100% found this document useful (1 vote)
283 views2 pages

Project Schedule (Realtime, Optimistic, Pesimistic Schedule)

The document outlines a project schedule for the construction of a three-storey building in Dagupan, Pangasinan. It includes item descriptions, quantities, units, and optimistic, most likely, and pessimistic duration estimates for general requirements, civil works, roofing works, and architectural finishes. The schedule involves tasks such as mobilization, permitting, excavation, concrete work, masonry, plastering, roof truss installation, flooring, and wall finishes.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
283 views2 pages

Project Schedule (Realtime, Optimistic, Pesimistic Schedule)

The document outlines a project schedule for the construction of a three-storey building in Dagupan, Pangasinan. It includes item descriptions, quantities, units, and optimistic, most likely, and pessimistic duration estimates for general requirements, civil works, roofing works, and architectural finishes. The schedule involves tasks such as mobilization, permitting, excavation, concrete work, masonry, plastering, roof truss installation, flooring, and wall finishes.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Project : CONSTRUCTION OF THREE STOREY BUILDING

Location : DAGUPAN, PANGASINAN


Subject : PROJECT SCHEDULE

MOST LIKELY PESSIMISTIC


Item Description Quantity Unit OPTIMISTIC TIME DURATION
TIME TIME
1.0 GENERAL REQUIREMENTS -
1.1 Mobilization/demobilization 1.00 lot 355.00 380.00 430.00 385.00
1.2 Bonds and Insurances 1.00 lot 355.00 380.00 430.00 385.00
1.3 Government Permits 1.00 lot 12.00 17.00 25.00 18.00
1.4 Preparation of Temporary Facilities including furnitures, electrical and water utilities 1.00 lot 6.00 8.00 9.00 8.00
1.6 Materials Testing 1.00 lot 355.00 380.00 430.00 385.00
1.8 Safety and Security Requirements 1.00 lot 355.00 380.00 430.00 385.00
1.9 Surveying and Stake-out 1.00 lot 355.00 380.00 430.00 385.00
1.10 As-Built and other deliverables 1.00 lot 11.00 13.00 18.00 14.00
1.11 Construction Engineering Supervision 1.00 lot 355.00 380.00 430.00 385.00
1.12 Others, Pls. specify:
a. - - -
- - -
2.0 CIVIL WORKS - - -
2.1 Clearing and Grubbing 283.00 sq.m 1.00 1.00 7.00 2.00
2.2 Excavation 225.00 cu.m 1.00 2.00 11.00 4.00
2.3 Gravel Bedding 50.00 cu.m 2.00 6.00 9.00 6.00
2.4 Soil Poisoning 518.00 sq.m 1.00 2.00 5.00 3.00
2.5 Vapour Barrier / Polyethylene Sheet Liner 283.00 sq.m 1.00 1.00 4.00 2.00
2.6 Backfill and Compaction 212.00 cu.m 1.00 3.00 9.00 4.00
2.7 Hauling / Disposal of Excess and Unsuitable Materials 13.00 cu.m 1.00 1.00 3.00 2.00
