0% found this document useful (0 votes)
92 views69 pages

Method Statement Example

Construction Work methodoloy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF or read online on Scribd
0% found this document useful (0 votes)
92 views69 pages

Method Statement Example

Construction Work methodoloy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF or read online on Scribd
You are on page 1/ 69
~~ pragados 42 EUS JOINT VENTURE ADDIS ABABA - MODJO - AWASSA ROAD REHABILITATION PROJECT METHOD STATEMENT REPORT Rey.1 January 1998 Rev.2 February 1908 Rev.3 October 1998 Rev.4 December 1998 1.0 Introduction -page 4 4.4 Executive Sumimiaty « page 4 1.0 Mobilization and Site Establishments . spade 6 2.0 Site Preparation ..... .- page 6 4.0 Drainage Works ....... page 13 4.7/4.8 Construction of paved ditches.. Page 13, 4.9 Cleaning of culverts... ae Paga 14 5.0 Road Base Construction 5.1 Construction of Subbase .. 5.2 Construction of base Course sage 15 page 15 page 18 6.0 Bituminous Pavements... cos Page 21 Asphalt Paving Works 7.0 Road Furniture . » page 25 8.0 Traffic Diversions ... ae page 26 (8.1 Traffic Management Measures) PART II: Modjo - Awassa section 1.0 Mobilization and Site Establishments... page 26 2.0): | ShelPreparaiion ici vai ee va emmiee aaa page 29 3.0 Earthworks ..... page 30 4.0 Drainage Works .... -page 34 4.7/4.8 Construction of paved ditches 4.12 Construction of corrugated metal pipe culverts.........page 5.0 6.0 8.0 9.0 Road Base Construction ... .page 39 51 Construction af Subbace page 99 5.2 Construction of base Course ... . page 40 Bituminous Pavement . page 44 Road Furniture wpoge 47 Traffic Diversions .. eee 48 (8.1 Traffic Managoment Mcaoures) Appendices. page 50 ‘A. List of plant and equipment... -page 51 B. Production requirements in the various Quarries Base course and Asphalt aggregates... spage 58 C. Method statement for the mixing ot subbase. material....... i s-page 65 ADDIS ABABA-MODJO-AWASSA ROAD REHABILITATION PROJECT MW TA NTI IN This report describes the methods the Contractor intends to follow and the key resources to be employed for the execution of the major activities of the Project, as revised by the Contractor, after works nave commenced on the Project. The report is prepared taking inlu Account the new strategy on Addis Ababa — Modjo section of the Contract, and considering the productivity parameters of the major (critical) equipment to be used for each activity. It is understood, however, that during the course of execution of the Contract, circumstances may furller uiclale alternative methods to tne ones described in this report, as well as the employment of altemative and/or increased resources for more expedient or cost efficient execution of some or all of the activities of the Project, In such circumstances the Contractor will discuss and agree with the Supervisor and/or his Representative such alternative methods and resources and update thie report accordingly. 1.1 Executive Summary This Metnod Statement report is sub-divided into two parts: PART I which covers the activities to be carried out for the Addis Ababa- Modjo section of the Works and PART II which covers the activities to be carried out for the Modjo-Awassa section of the Works, Tor each section of the Works Ure repuil overs tie major (critical) activities of the Project and gives, for these activities: A. A General description of the Project Activity or Activities covered by the Method Statement. B. _ A list of EquipmentMachinery the Contractor plans to use for carrying ‘out the Activity or Activities. C. _ Allist of the Key Personnel that the Contractor plans to engage for the execution of the Project Activity or Activities and D. A General idea of Production estimates that have heen uead to establish the duration of the Activity or Activities, Duration of activities in the Rar Chart may he shown to be longer than the. duration established in the Method Statement. In such cases a slack in the duration of the activity is assumed. Activities are numbered in accordance with the numbering of the Bill of Quantities (BOQ) and, therefore, the numbering sequence is not, in certain caeoe, continuoue. Non critical or minor activities of the Project are briefly covered, without following the above described format. The Contractor reserves the right to change or modify parts of the Method Statement to suit the requirements of the Programme and respond to circumstances that may arise in the course of execution of the Contract. In such cases due notice and full information will be submitted for the Supervisor's approval. It is understood, however, that whenever such approval or agreement by the Supervisor, is required, this will not be unreasonably withheld, bearing in mind the Contractor's privileye Wy programme: aid exeoule lke Works in te most efficient and cost effective manner, always within the requirements of the Contract. PART | : Addis Ababa - Modjo section “a Mobilization activities and the establishment of the Contractor's camp as well as the Supervisors facilities have been completed with the construction of the first camp at Km #44.0 and the operation of the first quarry at Km +60.0. Completion of the Contrarinr's Camp and Supervisor's facilities, however, refer to the extent that these should have been ready for the commencement of the Permanent works. Some of the Contractor's Installations will extend beyond the Contractual Mobilization period The above establishments will be used, mainly, for the Addis Ababa - Modjo section of the works but will serve also for the first part of the Modjo - Awassa section up to Km +113.U. The establishment of the first Borrow Pits has already taken place at the end of the Mobilization period 2.0 Site Preparation 24 Site Clearance and Removal of unsuitable Material. BOQ items: 2.4 Site Clearance 2.10 Removal of other unsuitable material and 2.13 Transport of unsuitable material Site preparation includes the Site Clearance operations, the Removal of unsuitable material and the Transport of this material, as designated by the ‘Supervisor, to areas outside the limits of view from the project. This will be done with written permission of the property owner or the authority having jurisdiction over the area on whose property the material is placed The volume of work involved in the above activities is insignificant and, therefore, not of critical importance to the worko on thie eection. These activities will be carried out using: JIN, Gal Mulurgrader 14G 4No. JCB backhoe/loader & 1No. Truck 15 m3 capacity The personnel intended to be engaged for the above activity will include: 1No, Foreman/Supervisor 2Nos. Machine Operators & 1No. Heavy Duty Truck Driver In addition, the above personnel will be assisted by General Labour, Securny and Trafic Controllers, Surveying Crew, Tine Keepers/Clieckers and other personnel as may be necessary. The above equipment and personnel is not exoected to be enaaaed for more than 10% of their capacity in the above activities leaving 90% of their capacity to be utilised in the built up of Shoulders and/or earthworks for climbing lanes activities, which will be carried out in parallel, for this section. For the performance of the roadbed preparation on the existing shoulders we are going to use a CAT 14G Motorgrader to remove sod and unsuitable material, the disposal of this material and level the top level of the shoulders before humidifying and compacting it to accept the next Layer of fill and/or subbase material specified in the new strategy of the Addis Ababa - Modjo part of the works. This activity will take place over the wholo width of tho road where traffic diversions will be used. Where Traffic diversion will not be used this activity will take place on only one of either Shoulders, along the side of the road, at any un lin, alluwing the traffic to use the other Shoulder and part of the existing road (on which there will be no construction activity) in lengths of up to an approved, by the Consultants, maximum length When one side (left or right shoulder) is completed we will proceed to complete the other Shoulder on the other side of the road. li ulinbing lanes this activity will be carried out independently, outside the existing carriage way and without interference with the Traffic. All the security traffic sians and other measures, as required by the Contract and the relevant Authorities, will be taken for the safe and efficient performance of these works. B. List of Machinery () 1 unit Motorgrader CAT 14. (ii) Water Bowzers as required (iil) 1 Unit Self Vibrating Rollers 1Stans Tyne HAMM 25200 (iv) 4 Unit CAT 966F Wheel Loader (¥) 3 Units Tipper Trucks ~ 16m ea. Other general equipment as Vehicles, Hand Rollers/Plate compactors. | awhed and Flatbed trailers, Mobile service units, as required. C.List of Personnel 1No Foreman 2.Nos Operators for the machinery. 2.Nos H.D. truck drivers as an average. In general. Helpers. Timekeaners/Cherkers, Laboratory techniciane, Land Surveyors and other Labour will be used as required. ‘D. Production Perimeters The quantitias involved in this operation aro 340000m2 to be carried oul in 9.5 calendar months, from mid October 1998, to beginning of August 1999. Assuming 35% production during the rainy season from mid June to end of July 1999 (1.5 months of rainy season) we will have approximately 9.25 working months (05 lass 1.5 x 0.65). ‘Assuming a 10hr/day shift, working 6daysiweek i.e. 260hr/month the volume to be handled by the above equipment is approximately 140m2/hr which will only require 15% of the capacity of the equipment during this period leaving enough time for tha equipment to be utilized in the Sito cloarance and the Construction of the Sub-base layers on the Shoulders. milling with WIRTGEN 2,500 milling machine. A. Description of the Activities, For te performance uf the roadbed preparation of the existing road we are using a WIRTGEN 2500 milling machine to mill the existing road surface shape and compact it to the designed profile. The final formation of the profile will be carried out on site by a Motorgrader CAT 16G. During formation adequate water will be sprayed to humidity, the Sub-base. and compact it. This activity will generally take place, in full widths of the road. The Traffic will be diverted through existing roads or diversions along the Addis ~ Ababa ~ Modjo Road all in accordance wilh a pre-approved Traffic Management Programme. Where Traffic diversions can not be used so that the Road Traffic can be entirely diverted from the existing Road this activity will be carried out in half widths allowing the Traffic to use only one lane and controlling the flow of Traffic at each and with STOP and GO Flag man This operation will be carried out only after bringing the level of the right and left shoulders up to the level of the existing Asphalt as described