Format - F7A
Type of Cross Drainage works : Face wall height 3.0 m
1 2 3 4 5 6 8
1 Excavation for Structures
Earthwork in excavation for foundation of structures upto 3 m
depth as per drawing and technical specification Clause 1104
includding setting out, construction of shoring and bracing, removal
9.1 Cum 80.820 113.00 9133.00
of stumps and other deleterious matter, dressing of sides and
bottom and backfilling with approved material.
2 Bedding of pipe
Type B (First Class) Bedding
Laying (First Class) bedding on well compacted sand, moorum as 9.2/(B)(i) Cum 3.730 1146.00 4274.00
per Clause 1105 (ii)
197839.00
Grand Total With GST+LC 19% = 235428.00
Quantity Calculation of 1000mm dia Single HP Culvert
Considering Length = 7.50m (3.0 m H)
Depth/
Sl.No. Item Unit No Length Breadth Quantity
Thickness
1 Earthwork in
exacavation cum
Face Wall 2 6.450 1.550 3.000 59.985
Bed 1 4.950 1.830 2.300 20.835
Total = 80.820
2 C.C.Work in
cum
Proportion 1:3:6
Face Wall 2 6.300 1.400 0.100 1.764
Total = 1.764
3 Bedding cum
Bedding 1 5.440 1.530 0.550 4.578
Deduct for pipe 1 5.440 0.156 -0.848
Total = 3.730
4 CC M15 cum
Face Wall 2 4.150 (1.25+0.5)/2 3.000 21.788
Parapet Wall 2 2.000 0.400 0.400 0.640
Apron US & DS 2 2.000 1.500 0.150 0.900
Deduct for pipe 2 (0.75+1)/2 0.785 -1.374
Total = 21.954
6 NP3 HP Rm 3 2.500 7.500