Management Plan
Management Plan
The HR system is a collective term for more specific solutions like HRMS (Human
Resources Management System), HRIS(Human Resources Information System), and
HCM(Human Capital Management software). we note that HR systems are usually
called start-up solutions to help recruiters in companies from the small business
segment.
what the system do: Payroll and benefits,Employee development and
performance ,Organizing and analyzing ,Management of employee
information ,Company documents management,Applicant tracking system ,Salary
and benefits administration ,Absence management, Compensation management.
The project team will be a matrix in that team members from each organization
continue to report to their organizational management throughout the duration of
the project. The project manager is responsible for communicating with
organizational managers on the progress and performance of each project resource.
PROJECT SCOPE
The system stores employee, company, customer and applicant data. It also displays
a personal file for each employee. It displays those accepted for work.
MILESTONE LIST
The below chart lists the major milestones for the HR System Project. This chart is
comprised only of major project milestones such as completion of a project phase or
gate review. There may be smaller milestones which are not included on this chart
but are included in the project schedule and WBS. If there are any scheduling delays
which may impact a milestone or delivery date, the project manager must be
notified immediately so proactive measures may be taken to mitigate slips in dates.
Any approved changes to these milestones or dates will be communicated to the
project team by the project manager.
Milestone Description Date
Project Start Preparing to start 10/23/2022
Testing start All functionality tested and all identified errors 01/07/2023
corrected
Project Complete Ending the project 01/30/2023
The WBS Dictionary defines all work packages for the HR System Project. These
definitions include all tasks, resources, and deliverables. Every work package in the
WBS is defined in the WBS Dictionary and will aid in resource planning, task
completion, and ensuring deliverables meet project requirements.
The HR System Project schedule was derived from the WBS and Project Charter with
input from all project team members. The schedule was completed, reviewed by the
Project Sponsor, and approved and base-lined. The schedule will be maintained as a
projectLibre Gantt Chart by the HR System Project Manager. Any proposed changes
to the schedule will follow TSI’s change control process. If established boundary
controls may be exceeded, a change request will be submitted to the Project
Manager. The Project Manager and team will determine the impact of the change
on the schedule, cost, resources, scope, and risks. If it is determined that the
impacts will exceed the boundary conditions then the change will be forwarded to
the Project Sponsor for review and approval.
Any team member or stakeholder may submit a change request for the HR System
Project. The HR System Project Sponsor will chair the CCB and any changes to
project scope, cost, or schedule must meet his approval. All change requests will be
logged in the change control register by the Project Manager and tracked through to
completion whether approved or not.
Communications Conduct:
Meetings:
The Project Manager will distribute a meeting agenda at least 2 days prior to any
scheduled meeting and all participants are expected to review the agenda prior to
the meeting. During all project meetings the timekeeper will ensure that the group
adheres to the times stated in the agenda and the recorder will take all notes for
distribution to the team upon completion of the meeting. It is imperative that all
participants arrive to each meeting on time and all cell phones and blackberries
should be turned off or set to vibrate mode to minimize distractions. Meeting
minutes will be distributed no later than 24 hours after each meeting is completed.
Email:
All email pertaining to the HR System Project should be professional, free of errors,
and provide brief communication. Email should be distributed to the correct project
participants in accordance with the communication matrix above based on its
content. All attachments should be in one of the organization’s standard software
suite programs and adhere to established company formats. If the email is to bring
an issue forward then it should discuss what the issue is, provide a brief background
on the issue, and provide a recommendation to correct the issue. The Project
Manager should be included on any email pertaining to the HR System Project.
Informal Communications:
While informal communication is a part of every project and is necessary for
successful project completion, any issues, concerns, or updates that arise from
informal discussion between team members must be communicated to the Project
Manager so the appropriate action may be taken.
For the HR System Project, control accounts will be created at the fourth level of the
WBS which is where all costs and performance will be managed and tracked.
Financial performance of the HR System Project will be measured through earned
value calculations pertaining to the project’s cost accounts. Work started on work
packages will grant that work package with 50% credit; whereas, the remaining 50%
is credited upon completion of all work defined in that work package. Costs may be
rounded to the nearest dollar and work hours rounded to the nearest whole hour.
