Spirax Pressure Reducing Valves DP17-IM-P100-05-EN
Spirax Pressure Reducing Valves DP17-IM-P100-05-EN
Spirax Pressure Reducing Valves DP17-IM-P100-05-EN
CTLS Issue 17
1. Safety information
2. General product
information
3. Installation
4. Commissioning
5. Maintenance
6. Spare parts
7. Fault finding
© Copyright 2018
IM-P100-05 CTLS Issue 17 1
Printed in GB
2 IM-P100-05 CTLS Issue 17
1. Safety information
Safe operation of these products can only be guaranteed if they are properly
installed, commissioned, used and maintained by qualified personnel (see
Section 1.11) in compliance with the operating instructions. General installation
and safety instructions for pipeline and plant construction, as well as the proper
use of tools and safety equipment must also be complied with.
Group 2
Product
Gases
i) The products have been specifically designed for use on steam, air and inert
industrial gases which are in Group 2 of the above mentioned Pressure Equipment
Directive.
ii) Check material suitability, pressure and temperature and their maximum and
minimum values. If the maximum operating limits of the product are lower than
those of the system in which it is being fitted, or if malfunction of the product
could result in a dangerous overpressure or overtemperature occurrence, ensure
a safety device is included in the system to prevent such over-limit situations.
iii) Determine the correct installation situation and direction of fluid flow.
iv) Spirax Sarco products are not intended to withstand external stresses that may
be induced by any system to which they are fitted. It is the responsibility of the
installer to consider these stresses and take adequate precautions to minimise
them.
v) Remove protection covers from all connections and protective film from all
name-plates, where appropriate, before installation on steam or other high
temperature applications.
1.2 Access
Ensure safe access and if necessary a safe working platform (suitably guarded)
before attempting to work on the product. Arrange suitable lifting gear if required.
1.3 Lighting
Ensure adequate lighting, particularly where detailed or intricate work is required.
1.8 Temperature
Allow time for temperature to normalise after isolation to avoid danger of burns.
1.12 Handling
Manual handling of large and/or heavy products may present a risk of injury. Lifting,
1.14 Freezing
Provision must be made to protect products which are not self-draining against
frost damage in environments where they may be exposed to temperatures below
freezing point.
1.15 Disposal
Unless otherwise stated in the Installation and Maintenance Instructions, this
product is recyclable and no ecological hazard is anticipated with its disposal
providing due care is taken. However, if the valve has any PTFE components, special
care must be taken to avoid potential health hazards associated with decomposition/
burning of this material.
PTFE:
- Can only be disposed of by approved methods, not inceration.
- Keep PTFE waste in a separate container, do not mix it with other rubbish, and
consign it to a landfill site.
2.2 Sizes and pipe connections - DP17, DP17G, DP17R, DP17Y and DP27G
DN15LC (not available for type DP17G), DN15, DN20, DN25, DN32, DN40 and DN50.
Screwed BSP (BS 21 parallel) or NPT (DN15 to DN25 only).
Pressure psi g
0 100 200 D 300
232
200 A B 400
Temperature °C
Temperature °F
150 300
F Steam F
100 saturation 200
50 curve
100
C E
0
0 5 10 15 20 25
Pressure bar g
Note: DP17, DP17G and DP27G have a variable rate conical pressure adjustable spring
fitted providing a downstream pressure range of 0.2 - 17 bar g.
DP17Y has a pressure spring with a range of 0.2 - 3 bar g.
DP17R Maximum downstream reduced pressure 15 bar g. The control pressure
signal to the pilot diaphragm must be approximately 0.7 bar above the required
reduced downstream pressure.
