● Project details
1. Kabeli B-1 Cascade HEP
● Capacity: 9.94 MW
● Issue date: 2070-3-28
● Agreement : 2075-08-09
● COD: 2078-10-16
● The project is also an R-O-R project developed at 40% probability of exceedance
● Capacity utilization :90% of contract energy since its commissioning.
● The project was completed at a cost of NPR 2,199 million (NPR 221
million/MW) at a D: E mix of 63:37.
2. Budhum Khola HEP
● Capacity:14.5 MW
● Issue date:2017-10-01
● Phase: Survey license approved
● COMPANY'S INVESTMENT
1. Api Power Company Ltd ( Thapathali, kathmandu)
● Establishment date: 5 Asadh 2060
● Ownership: transferred into public limited company in 6 shrawan 2020
● Investments : 20 millions
Hydro projects
Solar projects
Dhalkebar 1 MW solar project
● Installed capacity : 1 MW(AC side)
● Survey license: 14 mangsir 2073
● COD: 2 Magh 2078
● Revised COD: 2019-6-17
●
Hydropower projects
1. Iwa khola hydropower project
● Installed capacity: 9.9 MW
● Commissioned date : 2072-03-28
● Status: operational
● Generating electricity since 2076-06-20
3. Janata bank
● Investment: 60 million
●
Hydropower projects
1. Ridi khola hydropower station (palpa district)
● Installed capacity: 1.8 MW
● Commission date : 2070-04-24
● Generating electricity : 2070-04-24
● Status: operational
Solar projects
1. Butwal solar hydropower projects(Rupandehi)
● Power station capacity: 8.5 MW
● Solar panels: 32,640(each generating 330 Watt peak power)
● Construction began : 2019
● Construction ended: 2020 (constructed in 10 Months)
● Cost: 65.5 crores
● Agreement with NEA : 7.3/units for 25 years( after 25 years ownership will
be transferred to Nepal Government
● Status: commissioned
Hydroprojects
1. Uppalo Khimti HEV
● Installed capacity: 12 MW
● Energy: 72.57 GWH
● Investments: 75:25
● PLF: 69.04%
● Cost: 1392 million
● Agreement date: 2067-10-09
● RCOD : 2018-7-16
● PPA agreement: Rainy 4 and winter 7
● Escalation period: 9 yrs
Hydroprojects
1. Arun Kabeli 1
● Type : R-O-R
● Energy : 151.65 GWH
● Investments : 1500 millions
● PLF: 80%
● Cost: 5000 millions
● Agreement : 2012-7-13
● COD: 2019-11-09
● PPA details: Rainy 4.8 and winter 8.4