Installation Sequence
Installation Sequence
Installation Sequence
Classification: External
Title: Installation sequence description Doc.ID:
Revision: 2
Author: Pekka Piispa Status: Approved
Approved by: Pekka Piispa / June 23, 2020 Pages: 1 (15)
Project: P/19004- BMPP 60MW Kolaka 1
Description: Installation sequence of phase 1
Type: Description
1 LIST OF CONTENT
Contents
Installation sequence description, BMPP Kolaka 1 ..................................................................... 1
1 LIST OF CONTENT ................................................................................................................ 1
2 INSTALLATION SEQUENCE ................................................................................................. 2
2.1 Modules and units bellow main deck .............................................................................. 2
2.2 Modules and units on main deck –Engine hall ................................................................ 4
2.3 Modules and units on main deck – Utility block .............................................................. 9
2.4 Mechanical utility area and 150 kV substation .............................................................. 11
Doc. Classification: External
DocID: Revision: - 2(15)
2 INSTALLATION SEQUENCE
To assure a steady and fluent construction process and minimizing the possibility of damaging the
modules and units during construction, therefore, a timely installation schedule is essential.
The modules, all possible piping, cable trays and ducting should be installed in early-stage to the
blocks.
By avoiding cutting a large opening to the main deck for lifting modules to the tank top, the
following units are lifted and secured in place already at the point of joining the pontoon blocks
10X.
Once the blocks 103P, 103C, 103S, 104P, 104C and 104S between frames 39 to 79 are welded
together the units and modules are ready to be lifted on the place to the tank top (1400 above
baseline, -6.500 from the main deck).
Due to ongoing erection work on the inner bottom, the protection of the modules and units to be
reinforced with necessary material such a steel sheets or fireproof blankets.
Doc. Classification: External
DocID: Revision: - 4(15)
For minimizing time-consuming hauling of material via service hatch or possible bigger opening in
desired location on main deck, all possible equipment and material such prefabricated, pressure
tested and treated piping sections and piping supports, platform frames and stairs should place on
blocks 10X prior to continuing erecting of blocks 20X.
For instance, the piping located in the corridor between LFO Service tanks could be fabricated,
pickled, flushed and pressure tested in advance in order to install the section of the piping to the
final location with supports and brackets before continuing with following 20X blocks.
All loose materials located in the blocks 20X such piping sections, air ducting, ventilation fans and
silencers under the main deck should be positioned and secured before blocks 20X are installed
on top of blocks 10X.
This would minimize the time-consuming hauling of material through the service hatch to the below
deck.
If this is not possible and cutting of a temporary opening on the main deck will be necessary, the
following concerns shall be considered:
I. When closing the opening, necessary scaffolding below the main deck must be arranged. This
costs time, money and takes up workspace from other activities.
II. All materials such as modules, units, cables, and panels to be well protected prior to closing
the opening
III. Welding of the opening might deform shape of the main deck and change the alignment of the
engine base plates.
IV. The opening reduces the necessary free deck surface area from other uses.
V. The installation of ducting, piping or cabling under the deck cannot be completed on the
location of the opening.
To ensure a smooth and efficient erection, it is necessary to schedule tasks according to the
overall need for building project and not just the scope of the individual department. All tasks
require good coordination and time management between different sub-departments.
Figure 2. Location of modules and unit on the 20X blocks – Engine hall
Doc. Classification: External
DocID: Revision: - 7(15)
All welding work on the main deck such welding of the structural steels of the engine hall and utility
block, welding of baseplates for the EG sets, foundation frames for the units and modules to be
fully completed prior surface preparation and coating of the tanks below the main deck. This is
important to avoid damaging the finished coating on the tank.
These construction phases can be timed so that once the welding work on the main deck has been
completed in a certain area, the surface treatment of the tanks can be continued simultaneously
with the erection of the structural steel and the wall panels elsewhere.