under item 5.1 (Subpase Construction). Appropriate lighting and Traffic sings will be used for control and safety of the Traffic: during the night The length of this half width construction will be minimised as far as possible and requested for approval prior to commencement of the milling operation. Following this work we intend to proceed with the construction of the Base layer followed with the Asphalt works. That means that in general the distance hatwean the Suh-hase works and the finished Asphalt layer is going to he minimized as far as possible, and subject to the approval of the supervisor. All the security traffic signs and other measures, as required by the Contract and the relevant Authorities, will be taken for the safe and efficient performance of these works. B.List Of Machinery 4 unit WIRTGEN 2,500 Milling Machina 2 Units Motorgrader (CAT 14G and CAT 16G) Water Bowzers as required (iv) 1Unit Solf Vibrating Roller 15 Tone Type HAMM 2520D Other general equipment ae Vohioles, Lowbed & Flatbed trailers, Mobile service units fuelling Bowzers, Safety Equipment, as required. C.List Of Personnel 1No Foreman 4 Nos Operators for the machinery 2.Nos H.D drivers as an average. In general, Helpers. Timekeepers/Checkers. Laboratory tachnicians, | and Surveyors Safety personnel and other Labour will be used as required. R.Production Perimeters According to the Performance programme, the Subbase Milling works on the Auuis Ababa — Modjo part will commence at tne end of September 1998 and completed by mid July, 1999 i.e. in 9.5 calendar months or, assuming 20% production during the rainy season from mid June to mid July (1 month of rainy season), 8./U Working months (¥.o less 1 x 0.80). The total quantity of Sub-base material to be milled, shaped and compacted during this paring is + 500,000m? which amounts to + 57,500m2 per month. Assuming 10 hrs/day shift, working in 6 days/week 260 hr/month), the volume to be handled hy the ahove equipment is approximately 220 m2/hr Average net production for the WIRTGEN 2500 Milling machine is 240 m2/hr assuming an average milling thickness of 200mm. ‘Spreading, Forming and Compaction capacities ot the above equipment is adequate for the quantities involved in this activity as they can handle much more than 220m2/hr the production of the Milling machine. thworks A.__General Description Of Activities This covers Ure aulivilies un Audis Ababa - Muuju seuli under Bill of Quantities items : desuibed 2.7 Roadbed Preparation on existing surface in fill sections in climbing Lanes. 3.2 Ordinary Soils excavation 3.3. Sols excavation tor road widening 3.6. Fill for existing road reconstruction 3.8 Transport of soil material and The above activities cover mainly the areas where climbing lanes will be constructed. B. List Of Machinery (1) Motorgrader Type CAT 146 4No. For Spreading and shaping of fill matorial. (ii) Bulldozers Type CAT 08 AN. For site clearing, excavations, stock piling & spreading of material (iii) Excavators Type O&K type MH6 1Nos. For excavations and loading in the Borrow Pits (iv) Wheel Loaders Type CAT966F == 1No. For loading material from Site Clearance & Borrow Pits (v) Tipper Trucks 45m? Capacity 5Nos. For Transport of Material (vi) Self Vibrating HAMM 2520 D Rollers 418 Tons Capacity 1Nas. For eampaetion of Fill (vii) Water Bowzers 5,000/22,000 litres As For optimum moisture content required of Fill material |n addition to the above Equipment, general use equipment will be used to assist and facilitate the works. C.List Of Personnel 1 No. Foreman/Supervisor 5 Nos. Machine Operators 6 to 8 Nos. Heavy Duty Truck Drivers In addition to the Key Personnel mentioned for the above Activities, General Labour, Gang Leaders, Plant Supervisors/Mechanics, Security & Traffic Controllers, Laboratory Personnel, Surveying Crew, Time Keepors/Checkers and other labour will be engaged as required. D. Productivity Perimeters The Production eustput of the above Rocourooo (Equipment & Labuul) Iras been estimated on a 10hrs work per day ( 6 days a week ) Total quantity of material to bo handled by the above Resuurces Is “60,000 mz tor Roadbed preparation and *80,000 ms for fill in climbing lanes. ‘The above operations will be carried out from the end of December 1998 to the middle of February 1999 i.e. during a period of approximately1% months. The quality to bo handled by the above eyuipient (s approximately 60,000 +260x1.5 = 155 m2/hr for Road bed Preparation and 80,000 +260x1.5~ 205m2/hr for fill climbing lanes much less than the capacity of the equipment to used leaving onough spare capacity fur use in site clearance and diversions in the vicinity of the climbing lanes, 4.0__Drainage Works There are no major Drainage Worlta in the Addis Ababa - Modjo section except for the Construction of paved ditches in town sections (5550 ml) to be completed in 14 months (end of April 1998 to end of June 1999). Other Drainage Works in this section include the extension of existing culverts in the Climbing lanes, Cleaning of existing Culverts and Re-profiling of existing ditches. These are of minor nature and have no critical significance to affect the progress of the Works in this section. It is intended to sub-contract the Drainage Works of this section to one or more local sub-contractors and have these works carried out independently of the other activities. No major equipment are required for these works other than transport of materials and the Contractor intends to assist the local Sub-contractor(s), in this respect. Re-profiling of unpaved ditches and Construction of discharge ditches in this section, however, will not be Sub-Contracted and will be carted out in parallel with Construction of the Shoulders. ‘The Construction of reinforced concrete covers for the paved ditches is intended to be carried out independently at the Contractor's site installations at the Quarry at Km 60,00 for part of the works and at the Quarry at km 157.00 for the rest of the works. Alternatively these may be Sub-contracted to local companies but under the direct Supervision and control of the Main Contractor. When the Construction of paved ditches is completed or is at an advanced stage he reinforced cunuiete covers will Le transpurted frum the place where they are manufactured and placed on top of the paved ditches by a separate crew. 4d onstruction of. ling terrai in town section: Construction of paved ditches in town sections for Addis Ababa-Modjo section of the works includes the excavation of material, and construction of masonry paved ditches. For the execution of the job, sand from Meki, stone from km 60+000 and cement form Muger are intended to be used cement’ ‘sand ratio will be 1:3 This work is being carried out by an approved Sub-contractor. The following resources will be employed: B Plant and Equipment: No Concrete Mixer ‘4No Water Tanker 3Nos dump trucks for transportation of sand and stone Hand tools as required Personnel: 1 No Mason Foreman 4 No Machine operator Nos Dump truck Drivers 6 Nos Masons 39 Nos Labourers: In addition, the above personnel will be assisted by security and Traffic controllers. surveying crew, Time Keeper, Engineer (40%) and other personnel as may be necessary. 4.9 Cleaning of culverts Cleaning of culverts for Addis Ababa-Modjo-section of the works includes the excavation of suil material deposited in the oulverts and dicposal of excavated material outside the limits of view from the project. This activity will be carried out using hand tools such as shovels, picks and wheelbarrows. ‘The personnel intended to be engaged for the above activity will include. 1 No Labour gang leader 6 No Labourers In addition, the above personnel will be assisted by surveyor Timekeeper Engineer (20%) and other personnol ae may be necessary This activity will take place prior to milling of the existing carriage-way item 2.14 of the B.0.Q, descrived eater in this Method Statement report. For the performance of the shoulder built up on the Shoulders of the existing Toad we are going to use a CAT 14G Motorgrader tu scarily the exioting shoulders and mix it with other imported material to obtain the standards for sub base material, as specified in the new strategy of the Addis Ababa ~ Modjo part of the works. This scaritication will take place only in the areas where the thickness of the additional layer of the new material is not adequate to ensure proper bonding between the old and new layers (generally less than 10cm). Where the thickness of the new additional material to be used for shoulder built up is adequate (generally more than 40cm) the new layer will be constructed without prior scarification of the old (existing) layer. In both cases the surface of the existing shoulders will be cleaned from any sod and unsuitable material and the unsuitable material properly disposed of in accordance with the Contract requirements. The cleaned surface will then be watered prior to the construction of the new layer, for full layer eanstniction, or scarified. moistened and mixed with the new material, for small thickness shoulder built up. Tho matorial for tho shoulder build up will be transported tn the shoulders premixed in approved proportions and method (see Appendix C). ‘The bigger, than allowed in the opcoification, cizoe of material are going to be eliminated in the borrow Pits, by screening or other means, in case the material can not be reduced by Grader and/or the Vibrating Roller. The mixing ratios of fine material to cinder, if required will be determined by our laboratory and submitted for approval by the consultants. After the subbase mixture Is transported anid placed on the slivulders we will proceed to humidify, shape to the required profile and compact the sub-base This activity will take place, when there 1s no requirement for Fill material (no climbing lanes), on only one of either Shoulders along the side of the road, at any time, allowing the traffic to use the other shoulder and part of the existing toad (on which there will be no construction activity) in lengths ot up to a maximum to be approved by the Consultants. When one side (left or right shoulder) is completed we will proceed to complete the other side of the road with the Sub-base formation on the ‘Shoulder. in climbing lanes the build up of Subbase layers will take place in full width and with a Motorgrador after the Filling operations have heen completed as described earlier under the Earthworks section, for Addis Ababa - Modjo road, of this Method Statement report. The shoulder built up above the level of the existing carnageway 10 be milled will take place after completion of the binder course with the construction of the permeable (drainage) layer consisting of cinder material only and placed with a side Paver type DEMAG type SF-130P followed by the shoulder pultt up to the required level (just below the wearing course level) with Subbase material All layers above the existing road surface level will be applied with the side paver. All the security traffic signs and other measures, as required by the Contract and the relevant Authorities, will be taken for the safe and efficient performance af thase works. B Lis Of Magtinery (i) 1 Unit Bulldozer Type CAT DON (i) 1UnIt CAT S06F wheel toader (iil) 1 Unit of SCREEN (if required), for the screening of Subbase material at the Borrow Pits (iv) 1 Unit Motorgrader VAI 146 (v) 1 Unit side paver type DEMAG type SF-130P (vi) 4 Units of Tipper Trucks 15m3 capacity each (Average) (vii) Water Bowzers as required (viii) 1 Unit Self Vibrating Roller 15 Tons Type HAMM 2520D Other general equipment as Vehicles, Hand Rollers/Plate compactors, Lowbed and Flatbed trailers, Mobile service units, as required. Mf Person 1.No Foreman 4.Nos Operators for the machinery 6 Nos H.D Truck drivers as an average. In aeneral, Helpers, Timekeepers/Checkers, Laboratory technicians, Land Surveyors and other Labour will be used as required. D, Production Perimeters: According to the Performance programme, the Subbase will commence in mid November 1998 and completed by mid August 1999 i.e. in 9 calendar months or, assuming 20% production during the rainy season from mid June to mid August (2 months of rainy season). 