0% found this document useful (0 votes)
25 views5 pages

Assignment 3 - Fall 2020 - Model Answer

This document contains model answers to an assignment with three problems related to construction project management. Problem 1 involves calculating the daily production rate and optimal number of mixing and finishing crews needed to achieve a desired daily production rate of 75 cubic meters. Problem 2 involves calculating the cycle time and utilization factor of equipment in an earthmoving operation, including a loader, three trucks, and a bulldozer. Problem 3 similarly calculates cycle time, utilization factor, and how the addition of a second truck would impact utilization for an operation involving trucks, a crane, and two crews.

Uploaded by

Ibrahim Mahmoud
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
25 views5 pages

Assignment 3 - Fall 2020 - Model Answer

This document contains model answers to an assignment with three problems related to construction project management. Problem 1 involves calculating the daily production rate and optimal number of mixing and finishing crews needed to achieve a desired daily production rate of 75 cubic meters. Problem 2 involves calculating the cycle time and utilization factor of equipment in an earthmoving operation, including a loader, three trucks, and a bulldozer. Problem 3 similarly calculates cycle time, utilization factor, and how the addition of a second truck would impact utilization for an operation involving trucks, a crane, and two crews.

Uploaded by

Ibrahim Mahmoud
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

Cairo University

STRN 224: Construction Project Management


Fall-2020
Assignment 3-Model Answer

Problem 1:

- Cycle time (Operation) = Cycle time (Finishing crew) = 15 min


- Daily production rate (Mixing crew) = 0.5*(60/10) *8 = 24 m3/d
- Daily production rate (Finishing crew) = 0.5*(60/15) *8 = 16 m3/d

I. Daily production rate (Operation) = 0.5*(60/15) *8 = 16 m3/d


II. Optimal # of finishing crews with a single mixing crew (@ the first balance point) = Cycle time (Operation)/Cycle time (Mixing crew)
= 15/10 = 1.5 --> 2 crews or = Daily production rate (mixing crew)/Daily production rate (Finishing crew) = 24 / 16 = = 1.5 --> 2 crews

- Desired daily production rate = 75 m3/d


III. Optimum combination of mixing & finishing crews:
- # of mixing crews = 75/24 = 3.1 ---> 4 crews
- # of finishing crews = 75/16-= 4.68----> 5 crews
Cairo University
STRN 224: Construction Project Management
Fall-2020
Assignment 3-Model Answer

Problem 2:
a) Multiple Activity Chart:

b) Operation Cycle Time

Cycle time calculations Cycle time resource


Loader 3 * (5 + 1) 18
Truck 1 5+8+3+6 22
Truck 2 5+8+3+6 22
Truck 3 5+8+3+6 22
Bulldozer 3*4 12
Cairo University
STRN 224: Construction Project Management
Fall-2020
Assignment 3-Model Answer

Cycle time Operation = Max. Cycle time of resource = 22 minutes


Cycle Quantity = 15*3 45 m3
45 ∗ 60 ∗ 8
Productivity operation = = 981.8 m3/d
22

c) Utilization Factor:

Utilization Factor
Utilization Factor
calculations
Loader (18 / 22 ) * 100% 81.8 %
Truck 1 (22/ 22 ) * 100% 100 %
Truck 2 (22 / 22 ) * 100% 100 %
Truck 3 (22 / 22 ) * 100% 100 %
Bulldozer (12/ 22) * 100% 54.5 %
Cairo University
STRN 224: Construction Project Management
Fall-2020
Assignment 3-Model Answer

Problem 3:
a) Multiple Activity Chart:

b) Operation Cycle Time

Cycle time (Truck) = 12 mins


Cycle time (Crane) = 9 mins
Cycle time (Crew 1) = 10 mins
Cycle time (Crew 2) = 12 mins
Cycle time (operation) = 12 mins

c) Utilization Factor:

% utilization (Truck) = (12/12)*100 = 100 %


% utilization (Crane) = (9/12)*100 = 75 %
% utilization (Crew 1) = (10/12)*100 = 83.33 %
% utilization (Crew 2) = (12/12)*100 = 100 %
Cairo University
STRN 224: Construction Project Management
Fall-2020
Assignment 3-Model Answer

d) Without redrawing the multiple activity chart, calculate the utilization factor for each equipment and the two crews, in case a second
truck is brought to site.

Cycle time (Truck 1,2) = 12 mins


Cycle time (Crane) = 18 mins
Cycle time (Crew 1) = 20 mins
Cycle time (Crew 2) = 24 mins
Cycle time (Operation) = 24 mins
% utilization (Truck 1,2) = 50 %
% utilization (Crane) = 75 %
% utilization (Crew 1) = 83.33 %
% utilization (Crew 2) = 100 %