J-11011/146/2014-IA II (I)
Government of India
Ministry of Environment, Forests and Climate Change
(I.A. Division)
Indira Paryavaran Bhawan
Aliganj, Jorbagh Road,
New Delhi -110003
E-mail : [email protected]
Dated: 3rd November, 2014
To,
Shri Tapan J Solanki
Director
M/s Setco Chemicals (I) Pvt. Ltd.
Plot No. 788/1,
40 Shed Area, GIDC Vapi
Gujarat- 396195.
Email.: tjs@setcoc hemicals.com Fax.: +91 11 2422905/6/7
Subject: Manufacturing of Resins & Adhesives of M/s Setco Chemicals (I) Pvt. Ltd. at Plot No. 788/1,
40 Shed Area, GIDC Estate Vapi, Taluka Paradi, District Valsad, Gujarat -TOR reg.
Ref.: Your letter no. nil dated 24.03.2014
Sir,
Kindly refer your letter dated 24.03.2014 alongwith project documents including Form-I, Pre-
feasibility Report and draft ‘Terms of Reference’ as per the EIA Notification, 2006. It is noted that
proposal is for manufacturing of Resins & Adhesives of M/s Setco Chemicals (I) Pvt. Ltd. at Plot No.
788/1, 40 Shed Area, GIDC Estate Vapi, Taluka Paradi, District Valsad, Gujarat. Following products will
be manufactured:
S.N. Name of Product Quantity,( MTPM)
Existing Proposed Total
1 Printing 500 ----- 500
2 Ink Medium 100 ----- 100
3 Retarder 100 ----- 100
4 Foil wash 100 ----- 100
5 Alkyd Resin ---- 100 100
6 Pure Phenolic Resins ---- 50 50
7 Reduced phenolic Resin ---- 150 150
8 Polyurethane Resin ---- 300 300
9 Polyester Resin ---- 50 50
(saturated &
unsaturated)
10 Epoxy resin ----- 50 50
11 Polyamide Resin ----- 200 200
12 MF Resin ------ 50 50
13 UF Resin ----- 50 50
14 Ketonic Resin ----- 100 100
15 Acrylic Resin ----- 50 50
16 Emulsions ------ 50 50
17 Adhesives ----- 50 50
Total of Product Quantity 800 1250 2050
2.0 Draft Terms of Reference (TOR) have been discussed and finalized during the 21st
Reconstituted Expert Appraisal Committee (Industry) held during 30th -31st July and 1st August,
2014 for preparation of EIA/EMP report. Following are the ‘TORs’:
1. Executive summary of the project
2. Justification of the project.
3. Photographs of proposed plant site.
4. Promoters and their back ground.
5. Regulatory framework.
6. A map indicating location of the project and distance from severely polluted area
7. Project location and plant layout.
8. Infrastructure facilities including power sources.
9. Total cost of the project along with total capital cost and recurring cost/annum for environmental
pollution control measures.
10. Project site location along with site map of 10 km area and site details providing various
industries, surface water bodies, forests etc.
11. Present land use based on satellite imagery for the study area of 10 km radius. Details of land
availability for the project along with supporting document.
12. Location of National Park/Wild life sanctuary/Reserve Forest within 10 km radius of the project.
13. Details of the total land and break-up of the land use for green belt and other uses.
14. List of products along with the production capacities.
15. Detailed list of raw materials required and source, mode of storage and transportation.
16. Manufacturing process details along with the chemical reactions and process flow chart.
17. Site-specific micro-meteorological data using temperature, relative humidity, hourly wind speed
and direction and rainfall is necessary.
18. Ambient air quality monitoring at 6 locations within the study area of 5 km. aerial coverage from
project site as per NAAQES notified on 16th September, 2009. Location of one AAQMS in
downwind direction.
19. One season site-specific micro-meteorological data using temperature, relative humidity, hourly
wind speed and direction and rainfall and AAQ data (except monsoon) for PM10, PM2.5, SO 2, NOx
including VOCs shall be collected. The monitoring stations shall take into account the pre-dominant
wind direction, population zone and sensitive receptors including reserved forests. Data for water
and noise monitoring shall also be included.