7.4 working months (9 less 2 x 0.80), The total quantity of Sub-base material to be placed on the Shoulders and compacted during this period is + 90,000m3, which amounts to + 12,165m3 per month. Assuming a 10 hrs/day shift, working in 6 daysiveek 260 hr/month), the volume to be handled by the above equipment is approximately 47 m3/hr. This quantity can easily be handled by the above equipment in much less time than shown in our Time Space Diagram but it has to follow the Binder Course and cansentiontly the Rase Cauirsa aparations which are of Critical duration. ‘The mixing of the Subbase material is presented in Appendix C of this Method Statement Report. 5,2 Construction of Base course ‘This Work method covers the avtivily desuibed under item 5.2 Construction Of Base Course. The Production of the Base course material at the selected quarries is outlined in Appendix “B” of this Report. Hae 7 The base course material will be transported from either the Quarry at km+60.00 or the Quarry at km25.00 where the production will ha atnekpiled The Base course stockpile may be moistened, if necessary, at the stockpile. For the construction of the Base Course layer, we are going to use Motorgrader type CAT 14G for spreading and the final reshaping will be done by a Motorgrader lype CAT 10G with Levelling instrumentation for the final shaping. We will proocod to humidify, compact and test the final layer. The Compaction is going to be done with a Self-vibrating Roller of 15-Ton capacity. Construction width:- Where Traffic can be accommodated through diversions or existing roads the operation will be carried in the full width of the road. Where the Traffic cannot be diverled, however, the base course construction operation will be carried oul it half widllis Uf the rad allowing the other half of the road to be used by the Traffic in single lane movement controlled by STOP and GO Flagmen. All appropriate safety measures for the safe and uninterrupted flow of Traffic will be taken as described elsewhere in this Method Statement Report. 18 B._List Of Machinery (i) Tipping Trailers 18m? Capacity 6Nos_—_For the transport of materials (average) (ii) Motorgrader CAT 146 1No For Spreading of the material {iii Motorgrader CAT 16G 11No For shaping to the required levels (iv) Self-Vibrating HAMM 2520D- 1No For Compaction of the Roller 15 ton base course (v) Water Bowzers 16000/22,000 As. To give Fill material the litres Reyuited required moisture content In addition to the above equipment, general use equipment will be engaged to facilitate the works. (0.9. Mobile, Service units, Refueling Bowzers, Welding sets, Air Compreseore, Vehicles, additional trucke ae required ote ... ) G. List of Personnel 2 Nos Foremen / Supervisors 3 Nos Machine Operators 9 Nos heavy duty Truck Drivers (on average) In addition to the above Key Personnel, General Labour, Gang Leaders, Plant Supervisors/Mechanics, Security & Traffic Controllers, Laboratory Personnel, Surveying Crew, Time keepers! Checkers and other Labour will be engaged as required. The full team for laying Base course will be under the control of a Pavements Engineer. D. Productivity Perimeters The total quantity of base course material to be handled by the above resources is t 125,000 m3. The period shown in the Performance Program for the Construction of the Base course (Loauing, Transport, Spreaving, Levelling and Compacting) ts 10 calendar months (1% October, 1998 to end of July, 1999). Assuming 95% production during the rainy season (4.5 months) the duration of this activity will be 9 working months (10 less 1.5 x 0.65) In the 9 months required by the programme we must load approx. 13,900m3/month (4 125,000m3/9 months), 53m3/hr which can easily be handled by one CAT 966 Wheel Loader. Spreading and shaping of the final Road level will be done by the two Motorgraders, which are considered to be more than adequate for this operation Will the Muluiyaue: CAT 14@ we should be spreading & compacting aruund 2.000m'/day and with the Motorgrader CAT 16G we should be shaping 8,000m2/day (approx. 1.0Km of Road with Base course). For the Transport of the Base Course material from the quarries we are using Tipping Trailers 18.0m3 capacity each The average number of Tipping Trailers required to move the above quantities of Base course material, assuming an average travelling distance of 15Km from each Quarry, will be GNos, assuming 5 tips per day for each of the Tipping Trailers (540m3 per day/18m3 per truck/Strips per day per truck). In case the above assumed productions can not achieved the equipment described above will be supplemented by locally hired equipment available in the local market. 2» 6.0__Bituminous Pavement L iption Of Ac This item, which is considered the major items in the Contract covers most of the activities in series 6 (Bituminous Pavement) of the Bill of Quantities, namely: 6.1 Prime Coat 62 Tack-coat Emulsion 6.0 Aaphalt for binder Course: 6.11 Asphalt for wearing course and 6.13 Sealing of shoulders ( Single layer) Main Asphalt laying works have begun in the middle of October 1998, when Earthmoving and Drainage works have sufficiently advanced so that there are no interference and after adequate quantities of Crushed aggregates have been produced. tof in 1 No Asphalt Plant complete with 260 ton/hr theoretical Capacity 2 Nos Asphalt Laying Pavers VOGELE (8.5m laying width) 2 Nos tandem Rollers. 1Atone 2 Nos Pneumatic Tyre Rollers 2 No Bitumen Distributor/Sprayer 1 No Self Vihrating Roller 1.0m wide ( Shouldero ) 2 Nos Tractor Driven Mechanical Broom (for Road Cleaning ) 8 Nos Tipping Trailers 18.0m3 capacity (on average) 2 Nos wator Bowzore 6000/22,000 litres capacity (x) 2Nos Air Compressor 250 cfm with attachments and (xi) 2 Nos CAT 966 Front -end loader to help feeding the Asphalt Plant (xii) 4.No Acphalt oaw/outter (xiii) 2 Nos Chipping Spreaders In addition to the above fulltime Machinery other auxiliary equipment will be used such as Low and Flat bed trailers, Prim movers (for transportation of machinery), Fuel Bowzers, Mobile Service Units etc. 2 C.__List of Personnel 4 No Asphalt Plant Operator (Expatriate) 1 No Asphalt Plant Electrician (Expatriate) 1 No. Chief Asphalt laying Foreman 2 Noe Asphalt Foreman 43Nos Machine Operators 46Nos Heavy Duty truck Drivers In addition to the above main categories of Personnel, General Labour, Gang Leaders, Plant supervisors/Mechanics, Security and Traffic Controllers, ‘Screw men, Lineomon, laboratory and Surveying Crews. Time KeepersiCheckers and other Labour will be engaged as required. ‘The above Equipment and personnel resources are the total resources to be employed for the Asphalt works in the contract and in the first 14months of the asphalt works they will be mainly working on the Addis Ababa — Modjo section although sume or all of the recourses may be diverted to the Modjo ~ Awassa section depending on the circumstances at the time (e.g. not enough area ready for asphalt works to justify all the resources, or stoppage of works for any reason In the Auuis — Modjo section cte...). D, Productivity Paranusters: AN” INTRAME “ Latch type asphalt mixing Plant of theoretical Capacity of 260 ihr will be used to produce Asphaltic concrete mix. Tha works have been programmed considering @ practical rate of 195tons (75% of theoretical Production) with a working coefticient ot /U% In the dry season and 35% inthe rainy season (mid June to mid September) Ine Asphalt Plant Gan switch from ono typo ‘of Mix to another (eg Rinder to Wearing Course & vice versa) automatically & no delays are expected in this respect. The 1* location of the Asphalt Plant will be at km + 60.00 The Addis Ababa - Modjo part of the Project will be completed within 9% calendar months from eid uf October 1998 to mid August 1999 in acrnrdance with the contract requirements and as shown in our works Programme. The Asphalt works on the Modjo - Awassa Part up to Km108.00 will commence in parallel with the Addis Ababa - Modjo part with priority always tor the Addis Ababa - Mogio part until the mid August 1999 dead-line, when this part will be completed. The Asphalt works will start at Km + 60:00 and progress to Km 70:00 and will then be moving towards Addis Ababa, from km 60:00 (The surface treatment uf the shoulders and other tinishing works are scheduled to be carried out soon after the Wearing course for each section of the road that is laid so that the road is completed in its entirety as the works progress. The most critical activity determining the duration of the Asphalt works is the production of the asphalt aggregates covered under Appendix “B” of this Report. Assuming an availabilitylefficiency factor of only 70%, the production of the Asphalt Plant which will be operating (producing) from mid August 1998 to mid Apill 1989 for the Addis - Modjo section (total of 8 months) can reach a total Production of 284,000tons (8months x 195 whr x 0.70 x 260 hrs/month) or approximately 130% more asphaltic concrete mix than is required for this section leaving this excess of the produced quantity to be used for the Modjo - ‘Awassa section up to Km 118.0. The quantity of Asphalt (Binder plus Wearing Course) for the Modjo Awassa section up to Km + 118 is estimated to bo approx. 90,000 Tons or approx. 