................................................................................................... 31
4. Claim Administration and Mitigation.............................................. 36
4.1 Claim Administration Process................................................................... 36
4.2 Mitigation ......................................................................................................... 38
4.2.1 What to be done before work begins...................................... 38
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 IV
Causes of Claims on Road Projects in Ethiopia
LISTS OF FIGURES
Figure 1 Simplified Problem Tree (Identification of Study Problem) ....... 6
Figure 2 Study structure..................................................................... 9
Figure 3: Claim Administration Process.............................................. 36
Figure 4 Percentage of major category of claim factors....................... 55
Figure 5- Relative Percentage of Claimed and Granted Time and Cost 58
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 V
Causes of Claims on Road Projects in Ethiopia
LISTS OF TABLES
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 VI
Causes of Claims on Road Projects in Ethiopia
LISTS OF ACRONYMS
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 VII
Causes of Claims on Road Projects in Ethiopia
PART ONE
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 1
Causes of Claims on Road Projects in Ethiopia
1. Introduction
This paper has two major parts. The first part reviews conceptual and
contextual review of causes of claims in road projects and the second
part deals with a practical case study on the causes of claims on road
projects in Ethiopia.
Chapter one of this paper presents the background, aim & objective,
scope & limitation, and problem identification of this study. While the
second chapter briefly describes the study methodology and strategy
followed in writing this paper. Chapter three of this study is a literature
review on causes of claims and related issues such as classifications,
impacts, remedial rights, claim administration process and mitigation,
and claim awareness in Ethiopian construction industry. It also reviews
MoWUD, FIDIC and PPA standard conditions of contracts, which are
related to this study. Chapter four and five are the case study and
analysis of questionnaires part of this paper respectively and Chapter
six is discussion on the findings of the case study and results of the
survey questionnaires. Conclusion and few recommendations are
provided in the last chapter.
1.1 Background
Within the last decade, road sector development has been one of the
priority public investment areas for the success of the envisaged
Ethiopian economic recovery program. The free market economic
practice in Ethiopia has created a better opportunity for participation of
local and foreign investors in the construction activities. However,
achieving the required quality and completing projects within overall
budget and allocated time have been difficulties experienced during the
implementation of most road projects. Projects are unique and
complicated by their nature. High levels of art and craft are required to
translate an owner’s vision into plans and specifications, then into real
structures, one that fits the needs of the individuals and the public. In
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 2
Causes of Claims on Road Projects in Ethiopia
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 3
Causes of Claims on Road Projects in Ethiopia
The aim and objective of this thesis is to analyze the causes of claims in
road projects and forward recommendations for future action that helps
in mitigating claims. The study focuses on the root causes of claims.
The study also addresses types of claims, claim administration process,
impacts of claims and review of the conditions of contract. The cases
selected have been analyzed with the objective of identifying the root
causes of construction claims and enhance the management of claims
for efficient project deliveries. As a conclusion the thesis suggests
procedures and practices that seek to minimize the incidence of claims.
The following two major issues were delimited in this thesis. These
delimitations were related to the focus of the research problem. The two
main focuses are:
• The causes of claims
• Road projects.
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 4
Causes of Claims on Road Projects in Ethiopia
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 5
Causes of Claims on Road Projects in Ethiopia
Mitigation
Impacts of claims
Causes of claims in
Ethiopian road projects
Causes of claims on
road projects
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 6
Causes of Claims on Road Projects in Ethiopia
2. Methodology
2.1. Study methodology
The study strategy followed in this study is carried out after the
identification of the problem as a case to be studied. The six major steps
that are used in this case study is:
• Literature review on the trends and practices used in the
construction industry with respect to construction claims is
assessed as theoretical background. The literature survey
includes definitions, classifications, causes, impacts, mitigating
factors, provision of the MoWUD, FIDIC and PPA conditions of
contract and claim awareness in the Ethiopian construction
industry,
• Questionnaires are designed and distributed to those who take
part in the industry (clients, consultants and contactors). Some of
these questionnaires are filled in the form of interviews and some
are distributed with introduction on the topic as objective of the
research. The questionnaires are structured to address causes,
consequences, and current practices of the firms in minimizing
and/or administering claims. Moreover, their opinion on other
additional techniques were collected,
• Identification and Analysis of case study projects; these projects
were recognized and analyzed while processing the questionnaires
with clients, contractors and consultants. Analysis of the claim
cases of seven selected projects was carried out through
document study,
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 7
Causes of Claims on Road Projects in Ethiopia
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 8
Causes of Claims on Road Projects in Ethiopia
Thesis
Proposal
Literature
Review
Research Case
Instrument Identification
Conclusions
Recommendations
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 9
Causes of Claims on Road Projects in Ethiopia
PART TWO
LITRATURE REVIEW
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 10
Causes of Claims on Road Projects in Ethiopia
1 Claim Perspective
1.1 Definitions
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 11
Causes of Claims on Road Projects in Ethiopia
Valid claims are referred to those claims that the contractor is entitled
to. All parties involved in the contract (particularly the owner) should be
aware of the causes of valid claims. It often happens that claims that
might otherwise be valid are rejected because:
• Timely notice was not given,
• The claim is late,
• Contract procedures were not followed,
• Proper records were not kept
• The claim does not establish any valid entitlement under the
contract,
• Inadequate information is available or provided to verify the claim
or support its quantification. (Abera Bekele, 2005)
It is essential that for every claim, the contractor provide to the engineer
appropriately documented claims. K.L Scott, 1992 suggests the
following points to be included in claim documents.