20. Air pollution control measures viz. Multi-cyclone and bag filter etc. shall be proposed for the
effective control of gaseous emissions within permissible limits.
21. Control methanol emission from drying section.
22. Details of VOC monitoring system in the working zone environment, if any.
23. Name of all the solvents to be used in the process and details of solvent recovery system.
24. Design details of ETP, incinerator, boiler, scrubbers/bag filters etc.
25. Details of water and air pollution and its mitigation plan.
26. An action plan to control and monitor secondary fugitive emissions from all the sources.
27. Determination of atmospheric inversion level at the project site and assessment of ground level
concentration of pollutants from the stack emission based on site-specific meteorological features.
Air quality modelling for proposed plant.
28. Permission for the drawl of ground water from CGWA. Water balance chart including quantity of
effluent generated recycled and reused and discharged.
29. Action plan for ‘Zero’ discharge of effluent shall be included.
30. Treatment of phenol in the effluent, if any.
31. Ground water quality monitoring minimum at 6 locations shall be carried out. Geological features
and Geo-hydrological status of the study area and ecological status (Terrestrial and Aquatic).
32. The details of solid and hazardous wastes generation, storage, utilisation and disposal particularly
related to the hazardous waste calorific value of hazardous waste and detailed characteristic of the
hazardous waste. Action plan for the disposal of fly ash generated from boiler shall be included.
33. Precautions to be taken during storage and transportation of hazardous chemicals shall be clearly
mentioned and incorporated.
34. Authorization/Membership for the disposal of solid/hazardous waste in TSDF.
35. List of hazardous chemicals (as per MSIHC rule) with toxicity levels.
36. A write up on “Safe Practice” followed for methanol handling, storage, transportation and
unloading to be submitted.
37. A write up on “Treatment of workers affected by accidental spillage of chemicals”.
38. Locating the plant in open area instead of covered to be reviewed in view of safety consideration.
39. An action plan to develop green belt in 33 % area
40. Action plan for rainwater harvesting measures at plant site shall be included to harvest rainwater
from the roof tops and storm water drains to recharge the ground water.
41. Details of occupational health programme.
i. To which chemicals, workers are exposed directly or indirectly.
ii. Whether these chemicals are within Threshold Limit Values (TLV)/ Permissible Exposure
Levels as per ACGIH recommendation.
iii. What measures company has taken to keep these chemicals within PEL/TLV.
iv. How the workers are evaluated concerning their exposure to chemicals during pre-placement
and periodical medical monitoring.
v. What are onsite and offsite emergency plan during chemical disaster.
vi. Liver function tests (LFT) during pre-placement and periodical examination.
42. Details of occupational health surveillance programme.
43. Socio-economic development activities shall be in place.
44. At least 5 % of the total cost of the project shall be earmarked towards the Enterprise Social
Commitment based on Public Hearing issues and item-wise details along with time bound action
plan shall be prepared and incorporated.
45. Detailed Environment management Plan (EMP) with specific reference to details of air pollution
control system, water & wastewater management, monitoring frequency, responsibility and time
bound implementation plan for mitigation measure shall be provided.
46. EMP shall include the concept of waste-minimization, recycle / reuse / recover techniques, Energy
conservation, and natural resource conservation.
47. Corporate Environmental Responsibility
(a) Does the company have a well laid down Environment Policy approved by its Board of Directors? If
so, it may be detailed in the EIA report.
(b) Does the Environmental Policy prescribe for standard operating process/procedures to bring into
focus any infringement / deviation / violation of the environmental or forest norms / conditions? If so,
it may be detailed in the EIA report.
(c ) What is the hierarchical system or Administrative order of the company to deal with the
environmental issues and for ensuring compliance with the EC conditions. Details of this system
may be given.
(d) Does the company have a system of reporting of non compliance / violations of environmental
norms to the Board of Directors of the company and / or shareholders or stakeholders at large?
This reporting mechanism shall be detailed in the EIA report.
