Form - Scar Log
Form - Scar Log
20 days
Today's date is Friday, December 2, 2022
Date PO # or Quantity Date SCAR
Supplier Submitted by Part / Material # Description of Part / Material Nature of the Problem Sent ATTN TO: Date Sent to Supplier Action Due Date Overdue? Follow-Up Date Follow-Up Result If FAIL, Action to Take:
Submitted Reference # Effected Returned
Supplier Corrective Action Request (SCAR) Log Rev 01 Default is
20 days
Today's date is Friday, December 2, 2022
Date PO # or Quantity Date SCAR
Supplier Submitted by Part / Material # Description of Part / Material Nature of the Problem Sent ATTN TO: Date Sent to Supplier Action Due Date Overdue? Follow-Up Date Follow-Up Result If FAIL, Action to Take:
Submitted Reference # Effected Returned
Supplier Corrective Action Request (SCAR) Log Rev 01 Default is
20 days
Today's date is Friday, December 2, 2022
Date PO # or Quantity Date SCAR
Supplier Submitted by Part / Material # Description of Part / Material Nature of the Problem Sent ATTN TO: Date Sent to Supplier Action Due Date Overdue? Follow-Up Date Follow-Up Result If FAIL, Action to Take:
Submitted Reference # Effected Returned
Supplier Corrective Action Request (SCAR) Log Rev 01 Default is
20 days
Today's date is Friday, December 2, 2022
Date PO # or Quantity Date SCAR
Supplier Submitted by Part / Material # Description of Part / Material Nature of the Problem Sent ATTN TO: Date Sent to Supplier Action Due Date Overdue? Follow-Up Date Follow-Up Result If FAIL, Action to Take:
Submitted Reference # Effected Returned
Supplier Corrective Action Request (SCAR) Log Rev 01 Default is
20 days
Today's date is Friday, December 2, 2022
Date PO # or Quantity Date SCAR
Supplier Submitted by Part / Material # Description of Part / Material Nature of the Problem Sent ATTN TO: Date Sent to Supplier Action Due Date Overdue? Follow-Up Date Follow-Up Result If FAIL, Action to Take:
Submitted Reference # Effected Returned
Supplier Corrective Action Request (SCAR) Log Rev 01 Default is
20 days
Today's date is Friday, December 2, 2022
Date PO # or Quantity Date SCAR
Supplier Submitted by Part / Material # Description of Part / Material Nature of the Problem Sent ATTN TO: Date Sent to Supplier Action Due Date Overdue? Follow-Up Date Follow-Up Result If FAIL, Action to Take:
Submitted Reference # Effected Returned
Supplier Corrective Action Request (SCAR) Log Rev 01 Default is
20 days
Today's date is Friday, December 2, 2022
Date PO # or Quantity Date SCAR
Supplier Submitted by Part / Material # Description of Part / Material Nature of the Problem Sent ATTN TO: Date Sent to Supplier Action Due Date Overdue? Follow-Up Date Follow-Up Result If FAIL, Action to Take:
Submitted Reference # Effected Returned
Supplier Corrective Action Request (SCAR) Log Rev 01 Default is
20 days
Today's date is Friday, December 2, 2022
Date PO # or Quantity Date SCAR
Supplier Submitted by Part / Material # Description of Part / Material Nature of the Problem Sent ATTN TO: Date Sent to Supplier Action Due Date Overdue? Follow-Up Date Follow-Up Result If FAIL, Action to Take:
Submitted Reference # Effected Returned
Supplier Corrective Action Request (SCAR) Log Rev 01 Default is
20 days
Today's date is Friday, December 2, 2022
Date PO # or Quantity Date SCAR
Supplier Submitted by Part / Material # Description of Part / Material Nature of the Problem Sent ATTN TO: Date Sent to Supplier Action Due Date Overdue? Follow-Up Date Follow-Up Result If FAIL, Action to Take:
Submitted Reference # Effected Returned
Supplier Corrective Action Request (SCAR) Log Rev 01 Default is
20 days
Today's date is Friday, December 2, 2022
Date PO # or Quantity Date SCAR
Supplier Submitted by Part / Material # Description of Part / Material Nature of the Problem Sent ATTN TO: Date Sent to Supplier Action Due Date Overdue? Follow-Up Date Follow-Up Result If FAIL, Action to Take:
Submitted Reference # Effected Returned
Supplier Corrective Action Request (SCAR) Log Rev 01 Default is
20 days
Today's date is Friday, December 2, 2022
Date PO # or Quantity Date SCAR
Supplier Submitted by Part / Material # Description of Part / Material Nature of the Problem Sent ATTN TO: Date Sent to Supplier Action Due Date Overdue? Follow-Up Date Follow-Up Result If FAIL, Action to Take:
Submitted Reference # Effected Returned
Supplier Corrective Action Request (SCAR) Log Rev 01 Default is
20 days
Today's date is Friday, December 2, 2022
Date PO # or Quantity Date SCAR
Supplier Submitted by Part / Material # Description of Part / Material Nature of the Problem Sent ATTN TO: Date Sent to Supplier Action Due Date Overdue? Follow-Up Date Follow-Up Result If FAIL, Action to Take:
Submitted Reference # Effected Returned
Supplier Corrective Action Request (SCAR) Log Rev 01 Default is
20 days
Today's date is Friday, December 2, 2022
Date PO # or Quantity Date SCAR
Supplier Submitted by Part / Material # Description of Part / Material Nature of the Problem Sent ATTN TO: Date Sent to Supplier Action Due Date Overdue? Follow-Up Date Follow-Up Result If FAIL, Action to Take:
Submitted Reference # Effected Returned
Supplier Corrective Action Request (SCAR) Log Rev 01 Default is
20 days
Today's date is Friday, December 2, 2022
Date PO # or Quantity Date SCAR
Supplier Submitted by Part / Material # Description of Part / Material Nature of the Problem Sent ATTN TO: Date Sent to Supplier Action Due Date Overdue? Follow-Up Date Follow-Up Result If FAIL, Action to Take:
Submitted Reference # Effected Returned
SUPPLIER ACTION SYSTEM (SCAR)
TREND ANALYSIS REPORT
As of 2-Dec-22
Overview
Supplier Quantity of SAR parts per Supplier