A special attention to be made for the flatness of the main deck. Welding instruction to be strictly
followed when welding the blocks (20X) together in order to minimize deck straightening work prior
aligning base plates for the EG sets.
The following installation sequence can be used for timely progressing work:
1. Steel structure of engine hall, utility block and mechanical utility area
o The steel structure of engine hall should start in auxiliary area of EG set #6 and
continue systematically towards utility block and EG set #1. By doing so, the
construction of the utility block and engine auxiliary area can be conducted
simultaneously.
o The erection of the steel structure above the main deck can be continued keeping
in mind the installation order of the auxiliary and exhaust modules with the
associated air and exhaust ducts.
o As soon as practically possible, the installation of wall panels of auxiliary area and
utility block can be started.
o The rafters of the roof can be installed by leaving openings large enough to lift
auxiliary equipment and EG sets. The installation of the roof panels should be
postponed until all EG sets have been lifted onto engine foundation to steel
springs.
2. Engine foundation
o Simultaneously with erection of steel structure of engine hall, the steel baseplates
of the engine foundation to be positioned, aligned, shimmed/machined and fully
welded by following the welding instructions.
o A special attention to be paid for the parallel orientation of the baseplates of
individual steel spring packages. Tolerance for surface level difference between
any two points of foundation baseplates of the engine is ≤ 4 mm.
3. Piping
o The installation of piping fabricated at site, such cooling water piping between
modules and the radiators to be started.
o Installation of sprinkler and fire protection related piping to be started where
possible.
4. Auxiliary modules
o Auxiliary modules EAM, CBU and LO separator modules to be slide into position by
using opening in auxiliary area steel structure. For example, modules of the EG set
#1, 2 and 3 could be slide in from the opening of EG set #4 (frame 36-45). The rest
of the auxiliary modules of EG sets #4, 5 and 6 could be slid to position from
landing area A, B – 8, 9 (frame 63-72).
Doc. Classification: External
DocID: Revision: - 8(15)
5. Overhead crane
o The overhead crane of the engine hall can be lifted into position as soon as the
steel structure of engine hall allows. The crane can be utilized during construction
work.
9. EG sets
o Lifting of EG sets on its foundation.
17. Cabling
o The installation of cable trays and pulling the cable to be started.
Figure 3. Location of modules and unit on the 20X blocks – Utility block - +0.000 to +2.000
Figure 4. Location of modules and unit on the 20X blocks – Utility block +6.500
Doc. Classification: External
DocID: Revision: - 11(15)
The following installation sequence can be used for timely progressing work:
2. Utility block
o As soon as practically possible, the installation of wall panels and flooring of utility
block can be started.
5. Control room
o The installation of cubicles in the control room to be completed as soon as possible
in order to start with time-consuming cable pulling and termination phase.
1) Substation control panels
2) DC panel
3) Control panel, common
4) Control panel, engine wise
5) Fire detection panel
6) Frequency converter for radiator
7) Gas detection panel
The hot work on mechanical utility area on Main Deck (+0.000 or 7.900 A.BL) to be completed in a
timely manner in order to finalize surface preparation and coating of all hull structure tanks.
This is important to avoid damaging the finished coating on the tank.
Table 4. Mechanical utility area – Outside of engine hall and utility block
Figure 5. Mechanical utility area – Main deck- Outside of engine hall and utility block
Doc. Classification: External
DocID: Revision: - 13(15)
Figure 6. Mechanical utility area – +24.000- Outside of engine hall and utility block
Figure 7. Mechanical utility area - Outside of engine hall and utility block
Doc. Classification: External
DocID: Revision: - 14(15)
The following installation sequence can be used for timely progressing work:
2. Station transformers
o Station transformers could be installed to the foundation in order to complete the wall
panelling and roofing around.
4. Step-up transformers
o Once the fire walls and steel structures of substation and utility block are erected, the
step-up transformers can be installed.
13. Cabling
o Installation of cable trays and cable pulling for the units above roof can be started.