Method Statement For Civil Foundations & Grouting
Method Statement For Civil Foundations & Grouting
Method Statement For Civil Foundations & Grouting
Rev.
XXXX-XX-XXX-XXX-XXXX
001
Master Document Register For ME&I Project Majnoon Field Development
Revision History
Revision Revision
Approver Summary of Changes
Date Number
08-11-2022 001 Issued For Review
Holds
Hold Ref. Description / Reason for Hold Ref. Section
HOLD 1 xxxxxxxxxxxxxxx
HOLD 2
HOLD 3
Reference Documents
Ref. Document Number Rev. Document Title
1 xxxxx xxx xxxxxxxxxxxxxxxxx.
2
3
4
5
Table of Contents
REVISION HISTORY 2
HOLDS 2
REFERENCE DOCUMENTS 2
TABLE OF CONTENTS 3
2.0 ABBREVIATIONS 4
4.0 HSE 6
4.1 RISK ASSESSMENT 6
4.2 SAFETY PROCAUSION 6
5.0 RESOURCES 9
5.1 PERSONNEL 9
5.2 EQUIPMENT 9
7.0 PROCEDURE 11
7.1 HSS APPLICATION 11
7.2 NDT WELDING CLERANCE 12
7.3 SURFACE PREPARATION 12
7.4 JOINT COATING 13
7.5 FACTORY COATING AND REPAIRS 13
7.6 COATING REPAIR INSPECTION 13
7.7 FINAL PRE – LAYING INSPECTION 14
8.0 DOCUMENTATION 15
2.0 ABBREVIATIONS
QA/QC Engineer
Drawing Engineer
Material Engineer
Geodesy Engineer
HSE Engineer
Document Controller
Pump operator
Pump assistance
Vibrator man
Finisher
Crane operator
Iron worker
Carpenter
Labourer
5.0 RESPONSIBILITY
5.1 PROJECT MANAGER / CONSTRUCTION MANAGER
Has the responsibility to ensuring that all the activity is done without endangering health and
safety in accordance with the local legislation, client’s requirements and stipulations laid down
in the HSE management system document.
Ensure that all under groundwork related accidents are reported, investigated and that
corrective and preventive measures are taken, the accident investigation team has the power to
stop any work or operation under his authority on health, safety or environmental grounds until
effective measures have been taken.
Ensure that the required testing is undertaken by approved independent laboratories. Ensuring
that materials are inspected when delivered to site and it is complying with the COMPANY
approved specifications and maintaining all relevant records of QA/QC activities related to lifting
works.
CONTRACTOR shall assign HSE officers for performing internal inspections, advising
employees on subjects and concerning health and safety.
All activities shall be planned, supervised and carried out in a safe manner under the
control of a competent person, who knows the responsibilities.
All road movement equipment within site parameter shall be controlled by competent
banks man / flagman to ensure the speed control and Company regulations.
All equipment shall be suitable for the specified works and approved by COMPANY
Maintenance.
Approval must be obtained from the Engineer for waterproofing and backfilling works
prior to start slab on grade casting.
After the blinding is casted and placement of waterproofing is done, the preparation
and casting for foundation base on grade shall be done.
Any loose binder or ties along the splice’s reinforcement steel shall be re-tightened.
Bend inward the free ends of the binding wire or ties.
Use PVC spacer for vertical bars and concrete spacer for bottom as concrete covers.
Any damaged materials used for form work or shutter like plywood shall not be used.
All surface of forms or shutter facing concrete shall be treated with shuttering oil and
dampen with water few minutes before concrete will be poured.
Clean the slabs on grade using air compressor for dust or any small particles or
deleterious materials that may impair the workability of concrete.
The surveyor will then have checked the level of the projected top surface of the slab
and place level strips if necessary to mark the exact level.
The concrete mixer must be stopped at the check point for the inspection of slump
test and to obtain sample cubes for test.
Unload the concrete within 90 minutes from the batching plant loading time.
Compact the concrete properly by using mechanical vibrators, extra vibrator shall be
available in case of any shortage or mechanical problems.
Use the power float for the smooth finish surface purpose. Store extra power float
near the casting area in case of any mechanical malfunctioning.
Concrete pour card shall be filled by Quality Engineer and to be submitted to the
Engineer including concrete delivery notes, this task will be done whenever required.
Hyundai HD270
1 Concrete
Truck Mixer
9.2 EQUIPMENT
4 Aluminum L=8-10 m
screeding
5 Trowel h=20-50сm
9 Concrete vibrator
11 Level 2m
Shim plates shall be of machine type steel and shall not be removed. All levelling plates shall be
set to the proper elevation. The size of the grouting area shall be as per the foundation
drawings. If required proper shuttering to be done before pacing grout.
10.4 CURING
Curing shall be strict accordance with the manufacturer’s recommendations. The grout shall be
protected from extreme drying conditions by covering all exposed grout surfaces with
continually water or wetted hessian for a minimum three days.
5 SAFETY
All required permits will be obtained prior to any works commencing
All works shall comply with “Safety Plan” and municipality rules and regulations.
Skilled and unskilled labour shall need to use safety requirements such as safety
helmet, safety shoes, goggles, gloves, vest etc.
Safety devices and safety warnings shall be provided starting from the site entrance
gate till the casting area.
6
7
8
9