37% of the total Production of the Asphalt Plant at Km 60.0 for the period of + 8 months than it will be operating at this location. The proportion of Asphalt Production to be allocated for the Addis Ababa - Modjo and Modjo - Awassa part of the works (up to Km + 118.0) will therefore be 45% & 39% respectively, leaving 20% of the Production Capacity of the Asphalt Plant for slack. The Asphalt laying equipment, mentioned above, is adequate fur the whole Quantity produced and no problems are anticipated in handling the production of the Asphalt Plant. Where detours will be used to divert the traffic through diversions or existing roads along the Addis Ababa ~ Modjo section Asphalt layers will be constructed in full width of the road but laid in half widths of the carriage way. i.e. one lana af 3.5m width in rural areas and 6.0m width in Town areas. in a single operation and laid in echelon, avoiding, thus, as far as possible, longitudinal construction joints in the Asphalt layers. completing laying of tha full width of the Carriage way during the day's operation. Where Traffic can not be accommodated through diversions or existing roads the laying of asphalt will be carried out In naif widths up to a maximum lane length to be approved by the Consultants allowing the Traffic to use the other half and part of the shoulder in single lane (one way) Traffic flow Appropriate STOP and GO flag men will be used, in this case, to implement the Traffic Management measures required for the safe and uninterrupted flow of Traffic. 2B Two Asphalt paving finishers will be used on this activity on the same section of the works. Assuming laying speed of the Asphalt Finishers to be 4m/minute (Pavers Specification call tor a laying speed ot U to 15 meters/min), the total lane Kms to be laid are 44) Fur Aduls Ababa - Modjo section 60Km x 2 lanes x 2 layers = 240 Lane Kms, b) For Modjo - Awassa section 38 x 2 lanes x 2 layers = 152 Lane Kms Total 392 Lane Kms {at 4mimin 4 x 60 = 240m/hr or 0.24 Km/hr both pavers can lay a minimum theoretical length of 4.8 Kmn/day. Therefore, assuming a practical laying speed of 4Km/day the time required for 392 lane Kms is only 98 days (working) approximately 4 months.) 4 7.0__Read Furniture This activity includes the supply & installations of all Road Signs as well as the Road markings. Alll the Road furniture for the Contract will be supplied by Companies specialising in this type ot work and will be delivered to the Contractor's main stores from where an installation crew, under a competent supervisor, will begin erecting the various types of Road Fumiture at the specified locations, The timing and duration of this activity is shown in the Bar Chart Program. Road markings will be carried out by the Contractor's specialised personnel using @ purpose made Road marking machine ond using the specified type of Ruel Marking paint. Construction of the Addis Ababa — Modjo Road. Where no existing Roads are present or can be used, new Diversions will be constructed parallel and alongside the main Carriage-way will be constructed in accordance with the contract Specifications. These Diversion, will be either half width (one way Traffic) or full width (two way Traffic. A Traffic Management Proaramme has already been prepared and submitted ta the Consultants, in this respect. 25 8.0 Traffic Diversions This activity has been described under earthwork activity above (PART Il) of the Method Statement Report. 8.1 Traffic Management Measures: 8.1.1. Half Width Traffic Movement (one way traffic) All Traffic Management measures will be In accordance with the Traffic Management plan submitted to and approved by the Contracting Authority where half width Traffic flow will be used appropriate STOP and GO Flagmen will be used day and night with apprupriate lighting and satety Equipment. In the cases where half of the carriage - way width will be closed to Traffic, for the Construction works, appropriate measures will be taken to regulate traffic, moving in one direction at a time, for a maximum distance approved by the Consultant. Appropriate signage will be placed in accordance with the Contract and the Traffic Management plan before the section on which construction works are taking place tapering gradually to the full width to be closed to traffic. Road Signs will include : DANGER & WARNING Road Signs SLOW Signs UAL WORKS IN PROGRESS Signs DETOUR Signs NO OVERTAKING Signs ROAD CONSTRUCTION AHEAD Signs ONE WAY TRAFFIC Signs MAXIMUM SPEED Signs 25 Km PER HOUR Signs LOOSE GRAVEL Signs MEN WORKING Signs TRAFFIC DIRECTION Signs Road Limit Closure Devices (cones, painted barrels etc) Road Sian Stanchions & Strinad Mini Rarriars ROAD CLOSED Barricades with wings STOP Signs/ Flags Traffic Diractinn Chevrons Reflective Hazard Waming Tapes (yellow/black) DIVERSION ENDS sings Above Road Signs will include writings in English as well as in Amharic Languages, 6 In addition to the above Road Signs al either end of Ue Construction section of the carriage - way, Flagmen in proper uniform will be used day and night to regulate STOP & GO Flags/Signs so that one way Traffic may smoothly flow through the partly open carriage - width. Inese Flagmen will communicate with eacn other using short range Walkie - Talkies. All measures to be taken will be approved in advance by the Supervisor or his Representative and the Traffic Police. If necessary, the assistance of Traffic Police will be requested by the Contractor. Where any part of the road under construction remains incomplete during the day and part of the carriage width will have to be kept closed to the Traffic during the night, adequate traffic Management measures will be taken including Reflective Road Signs, Road Safety Lamps (battery operated) as well as Traffic Police assistance as required. 9.1.2 Full Width Closure of Road Sections Full width closure for the Carriage-way will be used only where two way Traffic can be accommodated on existing side Reads properly repaired and maintained or in appropriately constructed Traffic Diversions alongside the existing Addis Ababa — Modjo Carriage-way. In such cases where full carriage width will have to be closed for Road works to be carried out appropriate signage will be placed for a minimum distance of 300m warning Traffic about the closure and directing it to an appropriately establisned Diversion. Traffic Signs to be used in such cases will be similar to the ones to be used under 8.1.1above, depending on the type of Diversion that may be used at the time (one way or two way Traffic Diversion). In any case the length of these Traffic Diversions will be the maximum allowed and/or approved by the Consultants unless a Bitumen surfaced road section, more or less parallel to the main road, exisis and may be used as indicated in article 8.2.6.1 of the Technical Specifications ( PART L) of the Contract. 2 PART IL; MODJO - AWASSA SECTION 1.0___Mabilisation and Site Eetoblishments Mobilisation activities and the establishment of the Contractor's camp as well as the Supervisur’s facilities nave been completed by the end of the Contract Mobilisation period with the construction of the first camp at Km 44.0 and the operation of the first quarry at Km +60.0 The above establishments will be used, mainly, for the Addis-Ababa - Modjo. section of the works but will serve also for the first part of the Modjo - Awassa sactinn up to Km £113.00. The establishment of the first Borrow Pits will also take place towards the end of the Mobilisation period, These Borrow Pits will be used to provide Filling and Sub-base material for the requirements of the first part of the Modjo - Awassa section. With the completion of the Addis Ababa - Modjo section of the Works the first part of the Modjo - Awassa section, up to Km #113.00 will, also be, more or less, completed and arrangements will have commenced ta move the Contractor'e ac well as the Supervisor's Facilities to a new location at approximately Km +160.00. These Facilities will be ready by the end of July 1999. The Camp Installation and Supervisor's Facilities will be relocated to the new location with minimum inconvenience for the Supervisor & his Representative. The Permanent works are to be contininus without any interruption duo to the relocation of the Camp Installation and if necessary adequate, temporary facilities will be provided for the Supervisor & his Representative. The installation uf the Asphat Pant at the Second location (Km 158.00) will be completed in the middle of October 1999. At this location the Asphalt Plant will cater for the asphalt laying requirements of the section between Km +113,00 and km #184.00. (Max. travelling distance for the asphalt trucks will be (158-113)= 45Kms. 28 Finally the Asphalt Plant will be moved to Km +210.00 in May 2000. From this location the Asphalt plant will cater for the asphalt requirements of the last section of the Works frum Km £184.00 to Km 4275.00. (Max. travelling distance for the asphalt trucks will be (275-210) 65.00Km. Similarly the first pnsition of the Quarry, for the Crusher Plant, will be al Km 60.00 and will be successively moved to Km #118.00, Km +158.00, Km +210.00, Km 2236.00, and finally km +274.00 from where it will cater for the aggregates’ requiromente of the Asphalt Plant as well as Ite quantities required tor the Base course. The timing as well as the duration of each relocation is shown on the Contractor's Programme for the Works (Time Space Diagram) ‘The Borrow pits for Sub base and Filling material to be used for this section of the Works up to km:160.00 have already been identified and advised to the Supervisor. Some Applications for possession of the land whare those Borrow Pits have already been processed by the Supervisor and some will be submitted as the works progress and after the necessary laboratory tests have established the suital of the Rarrow Pits material. 2.0_Site Preparation Site Preparation for the Modjo Awasea acetion of the works includes ihe Site Clearance operations, the Removal of unsuitable material and the Transport of this material to areas outside the limits of view from the Project. This will be done with written permission of the property owner or the aullrurily having Jurisdiction over the area on whose property the material is placed. The other activities included under the Site Preparation saries nf the Rill of Quantities are directly related to the Drainage Works and/or Earthworks and as Such they are covered in the relevant part of this Method Statement Report. These activities will be carried out using: 1No, CAT D6 Bulldozer 1No. CAT Motorgrader 14G 1No. CAT 966 Front-end Loader & 8Nos. Truck 15 m9 capavily The personnel intended to be engayeu fur thie abuve activity will Include: 1No. Foreman/Supervisor 3Nos. Machine Operators & 8Nos. Heavy Duty Truck Drivers » \n addition, the above personnel will be assisted by General Labour, Security and Traffic Controllore, Surveying Crew, Time Keepers/Checkers and other personnel as may be necessary, Assuming a 10cm depth of top soil excavation for Site Claarance for a width of approx. 