Geomembrane Liners in Wastewater Treatment Ponds Whales and Their Prevention
Geomembrane Liners in Wastewater Treatment Ponds Whales and Their Prevention
Geomembrane Liners in Wastewater Treatment Ponds Whales and Their Prevention
Geomembrane liners
manufactured from polymers
such as high density
polyethylene (HDPE), linear
low density polyethylene
(LLDPE), polypropylene
(PP), polyvinyl chloride
(PVC), ethylene propylene
diene monomer (EPDM),
chlorosulfonated PE
(Hypalon ®), and PVC alloy
(XR-5®), and even more
sophisticated polymer alloys
are used very effectively in
reservoirs to contain potable
water, and in wastewater
treatment plant (WWTP)
lagoons to prevent
contamination of the
groundwater. But occasionally performance problems occur that are the result of inexperienced design,
sometimes poor installation, but rarely inadequate liner material.
The predominant problem is an assumption by the design engineer that an installed geomembrane liner will not
1/5
leak. It may not, but the chances are that it will. While this appears counter-intuitive, it is a design philosophy that
experienced engineers and regulators have come to accept, to the benefit of all, since the early 90s.
When wastewater leaks through a liner and remains in the subgrade soil microbiological reactions continue, water
reacts with any organic matter in the soil, and gases (mostly methane) are generated. The gases collect under the
liner of the lagoon which is often designed with a flat floor. The gases then lift the liner until it becomes influenced
by the water being drawn toward the aerators ultimately contacting the aerators. The liner is torn, increasing the
leakage rate and damaging the aerators. Increased leakage accelerates the formation of “whales”; large blisters of
liner above the surface of the water . Typically the whales contain gas above the water line and leaked water
below the water line. Thus the level of water below the liner is the same as that above the liner.
Increased leakage accelerates the formation of “whales”; large blisters of liner above the surface of the
water. Typically the whales contain gas above the water line and leaked water below the water line.
Frequently, a nonwoven geotextile is placed under the liner to act as a cushion for the geomembrane, a drainage
medium, and a gas venting medium. Gas vents may or may not be placed at the tops of the slopes to vent gases.
However, on more than one occasion gas vents have been seen below the maximum operating water level! In
some cases the geotextile is augmented, or replaced, by strips of geotextile/geonet/geotextile composite
(geocomposite) across the floor and up the slope to each vent. This often does not work. The in-plane flow
capacity of the compressed geotextile or the geocomposite strips is insufficient to handle the leak flow rate. When
the floor of the lagoon is flat, as mistakenly required by some state regulations, the leaked water cannot be
drained off to a sump and removed. Therefore it completely fills the void space within the geocomposite. Thus, the
gas that is generated cannot diffuse to the gas vents. It accumulates in the unavoidable high spots on the floor,
lifts the liner, and forms the whales. The resulting tensions in the geomembrane liner cause additional damage,
typically at fixed points such as pipe penetrations, resulting in more leakage and accelerating whale formation.
Statistics show that the number of leaks in a geomembrane lining system is a function of the area, or complexity of
the liner. Larger areas imply a lower proportion of detailed liner work and therefore a fewer defects per unit area.
Typically a liner with an area of 2.5 acres will have about 12 leaks while larger area liners have 1 leak per acre.
The number of leaks can be significantly reduced if knowledgeable geosynthetics construction quality assurance
(CQA), in addition to geotechnical CQA, is performed during liner installation. They can be reduced even further if
an electrical leak location survey is performed before, during, or after first filling of the lagoon.
Target Action Leakage Rates, above which leaks must be found and repaired, are typically 20 gallons per acre per
day (gpad) for landfill primary liners with a maximum 1 ft hydraulic head, and 500 gpad for WWTP lagoon single
liners with 6 ft hydraulic head. Therefore, these are the types of leak flow rates that must be safely handled by
underliner drainage systems. This requires specific liner design features.
The floor of the lagoon must be sloped to a sump, both for easy dewatering/desludging of the lagoon and for
drainage of the leaked liquid. There must be a pipe leak drainage system, or preferably a full geocomposite leak
drainage layer under the liner, also draining down gradient to a sump system where the leak flow rate can be
monitored and the leaked water removed. With the water removed, the sloping drainage system will also function
as an effective upgradient gas venting system to the gas vents at the top of the side slopes.
2/5
Very large whale in mine tailings pond -
flattened and thinned on one side.