Introduction: - describing the parties to the claim, giving brief details of
the project and those elements that have given rise to the claim. The
introduction should conclude with a statement to the effect that the
contractor is seeking reimbursement of direct loss and/or expense.
Contract details: - including the form of contract employed with the
appropriate amendments, the date of possession of site, date for
completion, date of practical completion and rate of liquidated damage,
etc. More importantly, all those express terms of the contract upon
which the contractor is to rely and any implied terms that may be
promoted should be set down. Any common law principles such as
misrepresentation should be highlighted.
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 12
Causes of Claims on Road Projects in Ethiopia
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 13
Causes of Claims on Road Projects in Ethiopia
point is that a party wishing to benefit from a common law remedy must
assert his right by claiming it, but the engineer has no implied authority
to settle such claims. (Houghs & Barber, 1992)
Ex gratia: - These sort of claims are not covered under the contract but
can be paid in a sense of “fairness” or equity. (A Continuing Professional
Development (CPD) study pack, 1995)
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 14
Causes of Claims on Road Projects in Ethiopia
2. Causes of claims
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 15
Causes of Claims on Road Projects in Ethiopia
1. Variations
Variations are a fact of life in the construction industry and give rise to
many problems, whichever form of contract is used (Vincent Powel
Smith, 1990). The 4th edition of the FIDIC International Conditions of
contract (1987) defines variations as:
• Increase or decrease of the quantity of work included in the
contract;
• Omissions of such work;
• Changes in the character, quality or kind of the work;
• Changes in the levels, lines, positions and dimensions o any part
of the works;
• The execution of additional work of any kind necessary for the
completion of the works;
• Changes in any specified sequence of timing of construction of
any part of the works.
All the standard form of contracts contains variations clauses because,
without an express power to direct departure from the original contract
work, the employer would have no power to order it.
2. Changes in design and specifications, and defective drawings
This includes errors, omissions, changes or ambiguities occurring in the
contract documents.
Errors, omissions and changes: - An incomplete, inaccurate or poorly
coordinated design inevitably will produce a project with conflicts and
unanticipated costs and delay. An accurate and complete design will
help in minimizing the risk of misunderstanding and litigation, and
provides more protection for the owner. (Greenberg Traurig, 2004).
Ambiguities: -Ambiguities and discrepancies can arise between
documents or within a given document. The legal rules for constructing
contracts operate to resolve ambiguities, but the answer provided by the
rules might not be satisfactory as regards what is actually to be built. A
discrepancy might even invalidate the contract if could not be resolved.
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 16
Causes of Claims on Road Projects in Ethiopia
2.1.2 Accelerations
Acceleration
When the owner orders completion of the project sooner than required
by the contract or orders work finished on the original completion date
failing to grant time extensions, which are due. Wagner, et al, xxxx
classified accelerations as direct and constructive.
Directed: - When projects delay or when projects are required to be
completed before its time, project doers are obliged to accelerate their
services or works to satisfy the requirements. The project doer is
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 17
Causes of Claims on Road Projects in Ethiopia
1. Changed conditions
Changed conditions are conditions other than what a wise person would
have expected. This includes:
• Subsurface of latent physical conditions differing materially from
those indicated in the contract.
• Unknown physical conditions at the site, of an unusual nature,
differing materially from those ordinarily encountered in work of
the character provided for in the contract (Wagner, et al,)
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 18
Causes of Claims on Road Projects in Ethiopia
1. Suspension
Suspension is work stoppage for the benefit of one of the parties in the
contract. In construction contracts the engineer has the authority to
suspend the progress of the whole or any part of the works. In such
cases the contractor is entitled to time extension and additional costs
incurred unless such suspension is provided for in the contract by
default or breach of contract by the contractor, by reasons of climatic
conditions or necessary for the proper execution or safety of the works.
If the employer fails to pay the contractor the amount due under
payment certificates, the contractor can suspend the work or reduce the
rate of the work.
2. Termination
Either or both parties have the right to terminate contract under certain
circumstances. However, before termination parties should describe the
contract events that trigger the termination of the contract under
certain conditions. In additions, there should be a description of the
methods of giving notice of exercise of the termination right and
whether the breaching party must be given an opportunity to cure the
breach before the other party can terminate the contract.
2.1.5 Delays
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 19
Causes of Claims on Road Projects in Ethiopia
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 20
Causes of Claims on Road Projects in Ethiopia
2. Designer Caused
Late shop drawing approval,
Design error,
Failure to accept
3. Contractor Caused.
Rework,
Lack of productivity,
Procurement failures
4. Force Majeure
FIDIC condition of contracts, 1987 defines force majeur as “an
exceptional event or circumstance:
• Which is beyond the parties control
• Which such party could not reasonably have provided against before
entering into the contract
• Which, have arisen, such party could not reasonably have avoided
or overcome
• Which is not substantially attributable to the other party.”
