Example Renovations Boq
Example Renovations Boq
9 September 2010
1 PRELIMINARIES
9 September 2010
Note:
1.0 Where possible it is preferred for clients to stay with the builders standard range.If you are unsure if
something is standard, then please phone for confirmation.
2.0 Owners Contact Number:
3.0 Contract Type -
4.0 Clients Name -
Total 3.1 COLOUR CONSULTANT $600.00
4 ENGINEER
9 September 2010
5 CONTRACTORS INSURANCE
6 Q.B.S.A INSURANCE
6.5 Q-LEAVE
8 TOILET HIRE
9 September 2010
8 TOILET HIRE
8.4 HIRE
10 RETAINING WALLS
9 September 2010
12 DEMOLITION
9 September 2010
15 FOOTINGS HARDWARE
16 FOOTINGS CONCRETE
17 FOOTINGS LABOUR
9 September 2010
17 FOOTINGS LABOUR
20 PLUMBER - DRAINAGE
22 BASE HARDWARE
23 BRICKLAYER BASE
9 September 2010
23 BRICKLAYER BASE
Rubbish:
1.0 The house is to be swept out daily, all rubbish is to be placed in the designated area or cage provided.
2.0 Rubbish areas & cages are intended for construction rubbish, subcontractors are to remove food scraps &
other personal rubbish from the construction site.
Total 23 BRICKLAYER BASE $300.00
27 BEDDING SAND
28 TERMITE TREATMENT
29 SLAB HARDWARE
9 September 2010
29 SLAB HARDWARE
30 SLAB CONCRETE
31 SLAB LABOUR
34 STRUCTURAL STEEL
9 September 2010
34 STRUCTURAL STEEL
9 September 2010
9 September 2010
36 FRAME HARDWARE
9 September 2010
38 CARPENTRY FRAME
9 September 2010
40 CRANE HIRE
Note:
41 ROOF COVERING
9 September 2010
42 WATERPROOFING
1.0 The house is to be swept out daily, all rubbish is to be placed in the designated area or cage provided.
2.0 Rubbish areas & cages are intended for construction rubbish, subcontractors are to remove food scraps &
other personal rubbish from the construction site.
30455 WATERPROOFING - URETHANE SEALING WET 17.66 m2 $60.00 $1,059.60 27 1
AREA FLOORS AND BALCONIES
30535 FIBREGLASS SHWR. TRAYS 1800 X 1000 W/- 1 Off $360.00 $360.00 27 1
FLOOR WASTE - INC. SUPPLY & INSTALL HOB
3054 SHWR, BATHS, CORNER & WALLS TO ROSE 1 Off $200.00 $200.00 27 1
HEIGHT 700 X 1000
3057 Waterproof Skirtings / Perimeter of wet areas 13.2 m $12.00 $158.40 27 2
44 PLUMBER'S ROUGH IN
1.0 Tapware is
2.0 Vanities are by
3.0 Vanity height
4.0 Whilst temperature safety valves are to be fitted to bathrooms & ensuites etc. Normal temperature hot water
is to be provided to the kitchen tap.
Rubbish:
1.0 The house is to be swept out daily, all rubbish is to be placed in the designated area or cage provided.
2.0 Rubbish areas & cages are intended for construction rubbish, subcontractors are to remove food scraps &
other personal rubbish from the construction site.
Total 44 PLUMBER'S ROUGH IN $2,932.97
9 September 2010
45 ELECTRICIAN
NOTE: Ensure that you have a copy of the light fitting selection \ order
If the electrical plan does not match the order & colour selection
Then please advise urgently
3195 EXTRA CIRCUIT LIGHTS 20max PER CIRCUIT 2 Off $80.00 $160.00 27 1
3196 EXTRA CIRCUIT POWER 30max PER CIRCUIT 2 Off $80.00 $160.00 27 1
3198 Telephone pre-wire per phone point (in addition to 2 Off $65.00 $130.00 27 1
initial first free pre-wire)
32087 PS to Upgrade fuse box if required 1 Off $600.00 $600.00 27 1
3209 Supply & Install Smoke Alarm, hard wired to 2 Off $135.00 $270.00 27 1
current standards.