10.0m (5.0m on either side of the road width) the quantities involved are +1,000m3 per Km. Thie quantity can easily be liandied by the above equipment in one day and, therefore, this equipment and personnel are not expected to be engaged for more than 25% of their capacity in the above activities, for the duration of these activities thus leaving 75% uf their capacity to be utilised together with other equipment in the activities discussed under the Earthworks & Diversions sections of this Report, which will be carried out in parallel, with the Site Clearance works. 3.0_Earthworks B._General Description Of Activities ‘This item Covers the activities on Modjo — Awassa section described under Bill of Quantities items : 2.9 Roadbed Preparation on existing surface in fill section 3.9 Ordinary Soils excavation 3.40 Geils excavation for vad widening 3.5 Construction of fil sections outside existing road 3.6 Fill for existing road reconstruction 9.7 Preparation uf sub grade 3.8 Transport of soil material and 8.0 Traffic Diversions The above activities cover the areas where, as a result of the filling operations, diversions ara to he constructed for uco by two — way traffic, generally fur the whole of the Road length where Filling works are to be executed except for the section of Shashemene by-pass where Traffic diversions are not required. The length of each of theeo diversions is not expected u exceed the 9,0 Km limit, specified in the Contract. A detailed list with the chainages and lenath of each Diversion will he suhmitted - to the Supervisor's representative, for approval as and when these diversions are required by the works, 30 C. List Of ine (1) Motorgraders Type CAT 166 & Type Cat 146 (ii) Bulldozers Type CAT D6 Gii) Excavators Type O&K type RH20 {iv) Wheel Loaders Type CAT 966 (v) Tipper Trucks 15m? Capacity (vii) Solf Vibrating HAMM 2620 D Rollers 15 Tons Capacity (vil) Water Bowzers —_5,000/29,000 litres No. 1No. 1No. 2Nos. 1No. 8Nos. 2Nos. As required For Scarification and Shaping to required levels For Traffic Diversions, statificalion and spreading ot fill materials. For site clearing, Diversions & spreading of material For excavations on the road & Borrow Pits For loading material from Site Clearance & Borrow Pits For Transport of Material For compaction of Fill For optimum moieture content of Fill material In addition to the above Equipment, general use equipment will be used to assist and facilitate the works (e.g. 966 loaders, CAT D9 Bulldozer, additional trucks as required, ate.) 31 Person 2 Nos. Foremen/Sunervisars 6 Nos. Machine Operators 10 to 12 Nos. Heavy Duty Truck Drivers In addition to the Key Personnel mentioned for the above Aulivilies, General Labour, Gang Leaders, Plant Supervisors/Mechanics, Security & Traffic Controllers, Laboratory Personnel, Surveying Crew, Time Keepers/Checkers and other lahouir will bo engaged ac required. D. Productivity Porimetera ‘The Production output of the above Resources (Equipment & Labour) has been ootimated on a 10hrs work per day ( 6 days @ Week ) Total quantity of material to be handled by the above Resources is + 960,000 m° aid tlre cuniroling factor in estimating the duration of these activities is the output of 0 & K type RH20 Excavators Assumed theoretical production for each Excavator: 150 m3/hr total for both will then be 300m3/hr. Availabiity/eticiency factor ot the Excavators is taken as 75%: therefore actual Capacity for both Excavators is 300x.75= 225m3/hr or 226 x 10hrsiday ¥ 6 dayshweek x 4.3 wooke/month: approx. 58,000.0 m3/montn The above operations will be carried out from the middle of August 1998 to the end of December 2000 i.e. during a period of approximately 29% months. Allowing 20% production during the rainy seasons (2% rainy seasons from the middle of August, 1998 to the middle of September 2000) the duration of the above activities, which aro plannod to be performed in parallel, is approx, 24.3 months (29%-8.0 x 0.80), during which total production will be 23.1 x 58,000 = approx. 1.34 million m’ (~39% more than the Contract requirement). Aaaitionally 1No. CAT 966 may assist, with a CAT D6. Dozer, the Excavators in the Borrow Pits and it is expected that the above equipment will have enough slack to carry out the Clearing of Site and construction of the Traffic Niversione during tho 29% months period that the above Activities will be carried out. Assuming a filing layer of 206m, the spreading and compaction equipment wil have to handle only about 11,250m2 per day (2,260m3/day /0.20) which is loss than approximately 75% of thoir combined capacily. The required number of 15m3 trucks to be used for the above activities is only 5 (2250m3/15m3 per truck/20trips per day) taking the avaraga distance from yo Borrow Fits that have been identified to be 10kms. However a total number of 8 trucks will be used in order to have enough slack to carry out the Site Preparation activities described under item 2.0 (PART II) above 3 4.0__Drainage Works The Drainage Works in the Modjo - Awassa section are to be completed in 29 calendar months (beginning of August 1998 to end of Decemher 2n0) {tis intended to sub-contract the Drainage Works of this section to one or more local sub-contractors and have these works carried out independently of the other activities but eammeneing with tho Site Clearance uperallons, All works required for tha Construction of pipe and box culverts as well as major drainage structures, in the areas where earthworks operations (item 3.0 Part iy are to be carried out, shall be completed before the commencement of these operations Equipment required for the Drainage works are mainly those necessary for the transport of materials and unloading of the steel pipes for culverts, cement, steel reinforcement and in general materials required for these works as well as those Fequirad for handling the excavation, concreting aid compaction of Backtilling material for drainage structures. The Contractor intends to assist, if necessary, the local Sub-contractor(s), in this respect, with its own equipment. Construction ot unpaved, discharge and cut-off ditches in this section, however, will not be sub-contracted and will be carried out by the Contractor, For this Operation 3Nos. O&K-MH6-A2-PMSIII Excavators on tyres will bo usod with appropriate buckets. Production of these Excavators is estimated to be +50m/hr (500m/day). The three Excavators will complete 41.5 Km of ditches por day and will require approx. 250 working days ta complete this oporation (well within the time stipulated in the Contractor's Bar Chart Programme). The Excavators will be assisted in this operation with other auxiliary equipment such as JOD Digyen/Backhive, Hand Rollers, Plate Compactors, Trucks for carting away surplus material, etc. The Construction of reinforced concrete envers for the paved ditches jo intended tu be carried out independently at the Contractor’ site installations or sub-contracted to local companies. When the Construction of paved ditches is completed or is at an advanced stage the reinforced concrete covere will be transported from the place where they are manufactured and placed on top of the paved ditches by a separate crew. 4 ling ten Construction of paved ditches in Rolling terrain and in town sections for Modjo-Awassa section of the works includes the excavation of material, and construction of masonry paved ditches. For the execution of the job, sand from Meki, stone from km 60+000 and cement form Muger are intended to be used cement/ sand ratio will be 1:3 This work is being carried out by an approved Sub-contractor, who will use a numbor of crowo doponding on the roquircmonto of the programme. The following resources will be employed for each crew working at each location. Plant and Equipment: 4No Gonerete Mixer ‘No Water Tanker Noe dump trucke for trancportation of cand and tone Hand tools as required Personnel: 1No Mason Foreman 4 No Machine operator 3. Nos Dump truck Drivers 6 Nos Masons 35 Nos Labourers In addition, the above personnel will be assisted by security and Traffic controllers, surveying crew, Time Keeper, Engineer (40%) and other personnel as may be necessary. 35 4.12_Construction of corrugated metal pipe Culverts = Gen The Activity refers to the construction of 800mm diameter corrugated metal pipe culverts and includes tie wunstruttion of the Foundations, ine assembly ot the pipe culverts and the filling of the trenches in accordance with the Contract Specifications (Sections 3.3.2, 4.2.3, and 4.2.4). 4124 442.44 4121.2 4121.3 41214 41215 yf Tre Excavation of trenches for pipe culverts will be in widths adequate for the fill of the trenches to be compacted with the specified, in this Method Statement, equipment. Excavation of trenches in embankments will be performed before the embankment has been constructed to the proposed profile grade and to such height above the bottom of the pipe as shown in the plans, This excavation will be carried out using a JCB-Backhoe or Wheel Excavator O&K (type MH6). Where a firm foundation is not encountered at the grade established, due to soft spongy, or other unstable soil, such unstable soil under the pipe and for a width of at least one diamotor on cach side of the pipe will be removed to the depth directed by the Supervisor and replaced with gravel or other suitable selected material properly ‘compacted to provide adequate support for the pipe. Where trenches or foundation excavations are required below the level of mass excavations for the road, the deplh of excavation of the trenches or foundations will be measured from ground level after ‘completion of the mass excavation, unless the Supervisor is satisfied Ural the excavation of the Wencnes of foundations trom the original ground level or any lower level was unavoidable. All Excavations tor cuiverts will be adequately protected against the possible ingress of water during rainstorms. 36 4.12.2 Construction of Pipe Culverts 412.24 AA detailed plan for the construction of each oulvert will be prepared and submitted, for approval, to the Supervisor, 4.12.2.2 Foundation matorial will bo applied in layers sul exceeaing U.1bm 4.12.2.3 412.24 4122.5 4122.6 412.34 4.12.3.2 4123.3 thickness. The Foundation layer of upto 0.30m depth under the culvert will be compacted to 95% of the optimum moisture content in accordance to AASHTO T99 ~ 94. The pipes will be laid horizontally with a cover, in the contre line, of 0.70m from the top of the pipe lu the top of the road surface. The pipes will be laid with the separate sections joined firmly together and with outside laps of circumferential joints pointing upstream and with longitudinal laps on the sides. The pipes will De lowered and placed into position by machine with appropriate supports and in no case they will be dragged on the ground, Uamaged pipes will be removed from site and the damaged parts replaced or, in case the Coating has been damaged, be painted with two. Coats of the prescribed coating yf tr Before the filing af the trenches starte, tho Contractor will verify Ue level of the in- and outlet of the culvert. Suitable material form the oxcavation of the trenches will be used for the fill. Surplus material may be used for subgrade or other purposes After tho bodding has been prepare and the pipe installed, the trench will be backfilled with fine computable soil selected form excavation or borrow. The material will be placed in layers adapted the compaction equipment but nut exveeding 0.15m in depth. Each layer will be moistened or dried to a convenient moisture content and thoroughly compacted to at least 95% of the maximum dry density (MDD) with mectianical compaction equipment. 