PMA Maximum allowable pressure @ 120 °C (248 °F) 25 bar g (362.5 psi g)
PMO Maximum operating pressure for saturated steam service 17 bar g (246.5 psi g)
Designed for a maximum cold hydraulic test pressure of: 38 bar g (551 psi g)
Note: With internals fitted, test pressure must not exceed: 25 bar g (362.5 psi g)
Temperature °F
150 300
100 200
50
100
0
0 5 10 15 20 25
Pressure bar g
PMA Maximum allowable pressure @ 120 °C (248 °F) 25 bar g (362.5 psi g)
PMO Maximum operating pressure including saturated steam service 10 bar g (145 psi g)
Designed for a maximum cold hydraulic test pressure of: 38 bar g (551 psi g)
Note: With internals fitted, test pressure must not exceed: 25 bar g (362.5 psi g)
3.1 Supply
DP17, DP17G and DP27G (Fig. 1)
These are supplied ready for fitting and have a variable rate conical pressure spring suitable
for a downstream pressure of 0.2 - 17 bar (3 - 247 psi).
DP17Y (Fig. 1)
The DP17Y is supplied as the DP17, but has a lower rate pressure adjustment spring for a
downstream pressure range of 0.2 - 3 bar (3 - 44 psi).
Alternative recommended
downstream pressure control
pipe connection (refer to
Section 3.8, page 14)
Electrical supply
It is important that the solenoid is connected to the correct voltage. Therefore always check
on the supply details which are stamped on the solenoid valve name-plate before attempting
to connect up.
Electrical connection is by cable plug to DIN 43650. All wiring, connectors, etc. in close
proximity to the valve should be of heat resisting type and comply with local and national
electrical codes.
Earth
The solenoid valve should be adequately earthed.
Solenoid valve
Fig. 2 DP17E
Fig. 3 DP17R
Pressure
Strainer with 100 mesh control Safety Discharge
Separator stainless steel screen pipe valve pipe Small bore
Pressure drain
reducing valve
Steam
supply
Spiratec 0.9 m, (3 ft) or 15 pipe
sensor diameters clear on either side
chamber Ball valve See Section 3.6, page 13.
Separator
Regulator
Compressed
Filter
Compressed air
air
DP17R
Installation for
compressed air Compressed
Fig. 4 Recommended installation (DP17G and DP27G) air trap
Steam supply
Steam supply
3.10 Bypass
Information regarding bypasses:
It may be necessary to ensure that primary fluid flow continues in the event of the main
control failing. This is often achieved by fitting a bypass around the control valve assembly.
A better option is a duplex valve assembly, installed in parallel with the main valve, as a
manual bypass cannot accurately control pressure/flow/temperature without constant
manual supervision. Conversely, a duplex control station will provide proper control, should
the main valve ever need to be removed.
Although not recommended, if a manual bypass valve is fitted, the bypass valve flow
coefficient (Kvs) should be the same as, or near to that of, the control valve. This means
that the manual valve and control valve could have different connection sizes. The bypass
valve should also be capable of throttling not just isolating, to reduce wear on the valve
when in service and to facilitate manual control.
Ideally, any bypass pipework should be arranged either above or alongside the main
assembly. On steam systems, it should never be below it.
Where there is downstream control equipment (B), particularly when it is fast acting
(for instance pulsed piston actuated valves) ensure the control equipment is at least 50
pipe diameters away from the DP17 to prevent pressure pulses being transmitted back
causing unstable operation and premature wear or if this is impractical an intermediate
vessel can provide a similar benefit.
Where a safety valve (C) is required to protect the system downstream of a DP17 and where
a control valve is also being used downstream of the DP17, it is recommended that the
safety valve is fitted downstream of the control valve rather than in between the DP17 and
the control valve. If any slight leakage occurs this will avoid any pressure build-up causing
nuisance operation of the safety valve but provide complete protection for the downstream
system.
Where valves are installed downstream of the DP17 (B) the intermediate downstream
pipework must be properly trapped (D) to ensure no condensate can buil up on the
downstream side of the DP.
C
A B
A
5. For correct operation of the valve it is important that the pilot and main valves are not
subjected to dirt or other hard particles. Therefore, prior to bringing the valve into
operation, ensure that the upstream pipework has been cleared of all loose dirt and
hard particles and that the main strainer screen is examined and cleaned if necessary.
