Multimedia Filter and Activated Carbon Filter Pilot Test Study

Download as pdf or txt
Download as pdf or txt
You are on page 1of 10
At a glance
Powered by AI
The document discusses the results of a pilot test study conducted on a multimedia filter and activated carbon filter to treat wastewater from a evaporation pond. The study aimed to test the removal of total suspended solids (TSS) and chemical oxygen demand (COD) from the wastewater.

The purpose of the project is to provide a containerized or skid mounted wastewater treatment plant to treat a portion of wastewater from an evaporation pond that is used to drain de-oiled wastewater from a Juaymah Terminal.

A pilot multimedia filter and activated carbon filter were constructed and tested. The tested process included clarification, multimedia sand filtration and activated carbon filtration. The efficiency was tested by measuring various water quality parameters at the inlet and outlet.

PROJECT: Contenairized wastewater treatment plant

Project Nbr : Contract Nbr : EPPM document Nbr Rev

Date Page 1 from 10

REPORT

MULTIMEDIA FILTER AND ACTIVATED CARBON


FILTER PILOT TEST STUDY

JUAYMAH TERMINAL CONTENAIRIZED WATEWATER TREATMENT


PLANT

0 27/11/2022
NAME AIMED NAME AIMED NAME AIMED
REV DATE Designation
Prepared by Verified by Approved by
Revisions report:

Revision No Revision Description


0 ISSUED FOR INFORMATION
NO.
PILOT TEST STUDY Rev. 0
PAGE: 3 / 10

TABLE OF CONTENTS

1 INTRODUCTION ................................................................................................................... 4
1.1 PROJECT BACKGROUND..............................................................................................................................4
1.2 PROJECT DESCRIPTION ............................................................................................................................... 4
1.3 DOCUMENT SCOPE ...................................................................................................................................... 4
1.4 DEFINITION .................................................................................................................................................. 4
2 METHOD AND MATERIAL .................................................................................................. 5
3 TEST RESULTS ....................................................................................................................... 9
NO.
PILOT TEST STUDY Rev. 0
PAGE: 4 / 10

1 INTRODUCTION

1.1 PROJECT BACKGROUND

The purpose of the project is to provide a containerized or a skid mounted wastewater treatment plant to
treat a portion of wastewater evaporation pond.

The evaporation pond is used to drain the de-oiled wastewater from the Juaymah Terminal.

1.2 PROJECT DESCRIPTION

This contract is to supply, operate, and maintain a wastewater treatment system (skid or containerized unit)
to treat the Juaymah Tank Farm evaporation pond wastewater for disposal into the marine environment.

1.3 DOCUMENT SCOPE

The scope of this document is to present an overview and give the results of the pilot test study on the
performance of multimedia filter and activated carbon filter in the TSS and COD removal.

1.4 DEFINITION

For the purpose of this document, the following definitions shall apply:

Project : Design, Supply Installation, Testing, Commissioning and operation of


wastewater treatment plant.

Contractor : EPPM “Engineering Procurement & Project Management”

Supplier : The party manufacturing and/or supplying the materials, equipment and
services required to perform the duties as specified by the Contractor.
NO.
PILOT TEST STUDY Rev. 0
PAGE: 5 / 10

2 METHOD AND MATERIAL

Organic matter in the effluent water as well as the performance of the ceramic filter have presented many
challenges during the last performance test of the plant. For that, a pilot test was conducted to enhance
organic matter and suspended solid removal to substitute the ceramic filter. The tested process combination
included the clarification, multimedia sand filtration and activated carbon filtration. The source water for
the pilot test has been took from the outlet of the degassing unit. The efficiency of process was assayed by
measuring the COD, Ammonia, turbidity, pH and residual chlorine at the effluent water. A sample was also
sent to laboratory for detailed analysis.

The pilot multimedia filter and activated carbon filter have been constructed as per the below table:

Table 1: Multimedia filter and activated carbon filter characteristics

PARAMETER UNIT VALUE

MULTEMEDIA FILTER

Internal diameter mm 95

Total Length mm 1400

Anthracite ( 0.8 - 1.6 mm ) height mm 650

Fine Sand ( 0.5 - 1 mm ) height mm 150

Coarse Sand ( 1 - 2 mm ) height mm 150

Fine Gravel ( 3 - 6 mm ) height mm 50

Medium Gravel ( 6 -12 mm ) height mm 50

Coarse Gravel ( 10 -18 mm ) height mm 50

ACTIVATED CARBON FILTER

Internal diameter mm 145

Total Length mm 1700

Activated carbon ( 0.8 – 0.9 mm ) height mm 1350

Fine Sand ( 0.5 - 1 mm ) height mm 50

Coarse Sand ( 1 - 2 mm ) height mm 50

Fine Gravel ( 3 - 6 mm ) height mm 50

Medium Gravel ( 6 -12 mm ) height mm 50

Coarse Gravel ( 10 -18 mm ) height mm 50


NO.
PILOT TEST STUDY Rev. 0
PAGE: 6 / 10

Figure 1: Pilot unit

Figure 2: Multimedia filter Layers


NO.
PILOT TEST STUDY Rev. 0
PAGE: 7 / 10

Figure 3: Activated carbon


The test was conducted as per the below configuration:

- The inlet flowrate to the plant was adjusted at 30 m3/h.

- Aluminum sulfate has been injected at the inlet of the DAF as a coagulant. The pH at the DAF is
around 7.1. The coagulation works very well, a large number of sufficiently large flocs are produced,
which neither float up nor sediment in the DAF.

Figure 4: Operating conditons of the DAF


- After the DAF, the caustic soda 50% has been injected to increase the pH to around 10.5 to
precipitate the dissolved material and to allow the proper pH for Ammonia removal.
NO.
PILOT TEST STUDY Rev. 0
PAGE: 8 / 10

Figure 5: pH at the existing clarifier


- After the clarifier, the sodium hypochlorite 12% has been injected for Ammonia and COD
oxidation.

- After the injection of sodium hypochlorite 12 %, the water reaches the degasing tower for
Ammonia stripping by countercurrent aeration.

- After the degasing tower, the water is fed into the aeration zone where the pH is adjusted to around
9.5 by injecting the HCL 33 %.

- After around one hour of operation as per the above configuration the plant has been stopped and
suspended solid allowed to settle in the aeration zone to simulate new clarifier.

- After 30 min of settlement, one of the injection pumps has been used to feed the pilot multimedia
filter and the activated carbon filter from the aeration zone.

Figure 6: Pilot test PFD


NO.
PILOT TEST STUDY Rev. 0
PAGE: 9 / 10

3 TEST RESULTS

Test has been conducted at two different filtration flowrate 120 l/h and 85 l/h. The following table
summarizes the analysis results:
Table 2: Test results

Parameter Unit Test 1 Test 2

Flowrate l/h 120 85

Multimedia filter filtration rate m3/h/m2 17 12

Activated carbon Empty bed contact time min 10 16

Activated carbon approach velocity m/h 7 5

COD mg/l 148 121

Turbidity NTU 0.37 0.26

Ammonia mg/l 0.1 1.2

pH - 8 7.9

Residual chlorine mg/l <0.2 <0.2

Parameter TEST 1 Results TEST 2 Results


AMMONIA
NO.
PILOT TEST STUDY Rev. 0
PAGE: 10 / 10

Parameter
TURBIDITY
pH
COD TEST 1 Results TEST 2 Results

You might also like