Table of Contents
1. Prepare the Robot Body
2. Make Holes in the Plastic Container
3. Insert the Push-to-Connect Tube Fitting
4. Insert the D-Shaft into the Spool
5. Assemble the Robot Spool
6. Tie a Loop Around the Spool
7. Attach the Robot to the Spool
8. Wind the String and Vine Robot
9. Insert the Bearing into the Bearing Base
10. Attach the Bearing Base to the Container Cap
11. Attach the Motor to the Motor Base
12. Add a Spider Coupler to the Motor
13. Assemble the Base Station
14. Checkpoint #1
15. Add the Aligning Shaft to the Outlet Tube
16. Add the Outlet Tube to the Base Station
17. Attach the Robot to the Outlet Tube
18. Attach the Hapkit and Upload Code
19. Run and Control the Robot
20. Connect to Air Compressor and Run
1
Step 1: Prepare the
9’3”
Robot Body
11. Cut 9 feet and 3 inches of plastic from the roll
2
1”
2. Using a permanent marker, mark straight line at 1”
2
1” from both ends. One of the ends must be marked
all around (as shown by the right end in Figure 2).
33. Heat seal the not-all-the-way-around end to
create a 1” thick rectangular pocket
44. Cut a 10 feet long length of string (about 1 foot
longer than your plastic’s length)
_______________________________________________
3
Quality Check:
• Make sure your 1” pocket is actually sealed
completely (must be airtight)
• You can inflate the tube to check, if necessary
2
Step 2: Make Holes
in the Plastic
Container
1
1. Using a permanent marker, sketch a 2” circle, 0.5”
circle, and a 0.125” circle in the locations shown in
Figure 1
22. Drill holes using the corresponding bits for each
hole. Use the largest bit available to you for the 2”
circle.
33. Use a Dremel to expand the 2” hole to the
appropriate size
_______________________________________________
Quality Check:
• Have the edge of the 2” hole about an inch from
the lid lip
• The locations of the holes are very forgiving
• It is fine if the holes are a bit oversized, since
we will be sealing them with hot glue.
1
Step 3: Insert the
Push-to-Connect
Tube Fitting
11. Align the tube fitting with the 1/4” hole made on
the side of the container
2
2. Screw the fitting into the container until it is flush
2
with the side (for your first time, you are threading
the plastic by doing so)
3 Apply hot glue around the fitting to create an
airtight seal at the connection point with the plastic.
_______________________________________________
Quality Check:
3 • Pull lightly on the fitting to see if it has been
secured
• Check around the edges of the glue for any gaps
• Once we pressurize the chamber, it will be
clear if the glue sealed correctly
1
Step 4: Insert the D-
Shaft into the Spool
11. Insert the D-shaft through the spool’s center.
2
2. Leaving about 0.25” of shaft coming from the
2 other side.
33. Add one of the spider couplers to the end with the
0.25” shaft extrusion and tighten the set screw
_______________________________________________
Quality Check:
• The flat part of the shaft must be facing the set
screw
3 • Don’t forget to tighten the set screw
*Mallet may be
useful
Step 5: Assemble the
1
Robot Spool
1. 1 Apply hot glue along the surface of the spool’s
main body.
2 Insert the circular disk (or spool cap) into the
shaft and press down to glue the two spool
parts together
2
_______________________________________________
Quality Check:
• Minimal gaps between the glued disk and main
spool body
• Use the string to test that it doesn’t get caught
in the gap where we applied glue.
1
Step 6: Tie a Loop
around the Spool
1.1 Loop one end of the string around the body of
the spool in an “X” shape
2 Pass the end over and through to close the loop.
2 Repeat once more to seal the knot.
3 Pull the other end of the string to tighten the knot
until it touches the spool body
_______________________________________________
Quality Check:
• Pull the string as shown in Figure 3 to make sure
the knot does not become undone.
• Make sure you cannot slip a pencil between the
3 string and the spool body.
1 2
Step 7: Attach the
Robot to the Spool
1.1 Using a permanent marker, mark two points
about 0.25” from the edge of the rectangular
pocket
2
Puncture the plastic at the marked points
3 Insert the string through one of the holes and
through the back of the other hole. Create a loop
for a knot
3 4
4 Tighten the knot and make a second knot if
necessary
_______________________________________________
Quality Check:
• Pull the string as shown in Figure 4 to make sure
the knot does not become undone.
1
Step 8: Wind the
String and Robot
1.1 Hold the string or plastic roll taught while winding
2 Keep the plastic as flush as possible to the main
body of the spool
_______________________________________________
2
Quality Check:
• The rolled up robot should not have visible
wrinkles when fully rolled as shown below
• Except for the plastic-to-string knot area
shown in Figure 2
1
Step 9: Insert the
Bearing into the
Spool Base
1.1 Insert the bearing into the large, circular disk’s
center. It is a press fit, so it might require some
force.
_______________________________________________
Quality Check:
• The bearing must be flush with the surface of the
disk
*Mallet may
be useful
1 2
Step 10: Attach the
Bearing Base to the
Container Cap
11. Add a healthy amount of hot glue to either side of
the bearing base
22. Find the center of the bearing and cap. Align the
3 two centers.