7 4123.4 4.12.35 412.36 Special care will be taken to compact thoroughly the material under the haunches of the pipe without displacing or damaging the pipe and to assure thal Ure backfill ralerial intimate vontact wilh the pipe. The backfill will be brought up evenly on both sides of the pipe for the full- required length, When the top of the pipe is above the top of the trench, embankment material wil! be placed ana compacted in layers not over U.15m thick tor a width on each side of the pipe, equal to at least twice the horizontal inside diameter of the pipe or 3.5 m. whichever is less. The embankment on each side of the pipe, for a distance equal to the horizontal inside diameter of the pipe, will be of the same material and compacted in the same manner as required for backfill In paragraph 3.3 above The embankment will be placed evenly on both sides of the pipe for the full width of the roadbed, up to an elevation 0.30m above the top of the pipe. Above this elevation and also above the top of a backfilled trench that is 30 cm. or more above the top of the pipe, the embankment will be placed in accordance with the requirements of Section 2.4 of the Technical Specification (Roadbed Preparation in fill sections) Compaction of fill in the trenches around the pipe culverts will be performed with mechanical plate compactors or hand operated double drum Rollers. using adequate water for maximum Pry Nensity as required by the Contract 4.12.4 Resources Equipment Manpower 1 No Excavator JCB or O&K type MH6 1 No Foreman 1 No Hand Roller Bomag B W 65H 1 No Machine Operator 1 No Plate Compactor 1 No Surveyor 4.No Water truck 2 Nos Fitters 4 Nos Labourer 38 3.0 Road Base U : struction of This work method covers the activities described under items 2.8 and 5.1 of The Dill of Quatiilies, Le, 2.8 Roadbed Preparation on existing road surface. 5.1 Construction of Subbase A.Ueseription Of The Activities, For the performance of the roadbed preparation of the existing ruad we are now using a WIRTGEN 2500 Milling machine to scarify and mix the scarified material ‘on the road with other imported material to obtain the standards for Sub-base material. Alternatively and when te aspliall thickness on the existing Road is of ‘small thickness so that it can be scarified, a CAT Motorgrader with Scarifiers or other appropriate equipment will be used. The bigger, than allowed in the specification, sizes of material are eliminated in the Borrow Pits, by screening or other means, or if in small quantities, on the road by hand. If they can not he reduced hy the CAT Motorgrader. The mixing ratios of fine material (cinder), have been determined by our laboratory and approved by the Consultants. Mixing is carried out either by pretnixing In the Borrow pit or by a Motorgrader CAT 14G on the road. After the mixing has been completed we will proceed to humidify, shape to the required profile and compact the Sub-base, Following this work we intend to proceed with the construction of the Base Course layer followed with the Asphalt works. In certain special circumstances, when changing the position of the Asphalt Plant or the Crusher Plant installations we will be forced to work in road lengths longer than the 5 km length limitation specified in Art. 8.22, Part L of the [echnical Specifications, subject to approval by the Client All the security traffic signs and other measures, as required by the Contract and the relevant Authoritics, will be taken for the safe and efficient performance of these works, 39 B.List Of Machinery 1 Unit Bulldozer Type CAT D6N 1 Unit Wheel Excavator O8K type MH6 {iv) 1 Unit of SCREEN (if required), for the screening of Subbase material at the Borrow Pits (v) 2 Units Matargrader CAT 14G 11 Units of Tipper Trucks 15m* capacity each ( Average ) Water Bowzers as required (viii) 1Unit Salt Vibrating Roller 15 Tons Type HAMM 2520D (ix) 1 unit WIRTGEN 2500 Milling Machine or other appropriate scarifying equipment. Other general equipment as Vehicles, Hand Rollers/Plate Compactors, Lowbed & Flatbed trailers, mobile service units, a9 required. C.List Of Poreennal 1 Foreman 7 Operators for the machinery 44 Truck drivers as an average. In general, Helpers, Timekeepers/Checkers, Laboratory technicians, Land Surveyors and other Labour will be used as required. Production Perimeters According to the Performance programme, the Subbase works will commence in the beginning of October 1998 and completed by mid January 2001 i.e. in 27% calendar months or, assuming 35% production during the rainy season from mid June to mid September (6 months of rainy season), 23.6 working months (27% less 6 x 0.65). Tne total quantity of Sub-base material to be placed and compacted during this, period is + 470,000m3, which amounts to + 20,000m3 per month. Assuming 210 hrs/day shift, working in 6 daysiweek, 280 hrimonth), the volume to be handled by the above equipment is approximately 77 m3/hr (ie. 310m*hr assuming an average thickness of 0.25m/m2 of Road bed preparation). 40 Considering a factor of availability/efficiancy. for tha above equipment, of 76% both the loading equipment (CAT 980) as well as the Motor Grader are more than adequate for this operation. (Theoretical luauiny capacity of Gat 98U Is ZUUMSINT and Spreading/Levelling capacity of CAT Motorgrader 14G is around 800m*/hr). Assuming that the WIRTGEN 2500 Milling Machine will have to scarify 90% of the Modjo-Awassa Road (1,080,000m? @ 90% at the rate of 240m/hr) it will require approximately 4,050 working nrs oF 1.6 months allowing 8.0 months for Addis Ababa — Modjo part of the work (500,000 m?) §.2 Construction of Base course This work method covers the activities descrihad under items 5.2 Conetruction OF Base Course. The Production of the base material at the selected quarries is covered in Apperidix “8” uf the Report. The mixing of the Subbase material is presented in Appendix C of this Method Statement Report n OF For the construction of the Base course layer, we are going to use Motorgrader type CAT 14G for cproading and the finel reshaping will be done Ly # Mulurgrader type CAT 16G with levelling instrumentation for the final shaping. We will proceed to humidify, compact and test the final layer. The Compaction is going to be done with a Self vibrating Roller of 15 Ton capacity. We plan to complete the top 200m of base course material on the shoulders immediately after the asphalt works. To obtain the requirad lavals in shoulders a Side Paver (1.5m wide) will be used. Compaction of the final layer of base course material on the shoulders will be done with @ 10ton Roller (lype HAMM HD 10) 1.0m wide. 41 List Of Machi Equipment Type cit Units Activity to be used “ Tipping Trailers 18m Capacity 1Nns_—For tho transport of materials (average) (ii) Motorgrader CAT 146 1.No For Spreading of the material Motorgrader CAT 166 1No For shaping to the required levels, (iv) Sell-Vibrating HAMM 2520D- 1No For Compaction of Roller 15 1on the hase course (¥) — Self-vibrating = HAMM HD10K-—1No For Compaction of Roller 10Ton 1.0m wide the Shoulders (vi) Water Bowzers —§000/22,000 As To give Fill material litres Required tho required moisture content (vii) Side Paver Type NFMAG 1 No For placing/spreauing Material on Shoulder In addition to the above equipment, general use equipment will be engaged to facilitate the works. (e.g. CAT D - 9 for clearing overburden in Quarries, service units, Vehicles, additional trucks as raquired ete «.. ) C. List Of the Personnel 20 Nos Crusher plant operators 2 Nos Foremen / Supervisors 6 Nos Machine Operators 13 Nos heavy duty Truck Drivers In addition to the above Key Personnel, General labour, Gang Leaders, Plant Suparvisars/Mechanice, Security & Traffic Controlieis, Laboratory Personnel, Surveying Crew, Time keepers/Checkers and other labour will be engaged as required, a2 D. Productivity Perimeters The period shown in the Performance Program for the Construction of the Base course in the Modjo-Awassa section of the works is 27% calendar months (beginning of October 1996 ty iid January 2001). Assuming 35% production during the rainy seasons (6 months) the duration of this activity will be 23.6 working months, In the 23.6 months required by the programme we must load approx. 17,330m3/month (£409,000m3/23.6 months), 66.66m3/hr which can easily be handled Ly Ue CAT 966 Wheel Loaders. Spreading and shaping of the final Road level will be done by the two Motorgraders, which are considered to be more than adequate for this operation. With the Motorgrader CAT 14G we should be spreading & compacting around 2,000m‘/day and with the Motorgrader CAT 16G we should be shaping 8,00012/day (approx. 