2.8 Concrete, 3000 psi (foundations/columns/beams/slab on fill/suspended slab(2F)/stairs/canopy) 231.00 cu.m 21.00 31.00 51.00 33.00
2.9 Formworks 1,714.00 sq.m 69.00 75.00 90.00 77.00
2.10 RSB 21,325.44 kgs 15.00 21.00 36.00 23.00
2.11 100mm thk. CHB Wall, including reinforcement 284.00 sq.m 8.00 10.00 34.00 14.00
2.12 150mm thk. CHB Wall, including reinforcement 1,202.00 sq.m 38.00 48.00 72.00 51.00
2.13 Plastering (interior and exterior walls) 2,972.00 sq.m 43.00 53.00 83.00 57.00
2.14 Others, Pls. specify: - - -
a. - - -
- - -
3.0 ROOFING WORKS - - -
3.1 Base Plate for truss, MS Plate 300 x 300 x16mm thk 27.00 set(s) 1.00 3.00 7.00 4.00
3.2 Anchor Bolt, 20mm dia x 400mm(A305) 108.00 set(s) 1.00 2.00 8.00 3.00
3.3 Roof Trusses 7,610.47 kgs 13.00 17.00 29.00 19.00
3.4 Roof Purlins 1,720.22 kgs 2.00 4.00 19.00 7.00
3.5 Sag Rod 12mmØ 110.00 set(s) 1.00 2.00 12.00 4.00
3.6 Cross Bracing, 20mmØ plain round bars including 20mm std. turnbuckles 12.00 set(s) 1.00 1.00 7.00 2.00
3.7 Pre-painted Hi-Rib G.I. Sheet, Long Span, Ga.#24 including insulation 242.00 sq.m 15.00 21.00 45.00 24.00
3.8 Stainless Gutter, Ga.#24 26.00 l.m 1.00 1.00 13.00 3.00
3.9 G.I. Flashing, Ga.#24, Prepainted 57.00 l.m 1.00 1.00 13.00 3.00
3.10 Others, Pls. specify: - - -
a. - - -
- - -
4.0 ACHITECTURAL FINISHES - - -
4.1 Floor Finishes - - -
4.1.1.Plain Cement Floor Finish 688.00 sq.m 12.00 15.00 35.00 18.00
4.1.2.Ceramic Floor Tiles,Unglazed/Matte, 200mm x 200mm x 6mm thk. Fin. @ CR 72.00 sq.m 5.00 7.00 22.00 10.00
4.1.3. Waterproofing for 2F Comfort Rooms 72.00 sq.m 1.00 2.00 14.00 4.00
4.2 Wall Finishes - - -
4.2.2. Ceramic Wall Tiles,Glazed, 200mm x 200mm x 6mm thk. Fin. @ CR 322.00 sq.m 25.00 30.00 54.00 34.00
4.3 Ceiling Finishes - - -
4.3.1. Ordinary Plywood 1/4" thk., in metal frame & tension rod supports 656.00 sq.m 54.00 66.00 96.00 69.00
4.4 Paint Finishes - - -
4.4.1. Wall Paint, Interior and Exterior, Semi-Gloss Latex Paint Finish 2,751.00 sq.m 154.00 164.00 194.00 168.00
4.4.2. Ceiling Paint, Semi-Gloss Latex Paint Finish 652.00 sq.m 34.00 44.00 68.00 47.00
4.4.3. Structural Steel Paint, Red Oxide Paint Finish 828.00 sq.m 42.00 52.00 82.00 56.00
4.5 Door Schedule - - -
4.5.1. D1, Tanguile Flush Door (0.90mW x 2.10mH) 15.00 set(s) 8.00 12.00 22.00 13.00
4.5.2. D2, Plywood Flush Door (0.70mW x 2.10mH) 5.00 set(s) 1.00 3.00 7.00 4.00
4.5.3. D3, Plywood Flush Door (0.65mW x 2.10mH) 18.00 set(s) 5.00 10.00 22.00 12.00
4.5.4. D4, Plywood Flush Door (0.80mW x 2.10mH) 3.00 set(s) 1.00 2.00 6.00 3.00
4.5.5. D5, Sliding Door Glass Panel with analok frame (1.60mW x 2.10mH) 2.00 set(s) 2.00 4.00 8.00 5.00