3210 Weatherproof Double GPO 1 Off $105.00 $105.00 27 1
32145 Underground power to small water tank next to 1 Off $198.00 $198.00 27 1
house
3216 Electrician - Hourly Rate 20 hour $65.00 $1,300.00 27 1
miscelaneous
3217402 Install IXL Tastic 3 in 1 exhaust fan 2 Off $78.10 $156.20 27 1
9 September 2010
46 ALUMINIUM WINDOWS
Please check builders order list against plans provided (plans must be current signed construction plans)
The onus is on the window supply company to supply windows as shown on the plans provided
and to check that pricing is correct before accepting our order.
If in doubt contact the office for confirmation.
67524 Louvers 9.63 m2 $660.00 $6,355.80 27 1
deliv-win DELIVERY 4.5 % of order $28,826.37 $1,297.19 0 1
Contract Type -
hand
ps Provisional Sum for Supply and Installation 1 Off $350.00 $350.00 0 1
reglaze hi-light
9 September 2010
9 September 2010
51 CARPENTER CLADDING
52 SCAFFOLDING
54 BRICKS
55 BRICK HARDWARE
9 September 2010
56 BRICKLAYER
Mortar Colour -
All Masonary walls require full height articulation at locations marked on the engineers plans.
Articulation shall be in accordance with the Cement & Concrete Association note TN61
please ensure that the correct materials are used & the correct brick tie procedure is followed.
Total 56.5 MASONRY ARTICULATION $105.60
9 September 2010
9 September 2010
MOULDINGS -
44870 SKIRTING AS PER SPEC 140.1 m $12.00 $1,681.20 0 1
MOULDINGS -
4489 42x19 FJ PINE DAR (5.2m) 52 L\M $2.06 $107.08 27 1
1/5.2
inc manhole frame
4490 68x19 FJ PINE DAR (5.2m) 26 L\M $3.41 $88.55 27 1
1/5.2
4491 DAR 93x19 FJ PINE JAMBS (5.2m) 46.8 L\M $3.50 $163.71 27 1
9 September 2010
64 INTERNAL STAIRS
65 CABINETMAKER
Colours:
Kitchen Benchtops -
Kitchen Cupboards & Doors -
Kitchen Kickboards -
Kitchen Knobs -
9 September 2010
65 CABINETMAKER
1.0 The house is to be swept out daily, all rubbish is to be placed in the designated area or cage provided.
46970 Provide 600mm wide Laundry base cupboards, 2.6 per mtr $481.57 $1,252.09 27 1
white lined to builders standard specification
(similiar to kitchen cupboards
Laundry base cupboards, 600mm wide, white lined with laminate top
Colours:
Laundry Benchtops -
Laundry Cupboards & Doors -
Laundry Kickboards -
Laundry Knobs -
4699 Provide 600mm high overhead cupboards, white 2.5 per mtr $321.05 $802.62 27 1
lined to builders standard specification (2.1 high )
Colours:
Kitchen Overheads -
46995 Provide "Bulkhead" above overhead cupboards - 3.7 per mtr $120.40 $445.48 27 1
to 300mm deep
4702 Provide 300mm wide flat breakfast bar extention of 3.7 per mtr $120.40 $445.48 27 1
kitchen benchtop
47031 Laminated appliance cupboard, linen, broom 00.5 per mtr $802.62 $401.31 27 1
cupboard or pantry to 2.1 high
4706 Laminated vanity units, up to 500 deep with 5.4 per mtr $602.00 $3,250.80 27 1
kickboards
Bathroom 1/2.6
Ensuite 1/2.8
4706-bath Bathroom vanity drawers (per set of drawers) 1 Off $100.00 $100.00 27 1
Bathroom Top -
Bathroom Doors -
Bathroom Kickboard -
Bathroom Knobs -
4706-ens Ensuite vanity drawers (per set of drawers) 2 Off $100.00 $200.00 27 1
Ensuite Top -
Ensuite Doors -
Ensuite Kickboard -
Ensuite Knobs -
471402 Kitchen Sink - Corsica - double bowl with single 1 Off $411.60 $411.60 27 1
drainer
KITCHEN SINK BOWL -
4734 FRIDGE PANELS 2400 1 Off $151.35 $151.35 27 1
563404 Semi Recessed Vanity Basin 3 Off $250.00 $750.00 27 1
Note: Tapware is