Reg Thomas, 2001 has listed factors that cause force majeur
• Hurricanes,
• Tornadoes,
• War
2.1.6 Miscellaneous
Claims, which do not fall into any of the above categories, are listed by
Wagner, et al,
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 21
Causes of Claims on Road Projects in Ethiopia
scope, time, money and risk allocation that leads to potential claims.
Such conflicts are usually the result of ambiguities regarding which
party is responsible for management of the construction work and
which is responsible for the design.
2. Refusal to Accept Completed Work
Owner refuses to takeover completed work and Contractor is forced to
maintain and protect the work.
3. Early Occupancy
Owner moves into facility and interferes with the Contractor.
4. Changes in Scope
Project’s purpose is altered or increased significantly.
5. Cardinal Change
Owner alters a project radically
6. Material Breach Violation of an important contract obligation
The different factors that give rise to claims are similar and repetitive in
nature. The following table summarizes these factors based on their
sources. (Table 1)
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 22
Causes of Claims on Road Projects in Ethiopia
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 23
Causes of Claims on Road Projects in Ethiopia
1.Time extension
Time extension is a provision for justified time delays. Time extensions
may or may not be entitled for compensation using critical path
method; it is only justified delays that occur on the critical path that is
compensable. The effect of time extension is to relieve liabilities of delay
damages such as liquidated damage. (Wubishet, 2006)
2. Liquidated damage
If the contractor fails to comply with the time completion in accordance
with contract document, then the contractor shall pay to the employer
the sum stated in the appendix to the tender to the tender as liquidated
damages (FIDIC, 1987). However, if the owner caused the delay the
liquidated damages provision will not be enforced. The followings are
the amount of liquidation damage the contractor has to pay in the
current practice of our construction industry.
For Buildings ----- 1/1000 birr of delayed amount per calendar delay
days
For Road projects ---- 50,000 -100,000 birr per calendar delay days
3. Cost compensation
Damages can involve additional costs incurred by the extended duration
of its performance. Damages typically include costs of idle labors and
equipment, higher costs of performance during the late period of time
and extended general conditions. (Wubishet, 2006)
Other remedial rights include
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 24
Causes of Claims on Road Projects in Ethiopia
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 25
Causes of Claims on Road Projects in Ethiopia
Clause
No. Description of claims Entitlement Due to
Repayment The
25 Contractor's failure to insure. successively Employer
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 26
Causes of Claims on Road Projects in Ethiopia
Clause
No. Description of claims Entitlement Due to
Repayment The
39.2 Removal of improper work & Material successively Employer
The
47.1 Delay in completion time Liquidated damage Employer
The
49.4 Remedy on contractor's failure Repayment Employer
The
contractor
/ The
52.1 Valuation of variations +/- cost Employer
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 27
Causes of Claims on Road Projects in Ethiopia
Clause
No. Description of claims Entitlement Due to
The
contractor
70.1 - Additions / / The
70.2 Changes in Cost & Legislation Omissions Employer
Table 2: Claim clauses in SCC for construction of civil work projects, MoWUD,
1994
3.2 FIDIC, 1987 provisions on claims
There are certain clauses, which provide the contractor with opportunities for
increasing the contract price, and certain clauses that entitle the employer to
receive payments from the contractor. These clauses are listed in tables 3 and
4. (FIDIC digest, 1990)
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 28
Causes of Claims on Road Projects in Ethiopia
Clause
No. Clause title Entitlement
Additional Cost +
6.3 & 6.4 Delay in engineering drawings with in reasonable time Time Extensions
Additional Cost +
17.1 Setting out(errors based on incorrect data) Profit
Additional Cost +
18.1 Exploratory boreholes Profit
Additional Cost +
20.3 Repairs and employer’s risks Profit
Additional Cost +
27.1 Fossils, antiquities, structures Time Extensions
Additional Cost +
31.2 Opportunities to other contractors Profit
Additional Cost +
36.5 Additional tests Time Extensions
Additional Cost +
40.2 Suspension Time extension
Additional Cost +
42.2 Employer’s failure to give possession Time Extension
Additional cost +
49.3 Cost of remedying defects Profit
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 29
Causes of Claims on Road Projects in Ethiopia
Clause
No. Clause title Entitlement
Additional cost +
52.1 Variations Profit
Additional cost +
65.3 Damage to works by special risks profit
Additional cost +
65.8 Termination of contract profit
Additional cost +
69 Default by the Employer Time Extension
Additional cost +
71 Currency and rate of exchange profit
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 30
Causes of Claims on Road Projects in Ethiopia
Clause
number Clause title Notice
The following table revises claim clauses provided in the new standard
condition of contract by public procurement agency.
