0% found this document useful (0 votes)
40 views2 pages

Project Identifier

The document outlines two infrastructure projects being undertaken by the local government of Pio V. Corpus, Masbate. The first project involves the concreting of 0.60km of road from Brgy. Bugang to Sitio Puro Casabangan at a cost of PHP 10 million over 120 days. The second project covers the concreting of 0.350km of road in Brgy. Bunducan at a budget of PHP 5 million to be completed within 90 days. Both roads will be 5 meters wide and have 0.20 meter thick concrete. The implementing agency is LGU-Pio V. Corpus with support from the DBM and DILG.

Uploaded by

kerwin jay
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
40 views2 pages

Project Identifier

The document outlines two infrastructure projects being undertaken by the local government of Pio V. Corpus, Masbate. The first project involves the concreting of 0.60km of road from Brgy. Bugang to Sitio Puro Casabangan at a cost of PHP 10 million over 120 days. The second project covers the concreting of 0.350km of road in Brgy. Bunducan at a budget of PHP 5 million to be completed within 90 days. Both roads will be 5 meters wide and have 0.20 meter thick concrete. The implementing agency is LGU-Pio V. Corpus with support from the DBM and DILG.

Uploaded by

kerwin jay
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

LGSF-FALGU

PROJECT TITLE : Concreting of Brgy. Bugang to Sitio Puro Casabangan


Road, Pio V. Corpus, Masbate
PROJECT DESCRIPTION : LENGTH OF 0.60KM, WIDTH OF 5.00M, THICKNESS OF 0.20M
PROJECT COST : PHP 10,0000,000.00
PROJECT LOCATION : BUGANG, PIO V. CORPUS, MASBATE
IMPLEMENTING AGENCY : LGU-PIO V. CORPUS
DEVELOPMENT PARTNERS : DBM/DILG
PROJECT DURATION : 120 CD
MGLOO/DILG FIELD OFFICER : GLENDA N. IBAÑEZ
LGSF-FALGU

PROJECT TITLE : Concreting of Brgy. Bunducan Road, Pio V. Corpus,


Masbate
PROJECT DESCRIPTION : LENGTH OF 0.350KM, WIDTH OF 5.00M, THICKNESS OF 0.20M
PROJECT COST : PHP 5,0000,000.00
PROJECT LOCATION : BUNDUCAN, PIO V. CORPUS, MASBATE
IMPLEMENTING AGENCY : LGU-PIO V. CORPUS
DEVELOPMENT PARTNERS : DBM/DILG
PROJECT DURATION : 90 CD
MGLOO/DILG FIELD OFFICER : GLENDA N. IBAÑEZ