48. Expansion/modernization proposals:
i. Copy of all the Environmental Clearance(s) including Amendments thereto obtained for the
project from MOEF/SEIAA shall be attached as an Annexure. A certified copy of the latest
Monitoring Report of the Regional Office of the Ministry of Environment and Forests as per
circular dated 30th May, 2012 on the status of compliance of conditions stipulated in all the
existing environmental clearances including Amendments should be provided. In addition, status
of compliance of Consent to Operate for the ongoing Iexisting operation of the project from SPCB
shall be attached with the EIA-EMP report.
ii. In case the existing project has not obtained environmental clearance, reasons for not taking EC
under the provisions of the EIA Notification 1994 and/or EIA Notification 2006 shall be provided.
Copies of Consent to Establish/No Objection Certificate and Consent to Operate (in case of units
operating prior to EIA Notification 2006, CTE and CTO of FY 2005-2006) obtained from the
SPCB shall be submitted. Further, compliance report to the conditions of consents from the
SPCB shall be submitted.
49. Any litigation pending against the project and/or any direction/order passed by any Court of Law
against the project, if so, details thereof.
50. A separate chapter on status of compliance of Environmental Conditions of Environmental
Clearances granted by State/Centre to be provided. As per circular dated 30th May, 2012 issued by
MoEF, a certified report by RO, MoEF on status of compliance of conditions of all ECs on existing
unit to be provided in EIA-EMP report.
51. A tabular chart with index for point wise compliance of above TORs.
The following general points shall be noted:
i. All documents shall be properly indexed, page numbered.
ii. Period/date of data collection shall be clearly indicated.
iii. Authenticated English translation of all material provided in Regional languages.
iv. The letter/application for EC shall quote the MOEF file No. and also attach a copy of the letter.
v. The copy of the letter received from the Ministry shall be also attached as an annexure to the final
EIA-EMP Report.
vi. The final EIA-EMP report submitted to the Ministry must incorporate the issues in this letter. The
index of the final EIA-EMP report must indicate the specific chapter and page no. of the EIA-EMP
Report.
vii. Certificate of Accreditation issued by the QCI to the environmental consultant shall be included. The
consultants involved in the preparation of EIA-EMP report after accreditation with Quality Council of
India (QCl) /National Accreditation Board of Education and Training (NABET) would need to include
a certificate in this regard in the EIA-EMP reports prepared by them and data provided by other
organization/Laboratories including their status of approvals etc. ‘Certificate of accreditation’ issued
by QCI to the environmental consultant should be included.
3.0 These ‘TORs’ should be considered for the preparation of EIA / EMP report for manufacturing of
Resins & Adhesives of M/s Setco Chemicals (I) Pvt. Ltd. at Plot No. 788/1, 40 Shed Area, GIDC Estate
Vapi, Taluka Paradi, District Valsad, Gujarat in addition to all the relevant information as per the
‘General Structure of EIA’ given in Appendix III and IIIA in the EIA Notification, 2006. The EIA/EMP as
per TORs should be submitted to the Chairman, Gujarat Pollution Control Board, (GPCB) for public
consultation. The SPCB shall conduct the public hearing/public consultation as per the provisions of EIA
notification, 2006.
4.0 You are requested to kindly submit the final EIA/EMP prepared as per TORs and incorporating
all the issues raised during Public Hearing / Public Consultation to the Ministry for considering the
proposal for environmental clearance within 2 years as per the MoEF O.M. No. J-11013/41/2006-IA.II
(I) dated 22nd March, 2010.
6.0 The consultants involved in the preparation of EIA/EMP report after accreditation with Quality
Council of India / National Accreditation Board of Education and Training (QCI/NABET) would need to
include a certificate in this regard in the EIA/EMP reports prepared by them and data provided by other
Organization(s)/Laboratories including their status of approvals etc.
(Lalit Bokolia)
Additional Director
Copy to :
1. The Chairman, Gujarat Pollution Control Board, Paryavaran Bhavan, Sector – 10, A, Gandhi Nagar
- 382 010, Gujarat (E-mail: [email protected] ; Fax No.: 079-23232156)
2. The Chief Conservator of Forests, Ministry of Environment & Forests, Regional Office, Kendriya
Paryavaran Bhavan, Link Road No.3, Ravi Shankar Nagar Bhopal-462016
(Lalit Bokolia)
Additional Director
Subject : Manufacturing of Resins & Adhesives of M/s Setco Chemicals (I) Pvt. Ltd. at Plot No.