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 31
Causes of Claims on Road Projects in Ethiopia
A. General
Cost
+
Execution of the work in accordance with Release from
16.1 the specifications and drawings performance
Additional Cost +
20.1 Historical or other interest discoveries Time Extensions
Additional Cost +
21.1 Possession of site Time Extensions
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 32
Causes of Claims on Road Projects in Ethiopia
B. Time control
Additional Cost +
30.1 Delayed orders by the Engineer Time extension
C. Quality control
D. Cost control
Additional cost
43.1& 43.2 Interest on delayed payment
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 33
Causes of Claims on Road Projects in Ethiopia
Repayment/termin
61.1 Contractor’s default ation
Release from
62.1 Frustration like war performance
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 34
Causes of Claims on Road Projects in Ethiopia
The provisions of the three standard condition of contract is more or less the
same except the following points
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 35
Causes of Claims on Road Projects in Ethiopia
• Claim Notification
• Claim Enforcement
• Claim Preparation
• Claim Submittal • Claim Closure
• Claim Handling
• Dispute Resolution
• Claim Approval
Claim Submittal
This is a process by which the claimant is obliged to claim within a
reasonable period of time (28 – 30 days in most contracts) followed by her/his
preparation for all substantial documents and legal aspects supporting
hers/his entitlements for an official submittal. This constituted that a claim
has been filed for its consideration if all these three sub processes called Claim
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 36
Causes of Claims on Road Projects in Ethiopia
Notification, Claim Preparation and Claim Submittal are fully undertaken by the
claimant.
Claim Processing
This process initiates checking of the claim whether, it is legally or
contractually supported or not; documents provided are valid and reliable to
substantiate the claim for consideration or not; and overall procedural
requirements have been followed or not. After verifying the validity of the claim
proper computations and evaluations will be carried out to present the
proposed compensation for the contractual parties the claim is applicable to.
Generally the sub process that undertakes these requirements is termed as
Claim Handling.
The contractual parties will pass through different dispute resolution system
(DRS) depending on their acceptance over the proposed compensation varying
from the simplest mediation by the consulting engineer to the final court
ruling in the form of litigation.
Claim Enforcement
This is a stage where the approved claim is enforced and finally becomes a
closure therefore two sub processes are included. The claim enforcement
process will entertain the inclusion of the approved claim into payment
certificates where their enforcement is due.
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 37
Causes of Claims on Road Projects in Ethiopia
4.2 Mitigation
For the successful delivery of the project all parties of the project are required
to adopt a policy of claim minimization / mitigation clear identification of
things to be done before and after the work commences, will minimize claims
and assist claim administration process
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 38
Causes of Claims on Road Projects in Ethiopia
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 39
Causes of Claims on Road Projects in Ethiopia
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 40
Causes of Claims on Road Projects in Ethiopia
The free market economy practice in Ethiopia has created a better opportunity
for participation of local and foreign contractors in the construction industry
activities with in the last decade. However, domestic construction companies
are not competitive enough with their international counterparts. In general,
Wubishet, 2004 has stated the reasons why the state of the domestic
construction industry is low as follows:
Despite all this, over 1400 local contractors of different categories have now
registered by the government authority; the financial, technical and
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 41
Causes of Claims on Road Projects in Ethiopia
managerial capability of the major of them is, however limited. (Abebe Dinku
and Girmay Kassay, 2003)
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 42
Causes of Claims on Road Projects in Ethiopia
The other effect of claims on project execution involve time extensions, which
affect project completion in the various local and international projects being
carried out in Ethiopia, there appears to be a common perception of accepting
time extensions more favorably than increased financial expenses.
The result of some surveyed projects shows that, none have been completed on
time. Rather all of them have been granted a time extension. Whilst time
extensions may appear to be necessary in some cases few if any professionals
view the issue of time extensions as a serious claim case. In this aspect it is
necessary to introduce in minds of the practicing Engineers and consultants
that time extension do also incur additional cost where the income or revenue
that may have been obtained from a timely completed project is lost. (Abebe
Dinku and Girmay Kassay, journal of EEA, 2003)
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 43
Causes of Claims on Road Projects in Ethiopia
sever than the financial impact may have on the total project life. (Abebe
Dinku and Girmay Kassay, journal of EEA, 2003)
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 44
Causes of Claims on Road Projects in Ethiopia
PART THREE
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 45
Causes of Claims on Road Projects in Ethiopia
Road sector development has been one of the priority public investment areas
for the success of the envisaged economic recovery program. Road being the
dominant mode of transportation in Ethiopia, both its quality and quantity
had extremely low and became impending to the governments effort in reviving
the economy. (Country poverty alleviation paper, 2002 as quoted by Tesfaye
Ayele). In order to change such sever situation of road infrastructure in the
country so that the transport sector could facilitate the national economic
development efforts, the government has launched a major Road Sector
Development Program (RSDP) in 1997.The program undertook a rapid
assessment of road network and established a phased program for
rehabilitation and upgrading of property segments.
The evaluation of RSDP implementation made by the ERA and the program
inspection office reveals that the weakness experienced by the ERA, during the
implementation of the program is the following.
• Lack of in- house experience in construction contracts
• Defective design works by the design contractors / deficiency in the
contract documents
• Lack of proper design reviews during the design stage of the projects
• Lack of coordination and delay in response by other government
institutions / streamlining
• Poor performance of contractors
• Claimant attitude / claimsmanship / by contractors, etc…
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 46
Causes of Claims on Road Projects in Ethiopia
The following table (Table 6) shows the causes of claims of the seven projects
as collected from the claim documents submitted by contractors.
