Chap 11 - Variance Analysis
Chap 11 - Variance Analysis
VARIANCE ANALYSIS
Standard costs are used for preparation of budgets. As a part of performance measurement, at end of
period, actual results are compared with budgets. Then the differences are analyzed to the lowest possible
level. This process is called variance analysis. Following major categories of variances are calculated:
Cost variances:
- Direct material cost variances
- Direct labor costs variances
- Variable overhead variances
- Fixed overhead variances
Sale variances
After calculation of all variances, a statement is prepared which reconciles budgeted profit with actual
profit incorporating all variances. This statement is called operating statement.
2. COST VARIANCES
(b) If inventory is measured at actual cost (i.e. MPV is recorded at the time of issuance)
[If nothing is mentioned even then assume this case in question]
(i) Total material cost variance
= SC x SQ – AC x AQ(used)
OR
= MPV + MQV
Illustration 1
Standard cost card (per unit):
Direct material 4Kg at Rs. 15 per Kg
Required:
Calculate (i) Material cost variance (ii) Material price variance (iii) Material usage/quantity variance,
assuming material quantities purchased and used are same.
Illustration 2
Standard cost card (per unit):
Direct material 4Kg at Rs. 12 per Kg
Required:
Calculate (i) Material cost variance (ii) Material price variance (iii) Material usage/quantity variance,
assuming material inventory is valued at standard cost.
Case - II Separate record of idle hours is kept OR Hours worked ≠ hours paid
(a) Idle time is not part of standard cost (i.e. ignored in standard card) (default case in exam)
(i) Total labor cost variance
= SR x SH – AR x AH(paid)
OR
= LRV + LEV + Idle time variance
Illustration 3
Standard cost card (per unit):
Direct labor 4 hours at Rs. 200 per hour
Required:
Calculate (i) labor cost variance (ii) labor rate variance (iii) labor efficiency variance.
Illustration 4
Standard cost card (per unit):
Direct labor 4 hours at Rs. 200 per hour
Required:
Calculate (i) labor cost variance (ii) labor rate variance (iii) labor efficiency variance (iv) idle time variance.
Illustration 5
Standard cost card (per unit):
Direct labor:
Work 3 hours at Rs. 100 per hour
Idle 0.5 hour at Rs. 100 per hour
Paid 3.5 hours at Rs. 100 per hour
Required:
Calculate (i) labor cost variance (ii) labor rate variance (iii) labor efficiency variance (iv) idle time variance.
Illustration 6
Standard cost card (per unit):
Variable overheads 5 machine hours at Rs. 20 per hour
Required:
Calculate (i) variable OH cost variance (ii) variable OH expenditure variance (iii) variable OH efficiency
variance.
Illustration 7
Standard cost card (per unit):
Fixed overheads 4 labor hours at Rs. 80 per hour
Required:
Calculate (i) fixed OH cost variance (ii) fixed OH expenditure variance (iii) fixed OH volume variance (iv)
fixed OH efficiency variance (v) fixed OH capacity variance.
3. SALE VARIANCE
3.1) Sales price variance
= AQ (sale) x Actual price – AQ (sale) x Standard price
Illustration 8
Standard cost card (per unit):
Rs.
Sale price 25
Material cost 8
Labor cost 4
Variable OH 2
Fixed OH 3
Actual sales for the month Rs. 270,000 (Rs. 27 per unit)
Labor hours worked 19,000 hours
Fixed overheads Rs. 1,615,000.
Required:
Calculate:
(i) sale price variance
(ii) sale volume variance, assuming absorption standard costing system is followed
(iii) sale volume variance, assuming marginal standard costing system is followed
Exam notes:
- If not given in question, students should prepare a detailed standard cost card first from
information given in question. It will help in calculating variances.
- If standard cost card is not given but budgeted P&L is given in question, then “per unit costs” from
budgeted P&L will be the standard costs.
- All above formulas are designed so that “positive” answer shows “favorable variance” and
“negative” answer shows “adverse variance”.
- All cost variances are calculated for actual FG production for the period instead of sales.
- If process costing is mixed, then SH/AH and SQ/AQ will be based on "equivalent produced FG
units for the period calculated using FIFO basis" instead of "actual FG units produced for the
period"
Rs. Rs.
Budgeted GP X
Sale variances:
Sale price variance X
Sale volume variance X X
Cost variances:
Material price variance X
Material usage variance X
Labor rate variance X
Labor efficiency variance X
Labor Idle time variance X
VOH spending variance X
VOH efficiency variance X
FOH spending variance X
FOH volume variance [Only for absorption costing] X X
Actual profit X
Exam notes:
- Add all “favorable variances” and deduct all “adverse variances” in above format.
- Replace "fixed OH efficiency and capacity variances" with "fixed OH volume variance" and
"Material yield and mix variances" with "material usage variance" if separately required in
question.
- If FG and WIP stocks are valued at actual cost then an adjustment is required as follows:
[Actual cost of closing stock - Standard cost of closing stock] XXX
[Standard cost of opening stock - Actual cost of opening stock] XXX
Exam notes:
If losses are also incorporated as a part of standard card then “SQ in SM” column is calculated as
follows:
If FG is given units:
SQ in SM = standard material (kg) x Actual FG production (units) / FG units for which standard is
set
If FG is given Kgs:
SQ in SM = standard material (kg) x Actual FG production (Kgs) / FG Kgs of which standard is set