788/1, 40 Shed Area, GIDC Estate Vapi, Taluka Paradi, District Valsad, Gujarat -TOR
reg.
M/s Setco Chemicals (I) Pvt. Ltd. have proposed for the award of ‘TOR’ for Manufacturing
of Resins & Adhesives at Plot No. 788/1, 40 Shed Area, GIDC Estate Vapi, Taluka Paradi, District
Valsad, Gujarat and have submitted duly-filled ‘Form-1’, draft ‘TOR’ and ‘Pre-feasibility Report’ as
per EIA Notification dated 14th September, 2006.
2.0 Plot area is 8801m2 of which greenbelt will be developed in 1164.6m2. Cost of project is Rs
5 crores. No Eco-sensitive Zone is located within 15 km distance. Proposal has been considered in
the EAC meeting as MoEF vide letter dated 10th June, 2014 has decided to keep OM dated 17th
September, 2013 in abeyance w.r.t re-imposition of moratorium in the 8 CPA. Following products
will be manufactured:
S.N. Name of Product Quantity,( MTPM)
Existing Proposed Total
1 Printing 500 ----- 500
2 Ink Medium 100 ----- 100
3 Retarder 100 ----- 100
4 Foil wash 100 ----- 100
5 Alkyd Resin ---- 100 100
6 Pure Phenolic Resins ---- 50 50
7 Reduced phenolic Resin ---- 150 150
8 Polyurethane Resin ---- 300 300
9 Polyester Resin (saturated ---- 50 50
& unsaturated)
10 Epoxy resin ----- 50 50
11 Polyamide Resin ----- 200 200
12 MF Resin ------ 50 50
13 UF Resin ----- 50 50
14 Ketonic Resin ----- 100 100
15 Acrylic Resin ----- 50 50
16 Emulsions ------ 50 50
17 Adhesives ----- 50 50
Total of Product Quantity 800 1250 2050
3.0 Total water requirement from GIDC water supply will be 10.2m3/day. The effluent generation
will be 19m3/day and treated in ETP. Power requirement will be 200 KVA. DG set (250 KVA) will
be installed. Sludge and filter cake will be sent to CHWTSDF. Spent solvent will be sent to
Authorized Re-processors. PAs have also presented the draft TORs for the preparation of
EIA/EMP.
4.0 The Expert Appraisal Committee (Industry) discussed and finalized the draft TORs in the
st
21 Reconstituted Expert Appraisal Committee (Industry) held during 30th -31st July and 1st
August, 2014 (F/X). ‘TORs’ suggested by the EAC (I) for incorporation in EIA/EMP study are as
follows :
1. Executive summary of the project
2. Justification of the project.
3. Photographs of proposed plant site.
4. Promoters and their back ground.
5. Regulatory framework.
6. A map indicating location of the project and distance from severely polluted area
7. Project location and plant layout.
8. Infrastructure facilities including power sources.
9. Total cost of the project along with total capital cost and recurring cost/annum for
environmental pollution control measures.
10. Project site location along with site map of 10 km area and site details providing various
industries, surface water bodies, forests etc.
11. Present land use based on satellite imagery for the study area of 10 km radius. Details of land
availability for the project along with supporting document.
12. Location of National Park/Wild life sanctuary/Reserve Forest within 10 km radius of the
project.
13. Details of the total land and break-up of the land use for green belt and other uses.
14. List of products along with the production capacities.
15. Detailed list of raw materials required and source, mode of storage and transportation.
16. Manufacturing process details along with the chemical reactions and process flow chart.
17. Site-specific micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall is necessary.
18. Ambient air quality monitoring at 6 locations within the study area of 5 km. aerial coverage
from project site as per NAAQES notified on 16th September, 2009. Location of one AAQMS
in downwind direction.