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 47
Causes of Claims on Road Projects in Ethiopia
No
Project Name Contractor Factors giving rise to claims
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 48
Causes of Claims on Road Projects in Ethiopia
No
Project Name Contractor Factors giving rise to claims
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 49
Causes of Claims on Road Projects in Ethiopia
No
Project Name Contractor Factors giving rise to claims
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 50
Causes of Claims on Road Projects in Ethiopia
No
Project Name Contractor Factors giving rise to claims
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 51
Causes of Claims on Road Projects in Ethiopia
The different factors giving rise to the claims of the seven studied projects are
totally twenty-seven factors. Those factors with high frequency are considered
to be predominant claim factors, as they are repeatedly occurring. Failure to
give possession of site and variations are predominant claim factors in almost
all projects. The twenty-seven factors can be regrouped into the following five
major categories based on their sources.
1. Employer’s / Engineer’s actions/ inactions: -factors included in this
category are:
• Failure to give possession of site
• Delayed supply of shop drawings
• Removal of obstructions
• Untimely advance payment
• Interference with the works
• Administrative breach
• Late instruction by the Engineer
• Delayed Engineer’s approval
• Failure to supply survey control points
2. Third party’s actions/ inactions: -this category includes factors that are
out of the control of the contracting parties. These factors are actions/
inactions that are caused by external parties like the government, local
peoples of other agencies act that affect the contract.
• Illegal labor strike
• Problem with imported materials
• Problems with crossing borders
• Problem with obtaining license
• Break down of law and orders
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 52
Causes of Claims on Road Projects in Ethiopia
Most of the above factors are similar and repeat themselves in the studied
projects. The relative frequency distribution of the twenty-seven factors that
are grouped in the above five categories are shown below. (Table 7)
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 53
Causes of Claims on Road Projects in Ethiopia
Frequency %
No Major category of factors
5 Force Majeur 3 5
Total 60 100%
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 54
Causes of Claims on Road Projects in Ethiopia
Deficiency in
contract
document,
36.7%
The result of the analysis of the seven studied projects reveals that the three
major reasons in the road projects that represent 86.7 %( fig, 3) of the causes
are:
• Employer’s / Engineer’s actions / inactions
• Deficiency in contract documents
• Third party actions / inactions
The following analysis can be made from the information given in the table
below (Table 8) excluding the ring road project.
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 55
Causes of Claims on Road Projects in Ethiopia
Original
Cost Cost
Original Time Time Contract
Project Claimed Granted
Contract Claimed Granted amount
Name (Million (Million
Period (Months) (Months) (Million
Birr) Birr)
Birr)
Woldiya-
Adigrat –
Zalambessa 36 30.35 24.13 203.41 4.75 1.00
Hirna-
Kulubi 30 24.53 4.4 188.08 443.6 62.013
Awash -
Hirna 36 26.63 16.23 256.54 91.72 Nill
Modjo –
Awash –
Mile 36 Nill 33 227.45 375.743 26.024
C1 –
C1 - 24 9.25
Mile – Assab C2 –
*C 1,2&3 C2 - 36 10.5 5.7 285.9 179.6 17.1
C1 – C1-
Chida – C1 - 36 43.9 C1-20.04 93.325 C1-84.5
Sodo C2 – C2–
C 1,2 C2 - 39 29.2 C2 – 2.8 110.60 C2-70.6 57.80
* C-Contract
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 56
Causes of Claims on Road Projects in Ethiopia
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 57
Causes of Claims on Road Projects in Ethiopia
process has some deficiencies and there is inefficiently in the overall project
management process of the project.
The results of the above analysis can be summarized using the bar chart as
follows:
100
80
Percentage
60
40
20
0
Time Cost
Remedial Rights
From figure 4, the following points regarding the claim situation in studied
projects shows that:
• The amount of extension of time claimed by the contractors (63.86 % of
contract period) is relatively higher than the amount granted by the
employer (38.94% of contract period).
• An average claim amount of 91.6% of the contract amount has a very big
difference to the initial contract budget. The average granted claim amount
of 12.01% of the contract amount, which is 13.1% of the claimed amount,
indicates the claimed amount is more exaggerated.
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 58
Causes of Claims on Road Projects in Ethiopia
As discussed in the methodology part of this case study, the second approach to
asses the causes of claims on road projects is the use of survey questionnaires to
gather the opinion of the practitioners. The questionnaires were designed to
collect data regarding the experience of construction firms with respect to the
causes, mitigation measures and early resolution practices of claims.
The questionnaires were grouped into three major sections. The three sections
and their area of assessment are the followings:
• Section one is related to the profile of the construction firms and their
experience in construction claims. In addition the practice of the firms
with regards to the use of different types of conditions of contracts has
been assessed.
• Section two is tailored to asses the relative occurrences of the various
claim factors /causes/in construction firms. Also it tries to asses the
occurrences of claims as time related and cost related claims.
• Section three of the survey questionnaires assesses the impact of
claims, the practice of the firms and clients in claim record system, the
culture of the firm to minimize and/or administer claims and it also
assesses the opinion of the respondents on what to do to reduce the
number of severity of claims or administer claims.
2.2. The respondents
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 59
Causes of Claims on Road Projects in Ethiopia
Contractors 13 11 84.6
Consultants 11 7 63.6
Clients 3 2 66.7
The respondents to the questionnaires are rated in the following form. 66.7%
of the respondents have won/awarded 10-20 contracts for the last ten-
years.41.7% of the respondents to the surveyed questioners rated the projects
they are involved has none to five claim cases.