Ballast on the liner is usually achieved with a concrete slab. There are three methods of liner/ slab interaction,
each with its own disadvantages. The liner can be attached to the side of the slab or to the top surface, or the slab
can be placed on top of the geomembrane liner. In the first case, providing proper support of the liner in the
slab/subgrade corner is of prime concern. Design philosophy is that the liner serve as a barrier only and not as a
load-bearing member of the system. Thus, safely bending a semi-rigid HDPE liner through 90° then attaching it to
the side of the slab only a few inches up from the corner is difficult. While the liner can be easily attached to the top
surface of the slab near the edge (with the soil surface at the same elevation as the slab surface) the concern is
with settlement of the subgrade at the edge of the slab and deformation (stressing) of the geomembrane over a
rough corner of the concrete. There are, therefore, some advantages to maintaining the continuity of the liner
underneath the slab.
One solution to these construction concerns might be to install thick concrete embedment liner on top of the
concrete slab poured on the subgrade, take extra care in compacting the subgrade at the edges of the slab (with
subgrade surface level with embedment liner surface), then to weld the geomembrane liner to the concrete
embedment liner. In this way there is a continuous geomembrane liner that can be tested for leaks electrically, and
there is no danger of the liner under the aerator being uplifted.
3/5
When a lagoon has experienced extensive liner whaling the liner must typically be removed so that all saturated
soil underneath it can be removed. Additional damage to the liner is unavoidable. The subgrade must be re-
compacted to provide a firm unyielding support for the geomembrane liner. Remember, the geomembrane acts as
a barrier, not as a load-bearing member of the system. Effective drainage, leak monitoring, leakage removal, and
gas venting systems must be installed. If temporary repairs are acceptable such as to provide a short term
operating extension it may be sufficient to cut the liner orthogonally from slope crest onto the floor midway
between each row of aerators, to insert high transmissivity drainage geosynthetic composite strips part way onto
the floor and up the slopes, and to install gas vents at the top of the slopes above the strips. All evident liner leaks
should be repaired at the same time – check pipe boots, repair patches, slopes at the elevation of aerator
bottoms, and liner under the aerators and at the edges of concrete slabs. This temporary remedy may not stop
leakage and the generation of gas but it can allow the venting of gas and the prevention of whales for some
period. Do recognize though that with water on both sides of the liner and with holes in the liner, HDPE, LLDPE,
and PP geomembrane liners, with specific gravities less than that for water, will still tend to float between fixed
points.
Case History
A WWTP/irrigation facility owner was pleased to have
saved $15,000 by hiring a local installer rather than a
nationally recognized installer to design/install a
single geomembrane liner in a 10 acre pond. A light
nonwoven geotextile was placed under the
geomembrane. It was later found that the geotextile
was not continuous. There were no leakage
monitoring/removal systems and no gas vents. On
first filling the pond would not hold water and about 12
whales quickly formed. Note that whales can also be
formed by air trapped under the liner during
construction. The pond was emptied. Visual
inspection and an electrical survey over about 1.25
acres of the liner revealed 109 leaks, from pinholes to
3 ft long lack of weld fusion and a large patch which had been 100% ground for welding but on which only 75% of
the periphery had been welded. The installer assured the owner that comprehensive CQC had been performed
during installation. The liner was remediated basically as described above, but with the addition of several side
slope vent pipes complementing the full leakage detection system (LDS) geocomposite. The vent pipes had
turbines on top of them that sucked the gas out when the usual winds blew. The leakage rate is now negligible,
whales – none. Total time lost? 1 year. Cost to owner? $1.3M. All for a saving of $15,000.
The leakage rate is now negligible, whales – none. Total time lost? 1 year. Cost to owner? $1.3M. All for
a saving of $15,000.
Lessons still being learned? Geomembrane and other geosynthetic-based lining systems function well and are
extremely cost effective when installed properly, as most are. When failures (whales) occur it is typically not a
geosynthetic materials problem. To avoid such problems use a design engineer experienced in geomembrane-
based lining systems, and use an experienced installer. However, it may even be difficult for an experienced
installer to satisfactorily deal with inappropriate design features. Hence the need for a specified Action Leakage
Rate – even CQA will not catch everything. Try to hire an experienced CQA firm reporting to the owner (engineer),
not to the general contractor. Perform a final leak test. A full hydrostatic test typically takes 14 days and will tell you
that there is a leak but not where. A geoelectric integrity/leak survey can cover 2 acre/day and pinpoint a leak in
real time.
4/5
Gas vent (arrowed) on side slope below maximum
water line.
5/5