19. One season site-specific micro-meteorological data using temperature, relative humidity,
hourly wind speed and direction and rainfall and AAQ data (except monsoon) for PM10,
PM2.5, SO2, NOx including VOCs shall be collected. The monitoring stations shall take into
account the pre-dominant wind direction, population zone and sensitive receptors including
reserved forests. Data for water and noise monitoring shall also be included.
20. Air pollution control measures viz. Multi-cyclone and bag filter etc. shall be proposed for the
effective control of gaseous emissions within permissible limits.
21. Control methanol emission from drying section.
22. Details of VOC monitoring system in the working zone environment, if any.
23. Name of all the solvents to be used in the process and details of solvent recovery system.
24. Design details of ETP, incinerator, boiler, scrubbers/bag filters etc.
25. Details of water and air pollution and its mitigation plan.
26. An action plan to control and monitor secondary fugitive emissions from all the sources.
27. Determination of atmospheric inversion level at the project site and assessment of ground
level concentration of pollutants from the stack emission based on site-specific
meteorological features. Air quality modelling for proposed plant.
28. Permission for the drawl of ground water from CGWA. Water balance chart including quantity
of effluent generated recycled and reused and discharged.
29. Action plan for ‘Zero’ discharge of effluent shall be included.
30. Treatment of phenol in the effluent, if any.
31. Ground water quality monitoring minimum at 6 locations shall be carried out. Geological
features and Geo-hydrological status of the study area and ecological status (Terrestrial and
Aquatic).
32. The details of solid and hazardous wastes generation, storage, utilisation and disposal
particularly related to the hazardous waste calorific value of hazardous waste and detailed
characteristic of the hazardous waste. Action plan for the disposal of fly ash generated from
boiler shall be included.
33. Precautions to be taken during storage and transportation of hazardous chemicals shall be
clearly mentioned and incorporated.
34. Authorization/Membership for the disposal of solid/hazardous waste in TSDF.
35. List of hazardous chemicals (as per MSIHC rule) with toxicity levels.
36. A write up on “Safe Practice” followed for methanol handling, storage, transportation and
unloading to be submitted.
37. A write up on “Treatment of workers affected by accidental spillage of chemicals”.
38. Locating the plant in open area instead of covered to be reviewed in view of safety
consideration.
39. An action plan to develop green belt in 33 % area
40. Action plan for rainwater harvesting measures at plant site shall be included to harvest
rainwater from the roof tops and storm water drains to recharge the ground water.
41. Details of occupational health programme.
i. To which chemicals, workers are exposed directly or indirectly.
ii. Whether these chemicals are within Threshold Limit Values (TLV)/ Permissible
Exposure Levels as per ACGIH recommendation.
iii. What measures company has taken to keep these chemicals within PEL/TLV.
iv. How the workers are evaluated concerning their exposure to chemicals during pre-
placement and periodical medical monitoring.
v. What are onsite and offsite emergency plan during chemical disaster.
vi. Liver function tests (LFT) during pre-placement and periodical examination.
42. Details of occupational health surveillance programme.
43. Socio-economic development activities shall be in place.
44. At least 5 % of the total cost of the project shall be earmarked towards the Enterprise
Social Commitment based on Public Hearing issues and item-wise details along with time
bound action plan shall be prepared and incorporated.
45. Detailed Environment management Plan (EMP) with specific reference to details of air
pollution control system, water & wastewater management, monitoring frequency,
responsibility and time bound implementation plan for mitigation measure shall be provided.
46. EMP shall include the concept of waste-minimization, recycle / reuse / recover
techniques, Energy conservation, and natural resource conservation.
47. Corporate Environmental Responsibility
(a) Does the company have a well laid down Environment Policy approved by its Board of
Directors? If so, it may be detailed in the EIA report.
(b) Does the Environmental Policy prescribe for standard operating process/procedures to bring
into focus any infringement / deviation / violation of the environmental or forest norms /
conditions? If so, it may be detailed in the EIA report.
(c ) What is the hierarchical system or Administrative order of the company to deal with the
environmental issues and for ensuring compliance with the EC conditions. Details of this
system may be given.
(d) Does the company have a system of reporting of non compliance / violations of environmental
norms to the Board of Directors of the company and / or shareholders or stakeholders at
large? This reporting mechanism shall be detailed in the EIA report.