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 60
Causes of Claims on Road Projects in Ethiopia
and force majeur. The ratings are summarized in the table as shown below
(table 10).
Very Do not
often Often Sometimes occur
Category of causes in % in % in % in %
Contract document
caused 10.1 25.3 64.6 0
The result of the average rate of claim factors shows that the majority of the
claim factors occur sometimes. In addition among the factors those occur often
and very often, the following three causes as the major claim causes that
occur frequently.
• Owner caused and consultant caused (29.8% & 34.7%)
• Deficiency in contract documents (35.4%)
• Third party actions / inactions (27.5%)
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 61
Causes of Claims on Road Projects in Ethiopia
In addition, further detailed analysis of the percentage of the ratings over all
the factors listed as the causes of claims in road projects was carried out and
the following two major results were obtained.
1. The major causes of claims in road projects were identified based on the
higher percentage given by the respondents in each category.
Owner caused
• Failure to give possession of site (53.9%)
• Changes in designs and specifications (53.3%)
• Extra work (50.0%)
Contractor caused
• Delay in completion time (71.5%)
• Inadequate investigation before bidding (42.9%)
Consultant caused
• Instruction for additional work (85.7%)
• Delayed approval of schedules, work orders, samples, laboratory tests,
etc… (41.6 %)
Third party caused
• Obstruction by local people (50%)
• Shortage and problem on delivery of materials (42.9%)
Contract documents caused
• Non availability of survey benchmarks (50%)
2. The attitude of the respondents towards certain specific claim factors was
clearly shown from the frequency distribution of the claim causes.
From the factors listed under the owner caused claims, almost all of the
respondents agree that termination and suspension do not occur in the
projects they experience.
From the factors listed under the contractor caused claims, most of the
contractor’s response towards unbalanced bidding, and not following
instructions was that these factors do not occur in their projects. However, the
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 62
Causes of Claims on Road Projects in Ethiopia
response of the consultants and clients towards the above mentioned factors
was often and sometimes respectively.
From the factors listed under the contract document caused claims, most of
the contractor’s response towards non availability of bench marks was that
this factor occurs very often in their projects. In the contrary, the response of
the clients and consultants towards this issue was that this factor only occurs
sometimes.
On the question regarding on the type of claims that usually occur in road
construction projects, the reply of the respondents was:
• Time claims only: 18.75%
• Both cost and time claims: 81.25%
Impacts
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 63
Causes of Claims on Road Projects in Ethiopia
The results of the above analysis suggests that design review before the
construction work begins and recording keeping during the construction
process are the major types of mitigation methods. Further the results shows
that open communication and partnering is an important mitigation method
that should be practiced from the inception to completion of a project.
The respondents were also requested to indicate the value of the use of
different techniques in reducing the incidence of and/or severity of
construction claims. Their response is shown below.
• Some of the techniques that are rated as very valuable with higher
frequencies are:
- Pre- construction/ pre- design investigation
- Construction scheduling
- Clear contract documents
- Roles and responsibilities of parties
- Design quality assurance/ quality control
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 64
Causes of Claims on Road Projects in Ethiopia
- Careful inspection
• Some of the techniques that are rated as valuable with higher frequencies
are:
- Partnering/ team building
- Planning and open communication
- Value engineering
- Construction meetings
- Constructability review
On the questions regarding the use of claim documentation system, which has
a very important input in administering claims, only 55.6% of the respondents
rated they have claim documentation system.
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 65
Causes of Claims on Road Projects in Ethiopia
PART FOUR
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 66
Causes of Claims on Road Projects in Ethiopia
This part of the thesis provides conclusions based on the findings form the
case study and questioners. It also contains recommendations of methods and
techniques that help in mitigating those claims that are taken as the major
sources of claims.
1 Conclusions
Both results of the analysis reveal that most of the factors that give rise to
claims are sourced out from the above mentioned categories. Most of the
conditions of contracts describe in their clauses that these major causes of
claims are the responsibilities of the employer fully or partially.
• Claims submitted by the contractors are exaggerated.
The results of the analysis of the studied projects show that there is a big
difference between the claimed and granted time extensions and additional
costs. This further shows that contractors are claim oriented and employers
are claim conscious, especially in claims for additional cost. (Refer section
1.2.2 of Part III)
• Contracting parties do not understand their duties and
responsibilities
The analysis of the data collected through questionnaires shows that the
employer’s, consultant’s and the contractor’s responses to some of the causes
of claims is contradicting. It seems that the responses are meant to avoid the
responsibility of their own faults.
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 67
Causes of Claims on Road Projects in Ethiopia
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 68
Causes of Claims on Road Projects in Ethiopia
On the basis of information gathered for this paper, the following research
topics have been identified as areas for further study:
• Techniques of enhancing quality of contract documents
• Enhancing claim management
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 69
Causes of Claims on Road Projects in Ethiopia
2 Recommendations
The purpose of the following recommendation is not to deeply address areas
that need improvement. The intention is only to point out some major issues
that need consideration to enhance the current practice of claim management.
It indicates what the current construction industry can learn from
construction claims submitted on the reviewed projects.
