Control Surveying1
Control Surveying1
1.1 Introduction
A. Traversing
B. Triangulation
C. Trilateration
1.3. TRAVERSE
1.3.1 Introduction
Figure 1.1
Bearing of a line is the horizontal angle from the north (N) or the
south (S) end of the meridian to the direction of the given line. They
can be NE. NW. SE. SW.
figure 1.3
figure 1.5
d) Open traverses
figure 1.6
Order of computation:
actual = actual =
f =
1:5000
f =
(a) (b)
Fig.1.1 triangulation nets
STANDARD CLASSIFICATION
Surveying Technology Department Control Surveying ( SUT 172) 13
1ST 2nd order 3rd order
ORDER Class I Class II Class I Class II
Discrepa
ncy b/n 1 part 1 part in 1 part in 1 part in 1 part in
measure 100,000 50,000 20,000 10,000 5,000
d and
compute
d length
of
baseline
Triangle
angular 1” 1.2” 2” 3” 5”
error
Recomm Furnishe Area Area General control
ended s control control control surveys referred to
uses for strengthe which national network
primary ns the contribut and local control
national national es to but surveys.
net work network supplem
metropol ental to
itan area the
surveys, national
scientific net work
2.6 Reconnaissance
C
B
A
h2
S-d
h1
S+d
2S
Example
Two triangulation stations A and B 110km apart have elevations of
320m and 950m respectively. The intervening ground at point D,
60km from station A has an elevation of 475m. Find out whether
Surveying Technology Department Control Surveying ( SUT 172) 17
stations A & B are inter visible. If not, calculate the height of the
signal at station B assuming station A as a ground station. The line of
sight should not pass nearer than 5m to the ground.
Solution
D
A
B
h1 60
h2
110
h1=320m ½(h2+h1)=635
h2=950m ½(h2-h1)=315
S+d=60km S2-d2 =(S+D)(S-D)
2S=110km =60 * 5
S=55 =3000
d=5km
So, the height of line of sight at station D above sea level is:
h=635 +315(5/55) – 3000(0.06735)
= 635 + 28.64 - 202.05
= 461.59m
a A
C b
A
In figure above, the length b is assumed to be known and it is desired
to determine the length c. With the sine law only the angles B and C
are used, and as a result the angle A has no direct effect on the
calculations and thus can be quite small without affecting the strength
of the figure.
Therefore, the strongest chain of triangle is the one whose distance
angles are near 900.There is a method of testing by which the strength
of figure is measured. The measure of the strength of figure with
respect to length is evaluated quantitatively in terms of a factor R
based on the probability.
Surveying Technology Department Control Surveying ( SUT 172) 19
R = { (D - C) / D } [ Σ{ δA2 + δAδB + δB2} ]
Example
Compute the strength of the fig. given below:
C D
a = 40
a h b = 60
c = 40
g d = 40
b e = 40
f = 50
g = 50
c f h = 40
d e
B
A
Solution
For the given figure the length of CD can be obtained in four different
ways.
II ABD AB AD 90 50 3
ACD AD CD 100 40 6
9 0.6*9=5.4
III ABC AB CB 80 60 2
CBD CB CD 90 50 3
5 0.6*5=3
IV ABD AB BD 50 40 14
CBD BD CD 50 40 14
28 0.6*28=16.8
The points forming the triangulation stations are selected on the basis
of visibility as for example on the top of hills or church steeples, or
radio towers, or water tanks. As a result, the points are not uniformly
spaced. Some of the points are obviously inaccessible and it is
necessary to establish eccentric stations from them and to determine
the distance and direction s from the main stations to the eccentric
stations.
Sometimes it is necessary to build special towers for making the
observations. These towers contain one tower built inside another so
that the towers supporting the instrument operator are independent.
For triangulation of lower accuracy, a small pole signal about 2m high
guyed in place, or an object already in place might be used for
sighting. As most triangulation works of higher accuracy are carried
out between late afternoon or an automobile headlight may be used
as signal. Signals should be free from phase.
In general, the types of signal used depend on the length of the line
accuracy required whereas its form depend s on the locality and
availability of materials.
Triangulation stations should be marked and referenced very
carefully for use at later days. The signal used must permit centring
the instrument if the station is to be occupied
(for instance, an iron pipe set vertically so that a pole can be inserted
in to it for sighting and this pole can be removed when centring the
instrument over the station).
When towers are required due to flat terrain, heavy timber or other
factors, it is necessary to determine the minimum height of the towers
required from the equation for the earth’s curvature and atmospheric
refraction.
Solution
Example
The elevation of measured base line is 540m above mean sea level.