48. Expansion/modernization proposals:
i. Copy of all the Environmental Clearance(s) including Amendments thereto obtained for the
project from MOEF/SEIAA shall be attached as an Annexure. A certified copy of the latest
Monitoring Report of the Regional Office of the Ministry of Environment and Forests as per
circular dated 30th May, 2012 on the status of compliance of conditions stipulated in all the
existing environmental clearances including Amendments should be provided. In addition,
status of compliance of Consent to Operate for the ongoing Iexisting operation of the
project from SPCB shall be attached with the EIA-EMP report.
ii. In case the existing project has not obtained environmental clearance, reasons for not
taking EC under the provisions of the EIA Notification 1994 and/or EIA Notification 2006
shall be provided. Copies of Consent to Establish/No Objection Certificate and Consent to
Operate (in case of units operating prior to EIA Notification 2006, CTE and CTO of FY
2005-2006) obtained from the SPCB shall be submitted. Further, compliance report to the
conditions of consents from the SPCB shall be submitted.
49. Any litigation pending against the project and/or any direction/order passed by any Court of
Law against the project, if so, details thereof.
50. A separate chapter on status of compliance of Environmental Conditions of Environmental
Clearances granted by State/Centre to be provided. As per circular dated 30th May, 2012
issued by MoEF, a certified report by RO, MoEF on status of compliance of conditions of all
ECs on existing unit to be provided in EIA-EMP report.
5.0 PAs may be requested as per DFA to :
i. Prepare EIA / EMP report for manufacturing of Resins & Adhesives of M/s Setco
Chemicals (I) Pvt. Ltd. at Plot No. 788/1, 40 Shed Area, GIDC Estate Vapi, Taluka
Paradi, District Valsad, Gujarat as per the above mentioned TORs in addition to all the
relevant information as per the ‘General Structure of EIA’ given in Appendix III and IIIA
in the EIA Notification, 2006.
ii. Address all the issues raised during the Public Consultation and incorporate them in the
final EIA/EMP report and submit a copy of the Public hearing report alongwith video film
to the Ministry for considering the proposal for environmental clearance within 2 years
as per the MoEF O.M. No. J-11013/41/2006-IA.II (I) dated 22nd March, 2010.
6.0 Simultaneously, a copy of the letter may also be sent to the Chairman, GPCB and
Regional Office of MoEF & CC intimating the award of TORs.
File is submitted for approval please.
(A.N. Singh)
Jt. Director
16th October, 2013
AD(LB)
MINUTES OF 21st RECONSTITUTED EXPERT APPRAISAL COMMITTEE (INDUSTRY) HELD
DURING
30th JULY 2014 TO 1ST AUGUST 2014
VENUE: Scope Complex, Core 6, 5th Floor, IOCL Conference Room, Ministry of Petroleum
and Natural Gas, Lodhi Road, New Delhi 110 003
21.1 Opening Remarks of the Vice -Chairman
At the outset, Vice -Chairman welcomed the members of the Expert Appraisal Committee
(Industry). Thereafter, agenda items were taken up for discussion. The deliberations held and
decisions taken are as under.
21.2 Confirmation of the Minutes of the 20th Reconstituted Expert Appraisal
Committee (Industry) held during 23-24th June 2014
The minutes of the 20th Reconstituted Expert Appraisal Committee (Industry) meeting held during
23-24th June 2014 were confirmed subject to the following corrections:
(1) 20.2 Confirmation of Minutes:
No. Agenda No.: 19.9.12 For Read
5 Public Hearing & After detailed deliberation, After detailed deliberation,
Annexure-7 the Committee the Committee
recommended the TOR at recommended the TOR at
Annexure-6 for preparation Annexure-8 (Pipeline) for
of EIA –EMP report along preparation of EIA–EMP
with Public Hearing at report along with Public
Viramgam only. Hearing at Viramgam only.
(2) Agenda Item 20.6.7: 1st Para:
Instead of the words “from 2x300 TPD + 3x100 TPD to 3x300 TPD”, read “from 3x300 TPD to
2x300 TPD + 3x100” TPD.
