भारत सरकार
Government of India
विद्युत मंत्रालय
Ministry of Power
के न्द्रीय विद्युत प्राधिकरण
Central Electricity Authority
विद्युत प्रणाली योजना एवं मूल्यांकन-I प्रभाग
Power System Planning & Appraisal-I Division
सेवा में /To,
Sh. Purnendu Kumar Chaubey
General Manager
SB Energy Renewables Ten Private Ltd
1st Floor, Worldmark-2, Asset Area-8
Hospitality District, Aerocity
Delhi – 110037
विषय : विद्यतु अधिनियम, 2003 की धारा 68(1) के तहत M/s SB Energy Renewables Sixteen Private Ltd को
पारे षण योजना “Connectivity system to M/s SBE Renewables Sixteen Private Limited for 180
MW Solar project in Jaisalmer, Rajasthan” के लिये भारत सरकार का पर्व
ू अनमु ोदन–सम्बधि
ं त
Sub: Prior approval of the Government of India under section 68(1) of the Electricity act, 2003 to
M/s SBE Renewables Sixteen Private Limited for the transmission scheme “Connectivity
system to M/s SBE Renewables Sixteen Private Limited for 180 MW Solar project in
Jaisalmer, Rajasthan”-reg.
संदर्भ /Reference:
i. SB Energy letter no. SBE/Sixteen/180 MW/Section-68 dated 02.06.2020
ii. CEA letter no. CEA-PS-11-21(25)/1/2018-PSPA-I Division dated 29.06.2020
iii. SB Energy letter no. SBE/Sixteen/180 MW/Section-68 dated 29.06.2020
iv. SB Energy letter no. SBE/Sixteen/180 MW/Section-68 dated 17.07.2020
Sir,
Reference is invited to the above mentioned letter, seeking prior approval of Government of
India under Section 68(1) of Electricity Act, 2003, in favor of M/s SB Energy Renewables
Sixteen Private Ltd for the transmission scheme “Connectivity system to M/s SBE Renewables
Sixteen Private Limited for 180 MW Solar project in Jaisalmer, Rajasthan” with the following
scope of work:
i. SBE Renewable Sixteen Pvt. Ltd. –Fatehgarh-II PS 220 kV S/c line (suitable to carry 300
MW at nominal voltage) along with associated bays at generation end.*
* Length of transmission line is approx. 12 km out of which approx. 9 km would be
implemented as S/c line on S/c towers and balance line near Fatehgarh-II PS substation would
be implemented as S/c line on M/c towers.
सेवा भवन, आर. के . परु म-I, नई दिल्ली-110066 टेलीफै क्स: 011-26102045 ईमेल:[email protected] वेबसाइट:www.cea.nic.in
SewaBhawan, R.K Puram-I, New Delhi-110066Telefax: 011-26102045 email: [email protected]: www.cea.nic.in
File No.CEA-PS-11-21(25)/1/2018-PSPA-I Division 569
I/10698/2020
2. The above transmission scheme with its specified scope of work has been agreed for 180 MW
plant capacity in 32nd meeting of NR Constituents regarding Connectivity & Long-Term Access
applications in Northern Region held on 28.02.2020.
3. CEA conveys the prior approval of the Government of India under section 68 (1) of the
Electricity Act, 2003 for the following overhead line under the transmission scheme
“Connectivity system to M/s SBE Renewables Sixteen Private Limited for 180 MW Solar
project in Jaisalmer, Rajasthan”:
i. SBE Renewable Sixteen Pvt. Ltd. –Fatehgarh-II PS 220 kV S/c line (suitable to carry 300
MW at nominal voltage).*
* Length of transmission line is approx. 12 km out of which approx. 9 km would be
implemented as S/c line on S/c towers and balance line near Fatehgarh-II PS substation would
be implemented as S/c line on M/c towers.
प्रतिलिपि/ Copy to -
(i) Joint Secretary (Trans), Ministry of Power, Shram Shakti Bhawan, New Delhi
सेवा भवन, आर. के . परु म-I, नई दिल्ली-110066 टेलीफै क्स: 011-26102045 ईमेल:[email protected] वेबसाइट:www.cea.nic.in
SewaBhawan, R.K Puram-I, New Delhi-110066Telefax: 011-26102045 email: [email protected]: www.cea.nic.in