Both the analysis of the case studies and the questionnaires has identified
Employer’s / Engineer’s actions / inactions, Deficiency in contract documents,
and Third party actions / inactions are the major causes of claims on road
projects in Ethiopia. Hence the following recommendations are focused
towards improvements to be made on these causes.
• Knowing the areas where conflict is likely to arise from experience and
carefully planning to address them,
• The design process has to be given adequate time and more investigation
has to be made during design reviews. A highly qualified and experienced
group of professionals has to make design reviews, constructability reviews
and value engineering studies on the final design before going to tendering.
These review tasks can also be given to the design review consultant if
there is lack of qualified in-house staffs.
• A standard checklist has to be prepared with all necessary details for
reviewing the completeness of designs, plans, specifications and tender
documentations. Accordingly documentations have to be checked before
floating the tender. The contract documentation problem areas
encountered or design deficiencies on projects undertaken previously can
be used to develop the checklist;
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 70
Causes of Claims on Road Projects in Ethiopia
• The client has to make sure that the contract documentation is free of
ambiguous terms of contract; errors and omissions; plans and
specifications are adequately referenced and coincide with the terms of
references before entering in to contract. Design consultants’ liability has
to include fitness for the purpose of the design work.
• During adopting any type of standard conditions of contract, care should be
taken on clauses to be added or amended with sufficient knowledge of their
implications.
• Clearly specification of expressed terms up on which the contractor is to
rely and implied terms which may be prompted should be set down
appropriately
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 71
Causes of Claims on Road Projects in Ethiopia
• Adequate time should be given for designers and design consultants for the
preparation of design work with fair fee
• Engineers should give instructions, approvals of schedules, work orders,
samples, laboratory tests, etc… at the right time.
• Adequate compensation should be given to the local peoples who will be
affected by the projects.
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 72
Causes of Claims on Road Projects in Ethiopia
REFERENCES
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 73
Causes of Claims on Road Projects in Ethiopia
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 74
Causes of Claims on Road Projects in Ethiopia
Appendix A
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 75
Causes of Claims on Road Projects in Ethiopia
Owner Caused
Changes in designs and specifications
Untimely payment
Failure to provide possession of site
Extra work
Termination
Inadequate bid information
Suspension
Late removal of obstruction
Contractor Caused
Unbalanced bidding
Inadequate investigation before bidding
Non-compliance with contract document
Schedule updates not done
Not following engineer’s instructions
Change in construction methods
Termination of contract
Lack of expertise
Delay in completion time
Subcontractor’s delay
Consultant Caused
Late instruction additional work
Delayed approval of schedules, work order, samples, lab. tests
Late instructions
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 76
Causes of Claims on Road Projects in Ethiopia
Impractical or impossible
Higher standards
Lack of expertise
other please specify________________
Contract Document
Ambiguity and discrepancies among documents forming contract
Conflicts in designs and specifications
Non availability of survey benchmarks
Errors and omissions
Other please specify________________
Differing conditions
Landslides
Sever weather condition
Shortage of suitable quarry
Other please specify_______________
Force Majeur
Flood
Site security problems
War & hostilities
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 77
Causes of Claims on Road Projects in Ethiopia
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 78
Causes of Claims on Road Projects in Ethiopia
----------------------- // -----------------------
Thank you
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 79
Causes of Claims on Road Projects in Ethiopia
Appendix B
Description / profile of the selected projects.
Project 1
Project name:-------------------------Woldya- Adigrat - Zalambessa road upgrading
project Contract no 2. Betemariam – wukro
Project length: ------------------------- 117.156 Km
Contractor: ----------------------------- China Wanbao Engineering Corporation
Construction commencement date: -April 4, 1999
Scheduled completion date: --------- April 3, 2002
Project duration: --------------------- 36 months
Original contract amount: ---------- Birr 203,410,054.65
Current status:------------------------
Project 2
Project name: ------------------------- Awash – Hirna – Dengego &
Dire Dawa – Dengego- Harrar
Project length: -------------------------91 Km
Contractor: -----------------------------Keangnam Enterprise Ltd. Of Korea
Construction commencement date: -June 4, 1999
Scheduled completion date:---------December 4, 2001
Project duration: --------------------- 30 months
Original contract amount: ---------- Birr 188.08 Million
Current status:------------------------ Completed
Project 3
Project name: -------------------------Awash – Hirna – Dengego &Dire Dawa-
Dengego- Harrar Contract No.1
Awash- Hirna
Project length: ------------------------- 140.7 Km
Contractor: -----------------------------CRBC
Construction commencement date: -June 8, 1999
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 80
Causes of Claims on Road Projects in Ethiopia
Project 4
Project name:------------------------- Modjo - Awash – Mile
Contract No. 1 Modjo -Awash
Project length:-------------------------160.3Km
Contractor:-----------------------------Keangnam Enterprise Ltd. Of Korea
Construction commencement date:-April 1, 1999
Scheduled completion date:---------April 1, 2002
Project duration: --------------------- 36 months
Original contract amount: ---------- Birr