Note: After installation or maintenance ensure that thet system is fully functional. Carry
out tests on any alarms or protective devices.
WARNING
Direct injection systems
This product contains a rust inhibitor to protect it against corrosion during
storage. To avoid any possible contamination of your product, after first blowing
down the approach pipework, we recommend that the valve is blown through
thoroughly in order to remove any trace of the inhibitor.
2, 6 3 2, 9
4 4
Steam flow
5 ]
Fig. 8 Setting procedure sequence DP17, DP17E, DP17G, DP17Y and DP27G
3, 7, 8 2, 9
2, 6
4 4
Steam flow
5 ]
5
Condensate
return ] See Section 3.6, page 13
Warning:
The body gasket (all DP17 derivatives) and actuating chamber gasket (DP17R)
contains a thin stainless steel support ring which may cause physical injury if not
handled and disposed of correctly.
- Main diaphragms.
- Pilot diaphragms.
Pilot diaphragms
Pilot valve
Body gasket chamber assembly
(see warning above) Main valve screen
Main
diaphragms
3
1. Release the lock-nut. 4
2. Turn the adjustment screw anticlockwise. Ensure there
is no compression on the pressure adjustment spring.
DP17R 4
Unscrew the securing nuts and remove the air control
block and diaphragms.
5
7
7
10. Ensure that the main valve return spring is still in position. Any trapped dirt or scale
should be removed from the pilot valve assembly. If appropriate, the complete pilot
valve chamber assembly can be refitted following Steps 14 to 21. If necessary, the
complete pilot valve chamber assembly should be replaced as follows:
Note: The pilot valve assembly is no longer available as a standard spare. Because of
the difficult process described in Step 13, it has now been discontinued. The complete
pilot valve chamber assembly is the recognised spare. However for customers with pilot
valves only still in stock, these can be used by following Steps 11-13. This assembly
contains 2 off PTFE seals. The following handling precautions should be observed.
11. Unscrew and remove the pilot valve assembly (22 mm A/F)
12. Screw the new pilot valve into the housing. Torque 45 - 50 N m (33 - 37 lbf ft).
13. Check that there is a very slight clearance between the top of the plunger and a straight
edge placed across the diaphragm location recess. (N.B. Because of production
tolerances the plunger is supplied slightly longer than is always required and it will
generally be necessary to grind or machine material off the top end to give the correct
length). After machining make sure the sharp edges are removed from the top of the
plunger as these could damage the diaphragm.
14. Remove the screen and clean. Ensure that the gasket faces are clean.
15. Ensure that the main valve return spring is still in position.
18. Refit the two diaphragms making sure that they are fitted the same way round as they
were removed and that all contact faces are clean. Diaphragms showing signs of wear
or damage should be replaced.
DP17R
Assemble the air control block and tighten the nuts to the recommended torques shown
in Table 1, page 21.
21. Refit the pipework and retighten the unions to ensure a steam tight seal.
Bring the valve back into commission by following as many Steps as are necessary in
Section 4, page 16.
20
10
19
18
21 17
21
11
16
14 17 14
13
12
15
Table 1
Recommended tightening torques for pilot valve chamber nuts
Size of valve Nut size Tightening torques
½", ¾", 1" M10 40 - 50 N m (30 - 37 lbf ft)
DN15, DN20, DN25 and DN32
DN40 and DN50 M12 45 - 55 N m (33 - 41 lbf ft)
DP17R
Remove the pilot valve housing, complete DP17 shown
with air control block.
DP17R
Isolate the actuating air supply and zero the
pressure.
DP17R
Unscrew the securing nuts and remove the air
control block and old diaphragms.
DP17R
Assemble the air control block and tighten the
nuts to the recommended torques shown in 39
Table 1, page 21.
DP17R
Isolate the actuating air supply and zero 46
the pressure.
DP27G shown
DP17G
If there is any wear or damage to the
nitrile face then the head assembly must
be replaced.