30th July 2014
21.3 Environmental Clearance
21.10.15 Manufacturing of Resins & Adhesives of M/s Setco Chemicals (I) Pvt. Ltd. at Plot No. 788/1, 40 Shed Area,
GIDC Estate Vapi, Taluka Paradi, District Valsad, Gujarat (TOR)
The project authorities and their consultant gave a detailed presentation on the salient features of the project and
proposed environmental protection measures to be undertaken alongwith the draft Term of References for the
preparation of EIA-EMP. All Synthetic Organic Chemicals Industry (Bulk Drugs & Intermediates) located inside the
notified industrial area/estate are listed at S.N. 5(f) under category ‘B’ and appraised at State level. However,
applicability of general condition due to project location within interstate boundary, proposal is treated as category ‘A’
and appraised at Central Level.
M/s Setco Chemicals (I) Pvt. Ltd. has proposed for setting up of Manufacturing Unit of Resins & Adhesives at Plot No.
788/1, 40 Shed Area, GIDC Estate Vapi, Taluka Paradi, District Valsad, Gujarat. No Eco-senstivie Zone is located within
th
15 km distance. Proposal has been considered in the EAC meeting as MoEF vide letter dated 10 June, 2014 has
th
decided to keep OM dated 17 September, 2013 in abeyance w.r.t re-imposition of moratorium in the 8 CPA. Plot
2 2
area is 8801m of which greenbelt will be developed in 1164.6m . Cost of project is Rs 5 crores. Following products will
be manufactured:
S.N. Name of Product Quantity,( MTPM)
Existing Proposed Total
1 Printing 500 ----- 500
2 Ink Medium 100 ----- 100
3 Retarder 100 ----- 100
4 Foil wash 100 ----- 100
5 Alkyd Resin ---- 100 100
6 Pure Phenolic Resins ---- 50 50
7 Reduced phenolic Resin ---- 150 150
8 Polyurethane Resin ---- 300 300
9 Polyester Resin (saturated & ---- 50 50
unsaturated)
10 Epoxy resin ----- 50 50
11 Polyamide Resin ----- 200 200
12 MF Resin ------ 50 50
13 UF Resin ----- 50 50
14 Ketonic Resin ----- 100 100
15 Acrylic Resin ----- 50 50
16 Emulsions ------ 50 50
17 Adhesives ----- 50 50
Total of Product Quantity 800 1250 2050
Total water requirement from GIDC water supply will be 10.2m3/day. The effluent generation will be 19m3/day and
treated in ETP. Power requirement will be 200 KVA. DG set (250 KVA) will be installed. Sludge and filter cake will be
sent to CHWTSDF. Spent solvent will be sent to Authorized Re-processors.
The Committee prescribed generic TOR at Annexure-8 for preparation of EIA-EMP report alongwith Public Hearing.
*************
J-11011/112/2014-IA II (I)
Government of India
Ministry of Environment and Forests
(I.A. Division)
Indira Paryavaran Bhawan
Jor Bagh Road, Aliganj
New Delhi – 110 003
E-mail : [email protected]
Telefax : 011: 2436 0108
Dated: July, 2014
To,
Shri Vijender Goel
Director
M/sHim Chem Enterprises
Plot No. 102, 103,
Village Bela Bithri Haroli District Una
Himachal Pradesh 174301
Subject: Expansion of existing Project Specialty Chemicals of M/s Him Chem Enterprises at
village Bela Bithri, Haroli, Dist. Una, H.P. (TOR)
Ref. No.: Your Letter no. HIM/EC/2013-14/023 dated 27.01.2014
Sir,
The Ministry has received your above mentioned project proposal. The information given in
Form-I along with Project summary and draft TORs will be placed before the 21st Reconstituted
Expert Appraisal Committee (Industry) on 31st July, 2014(10.00 AM)# (item no.21.10.4) to be held
at Scope Complex, Core 6, 5th Floor, IOCL Conference Room, Ministry of Petroleum and Natural
Gas, Lodhi Road, New Delhi 110 003 subject to submission of additional information desired by the
Ministry if any.
