He O&m
He O&m
He O&m
1
CONTENTS
1. Installation ...................................................................................................................................................................3
1.1 Mechanical installation ........................................................................................................................................3
1.1.1 Location...........................................................................................................................................................3
1.1.2 Pipework..........................................................................................................................................................3
1.1.3 Foundation ......................................................................................................................................................3
1.1.4 Vibration dampers ...........................................................................................................................................3
2. Product description .....................................................................................................................................................5
2.1 Teral HE booster pump system ............................................................................................................................5
3. Shihlin SS2 KP Series Inverter Operations ...................................................................................................................6
3.1 Shihlin SS2 KP Series Operation..........................................................................................................................6
3.2 Shihlin SS2 KP Series Inverter Parameter Settings ..............................................................................................6
3.3 Shihlin SS2 KP Series Inverter Common Alarm Codes .........................................................................................7
4. Fault Finding Chart ......................................................................................................................................................8
2
1. Installation
Warning
Installation and operation must comply with
local regulations and accepted codes of good
practice.
1.1.1 Location
The booster system must be installed in a well ventilated room to ensure sufficient cooling of the pumps and control cabinet.
The booster system must have a 1-metre clearance in front and on the two sides for inspection and dismantling.
1.1.2 Pipework
Arrows on the pump base show the direction of flow of water through the pump. The pipework connected to the booster system
must be of adequate size. The pipes are connected to the manifolds of the booster system. Either end can be used. Apply sealing
compound to the unused end of the manifold, and fit the screw cap. For manifolds with flanges, fit a blanking flange with gasket. To
achieve optimum operation and minimise noise and vibration, it may be necessary to consider vibration dampening of the booster
system.
Noise and vibration are generated by the rotations in the motor and pump and by the flow in pipework and fittings. The effect on the
environment is subjective and depends on correct installation and the state of the other parts of the system.
If booster systems are installed in blocks of flats or the first consumer on the line is close to the booster system, it is advisable to fit
expansion joints on the suction and discharge pipes to prevent vibration being transmitted through the pipework.
All nuts should be re-tightened prior to start-up. The pipes must be fastened to parts of the building to ensure that they cannot move
or be twisted.
1.1.3 Foundation
The booster system should be positioned on an even and solid surface, for instance a concrete floor or foundation. If the booster
system is not fitted with machine shoes, it must be bolted to the floor or foundation.
To prevent the transmission of vibrations to buildings, it is advisable to isolate the booster system foundation from building parts by
means of vibration dampers. Which is the right damper varies from installation to installation, and a wrong damper may increase the
vibration level.
Vibration dampers should therefore be sized by the supplier of vibration dampers. If the booster system is installed on a base frame
with vibration dampers, expansion joints should always be fitted on the manifolds. This is important to prevent the booster system
from "hanging" in the pipework.
Electrical installation
Warning
The electrical installation should be carried out
by an authorised person in accordance with
local regulation and the relevant wiring diagram.
regulations and the relevant wiring diagram.
3
The electrical installation of the booster system must comply with enclosure class IP54. Make sure that the booster system is
suitable for the electricity supply to which it is connected. Make sure that the wire cross-section corresponds to the specifications in
the wiring diagram
After having carried out the mechanical, electrical and hydraulic installation proceed as follows:
4
2. Product description
As standard, Teral HG booster systems consist of two to four AB / AHN / AHI pumps coupled and mounted on a common mild steel
base frame with all the necessary fittings and a control cabinet.
Fig. 3 HE System
Nr. Descriptions
1 Control cabinet
2 Isolating valve
3 Common base plate
4 Suction manifold
5 Teral pump and motor
6 Pressure transmitter
7 Pressure gauge
8 Discharge manifold
9 Pressure tank
5
3. Shihlin SS2 KP Series Inverter Operations
For detailed operation procedures, kindly refer to the Shihlin SS2 Inverter user manual.
Nr. Descriptions
1 LED screen
2 SS2 operation panel
3 Knob
4 Top cover
For all the system that had been delivered, all vital parameters had been pre-set. These parameters are suitable to be used for
inverter from 0.75kW until 2.2kW. Below are the parameters:
For detailed alarm codes, kindly refer to the Shihlin SS2 Inverter user manual.
7
4. Fault Finding Chart
Warning
Before making any connections in pumps, terminal boxes or breaker cabinet, make sure that the
electricity supply has been switched off for at least 10 minutes and that it cannot be accidentally
switched on.
Wait until the pressure has dropped, or lower the pressure on the discharge
Current pressure is higher than or equal to the setpoint.
side of the Teral Water Pump Booster System, and check that the pumps start.
The pumps start, but stop immediately. Re-establish the supply of water to the Teral Water Pump Booster System.
Dry running or no inlet pressure.
The operating pressure is not reached. When the inlet pressure has been re-established, the pumps will restart.
Inlet pressure to low. Check the suction pipe and possible suction strainer.
Unstable water delivery from Teral Suction pipes or pumps partly blocked by impurities. Clean the suction pipes, strainer or pumps.
Water Pump Booster System [applies
to unstable water supply]. Pumps suck air. Check the suction pipe for leakages.
Suction pipe or pumps blocked by impurities. Clean the suction pipe or pumps.
Pumps are running, but deliver no
Non-return valve blocked in closed position. Clean the non-return valve. The non-return valve must move freely.
water.
Suction pipe leaky. Check the suction pipe for leakages.
Air in suction pipe or pumps. Vent and prime the pumps. Check the suction pipe for leakages.
Leakage from the shaft seal. Shaft seal is defective. Replace the shaft seal.