Note: Vanities are by
56958 ### EXTRA ALLOWANCE FOR 2 PAK DOORS 4.2 m $264.87 $1,112.44 27 1
TO KITCHEN CUPBOARDS ###
569580 ### EXTRA ALLOWANCE FOR 2 PAK DOORS 3.9 m $529.73 $2,065.95 27 1
TO KITCHEN CUPBOARDS WITH EXPOSED
BACK ###
56959 ### EXTRA ALLOWANCE FOR 2 PAK DOORS 2.7 m $176.58 $476.77 27 1
OVERHEAD CUPBOARDS ###
569591 ### EXTRA ALLOWANCE FOR 2 PAK DOORS 5.7 m $232.76 $1,326.75 27 1
TO VANITIES ###
5700-pan Upgrade pantry to vinyl wrap or 2 Pak 1.2 m $296.98 $356.38 27 1
57681 Clarke 45 litre insert trough with bypass 1 Off $257.40 $257.40 27 1
note Please Note: 1 Off $0.00 $0.00 27 1
# a dishwasher provision is required in this house
ps Provisional Sum for Supply and Installation 500 Off $1.00 $500.00 27 2
handles upgrade
9 September 2010
65 CABINETMAKER
67 CARPENTER FIXOUT
9 September 2010
71 CERAMIC TILES
9 September 2010
72 CERAMIC TILER
Fixtures
Rubbish:
1.0 The house is to be swept out daily, all rubbish is to be placed in the designated area or cage provided.
2.0 Rubbish areas & cages are intended for construction rubbish, subcontractors are to remove food scraps &
other personal rubbish from the construction site.
50932 Tiler to supply silicone 3 Off $12.00 $36.00 27 1
9 September 2010
78 SANITARY WARE
9 September 2010
78 SANITARY WARE
1.0 The house is to be swept out daily, all rubbish is to be placed in the designated area or cage provided.
2.0 Rubbish areas & cages are intended for construction rubbish, subcontractors are to remove food scraps &
other personal rubbish from the construction site.
Total 78.5 PLUMBERS FIT OFF $7,274.85
80 PAINTER
9 September 2010
80 PAINTER
9 September 2010
80 PAINTER
81 WHITE GOODS
82 LIGHT FITTINGS
9 September 2010
82 LIGHT FITTINGS
83 CURTAINS/VENITIAN BLINDS/SHUTTER
84 TV ANTENNA
Rubbish:
1.0 The house is to be swept out daily, all rubbish is to be placed in the designated area or cage provided.
2.0 Rubbish areas & cages are intended for construction rubbish, subcontractors are to remove food scraps &
other personal rubbish from the construction site.
32070 Upgrade to larger Antenna 1 Off $68.00 $68.00 27 2
NOTE: Confirm TV points, splitter & amplifier requirements & advise of extra costs so that we can have the
client authorise a variation before we continue with installation
32071 TV POINTS " F" CONNECT SPLITTER 2-4 1 Off $23.76 $23.76 27 3
POINTS
Total 84 TV ANTENNA $341.76
9 September 2010
88 CONCRETOR EXTERNAL
9 September 2010
89.6 SHUTTERS
91 PAVERS
94-1000 INSULATION
9 September 2010
94 HOUSE CLEAN
96 LANDSCAPING
98 FLOOR COVERINGS
Contract Type -
7074-step Extra labour allowance to lay "Carpet" to stair 17 Off $5.00 $85.00 1 1
treads (extra carpet required to cover face of
treads)
Total 98 FLOOR COVERINGS $3,645.00
9 September 2010
105 ESTIMATING
117 MAINTENENCE
9 September 2010
Please send a copy of your report to our office for our files.
7581 Hand Over Clean and tidy up, cost of filler & 220.14 m2 $1.20 $264.23 27 1
cleaning gear etc....
Contract Type -
Approximate handover date of is to be confirmed closer to the date.
Please contact the supervisor to arrange a suitable time for inspection.
Please contact the office for the following if you dont have them
1. Plans & Elevations
2. Colour Selection
3. Copy of Contract Specification
4. Copy of post contract variations.
Please send a copy of your report to our office for our files.
Total 160 HANDOVER INSPECTIONS $624.32