In this regard, you are requested to forward a copy of Form-1, Pre-feasibility Report and
draft ‘TOR’ to all the members of the Expert Committee (I) by courier/speed post alongwith soft
copy in CD/through e-mail well in time. Name and address of the members are enclosed for
necessary action. Please avoid delivery of documents by hand and separate meetings with
members / Chairman in this regard.
Further, you are requested to depute your senior officer/consultant who can explain the
project and also respond to the queries/suggestions which Committee may ask during the
discussion and may make as well necessary commitments to attend the meeting. The
representatives would be required to make a presentation on the salient features of the project and
proposed ‘TOR’.
A copy of the above mentioned documents may also be sent to the Chief Conservator of
Forests (Central), Ministry of Environment & Forests, Regional Office, Kendriya Bhavan, 5th Floor,
Sector-H, Aliganj, Lucknow-226024 if any.
Salient features (1-2 pages) of the proposed project mentioning title of the project, land acquired,
cost of the project, capital and recurring cost towards environment protection measures; proposed
facilities and production capacities in tabular form, air pollution control measures proposed, water
requirement, waste water treatment, recycle & reuse, solid / hazardous waste management and
disposal, green belt may also be submitted by e-mail to [email protected]
Kindly confirm your participation and also send information as per the Agenda at the
Ministry’s website: www.envfor.nic.in to all concerned.
(Dr. T. Chandini)
Director
LIST OF MEMBERS OF THE EXPERT APPRAISAL COMMITTEE (INDUSTRY)
SHRI M RAMAN Chairman
3/686, Cauvery Nagar, Kuppam Road
Kottivakkam
Chennai – 60041
e-mail : [email protected]
DR. R K GARG Member
Vice-Chairman, Expert Appraisal Committee (I)
4, Vikram Jyoti Co-Operative Society ,
Opp. Telecom Factory,
Deonar, Mumbai - 400 088
Maharashtra
E mail [email protected]
Member
DR. B SENGUPTA Member
Former Member Secretary, CPCB,
Member, Expert Appraisal Committee (I)
16 161, Medha Apartment,
Mayur Vihar, Phase-I, Delhi-91
E-mail: [email protected]
SHRI RAJAT ROY CHOUDHARY Member
12/37, Karpagam Avenue, 1st street
R.A. Puram, Chennai - 600028
E mail: [email protected]
E mail: [email protected]
DR. S.D. ATTRI, DIRECTOR Member
Environment Monitoring and Research Centre
India Meteorological Department,
New Delhi – 110003
E-mail:
[email protected]SHRI NIRANJAN RAGHUNATH RAJE Member
Member, Expert Appraisal Committee (I)
A-648, Sushant Lok-1
Gurgaon – 122 002
Haryana
E-mail: [email protected]
DR. ANTONY GNANAMUTHU Member
Old No. 53 and New No. 103, Padmanabha Nagar
Adya, Chennai, Tamil Nadu
E-mail:
[email protected]DR. S.K.DAVE Member
A/1, Nanalal Park,
Opp. Ideal Colony,
Jai Hind Char Rasta,
Maninagar Ahmedabad-380 008
Gujarat.
E mail :
[email protected] /
[email protected]DR. R.M. MATHUR, Director, Member
Central Pulp and Paper Institute,
Paper Mill Road,
P.B.No.174, Saharanpur-247 001.
Uttar Pradesh.
E-mail:
[email protected]PROF. C.S. DUBEY Member
Department of Geology
Delhi University
Delhi-110 007
E-mail:
[email protected] /
[email protected]PROF. R.C. GUPTA Member
Former Head
Department of Metallurgical Engineering
(A Centre of Advanced Study)
House No. P 1/ 9, Lane 15, Ravindrapuri Colony , Durgakund,
Varanasi-221005
Email [email protected]
E-mail: [email protected]
DR. PREM SHANKAR DUBEY Member
Member ,EAC (I)
86, Mahasweta Nagar,
Ujjain – 456 010.
Madhya Pradesh
E-mail: [email protected]
Dr. T.Chandini Member Secretary
Director, MoEF
E-mail : [email protected]
Telefax : 011: 2436 0108