3 Press the two parts together
_______________________________________________
Quality Check:
• Do not let the bearing come into contact with the
hot glue. This could mess up your bearing.
• Make sure your 3D printed part is leveled and not
angled
• You want full contact with the cap
1 2
Step 11: Attach the
Motor to the Motor
Base
1
1. Slide two wires through the base’s outer holes and
strip them as shown in Figure 1
3
2
2. Loop them through the motor leads
3
Solder the wires to the motor
4 Insert the motor into the base
_______________________________________________
4
Quality Check:
• If you opted to make a side hole for the wiring
rather than at the top, slide the wire’s through the
base’s side hole to keep things together
1
Step 12: Add a Spider
Coupler to the Motor
1 Insert the spider coupler into the motor shaft while
making sure that the set screw and the flat side of
the shaft are together.
2
Tighten the set screw
2
3 Push the coupler’s rubber insert into the spider
coupler as shown in Figure 3
_______________________________________________
Quality Check:
• Twist the spider coupler to make sure it is NOT
free spinning
• If it is, check that you have tightened the set
screw on the flat side of the motor shaft
3
1 2
Step 13: Assemble
the Base Station
1 Pass the motor wires through the 1/8” hole at the
bottom of the container
2 Add hot glue to the bottom of the motor base
and press the base flush with the bottom of the
container. Check that the motor shaft is
centered with respect to the container
3 3 Insert the non-coupler side of the spool into the
bearing
_______________________________________________
You should
now have:
4
Step 13: Continued
4 Connect spider couplers to add the spool to
the base station
5 Put on and twist the cap until the container is
sealed
_______________________________________________
5
2
Checkpoint #1
1 All parts, except for the motor, should be on the
same vertical axis
2 The spool shaft must be inserted in the bearing
and the cap tightly screwed on
3 No parts come loose
4 Seal the top wires with hot glue
3
_______________________________________________
4
1
1
Step 14: Add the
Aligning Shaft to the
Outlet Tube
1
2 1. Insert the wooden dowel piece into the straw to
make a makeshift bearing
2. Add two drops of crazy glue (one drop at each
2
end)
3 Press the dowel into extruder until it is flush with
the edge
_______________________________________________
3
Quality Check:
• Make sure that the dowel does not budge when
pressed
• Add crazy glue after step 3 as you see
necessary
• Make sure the straw is not glued down and can
rotate freely
1
Step 15: Add the
Outlet Tube to the
Base Station
11. Insert the outlet into the 2” hole you made in the
container. About 1/8” of insertion should be
2
enough to have a grip on the other side.
22. Rotate the extruder until the shaft is vertical
3 Hot glue all around the edges of the extruder to
make an airtight seal.
_______________________________________________
Quality Check:
3 • Make sure that the extruder does not budge
when moved
• If there are sharp edges on the extruder, use
sand paper to remove them.
• Not doing so may puncture the robot.
1 2
Step 16: Attach the
Robot to the Outlet
Tube
1
1. Pull the plastic roll through the outlet tube. If your
spool unrolls on the left, pass it on the right side of
the shaft as shown in Figure 1.
22. Open up the plastic roll
3 Turn the plastic inside out and fit it over the
extruder.
3 4 4 Pull the plastic back to remove any crumpling.
_______________________________________________
Top View of Robot Plastic Roll
Spool
Aligning Shaft
Outlet Tube
1
Step 16: Continued
11. Align the circular marking on the plastic roll with
the edge of the extruder, as shown.
22. Use the string-backed tape to create an airtight
seal and set the robot in place
_______________________________________________
2
1
Step 17: Attach the
Hapkit and Upload
Code
1
1. Connect the motor to the Hapkit by using the
onboard motor driver as shown on the left (white
wire first, followed by the black wire)
22. Download Arduino and upload the
“PreformedVine_KeyboardControl.ino” code to the
2 board
Compile - This loads the code
Name of the file _______________________________________________
Serial Monitor -
Interact with the Quality Check:
code here • Pull lightly on the wires to make sure they have
been set in place
• You can download the Arduino program here
Code goes here
Step 18: Run and
Control the Robot
11. While the USB cable connects your computer to
the Hapkit, open the serial monitor
22. You can control the robot by sending single,
capitalized characters through the serial monitor:
• “W” is forward growth (the motor rotates to
help release the stored material). Growth
requires the compressor to provide pressure.
• “S” is retraction (the motor rotates in the
opposite direction to store the extruded
W material)
• “D” increases the speed of the motor
A S D • “A” decreases the speed of the motor
• “ ” stops the motor
SPACE BAR STOP _______________________________________________
Action Quality Check:
Keyboard • If “S” unspools the material or “W” pulls the
material in, then your black and white cables
are flipped.
1
Step 19: Connect to
Air Compressor and
Run
1
1. Attach the clear tubing to the push-to-connect
tube fitting on the side of the base station
22. Connect the clear tubing you just used to the air
regulator and the air regulator to your air supply
2 33. Set the pressure to ~1.5psi for growing the Vine
Robot
_______________________________________________
Quality Check:
• Once you have pressurized the chamber, listen
for any air leaks
• Use hot glue or an epoxy to seal the leaks
Final Assembly