The recorded length of the base line is 1035.407m. Compute the length
of the base line at sea level
Solution
S = RD / (R+h)
= (6372200* 1035.407) / (6372200+540)
= 1035.319m
b) Angle measurement
Example
1. For the triangles shown, the measured angles are given . Make
station and figure adjustment to the angles.
A Measured angles
3 41 16 10
D
1 53 33 20
2 9 265 07 45
10 91 16 10
268 43 30
35 07 00
78 42 30
5 4 246 11 00
7 60 01 05
B 6
8 249 59 15
solution
Surveying Technology Department Control Surveying ( SUT 172) 26
a) station adjustment
b) Figure Adjustment
A
a b
h c
g d
f e
Base line D
a) Geometric condition
1) the sum of interior angles of a triangle should be 1800.
For ABC ; a + b + c + d = 180
For BCD; c + d + e + f =180
For ABD; a + b + h + g =180
For ACD ; h + g + f + e = 180
2) The sum of interior angles of quadrilateral should be 3600.
a + b + c + d + e + f + g + h = 360
3) The sum of opposite angles ( at the intersection of the diagonal)
should be equal.
a+b=e+f
c+ d = g + h
Surveying Technology Department Control Surveying ( SUT 172) 28
b) Trigonometric condition
Log { (sin a) ( sin c) ( sin e) ( sin g ) } – log{ ( sin b)( sin d)( sin f)( sin h)}
=0
Logsina+ Logsinc+ Logsine+ Logsing = Logsinb + Logsind + Logsinf +
Logsinh
This geometric condition to be satisfied for quadrilateral adjustment
Steps in the adjustment of quadrilaterals
1. Correct each of the eight angles so that their sum will be exactly
360.
2. Adjust the vertically opposite angles so that their sum should be
equal.
3. Record the log sines for every alternate angles
4. For each angle record the tabular logarithmic sine difference for
1” opposite each logarithm.
5. Find the average required change (α ) in log sines by dividing
the differences between the sums by eight.
6. Find the average difference () for 1”.
7. The ratio of (α/) gives the number of seconds or arc to be
applied as a correction . this correction is added to each of the
four angles whose sum of log sines is the smaller and subtracted
from each of the other four angles whose sum of log sines is
the larger, and thus the correct value of angles are obtained.
Example
1.Make the necessary adjustment for the following quadrilaterals.
B
A Measured angle
b c a = 38 44 06
a d b = 23 44 38
c = 42 19 09
d = 44 52 01
e = 69 04 21
f = 39 37 48
g = 26 25 51
h = 75 12 14
h e
g f = 360 00 08
C
Correction: add 2.47” to all angles whose sines of log sine is smaller
( i.e for angles a, c, e and g ) & vice-versa( subtract 2.47” from b, d, f,
and h )
Note : If the corrections are properly applied,the sum of the logsines
of the corrected angles will agree with in 1 or 2 in the last 7th decimal
place.
B S
3 4
2 5
8
7
9
1 6
M
Y
e2 e1
E 1
e1’’ =
The value of L is not known but its approximate value can be taken as
EY and EM which is obtained by a preliminary computation of the
triangles using E as the triangulation station.
The sin of the correction is given by sin 1 and if the ratio d/D < 1/140
the formula cannot be used, but the ratio is not likely to be less than
this in practice.
Therefore;
e1 = and e2 =
So that;
Direction CY = direction EY + e1
Direction CM = direction EM + e2
Angle MCY in main triangulation scheme
= direction CY – direction CM
= direction EY + e1 – (direction EM + e2)
Example
D
A
Solution
Converting the observed angles taken at E into clockwise
directions gives, with direction EB as a reference direction:
ED = 169027’47. 18’’ = 1
EA = 169027 47.18’’ + 95016’40. 52’’
= 264044’27. 7’’ = 2
Reduction to centre
Station A D
Two sides of each triangle are computed by using the law of sines,
since one side of the triangle is always known and the three angles
have been measured and adjusted. In computing the sides of the
triangles in a quadrilateral, such as that in fig. below, the solutions of
two triangles is sufficient to compute the positions of the forward
triangulation stations. The two triangles chosen must be the strongest
route through the quadrilateral.
a = 63017'28.12''
C b = 84018'20.37''
c = 17052'26.69''
d = 30041'16.98''
D f e = 47007'55.96''
f = 66035'55.30''
g e g = 35034'51.76''
h= 14031'44.82''
d
a b c B
In the figure above, the side AB is the known or measured line of the
quadrilateral, and the strongest route is obtained by considering
triangle ABC and triangle DAC in that order. To check the accuracy of
the fieldwork or the consistency of the figure adjustment, the two
triangles ABC and triangle BDC can be computed in that order. This
computation gives a check on the length of the side CD, which is the
forward side of the quadrilateral. However, only the result for the
strongest route will be used in the further computations.