4.5.6. Gate and Fence 1.00 set(s) 1.00 2.00 12.00 4.00
4.6 Window Schedule - - -
4.6.1. W1, Steel Casement Window (1.60mW x 1.25mH), 4 equal panels with grills 15.00 set(s) 16.00 21.00 35.00 23.00
4.6.2. W2, Steel Casement Window (0.80mW x 0.60mH). 2 equal panels 15.00 set(s) 4.00 6.00 16.00 8.00
4.6.3. W3, Steel Casement Window (0.50mW x 0.50mH) 18.00 set(s) 2.00 4.00 14.00 6.00
4.00 set(s) 2.00 4.00 10.00 5.00
4.6.4. W4, Steel Casement Window with Analok Frame (2.30mW x 1.20mH), 4 equal panels
4.7 Stair Finishes - - -
50mmØ BI Pipe handrail 118.00 l.m 14.00 19.00 34.00 21.00
25mmØ BI Pipe midrail 108.00 l.m 12.00 17.00 32.00 19.00
Aluminum Stair Edging, anodized edging; 1.30m length. 55.00 pcs 2.00 7.00 22.00 9.00
4.8 Handrails - - -
50mmØ BI Pipe handrail 104.00 l.m 14.00 17.00 29.00 19.00
25mmØ BI Pipe midrail 45.00 l.m 5.00 8.00 20.00 10.00
4.9 Others, Pls. specify: - - -
a. - - -
- - -
5.0 ELECTRICAL WORKS - - -
SUPPLY OF MATERIALS AND ELECTRICAL EQUIPMENT: - - -
A. Electrical Equipment - - -
5.1 Panel Board A to E 15.00 assy(s) 15.00 17.00 23.00 18.00
Main: 60AT/100AF, 230V, 2P, 60Hz, MCCB, Bolt on Type - - -
Branches: - - -
1 - 15AT/100AF, 230V, 2P, 60Hz, MCCB - - -
3 - 20AT/100AF, 230V, 2P, 60Hz, MCCB - - -
2 - 30AT/100AF, 230V, 2P, 60Hz, MCCB - - -
5.2 Panel Board Reception 1.00 assy(s) 1.00 2.00 5.00 3.00
Main: 40AT/100AF, 230V, 2P, 60Hz, MCCB, Bolt on Type - - -
Branches: - - -
1 - 15AT/100AF, 230V, 2P, 60Hz, MCCB - - -
2 - 20AT/100AF, 230V, 2P, 60Hz, MCCB - - -
3 - 30AT/100AF, 230V, 2P, 60Hz, MCCB - - -
5.3 Enclosed Circuit Breaker - - -
60 Amp, 230V, 2P, 60Hz, MCCB 15.00 set(s) 1.00 2.00 7.00 3.00
40 Amp, 230V, 2P, 60Hz, MCCB 1.00 set(s) 1.00 1.00 6.00 2.00
5.4 Electrical Meter - - -
kw-hr meter 16.00 set(s) 2.00 3.00 8.00 4.00
B. Wires and Cables - - -
5.5 THWN Wire - - -
80 mm² THWN Wire 24.00 mtrs 1.00 2.00 8.00 3.00
22 mm² THWN Wire 12.00 mtrs 1.00 1.00 7.00 2.00
14 mm² THWN Wire 618.00 mtrs 4.00 6.00 26.00 9.00
8.0 mm² THWN Wire 87.00 mtrs 1.00 1.00 11.00 3.00
5.5 mm² THWN Wire 354.00 mtrs 1.00 2.00 14.00 4.00
3.5 mm² THHN Wire 954.00 mtrs 4.00 5.00 25.00 9.00
2.0mm² THHN Wire 1,125.00 mtrs 5.00 7.00 31.00 11.00
C. Conduits and Raceways - - -
5.6 Conduits - IMC Pipe - - -
50 mm DIA. IMC Pipe 4.00 length 1.00 1.00 5.00 2.00
25 mm DIA. IMC Pipe 103.00 length 8.00 10.00 30.00 13.00
20 mm DIA. IMC Pipe 13.00 length 1.00 2.00 17.00 5.00
15 mm DIA. IMC Pipe 236.00 length 18.00 23.00 53.00 28.00
5.7 Cable Tray - - -
150mmD x 225mmW Cable Tray, Ladder Type 1.00 length 1.00 2.00 6.00 3.00
D. Wiring Devices - - -
5.8 Lighting Fixtures - - -