53
¾" and DN20 36 mm A/F (External) 140 - 150 N m (103 - 111 lbf ft)
1" and DN25 19 mm A/F (Inside) 230 - 250 N m (170 - 184 lbf ft)
55. Refit the main valve head, making sure that the valve locates on the seat.
56. Check the valve lift shown in Table 3 using a depth gauge.
Depth gauge
59
57
55
58
56
Table 3
Size of valve Valve lift
DP17R
Assemble the pilot valve housing
complete with the air control block and
tighten the nuts to the recommended
torques shown in Table 1, page 21.
DP27G shown
68. Undo the retaining nut and slip the entire solenoid enclosure off the solenoid base and
sub-assembly or plugnut/core tube sub-assembly.
69. Unscrew the bonnet or solenoid base sub-assembly and remove the core spring, core
assembly and body gasket.
All the parts are now accessible for cleaning or replacement. Replace worn or damaged
parts with a complete Spare parts kit (item 'W', pages 30 and 31) for best results.
70. Reassemble in reverse order paying careful attention to exploded views provided.
71
68
72
70
69
CAUTION
The solenoid must be fully reassembled
as the housing is part of, and completes
the magnetic circuit.
Coil replacement
Switch off the electrical power supply and
disconnect the coil lead wires.
** Note: This does not apply to DP17G soft seat pilot valve or main valve assemblies.
Screwed Flanged
*** ***
Maintenance kit a a a b f f a b c d e
Main diaphragm a a a b a a a b b c c
Pilot diaphragms † a a a a a a a a a a a
PTFE seals a a a a a a a a a a a
Internal strainer † a a a b f f a b c d e
Pressure adjustment
a a a a a a a a a a a
spring
Body gasket † a a a a a a a a a b b
Set of diaphragm
† a a a a a a a a a b b
securing bolts and nuts
Available spares
Maintenance kit
A stand-by set of spares for general maintenance purposes and covers all spares marked *
Internal strainer * M
DP17, DP17E,
Pressure adjustment spring 0.2 to 17 bar (3 to 247 psi)
DP17G and DP27G O
(Not required for DP17R)
DP17Y 0.2 - 3 bar (3 - 44 psi)
Set of spring housing/actuating chamber cover securing studs and nuts (set of 4) S
Replacement coil X1
Example:
1 - Main valve assembly for a Spirax Sarco 1" DP17 pilot operated pressure reducing valve.
B
Q
C1 X1
W
C
R
P1 X2
P
T
N R
V
T
Main valve assembly
K
L
A
Y
M V
3. Pipe assembly (Item 'P' on page 31) blocked. Remove by uncoupling the union nuts and
blow through to clear obstruction.
4. Control orifice blocked. Unscrew from the outlet port and clear out obstruction. For
identification this coupling has a groove around the hex.
a) Check that the upstream pressure is correct. If it is low, the capacity of the valve
will be reduced.
b) Ensure that the pressure control pipe is fitted as recommended in Section 3.8 and
if necessary fit an external pressure control pipe as described. If the downstream
pressure is still too low, then a larger valve with more capacity is required.
2. Control orifice (item 'P1' on page 31) blocked. Unscrew the pipework from the side of
the body and clean out. For identification this coupling has a groove around the hex.
3. Pilot valve diaphragms fractured. Check and replace (see page 31).
2. If the upstream pressure is correct, and stable, set the valve on dead-end conditions.
Apply full-load to the valve. If the downstream pressure drops excessively during full-load
condition, it is likely that the valve is undersized, in which case it should be replaced.
Once it has been determined that the upstream pressure is correct and stable, and
that the valve is correctly sized, the following check should be carried out on the valve:
3. Steam is very wet. Ensure the valve installation is as recommended in Fig. 4, page 12.
4. The point at which the external pressure control pipe is tapped into the main is in a
turbulent area. Refer to Section 3.8 for guidance.
5. Loose dirt in the pipe assembly (Item 'P' on page 31). Remove the pipe assembly. Blow
through to clear.