If the coordinates of stations A and B are known, the length of line BA
computed by:
Surveying Technology Department Control Surveying ( SUT 172) 35
DAB = [ (EB - EA)2 + (NA - NB)2 ]1/2
DAB= 3000.000m
With the side AB known, the sides AC and CB are computed by using
the law of sines.
Also,
Triangle CAD
CA 3068.554
0
D h+g 50 06'36.58'' 0.76727890
C f 66035'55.30'' 0.91774558
A) Computation of Azimuths
If the coordinates of stations A and B are known, the azimuth from
north of the line AB is determined by:
tan AAB =
AAB = tan-1
AAB = 104042'56.6''
The coordinates of all the stations throughout the triangulation system are
results. In this case a traverse extending from one fixed point to another
compass rule.
3. TRILATERATION
Cos α =
Cos β =
Cos γ =
Before the lengths of the lines in the trilateration net can be used in
any subsequent computations, their slope lengths determined by
the instrument and corrected for atmospheric conditions must be
reduced to the corresponding sea-level distance.
δ = BAB’=
where θ is vertical angle at A and
β is vertical angle at B
AB1= S cos δ
BB1= S sin δ
D3 = ---------------------------------------(d)
The arc length on the sea-level can be computed from this chord
distance as:
D1= R θ
D2 = 2Rsin-1[D3/2R]--------------------------------------------------------(e)
Equations (d) and (e) can be used to compute the distance on any
level surface by simply modifying the heights of the endpoints as
appropriate. To compute the chord distance between two points at
different elevations, for example D1, the following equation is used:
3.2.1 INTERSECTION
Intersection is a method of locating a point with out actually
occupying it. In figure below, points A and B are stations in a control
network already surveyed and in order to coordinate unknown point
C which lies at the intersection of the lines from A and B, angles and
are observed.
A
γ
C
B φ δ
β
α
A
C
3.2.2 RESECTION
B C
c B
A
α1 α2
α
P'
P''
Example
1. In the figure above, angles X and Y were measured.
P' = 30042’37’’
P'' = 25012’15’’
Coordinate points A, B, and C have coordinates (in metre) of:
XB = 12750.000 XA = 16820.540 XC = 22190.788
YB = 10271.000 YA = 10105.772 YC = 11317.229
Solution
1. Compute b, c, and α
c =
=
=
c = 4073.892
b=
=
b = 5505.197
α = azimuth of AB – azimuth of AC
= AAB - AAC
AAB = tan –1
AAC = tan –1
2. Compute X + Y
1/2(X + Y ) = 360 – (α +p'' + p')
= 360 – (195002’12. 47’’ +30042’37’’ + 25012’15’’)
= 109002’55. 53’’
3. Calculate X and Y
1/2(X-Y)=tan-1[cot(Z+450)tan1/2(X+Y)]
Z + 45 = 76040'36.93"
Example
2. The coordinates of two control points A and B are XA=
602,105.32 and YA= 126,118.90m; XB= 601,048.82m and YB =
Surveying Technology Department Control Surveying ( SUT 172) 50
125,613.48m. The clockwise angle at A from B to unknown point
P is 52018'46.2'';the counter clockwise angle at B from A to P is
37028'16''. Compute the coordinates of P by intersection.
SOLUTION
B
A
64026'02.3'' + 1800
= 244026'2.3''
ABA= azimuth of AB +or - 1800 = 64026'2.3''
A + B + P =1800
52018’46.2’’ + 37028’16’’ + P =180
P = 90012’57.8’’
DAP = DAB * sinB/sinP
= 1171.171 * sin 37028’16’’/sin 90012’57.8’’
= 712.500m
DBP = DAB * sin A/sinP
= 1171.171 * sin 52018’46.2’’/sin 90012’57.8’’
= 926.825m
EP = EA+DAP*sin (AAP)
= 602,105.32+712.500*sin2960 44’ 48.5’’
= 601,469.055
NP = NA+DAPcos (AAP)
=126,118.90+712.500*cos2960 44’ 48.5’’
=126,439.560
EP = EB + DBP*sinABP
= 601,048.82 + 926.825*sin260 57’ 46.3’’
= 601,469.054
NP =NB+DBPcosABP
=125,613.48+926.825*cos260 57’ 46.3’’
=126,439.560
C
B
es=