1.0Km oT Koad with Base course). The average number of Trucks required to move the above quantities of Base vourse material, assuming an average travelling distance of 20Km from each Quarry, will be 10, assuming 4 trips per day for each truck (670m3 per day/18m3per truch/Strips per day per truck). B 6.0 Bituminous Pavement A. General description Of Activities This section of the method statement covers the following items of the Bill of Quantities namely = 6.1 Prime Coat 6.2 Tackcoad Emulsion 6.9 Asphalt tor Binder Course 6.11 Asphalt for wearing course and 6.13. Sealing of shoulders ( Single layer) Asphalt works will begin approximately around he end of October,, when the earthmoving and drainage works are sufficiently advanced so that there are no interference and after adequate quantities of Crushed aggregates are produced. B List of Machinory (i) 1No Asphalt Plant complete with 260 ton/hr theoretical Capacity (ii) 2.Noo Asphalt Laying Pavers (Finishers) — type VOGELE (iii) 2Nos Tandem Rollers 10tons (iv) 3Nos Pneumatic Tyre Rollers (¥) 2No__ Bilumen Distributors/Sprayers (vi) 1No Self Vibrating Roller 1.0m wide ( Shoulders } (vil) 2No _ Tractor Driven Mechanical Broom ( for Road Cleaning ) (vill) 13 Nos Tipping trailers 18m3 capacity (x) 2Nos Water Bowzers 5,000/22,000 litres capacity () 2No Air Compressors 250 cfm with attachments (x1) 2Nos CAT 966 Front-end loaders for feeding the Asphalt plant (xii) 1.No Asphalt Saw/Cutter (xiii) 2 Nos chipping spreaders {In addition to the above full time Machinery other auxiliary equipment will be used euch ae Decanting plant, Cmulsion plant, Aspliall Tankers, Generator Sets, Low & Flat bed trailers, Prime movers (for transportation of machinery), Fuel Bowzers, Mobile Service Units ete, C.List Of Personnel 1 No Asphalt Plant Operalu: (Expatriate) 1 No Asphalt Plant Electrician (Expatriate) 1. No Chief Asphait laying Foreman 2 Nu aspliall Foreman 13 Nos Machine Operators 16 Nos Heavy Duty truck Drivers 44 I? Addition to the above main categories of Personnel, General Labour, Gang teaders, Plant Supervisors/Machanies, Security & Traffic Contiullers, Screwmen, finesmen, Laboratory & Surveying Crews, Time KeepersiCheckers and other 'abour will be engaged as required. ee 1 ltt Adis Ababa - Modjo section part or all of the resources may be civerted to the Modjo -Awassa section depending on the circumstances at the tine (@.g. not enough area ready for asphalt works to justify all the resourcso, ee Stuppage OF WOrKS for any reason in the Addis - Modjo section etc.) D. Productivity Parameters Prime Coat, Cut Back and Tack coat Emulsion specified in the contract will be applied to the Base and Binder course respectively with sanarata sprayor trucke ong for the Cutback and one for the Emulsions, The rato of application will be determined with the supervision and advice of the Consultants and the Sprayor Trucks calibvaled avcoraingly. Some quantities of Cut Backs and Emulsions have been imported in drums and any additional Guantities required for the works will be manufactured by ourselves in the specially importod Emulsion plant. An” INTRAME "batch type asphalt mixing Plant of theoretical Capacity 260vhr will be used to produce Asphallic concrete mix The works have been programmed considering a practical rate of 195 hr ( 260 @ 75%) with a working coefficient of 70% in the dry season and 35% in the fainy eoacon (mid June to mid September). This hypothesis guarantees a placement rate for all the Asphalt paving in a Period of approximately 18 months of continuous laying although the Aspirall laying operations are scheduled to be completed in 27% calendar months, The 1* location of the Asphalt Plant will be at km +: 60.00 The Asphalt works on the Modjo - Awassa Part will commence in parallel with {he Addis Ababa - Modjo part with priority always for the Addis Ababa - Modjo. Part until the mid August 1999 dead line when thio part will be cuvnpleled. The Asphalt works on the Modjo - Awassa part will continue up to Km #108,00 approx. before the Asphalt Plant is relocated to Km + 158.00 and finally at its ast location at Km + 210.00 (3 Asphalt Plant locations in all), The works will always progress ( in general ) from Km £70.0 and moving in one direction, towarde Awaosa without haviny (v shift the Aspnalt laying equipment back and forth. 45 During the periods when the asphalt Plant will be inactive, due to relocation of fhe Plant (involving uistriantiing and re - erection activitios) the surface treatment of the shoulders and other finishing works will be carried out, Additionally these works are scheduled to be carried out soon after the Wearing course for vavii section of the road that is laid is carried out that the road is completed in its entirety as the works progress and are advancing towards Awassa. The most crtical activity determining the duration of the Asphalt laying works is the production of the Asphalt and Base course aggregates covered undor the Felevant item (Construction of Base course) of this Method Statement Report. Assuming that the Asphalt producing and laying operations will be operating from the beginning of November 1998 to mid February 2001 (intal 27% ealends. morns - ess 3 months for relocation, less 3 months rainy season ( 2 rainy Seasons x 0.50 ) i.e. 21% working months at a production rate of 230Uhr x 0.70 = 160 thr the total Production during this parind will be in oxcoes of 899,980 tons (21.5 months x 230 Uhr x 0.70 x 260 hrs/month) or approximately 100% more asphaltic concrete mix than is required for the Contract. The Asphalt laying equipment wietitioned above is more than adequate for the whole quantity produced and no problems are anticipated in handling the production of the Asphalt Plant. Assuming an average hauling distance for the Asphalt (between the Asphalt Plant and the Laying crew) of 30Kms and taking an average production of 1200.0tons per day. the total na af 18m3 (35tonc) Tipping Trailers tequired tor the operation, assuming 4 trips per truck per day is only 9 Tipping Trailers on average (1200tons/35tons/Atrips) 46 Z9__ Road Furniture ‘This activity includes the supply & installations of all Road Signs as well as the Road markings All the Road furniture for the Contract will be supplied by Companies specialising in this type of work and will be delivered to the Contractor's main stores fram where an installalion Crew, under a competent supervisor, will begin erecting the various types of Road Furniture at the specified locations. The timing and duration Of this activity is shown in the Bar Chart Program. Road markings will be carried out by the Contractor's specialised personnel using @ purpose made Road marking machine and using the specified type of Road Marking paint. a” 2.0 Traffic Diversions This activity has been described under earthworks activity above (PART Il) of the Metnod Statement Report, Bl Traffic Manz Mi 8.1.1 Half Width Traffic Movement (one way traffic) All Traffic Management measures will be in accordance with the Traffic Management plan submitted to and approved by the Contracting Authority where half width Trattic tlow will be used appropnate SUP and GU Flagmen will be used day and night with appropriate lighting and safety Equipment. In the cases where half or 1/3 of the carriage - way width will be closed to Traffic for the construction works (Repair of existing shoulders, or Asphalt laying) appropriate measures will be taken to regulate traffic, moving in one direction at a time, for a maximum distance approved by the Consultants. Appropriate signage will be placed startina in accordance with the Contract on which construction works are taking place tapering gradually to the full width to be closed to traffic. Road Signs will include : DANGER & WARNING Road Signs SLOW Signs ROAD WORKS IN PROGRESS Signs DETOUR Signs NO OVERTAKING Signs ROAD CONSTRUCTION AHEAD Signs ONE WAY TRAFFIC Signs MAXIMUM SPEED Signs 25 Km PER HOUR Cigna LOOSE GRAVEL Signs MEN WORKING Signs TRAFFIC DIRECTION Signs: Road Limit Closure Devices (cones, painted barrels etc) Road Sign Stanchions & Striped Mini Barriers. ROAU CLUSED Barricades witn wings STOP Signs/ Flags Traffic Direction Chevrons Reflective Hazard Waring Tapes (yellow/biack) DIVERSION ENDS sings. 48 Above Road Signs will include writings in both English as well as Amharic Language. In addition to the above Road Signs, at either end of the Construction section of the carriage - way, Flagmen in proper uniform will be used day and night to regulate STOP & GO Flage/Signo oo that one way Traffic may smoothiy tow through the partly open carriage - width. These Flagmen will communicate with each other using short range Walkie - Talkies. All measures to be taken will be approved in advance by the Supervisor or his Representative and the Traffic Police. If necessary the assistance of Traffic Police will be requested by the Contiaclut Where any part of the road under construction remains incomplete during the day and part of the carriage width will have to be kept closed to the Traffic, adequate traffic Management measures will be taken including Reflective Road Signs, Road Safety Lamps (battery operated) as well as Traffic Police assistance, will be used as required. 8.1.2 Full Width Closure of Road Sections In cases where full carriage width will have to be closed far Rnad works to be carried out appropriate signage will be placed for a minimum distance of 300m warning Traffic about the closure and directing it to an appropriately established Diversion Traffic Signs to be used, in such cases will be similar to the ones to be used under 8.1.1 above. depending an the tyne of Diversion that may be available at the tine (one way or two way Traffic Diversion) 49 9.0 APPENDICES A. List of Plant & Equipment. B. Production Requirements in the various Quarries Base course and Asphalt Aggregates. C. Method Statement for the mixing of subbase material. Plant List On Site As On 21st October 1908 4._ BULLDOZERS Make Model eeeateten Quantity CATERPILLAR CAT DH BULLDOZER 2 UNITS CATERPILLAR CAT DSN BULLDOZER TUNIT 2._WHEEL LOADERS Make Modal Doseription ‘Quantity iT] CATERPILLAR __| CAT 96F I WHEEL LOADER [4 UNITS [CATERPILLAR CAT 9888 WHEEL LOADER | 1 UNIT 3._DIGGER/LOADERS Mai Modal Deceription [Quantity JCB ‘3CX SMT3 | DIGGER/LOADER | 2 UNITS CONTRACT. ate J 4._EXCAVATORS (CRAWLER) Make a —__[Beseription | Quantity] CATERPILLAR 245D EXCAVATOR T UNIT ] 8K [RH20-PMS-VLC600_| EXCAVATOR _ 2 UNITS | 5._EXCAVATORS (WHEEL) Make Model Quanti Oak att MH6 AZ EXCAVATOR 3 UNITS 6. MOTORGRADERS Make Model Description ‘Quantity CATERPIITAR CAT 14 MOTORGRADER | S UNITS ‘CATERPILLAR CAT 166 MOTORGRADER | 2 UNITS 7,_ CRAWLER DRILLS Make Moder Description Quanti ‘ATIAS COPCO ROC 748 He CRAWLER ORL | UNIT 8_AGR. TRACTORS Make Model Description Quantity FORD 4610 ‘AGR TRACTOR S UNITS 9._ROLLERS (SLF-PR. VIBR) Make Model Doceription Quantity, HAMA 2520 D ROLLER 4 UNITS 52 10, ROLLERS (TANDEM) [Make ‘Model Description ‘Quantity } | HAMM DW ROLLER UNIT | [BOMAG. BWi67 AD [ROLLER ZUNITS 11. ROLLERS (PNEUM. TYRE) ‘Make Model Description ‘Quantity BWZUR ROLLER 2 UNITS 12, KULLERS (SP. PED. OFTD) ‘Make [wogel Description ‘Quantity [BOMAG BWeSH ROLLER QUNITS BOMAC 13. PAVER FINISHERS. Make ‘Model Description Quantity a} DEMAG ‘SF-130P SIDE| PAVER FINISHER — | 1 UNIT PAVER ia i [VOGELE ‘SUPER 1600 PAVERFINISHER | 2 UNITS 14, ASPHALT PLANERS. Make Model Description Guantity WIRTGEN ‘SF 500C4 [ASPHALT PLANER | 4 UNIT [wikteen wr 2600 ‘ASPHALT PIANER [7 UNIT 15. RD. MARK'C MACHINES Make Model Description ‘Quantity HOFMANN. RM 50H RD. MARK’S | 7 UNIT ui MACHINES 46, RD, BRUSHERS Make Model Description Quantity ‘STURDILUXE RF? RD. BRUSHE 3 UNITS 17. TRUCK (CHASSIS) Wake Model Description ‘Guanti [VECO PEGASO 2217 4Wi0_| SERVICE UNIT 1 UNIT VECO. PEGASO 1135-L/30_| FUEL BOWSER: (UNIT [veco, PEGASO 1217.00 | FlIFI BOWSER UNIT MERCEDES __| 1838 TRUCK + CRANE ___| 1 UNIT MERCEDES 1831 4X2 TRUCK + CRANE | 1 UNIT MERCEDES 2423 BX? TRUCK + CRANE TUNIT a MERCEDES: 263116X4 [TIPPER TRUCKS | 15 UNITS | 3 18. PRIME MOVERS [Make Model Description [Quantity MERCEDES: 1933S/4X2 _| PRIME MOVER SUNITS MERCEDES 2636S/6X4 PRIME MOVER. 