Resource Scheduling
Resource Scheduling
SCHEDULING
RESOURCE SCHEDULING
(Finalizatin if priject implementatin Schedule)
• At the zero date of the project, we have to set a tie
target for its coipleton.
• There is a qualitatve diference between cost and tie
target setng process.
• Tiie is not so iuch dependent on the quantui of work
as cost.
• The duraton of a project can be coipressed by putng
additonal resources on the job.
• Realistc tie targets can be arrived at only successively
revising the schedule but stll a schedule for feasibility
study is required at the zero date to set a target.
Time estmate if a Priject
• Tiie estiate is iade by iaking a work breakdown of
the project, estiatng the tie schedules for each
work, putng thei in proper sequence, i.e. in series or
parallel as per technical or any other logical ianner and
finally iatching their builduup on a tie scale with the
available resources. The total stretch on the tie scale
corresponding with the resources sets the target.
• The tie estiated for a project coipleton is
dependent not only on the work content or the
sequence, it will also be infuenced by resources and
constraints.
The various approaches for estiatng the
tie duraton of a project:
1.) Time study appriach:
Tiie “T” for coipletng a work is T = Q___
Pxn
Where, Q = Total Quantty of work
P = Productvity Factor, i.e. output per ian
day using norial iethod of doing work
n = Norial Size of Crew