Pinlight Fixture 42.00 set(s) 4.00 6.00 12.00 7.00
20W Fluorescent Lamp 35.00 set(s) 4.00 5.00 15.00 7.00
1 Gang Switch 36.00 set(s) 2.00 5.00 15.00 7.00
2 Gang Switch 15.00 set(s) 1.00 2.00 12.00 4.00
3 Gang Switch 3.00 set(s) 1.00 1.00 11.00 3.00
5.9 Power Receptacles - - -
Duplex Outlet with ground, 230V, 2P, 60 Hz 84.00 set(s) 2.00 4.00 18.00 6.00
Special Purpose Outlet with ground, 230V, 2P, 60 Hz 21.00 set(s) 1.00 1.00 15.00 4.00
Weatherproof Duplex Outlet, 230V, 2P, 60 Hz 18.00 set(s) 1.00 1.00 15.00 4.00
- - -
6.0 SANITARY / PLUMBING - - -
6.1 Construction of Septic Vault 1.00 lot 1.00 2.00 17.00 5.00
6.2 Utility Fixtures and accessories - - -
6.2.1. Water Closet, complete with fittings 18.00 unit(s) 3.00 5.00 25.00 8.00
6.2.2. Shower set, complete with valve and fittings 18.00 unit(s) 2.00 3.00 23.00 7.00
6.2.3. Wall Hung Lavatory set, complete with faucet and fittings 18.00 unit(s) 3.00 5.00 25.00 8.00
6.2.4. Kitchen Sink, stainless, complete with faucet and fittings 18.00 unit(s) 3.00 5.00 25.00 8.00
6.2.5. Grease Trap complete w/ fittings 18.00 unit(s) 3.00 5.00 25.00 8.00
6.2.6. Floor Drains, 4" x 4" steel stainless type 30.00 unit(s) 1.00 2.00 22.00 6.00
6.2.7. Hose Bibb 5.00 unit(s) 1.00 1.00 21.00 5.00
6.2.8. Soap Holder 18.00 unit(s) 1.00 2.00 22.00 6.00
6.2.9. Tissue Holder 18.00 unit(s) 1.00 2.00 22.00 6.00
6.2.10. Bidet Spray/Ablution Hose 18.00 unit(s) 1.00 1.00 21.00 5.00
6.2.11. Facial Mirror, 500mm x 800mm 18.00 unit(s) 1.00 3.00 23.00 6.00
6.3 Storm Drainage System - - -
6.3.1. uPVC PIPES (3.0 Meters Length) x 160mmØ 48.00 lengths 4.00 5.00 20.00 8.00
6.3.2 Roof Strainer (100mmØ) 7.00 units 1.00 1.00 21.00 5.00
6.3.3. Catch Basins 13.00 units 1.00 2.00 7.00 3.00
6.3.4. Fittings (tee, wye, elbows, etc.) 1.00 lot 3.00 5.00 20.00 8.00
6.4 Soil, Waste Pipes and Vent System - - -
6.4.2. uPVC PIPES (3.0 Meters Length) x 110mmØ 54.00 lengths 4.00 7.00 22.00 9.00
6.4.3. uPVC PIPES (3.0 Meters Length) x 90mmØ 18.00 lengths 2.00 3.00 18.00 6.00
6.4.4. uPVC PIPES (3.0 Meters Length) x 63mmØ 24.00 lengths 2.00 3.00 18.00 6.00
6.4.5. Fittings (tee, wye, elbows, etc.) 1.00 lot 4.00 7.00 22.00 9.00
6.5 Cold Waterline System - - -
6.5.1. Polypropylene Pipe, PN10/PN16 Pipe, 4.0 mts. Length DN 20 mmØ (1/2") 160.00 lengths 15.00 20.00 35.00 22.00
6.5.2. Water meter 25 mmØ 16.00 unit 1.00 1.00 11.00 3.00
6.5.3. Fittings (tee, elbow, etc.) 1.00 lot 15.00 20.00 35.00 22.00
6.5.4. Gate Valves 50 mmØ 2.00 pcs 1.00 1.00 11.00 3.00
6.5.5. Gate Valves 20 mmØ 18.00 pcs 1.00 1.00 11.00 3.00
6.6 Others, Pls. specify: -
a.

Prepared by: ENGR. CHRISMAE JHUNRIEL LLORCA

You might also like