Current status:------------------------ Completed
Project 5
Project name------------------------Addis Ababa Ring Road
Project length:-------------------------
Contractor: -----------------------------CRBC
Construction commencement date: -May, 1999
Scheduled completion date: ---------
Project duration: ---------------------
Original contract amount: ----------
Current status:------------------------
Project 6
Project name: ------------------------- Mile- Assab Road
Project length: -------------------------199 Km
Contractor: -----------------------------SOGEA – French company
Construction commencement date: -March 1995
Scheduled completion date: ---------December 4, 2001
Project duration: --------------------- 60 months
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 81
Causes of Claims on Road Projects in Ethiopia
Project 7
Project name: ------------------------- Chida – Sodo Feeder, Contract 1
Project length: -------------------------166.5 Km
Contractor: -----------------------------Salini
Construction commencement date: -December 1994
Scheduled completion date: ---------October 1998
Project duration: --------------------- 75 months
Original contract amount: ---------- Birr 203.925Million
Current status: ------------------------ Completed
Addis Ababa University, Department of Construction Technology and Management Augest, 2006 82
Causes of Claims on Road Projects on Ethiopia
Appendix A
Owner Caused
Changes in designs and specifications
Untimely payment
Failure to provide possession of site
Extra work
Termination
Inadequate bid information
Suspension
Late removal of obstruction
Contractor Caused
Unbalanced bidding
Inadequate investigation before bidding
Non-compliance with contract document
Schedule updates not done
Not following engineer’s instructions
Change in construction methods
Termination of contract
Lack of expertise
Delay in completion time
Subcontractor’s delay
Consultant Caused
Late instruction additional work
Delayed approval of schedules, work order, samples, lab. tests
Late instructions
Impractical or impossible
Higher standards
Lack of expertise
other please specify________________
Contract Document
Ambiguity and discrepancies among documents forming contract
Conflicts in designs and specifications
Non availability of survey benchmarks
Errors and omissions
Other please specify________________
Differing conditions
Landslides
Sever weather condition
Shortage of suitable quarry
Other please specify_______________
Force Majeur
Flood
Site security problems
War & hostilities
*4. Please indicate the value of the use of the following techniques in
reducing the number of severity of claims or resolving claims
Please indicate on the boxes using the following criteria
1. Very valuable 2. Valuable 3. Not valuable
Roles and responsibilities of parties
Pre design / pre construction investigation
Internal professional managers
Construction / program management consultants
Design quality assurance / quality control
Construction meetings
Construction scheduling
Clear contract document
Keeping records
Choosing appropriate delivery system
Planning & open communication
Partnering / team building
Enhanced quality of contract document
Constructability review
Value engineering
Design review
Proper subsoil and geotecnical survey
Careful inspection
Other please specify-
____________________________________________________
----------------------- // -----------------------
Thank you
Appendix B
Description / profile of the selected projects.
Project 1
Project name:-------------------------Woldya- Adigrat - Zalambessa road
upgrading project Contract no 2.
Betemariam – wukro
Project length: ------------------------- 117.156 Km
Contractor: ----------------------------- China Wanbao Engineering Corporation
Construction commencement date: -April 4, 1999
Scheduled completion date: --------- April 3, 2002
Project duration: --------------------- 36 months
Original contract amount: ---------- Birr 203,410,054.65
Current status:------------------------
Project 2
Project name: ------------------------- Awash – Hirna – Dengego &
Dire Dawa – Dengego- Harrar
Project length: -------------------------91 Km
Contractor: -----------------------------Keangnam Enterprise Ltd. Of Korea
Construction commencement date: -June 4, 1999
Scheduled completion date:---------December 4, 2001
Project duration: --------------------- 30 months
Original contract amount: ---------- Birr 188.08 Million
Current status:------------------------ Completed
Project 3
Project name: -------------------------Awash – Hirna – Dengego &Dire Dawa-
Dengego- Harrar Contract No.1
Awash- Hirna
Project length: ------------------------- 140.7 Km
Contractor: -----------------------------CRBC
Construction commencement date: -June 8, 1999
Scheduled completion date: --------- June 7, 2002
Project duration: --------------------- 36 months
Original contract amount: ---------- Birr 256,542,439.10
Current status: ------------------------
Project 4
Project name:------------------------- Modjo - Awash – Mile
Contract No. 1 Modjo -Awash
Project length:-------------------------160.3Km
Contractor:-----------------------------Keangnam Enterprise Ltd. Of Korea
Construction commencement date:-April 1, 1999
Scheduled completion date:---------April 1, 2002
Project duration: --------------------- 36 months
Original contract amount: ---------- Birr
Current status:------------------------ Completed
Project 5
Project name------------------------Addis Ababa Ring Road
Project length:-------------------------
Contractor: -----------------------------CRBC
Construction commencement date: -May, 1999
Scheduled completion date: ---------
Project duration: ---------------------
Original contract amount: ----------
Current status:------------------------
Project 6
Project name: ------------------------- Mile- Assab Road
Project length: -------------------------199 Km
Project 7
Project name: ------------------------- Chida – Sodo Feeder, Contract 1
Project length: -------------------------166.5 Km
Contractor: -----------------------------Salini
Construction commencement date: -December 1994
Scheduled completion date: ---------October 1998
Project duration: --------------------- 75 months
Original contract amount: ---------- Birr 203.925Million
Current status: ------------------------ Completed