Protection Presentation 2017 - Section 1
Protection Presentation 2017 - Section 1
System Studies
Overview
• Introduction
• Protection fundamentals
– Objectives, components and performance criteria
– Protection zones and reliability
– Fault types, clearance and system impact
– Study considerations
• Transpower protection schemes
– Transmission line protection
– Transformer protection
– Busbar protection
– System protections (AUFLS, AUVLS, SPSs)
• Protection testing and commissioning
Purpose and Objectives
– Review protection concepts
– Review Transpower protection
implementation and commissioning practice
– Protection consideration for power system
studies
• What equipment trips after a fault occurs?
• What is the sequence and timing of trips after a
fault occurs?
• How will protection perform under load conditions?
Protection
Fundamentals
Protection Objectives
Relay Relay
Protection Components
Protection Components
Protection Performance
• Protection Performance Criteria
– Speed
– Reliability / dependability
– Selectivity / discrimination / security
– Sensitivity
• Transpower Protection Design Policy: TP.GP 01.06
• Aspects for Power System Studies
– Protection zones
– Protection reliability
– Protection clearing times
Protection Zones Example (1)
B2 T1 B3
B1 C D B4
L1 L2
A B E FF
G H
H
L3
Protection Zones Example (2)
To Stratford
To Transformers
402 442 462
T1 T2 BUS B
2832 2772
To 33 kV Bus
Unit and Non-Unit Protection
Relay Relay
Relay
Protection Coordination
Relay Relay
Protection Reliability Design
Relay
• Main protection
• Protection Failure
– Mal-operations Relay
• Backup protection
– Local backup
Relay Relay
– Remote backup
CBF
– Circuit breaker failure
Relay
Faults Types
• Fault types: • Power system stability
– Phase and earth impact
connections (3P, 2PE, 2P,
PE)
– Bolted vs. high resistance
– Equipment abnormalities
Fault Clearing Time
• Fault clearing time impact
• Fault clearing time
calculation
Relay Fault
Detection Time
Relay Time
Events
Delays
Relay Contact
Operation /
Signalling
Circuit Breaker
Clearing
Time
Example
B T1
B2 B5
A C
G1
L1 L2
A1 A2 B1 B3 C1
G2
Equipment Op Time [ms] C3
L2 Main 1 20
L2 Main 2 40
CB B3 CBF 200 B4
L3 C2
L1 Backup 800
L3 Backup 800
G2 Backup 2000
CB A1, A2 50
CB B1, B2, B3, B4 50
CB C1, C2, C3 100
Example – Intact System
T=0 : fault occurs
B T1
∆T = +20 : L2 Main 1 operates
∆T = +50 : CB B3 and CB C1 clear B2 B5
A L2 Main 1 L2 Main 1 C
G1 L2 Main 2 L2 Main 2
L1 Backup
L1 L2
A1 A2 B1 B3 C1
G2
CB B3 CBF
A L2 Main 1 L2 Main 1 C
G1 L2 Main 2 L2 Main 2
L1 Backup
L1 L2
A1 A2 B1 B3 C1
G2
CB B3 CBF
A L2 Main 1 L2 Main 1 C
G1 L2 Main 2 L2 Main 2
L1 Backup
L1 L2
A1 A2 B1 B3 C1
G2
CB B3 CBF