CE155P Module Exam 1
CE155P Module Exam 1
Module Exam 1
Instruction: Use only a short bond paper in answering this exam. Write your name and student number
on all sheets. Box your final answer.
I. Fill in the Blank
1. ___________is a person who estimates the cost of the materials and labor necessary for a project.
2. ___________refers to complete design that used for bidding.
3. ___________reflect all changes made in the specifications and working drawings during the construction process.
4. ___________refers to plans, sections, and elevations showing layout and levels of all concrete members within the structure.
5. means the excavation of on-site soil materials including trenching required by the Contract Documents
6. Builders can make ______ concrete even stronger by using steel reinforcement bars
7. __________ with a low hardening characteristics concrete
8. Maximum size of gravel should exceed ____ of the minimum thickness of the member structure.
9. ___________may be added during the preparation of the concrete.
10. The crude oil is mixed with No. 40 motor oil to a proportion of ___________mixtures or with varying viscosity depending upon the
temperature condition.
11. When dry gypsum powder is mixed with water it gets ___________.
12. The preparation of surface and application of gypsum plaster should be apt to prevent___________.
13. Wet materials that spread over wall or roof surfaces should not be more than ___________
14. Rough cast finish is also called as ___________.
15. Textured finish is obtained from the ___________ plastering.
1. Estimate the quantity of cement, sand, and gravel for the concrete slab on fill of the foundation plan shown
below, using 150mm thick Class C concrete mixture (40 kg/bag). The exterior walls and columns are 150mm
thick, and they should be excluded in computing the area of the concrete slab. The spaces occupied by the
interior columns may be neglected. Use a 10% allowance for wastage.
2. From the foundation plan and details of the footings and columns shown below, estimate the quantity of
cement and aggregates required for the continuous concrete footing of the CHB walls enclosing the building.
Class A concrete mixture is specified to be used (50kg/bag). Use a 10% allowance for wastage.
3. Shown below are the drawings of a stair to be constructed out of Class A concrete mixture (50kg/bag).
Estimate the quantity of cement and aggregates required. Use a 0.5% allowance for wastage. (The steel
reinforcing bars are not shown)
4. Estimate the quantity of cement, sand and gravel needed for the stairs and landings shown below, using
Class A concrete mixture (40kg/concrete). Use a 5% allowance for wastage.
5. Estimate the number of full-length bars required for the four (4) longitudinal reinforcements of the one-span
beam in Figure (a) and those of the continuous beam in Figure (b) based on these data: