Module - 2
Module - 2
ESTIMATION OF STRUCTURES
2.1 Introduction:-
Generally all the Civil Engineering projects like roads, railways, earth dams,
canal bunds, buildings etc. involves the earth work.This earth work may be
either earth excavation or earth filling or Some times both will get according
to the desired shape and level. Basically the volume of earthwork is
computed from length, breadth, and depth of excavation or filling.
In this chapter the various methods of calculating the earth work quantities
shall be discussed.
0.5 - 1 lift }
Calculation of earth work for Roads:
7.3.1 case 1) volume of earth work in banking or in cutting having "no
longitudi-nal slope".
V = (bd+2x1/2x ndx d)L
V = (bd+nd2)L
Case 2:
When the ground is in longitudinal slope or the formation has uniform gradient
for a length the earth work may be calculated by the following methods.
Am = (A1 + A2) / 2
Let A1 ,A2 ,A3 and An are the cross sectional areas along L.S of Road 'L" is
the distance between two cross sections.
The volume of earth work
V= [
L ( A + A ) +4(A +A +A +..... +A ) + 2(A +A + ....... + A )
1 n 2 4 6 n−1 3 5 n−2]
3
length
= (Sum of first and last areas)+4(even areas)+2(odd Areas)]
3
Example 7.1 : Find the volume of earth work in embankment of length 12m.
Top width is 5.5m and depth is 2.5m the side slopes ara 1½:1
Sol : Top width b=5.5m
5.5
Depth d= 2.5m
2.5 1½:1
side slopes =1½:1 i.e. n=1.5
length L=12m
Volume of earth work V = (bd+nd2)L
= (5.5 ×2.5+1.5×2.52)12
= 77.5m3
Example 7.2 : The depths at two ends of an embankment of road of length 70m
are 2m and 2.5m. The formation width and side slopes are 8m and 2:1
respectively. Estimate the Quantity of earth work by
a) Mid Sectional Area (ii)Mean sectional Area method.
Sol: a) b=8m, d1=2m, d2=2.5m, l=70m, n=2
The following width of road embank ment is 10m. The side slopes are 2:1 The
depth along the centre line road at 50m intervals are 1.25, 1.10, 1.50, 1.20,
1.0,1.10, 1.15m calculate the Quantity of earth work by
a) Mid sectional rule
b) Trepezoidal rule
c) Prismoidal rule
a) Mid Sectional rule : b=10m, n=2.
Total 4135.49m3
a) Trepezoidal rule
A= bd +nd2
2 2
A1= bd1+nd =1 10x 1.25+2x 1.252= 15.625 m
2 2 2
A2 = bd2+nd2 = 10x 1.10+2x 1.10 =13.42m
2 2
A3 = 10x 1.15+2.1.15 = 14.145m
2 2
A4 = 10x 1.2+2x1.2 =14.88m
2 2
A5=10x 1.0+2x1 =12.0m ,
A6 = 10 x 1.1 +2x1.12 = 13.42m2
2
A7 = 10x1.15+2x1.152= 14.145 m
Volume of earth work by Trepezoidal rule
A + An
+(A 2 + A + .. A n−1 )
L
2
15.6 25
V = A1 + An + {A2 + A3 + …… + An}
2
= 4137.50 m3
a) By Prismoidal rule
L
v = 3 [(A1 +An ) + 4(even Areas) +2(Odd Areas)]
L
= 3 [(A1 +A7 ) + 4(A 2 + A4 + A6 ) + 2(A3 + A5 )]
50
= 3 [(15.625 +14.145) + 4(13.42 +14.88 +13.42) + 2(14.145 +12)]
= 4149 m3
Example 7.4:- Estimate the Quantity of earth work for a portion of road
from the following data
Chainage 0 1 2 3 4 5 6 7 8 9
RL 7.50 7.70 7.50 7.25 6.85 6.95 6.70 6.45 6.30 5.95
Sol : -
b=12m n=5
Prismoidal formula :
L[( A + A ) + 4(even areas) + 2(Odd areas) ]
V= 3 1 n
L
= 3 [( A1 + A10 ) + 4(A2 + A4 + A6 + A8 ) +2(A3 + A5 +A7 + A9 ) ]
V = 317.27 m3
The formation level at chainage zero is 22.0 and having a rising gradient of 1 in
100 the top width is 12.0m and side slopes are1½ :1 Assuming the trans-
verse direction is in level. calculate the quantity of earth work by
a) Trepezoidal formula b) Prismoldal formula
= 969.5 m3
b) Prismoidal formula
L
V= 3 [( A1+An)+4(even Areas ) +2(Odd Areas) ]
20 = 3 [
(19.74+2.46)+4(16.56+6.325+1.2+5)+2(12.01+1.215)]
= 968.33m3
Example 7.6:-From the above problem if the formation level at 0th chainage in
20m. Calculate the volume of earth work by using the formulas?
2
7.74+26.46
20 +(10.56+15.015+21.375+28.215+28.215)
= 2
= 2409.6 m3
Example 7.7:-From the same above problem 7.6 if the gradient is in 100 falling
calculate the quantity of earth work by using the formulas
a) Trepezoidol formulae:
Vol.of earth work in cutting
A +A
n + (A + A +........ + A
n −1 )
1
V= L
2 3
2
7.74+76.86
20 +(16.56+28.215+43.335+60.375+69.615)
=
Example 7.8:- From the problem 7.5 if the gradient is 1 in 100 raising upto 40th
chainage and 1 in 100 falling ragient from 40th Chainage to 120th chainage.
Calculate the vol of earth work by using the formulas.
Chainage R.L. F.L. Depth (d)of . Area of .
Embank Cutting
(m) Embank- Cutting ment
ment bd+nd2 bd+nd 2
23.5
23 22.9 23
22.7
22.5
R.L&F.L's
22.2 22.4 2
22.1
22 22 22 21.8 G.L's
21.5 21.5 21.6 F.L's
21 21
20.5 20.6
20
0 20 40 60 80 100 120 140
Chainage
2 20
x= 0.8 = 8 = 2.5
vol of earth work in embankment
Chainage 0 20 40 60 62.5
here the intervals are not equal so we have to take the seperate volumes
from oth chainage to 60th chainage and 60th chainage to 62.5 chainage
V = Vol (0 - 60) + vol(60 - 62.5)
19.74 +1.215 1.215 +0.00
= 20 +(16.56 +12.01) +2.5
2 2
3
= 782.46m
By Prismoidal
V = 20 [(19.74 +1.215) + 4×16.56 + 2 ×12.01]+ 2.5[(1.215 +0.00)]
3 3
3
= 742.44 m
Vol of earth work in cutting
1.85 2:1
Chainage in m 0 30 60 90 120
The Formation level at chinage zero is 28 and having the rising gradient of
1 in 100 the top width is 10m and the side slopes are 1½ horizontal to 1
vertical Assuming transverse slope is level calculate the volume of earth
work.
2. The reduced level of ground along the centre line of a proposed road from
chaiage 0 to 6 are given below. The formation level at '0' chainage is 10.00
andtheroad is indown wardgradientof 1in 100 formation widthofroad
is 10m and side slopes are 2:1 for both banking and cutting. Length of
chain is 20m calculate the quantity of earth work required by a) Trepezoidal
rule b) Prismoidalrule.
Chainage 0 1 2 3 4 5 6