4 UNITS iti MERCEDES 2628 S/32 6X4 PRIME MOVER 4 UNITS MERCEDES | 19338/6X4_ “PRIME MOVER 2UNITS 19. TRAILERS (FLAT-BED) Make Moder Description — [sean FRUEHAUF PB-F2PG-125 TRAILER [UNIT 20. TRAILERS (TIPPER) ‘Make Model Description ‘Quantity FRUEHAUF D-32. A 76/25 TRAIFR) 7 UNITS FRUEHAUF VBH-F A3” PPP-| TRAILER 3S UNITS 82/25-S_ 21. LOWLOADERS Make Model Description Quant a] [TRABOSA SRGT 45 LOWLOADER TUNIT LTRABOSA GLi604 | LOWLOADER: UNIT, 22. BIT. DISTRIBTR. TANKS Make Model Description Quantity CARTEM 3654 BIT.DSTR TANK- TUNIT 6000LTR. CARTEM 3655 BIT.OSTR.TANK- UNIT L 10000LTR. BEE 23, IRAILEK 1ANKERS Make Model Description. [Quantity HYDRO TRAILER TANKER | 3 UNITS: LECI Di3s7 TRAILER TANKER __| 3 UNITS a 24, BITUMEN TRANSPORT TRAILERS Wake Model Description Quantity LECINENA D360 SRCZE BITUMEN TR | SUNITS. TRAILER APRON 1432 SRZ BITUMEN TROT UNIT TRAILER LECT D419 CFZIPV BITUMEN TR. | 1 UNIT TRAILER LECI 17070 BITUMEN TR. | 1 UNIT TRAILER, HE sa 25. PICKS-UPS LIGHT DUTY ‘Model Description ‘Quantity RENAULT EXPRESS VAN 1.9 | PICK-UPS LIGHT | 10 UNITS DUTY 26. HEAVY DUTY CARS Make. Madel Doseription ‘Quantity NISSAN | TERRANO ISIW_| HEAVY DUTY CAR | 5 UNITS NISSAN THIGH” ROOF LWB) HEAVY DUTY CAR | 8 UNITS awn NISSAN DICAB PICK” UP | HEAVY DUTY CAR | T UNIT 4wiD NISSAN HIROOF 260 4WID [ HEAVY NliTY aR |S UNITS LUXE NISSAN SICABIN PICK UP | HEAVY DUTY CAR | SUNITS 4wiD 27. PASSENGER CARS Make ‘Model Description ‘Quantity RENAULT CLIO 1.9 PASSENGER CAR | 4 UNITS 28. AMBULANCES: [Make SS —«| Model Description ‘Quantity NISSA ‘4WID - AMBULANCE | AMBULANCE UNIT tt 29. CRANES (MUBILE) ‘Make Model Description ‘Quantity BENDINI A600 | CRANE UNIT. 30. DUMPERS MaKe Model ‘Seription Quantit ‘AUSA | 200 RM DUMPER| ‘SUNITS 31. SLF-LOAD MIXERS Make Model Description ‘Quantity DIECT | F 2400 ‘SLF-LOAD MIXER _| 1 UNIT 32. WATER PUMPS (ENG) Make Model scription Quantity ACME | WATER PUMP. UNIT. PIVA MBD-82P WATER PUMP 10 UNITS: 33. AIR COMPR’S (SMALL) Make Moder Description Quantity ATI AS COPCO wasaann AIR COMPR'S _[2unrs id 34. AIR COMPR’S (LARGE) Make Model Description ‘Quantity "ATLAS COPCO XAS1250D ‘AIR COMPR'S 2UNITS 35. GENERATOR (S) Make Model Deserintion Quantity F.G. WILSON. P40 GENERATOR 2 UNITS: CATERPILLAR OLYMPIAN GE 75__| GENERATOR 2UNITS | 1 F.G. WILSON | P60 GENERATOR 2 UNITS 36. GENERATOR (L) Make Mod Description [Quantity F.G. WILSON P160 GENERATOR 2 UNITS F.G. WILSON, F300 GENERATOR 2UNITS 4 CATERPILLAR GENERATOR 4 UNIT F.G. WILSON Pato GENERATOR 2UNITS_ 37. CONCR. CUTTING M/C fm Model Description ‘Quantity 500 ASPHALT CUTTING | 3 UNITS: MIC 38, PRIMARY CRUSHER Make Model Description ‘Quantity NORDBERG C1258 PRIMARY CRUSHER | 1 UNIT 39. SECONDARY CRUSHER Make Model Description Quantity TARON PLi3T ‘SECONDARY TUNIT CRUSHER 40. TERTIARY CRUSHER ‘Make ‘Model [Description ‘Quantity TARON AA2 TERTIARY TUNT CRUSHER. 56 41. HYDRAULIC HAMMERS: Make Model __ [Description ‘Quantity KRUPP M720 HVORAULIC TUNIT | HAMMER, 42. ASPHALT PLANTS Make Model Description ‘Quantity INTRAME, UM-260 ASPHAIT PLANT [1 UNIT 43. PLATE VIBRATORS: Make Model Description [ Quantity | BOMAG BP15/45D2 | PLATE VIBRATOR __| 4 UNITS tt 44, WELD'G SETS (ENG) Make Model Description Quantit (MPN MPM 16/400 -PS | WELD'G SET [3 UNITS 45. EMULSION & DECANTING PLANT Make Model Description Quantity MASSENZA DECANTING PLANT _| 1 UNIT MASSENZA MG 40 HEATING UNIT UNIT MASSENZA EMULSION PLANT [UNIT 7 Sueld Sujusarng pus oysrUd af 40 siuawoesnbel uoROMPO 84) OF sSonguenb onogy :8TOR, Tamm vee | Sea ae ae | Wwior tte | genta weydey] un =j00 02 we . wos sun ovs12 7una1 opgee Run eee 0s ’ weudsy| uN ‘sus Ze Set | ae 00'Stz + Wye ovssz¥ wyos og zzz" uy ‘oser| post v COBEZF wn OO vaTTUN ARLE] —BUNDOTE | NOTE oe a wartal (S ze Ruy 0 00 vesRWH e804 poe | atti aa DorarFUna OST Fava] SaNGETT | ano ar “of a owen Fa 00°F) FUMO} OO-BELT WH ose gost outignt weudsy| IN, ‘suxo0'eh a 00'S) + w]e er w4 0 ov 06 uy eee ‘ Trends) aN say 00 ze cos uD oszv7 un orovorsun ose ‘ CGS uno OFT Fn | RANGERS SONOS Te ne cape Fan O8=Uy 01 OS 2¥sUIH gu OO aan ave TRE ae | 2RrWae G349A09 38 OL SCNVISIC G39NIOUd 38 01 S31VOIYSSV JO IdAL 20 yRaseNt vay GNONT IU OF THMOTT Sx1VOTUTOY G3ASMAT IO STUUNWNO ‘omen ior snoz-sopsteg LAC = Mos rit For the Production of base materials and Asphalt aggregates for the Addis Ababa - Modjo section we are proposing to explore the Quarries at the following locations : Q, Km +60,00 0.5 Km Right & 1.1 Km Right and Q9 Km + 25.00 0.5 Km Right A detailed investigation has been carried out in each of the above Quarries so that the properties and the quality of the material as well as the quantities to be produced at each of the quarries was established in advance, Our Crusher Plant has theoretical production for base material, of 400 ton/hr and will be able to produce, as well, the aggregates for asphalt in quarry Q1. When producing aggregates for asphalt the Crusher Plant will be able to produce 360ton/hr. When producing both Base course and Asphalt aggregates the combined theoretical production of the Crushing Plant is assumed to be 37Ston/hr. Above production figures are theoretical and the actual prodiictinn figuras will be approx. 75% of the theoretical ones. To complete this operation the Crusher Plant will be assisted by a Crawler drilling Machine Involved drilling holes for the in Diasting. We nave assumed that at least a 90% of the Quarry materials will require the utilisation of explosives. For this operation (Base course and Asphalt aggregates production), we will have in addition to the Crusher Plant (Primary Secondary and Tertiary) one unit of Atlas COPCO 748C or similar Drilling equipment, a Crawler excavator type CAT 245 and a Dozer CAT DON on part time basis. These machines will bo ascisted by the: necessary machinery for the Stockpiles (Front-end loaders, trucks etc.) B. List of Personnel 1No. Crusher plant Supervisor 1No. Quarry superintendent (Explosive specialist) 2.No. Crusher plant Foremen (No for Primary/Secondary plant 4No for Tertiary plant) and 9 2Nos. Crusher plant operator and Mechanics crews (No for Primary/Secondary plant 1No for Tertiary plant) and other Machine operators as required. The above personnel may be duplicated if a night shift operation becomes necessary. G. List Of Machinery Equiement Type — Capacity/Modcl Units Activity to. be used (i) Crusher Plant 400tontufor 1.No For Production of Base Base agareg. course & Asphalt 350ton/hr for Doareacice asphalt aggreg. (Theoretical Production ) (ii) — Drilling Machine Atlas — COPCO 1No For blasting 748.C (iil) Explosor 2No Use for activating the Machines electrical detonators (iv) Crawler Excavator CAT 245 1No Rock Excavation and Loading for Crusher feeding (Vv) Whee! Loader CAT 966 2Nos — Stockpiling & Loading of materials for the road (vl) Bulldozer CAI DYN 1No For clearing overburden material in quarries and piling up Rock near the crawler Excavator A full team of specialized crew will be working at the Quarry for the production and loading of both the Base course and Asphalt aggregates to support the field laying operations. 60 D. Productivity Perimeters The productivity output of the above resources (equiprenl) las been estimated on a 10hr work per day, six days a week i.e. 260hrs per month. The production ir the Quattizs will alsu Le increased, as necessary, with a couple shift work cycle. The total quantity of Base course for the Addis Ababa — Muyjy part of the works and the Modjo-Awassa part upto km#90:00 is + 125,000m’ that is about 265,000Tons. 200,000 Tons of the above Quantity of Base Course material will be produced at ‘our quarry at km+ 60.00 and 65,000 tons from the Quarry at km 25.00, The Quarry Q, at km=60:00 will also produce the total quantity of Asphalt aggregates for the Addis Ababa - Modjo section as well as the quantities for ‘Asphalt up to km.L1 13:00. Total quantity for aggregates required for Asphalt will be all produced at the quarry at km. 60.00 and is 1 190,000Tans. The Total quantity of material (Base Course and Asphalt aggregates) to be producod at tho above two quarries is 1455,000 Tons. In accordance with our programme we have started with the production of aggregate at tho ond of Junc 1908 and will work in the Quarry at km 00.00 up tu mid March 1999 and at the quarry at km 26.00 from the end of March 1999 to end of July 1999, i.e. 13 calendar months. ‘Assuming 35% production in the rainy season (0.5 rainy season ~ 1.5 months) and considering 2 positions for the Crusher Plant, with 2 weeks for dismantling and re- reetion of the Crusher at the new location the total working time for the plarit will be 11.50 months (13 months less 1.50 months of no production (1.5x0.65+0.50)). Considering a theoretical production of 375 thr (average production for buth Base course and asphalt aggregates) with an availability/efficiency factor of 75% ( for rains, equipment failure etc. ) the total production of the Crusher Plant working for 11,50 months ( at 260 hours/month ) will be 375x0.75x1 1.50x200=840,000 tons which is more than the total quantity required for both Base course and Asphalt materials working only one shift of 1hours/day. ‘The wheel loader CAT 966 will be able to load approx. 135m3/hr (theoretical production 180m"/hr x 0.75), approx. 1,350m*/day. o PART Il Modjo ~ Awassa Section A. Desuription Of The Acuvities For the Production of base materials on the Modjo-Awassa Road, we have Proposed to explore the Quarries at the following locations : @, Km+60,00 7.1. Km Right 2 kKm= 118.00 3.0 Km Right & 3.5 Km Right Q3 km= 158.00 9.6 Km Right Q4 Km+210.00 6.0 Km Right ao Km z30.0U 0.5 Km Left Q6 Km +274.00 0.4 Km left A detailed investigation will be carried out in each of the above Quarries so that the properties and the quality ot the material as well as the quantities to be produced at each of the quarries is established in advance. We intend to install a Crusher Plant of 400 ton/hr theoretical production for base material, that will be able to o produce, as well, the aggregates for asphalt in ‘some of these quarrioe, Whon producing aggregates for asphallt the Crusier Plarit will be able to produce 350ton/hr. When producing both Base course and Asphalt aggregates the combined theoretical production of the Crushing Plant is assumed to be 375ton/hr. Above production figures are theoretical and the actual Production figures will be approx. 75% of the theoretical ones. To complete this operation the Crusher Plant will be assisted by a Crawler drilling machine involved in blasting. We have assumed that at least a 90% of the Quarry materials will require the utilisation of explosives. For this operation (Base course and Asphalt aggregates production), we will have in addition to the crusher plant, one unit of Atlas COPCO 748C or similar, and a Crawler excavator type CAT 245. These macitines will be assisted by ine necessary machinery for the Stockpiles (Front end loaders, trucks etc.) @

You might also like