Cost and Schedule Performance Index (CPI and SPI respectively) will be reported on a
monthly basis by the Project Manager to the Project Sponsor. Variances of 10% or
+/- 0.1 in the cost and schedule performance indexes will change the status of the
cost to yellow or cautionary. These will be reported and if it’s determined that there
is no or minimal impact on the project’s cost or schedule baseline then there may be
no action required. Cost variances of 20%, or +/- 0.2 in the cost and schedule
performance indexes will change the status of the cost to red or critical. These will
be reported and require corrective action from the Project Manager in order to bring
the cost and/or schedule performance indexes back in line with the allowable
variance. Any corrective actions will require a project change request and be must
approved by the CCB before it can be implemented.
Earned value calculations will be compiled by the Project Manager and reported at
the monthly project status meeting. If there are indications that these values will
approach or reach the critical stage before a subsequent meeting, the Project
Manager will communicate this to the Project Sponsor immediately.
The Project Sponsor is responsible for formally accepting the project’s final
deliverable. This acceptance will be based on a review of all project documentation,
testing results, beta trial results, and completion of all tasks/work packages and
product functionality.
Once a preliminary schedule has been developed, it will be reviewed by the project
team and any resources tentatively assigned to project tasks. The project team and
resources must agree to the proposed work package assignments, durations, and
schedule. Once this is achieved the project sponsor will review and approve the
schedule and it will then be base lined.
The project manager will be responsible for facilitating work package definition,
sequencing, and estimating duration and resources with the project team. The
project manager will also create the project schedule using ProjectLibre and validate
the schedule with the project team, stakeholders, and the project sponsor. The
project manager will obtain schedule approval from the project sponsor and baseline
the schedule.
The project sponsor will participate in reviews of the proposed schedule and approve
the final schedule before it is base lined.
The project stakeholders will participate in reviews of the proposed schedule and
assist in its validation.
The Project Sponsor is responsible for approving all quality standards for the HR
System Project. The Project Sponsor will review all project tasks and deliverables to
ensure compliance with established and approved quality standards. Additionally,
the Project Sponsor will sign off on the final acceptance of the project deliverable.
The Project Manager is responsible for quality management throughout the duration
of the project. The Project Manager is responsible for implementing the Quality
Management Plan and ensuring all tasks, processes, and documentation are
compliant with the plan. The Project Manager will work with the project’s quality
specialists to establish acceptable quality standards. The Project Manager is also
responsible for communicating and tracking all quality standards to the project team
and stakeholders.
The Quality Specialists are responsible for working with the Project Manager to
develop and implement the Quality Management Plan. Quality Specialists will
recommend tools and methodologies for tracking quality and standards to establish
acceptable quality levels. The Quality Specialists will create and maintain Quality
Control and Assurance Logs throughout the project.
The remaining member of the project team, as well as the stakeholders will be
responsible for assisting the Project Manager and Quality Specialists in the
establishment of acceptable quality standards. They will also work to ensure that all
quality standards are met and communicate any concerns regarding quality to the
Project Manager.
Quality control for the HR System project will utilize tools and methodologies for
ensuring that all project deliverables comply with approved quality standards. To
meet deliverable requirements and expectations, we must implement a formal
process in which quality standards are measured and accepted. The Project
Manager will ensure all quality standards and quality control activities are met
throughout the project. The Quality Specialists will assist the Project Manager in
verifying that all quality standards are met for each deliverable. If any changes are
proposed and approved by the Project Sponsor and CCB, the Project Manager is
responsible for communicating the changes to the project team and updating all
project plans and documentation.
Quality assurance for the HR System project will ensure that all processes used in the
completion of the project meet acceptable quality standards. These process
standards are in place to maximize project efficiency and minimize waste. For each
process used throughout the project, the Project Manager will track and measure
quality against the approved standards with the assistance of the Quality Specialists
and ensure all quality standards are met. If any changes are proposed and approved
by the Project Sponsor, the Project Manager is responsible for communicating the
changes to the project team and updating all project plans and documentation.
RISK MANAGEMENT PLAN
The risk in the HR System are:
System users don't change their business process to meet best practices.
The selected technology doesn't adequately meet the business needs
We will do our best to manage these risks.
The HR System Project will consist of a matrix structure with support from various
internal organizations. All work will be performed internally. Staffing requirements
for the HR System Project include the following:
Project Manager (1 position) – responsible for all management for the HR System
Project. The Project Manager is responsible for planning, creating, and/or managing
all work activities, variances, tracking, reporting, communication, performance
evaluations, staffing, and internal coordination with functional managers.
RESOURCE CALENDAR
180
160
140
120
100
80
60
40
20
0
Oct Nov Dec Jan
COST BASELINE
The cost baseline for the HR System project includes all budgeted costs for the
successful completion of the project.