Method Statement Earthing, Bonding and Lightning Protection Latest
Method Statement Earthing, Bonding and Lightning Protection Latest
METHOD STATEMENT OF
ELECTRICAL ROUGHING-INS
AT BUILDING WORKS
Method Statement
Electrical Roughing-ins at Building Works
Date:
TABLE OF CONTENTS
1. INTRODUCTION.................................................................................................................................2
2. SCOPE OF WORKS............................................................................................................................2
3. RESPONSIBILITIES............................................................................................................................2
4. TOOLS/EQUIPMENTS........................................................................................................................3
5. MATERIALS.......................................................................................................................................3
6. HANDLING AND STORAGE.................................................................................................................3
7. METHOD OF STATEMENT FOR GROUNDING SYSTEM INSTALLATION...............................................4
8. HEALTH, SAFETY AND ENVIRONMENT (HSE)....................................................................................5
APPENDICES:
2
Method Statement
Earthing, Bonding and Lightning Protection System at Building Works
Davao City Bypass Construction Project (DCBCP) Package I-1 Doc. No.:
Sta. 12+800 to Sta. 23+500
1. INTRODUCTION
The purpose of generating this Method Statement is to define the procedure step by step to implement
the correct practices for Installation of Earthing, Bonding and Lightning Protection System through the
guidelines contained herein so as to ensure that the job execution complies with the requirements and
serves the intended function to a satisfactory level.
2. SCOPE OF WORK
This Method Statement refers to various work procedure contained within project control documents,
which explains and covers the installation of Earthing, Bonding and Lightning Protection
3. RESPONSIBILITIES
6. Skilled 4-person To install the pipe laying layout based on plan
3
Method Statement
Earthing, Bonding and Lightning Protection System at Building Works
Davao City Bypass Construction Project (DCBCP) Package I-1 Doc. No.:
Sta. 12+800 to Sta. 23+500
4. TOOLS/EQUIPMENTS
The following equipment are required for the site preparation works.
7. Shovel 2 Units
5. MATERIALS
Ground Rod, Bare Copper Wire shall be in line with the approved material submittal and approved
shop drawings by local rules and regulations.
On receipt of the Grounding materials at site necessary precautions shall be taken for unloading,
shifting and storage as follows:
1. Materials shall be stored in a covered and dry space at all the time to avoid corrosion.
4
Method Statement
Earthing, Bonding and Lightning Protection System at Building Works
Davao City Bypass Construction Project (DCBCP) Package I-1 Doc. No.:
Sta. 12+800 to Sta. 23+500
2. All materials received at site shall be inspected and ensured that the materials are as per
approved materials submittal.
3. Any discrepancies, damage etc., found will be notified and reported for further action.
4. Materials found not suitable for site use will be removed from site immediately.
5
Method Statement
Earthing, Bonding and Lightning Protection System at Building Works
Davao City Bypass Construction Project (DCBCP) Package I-1 Doc. No.:
Sta. 12+800 to Sta. 23+500
The conductors to be connected shall be cleaned using file card brush and kept inside the
weld cavity of the mould (refer page 119,138 & 139). A steel-retaining disc is positioned in the
bottom of the crucible of the mould to retain the weld powder and starting powder which is
poured in on top. Ignited with a spark gun, the starting powder sets off an exothermic reaction
in the weld powder, reducing it to molten copper alloy. This instantaneously melts the retaining
disc, and flows down to the weld cavity, where it partially melts the conductors, before cooling
6
Method Statement
Earthing, Bonding and Lightning Protection System at Building Works
Davao City Bypass Construction Project (DCBCP) Package I-1 Doc. No.:
Sta. 12+800 to Sta. 23+500
to leave a fusion weld of great mechanical and electrical integrity. All joints shall be checked
for continuity before back filling as per the approved test format to ensure an efficient
grounding system.
O LIGHTNING PROTECTION SYSTEM:
The conductor is of 25x 3 mm bare aluminum tape conductor / bare copper tape conductor.
The roof grid shall be properly fixed to the standing seam with DC tape clips. Wherever offset
is coming square tape clamps shall be used for connecting the tape. Down conductors shall
be positioned to provide the most direct path from aluminum bare tape to copper tape
termination to a low impedance grounding system, to ensure safe and effective dissipation of
the lightning impulse. The down conductors shall be clamped at regular intervals to the wall
or structure and finally shall be connected to the earth pits by using appropriate clamps. The
rod to tape clamp connection shall be tightened to the required torque.
O TESTING OF EARTH RESISTANCE
The Basic Procedure for the fall of potential method is to first connect the test
set terminals C1 and P1 to the ground electrode under test.
Connect the test set C2 terminal to a current probe located some distance
from the electrode and finally connect to the test set P2 terminal probe located
a variable distance between.
The two probes normally are located in a straight line
At each potential probe location, the resistance is recorded.
Fig. 1
7
Method Statement
Earthing, Bonding and Lightning Protection System at Building Works
Davao City Bypass Construction Project (DCBCP) Package I-1 Doc. No.:
Sta. 12+800 to Sta. 23+500
The Health Safety and Environment Project Management Plan institutes the overall mechanism for the
risk management processes with regard to the Project. Processes are implemented at the earliest
stages within the project cycle, identifying risk and facilitating an opportunity for the application of
appropriate mitigation strategies. As an integral part of the planning process, prior to the commencement of
any operational activity a suitable and sufficient specific assessment (RA) of the risks associated with the
works should be undertaken.
Safety Instructions:
Starting instructions will be given by the supervisors at the start of each activity to explain the
methodology of works and to communicate safe working procedures to the operatives. These
talks are structured in a way to highlight to major risks involved in the activity and the various
control measures required in order to minimize the risk. It is delivered in a manner such as the
8
Method Statement
Earthing, Bonding and Lightning Protection System at Building Works
Davao City Bypass Construction Project (DCBCP) Package I-1 Doc. No.:
Sta. 12+800 to Sta. 23+500
Toolbox talk meetings will be held for each crew, on group or employees, regarding more
general topics of the Project HSE Policy; for example, lessons learned, near-miss reports,
implementation of the requirements and message from the LBS management or Employers
HSE personnel.
Hard Hats
Safety Boots with ankle support and steel toe caps
Safety Goggles
High Visibility Vests / Overalls with integrated reflective strips
Hand Gloves
Face Masks
A variety of mechanisms, such as method statement briefings and toolbox talks will be
implemented to ensure all relevant personnel is appropriately informed
In addition to their safety induction received at their arrival on-site, all the workers will have
a toolbox meeting in order to be briefed about the risks of their specific work task, prior to
the start of works.
9
Method Statement
Electrical Roughing-ins at Building Works
Davao City Bypass Construction Project (DCBCP) Package I-1 Doc. No.: SUTJV (ST)-MS-040-A1
Sta. 12+800 to Sta. 23+500
APPENDIX 2
Drawings
Risk Assessment