Tech Guide
Tech Guide
16-EG1 (597)
TM
MILLENNIUM
YIA Single-Effect Absorption Chillers
28377A
120-1377 TONS
(420 - 4840 kW)
TABLE OF CONTENTS
INTRODUCTION ................................................................................................... 4
RELIABILITY FEATURES ..................................................................................... 5
HOW IT WORKS ................................................................................................... 7
CONTROL SYSTEM ............................................................................................. 9
MECHANICAL SPECIFICATIONS ....................................................................... 11
OPTIONAL FEATURES ...................................................................................... 14
APPLICATION DATA ........................................................................................... 15
RATINGS ............................................................................................................ 29
NOZZLE ARRANGEMENTS ............................................................................... 33
PHYSICAL DATA ................................................................................................. 35
VALVE SELECTION CURVE .............................................................................. 38
PRESSURE DROP CURVES .............................................................................. 39
ELECTRICAL DATA ............................................................................................. 50
GUIDE SPECIFICATIONS .................................................................................. 52
LIST OF ILLUSTRATIONS
FIG. PAGE
1 Millennium Single-Stage Absorption Chiller Features .................................... 6
2 Standard Steam / Hot Water Cycle Diagram .................................................. 8
3 Millennium Control Center ............................................................................. 9
4 Typical Steam Piping .................................................................................. 19
5 System 1: Atmospheric Condensate Return System .................................. 24
6 System 2: Vacuum Condensate Return System .......................................... 25
7 System 3: Vacuum Condensate Return System with Steam Inlet
and Condensate Outlet Under Vacuum ........................................................ 25
8 Typical Hot Water Piping ............................................................................. 26
9 Typical Part Load Steam Consumption – Std. Unit ...................................... 29
10 Typical Chiller Start-Up Performance ........................................................... 29
11 Typical Chiller Cooling Capacity for Required LCHWT ................................. 31
12 Typical Chiller Cooling Capacity for Avail. Steam Inlet Press. ..................... 31
13 Typical Chiller Steam Consumption for LCHWT ........................................... 31
14 Steam Chiller Nozzle Arrangements ........................................................... 33
15 Hot Water Chiller Nozzle Arrangements ....................................................... 33
16 Unit Dimensions ......................................................................................... 35
17 Cage Type Steam Valve Press. Drop for Low Steam Flow App .................... 38
LIST OF TABLES
TABLE PAGE
1 Enthalpy Values .......................................................................................... 18
2 YIA Chiller Shell and Tube Volumes ............................................................ 22
3 Generator Heat Loss (English) .................................................................... 27
4 Generator Heat Loss (Metric) ...................................................................... 27
5 Approx. Insulation for Hot and Cold Surfaces (English) ............................... 28
6 Approx. Insulation for Hot and Cold Surfaces (Metric) ................................. 28
7 Nominal Ratings, Steam Machines (English) .............................................. 29
8 Nominal Ratings, Steam Machines (Metric) ................................................ 30
9 IPLV Analysis ............................................................................................. 32
10 Fouling Factor ............................................................................................. 32
11 Evaporator Pass Arrangements .................................................................. 34
12 Absorber / Condenser Arrangements .......................................................... 34
13 Hot Water Generator Nozzle Arrangements ................................................. 34
14 Electrical Data ............................................................................................ 50
2 YORK INTERNATIONAL
FORM 155.16-EG1
28377A
NOMENCLATURE
YIA ST 8E1 46 A S
YORK INTERNATIONAL 3
YORK Millennium TM
YIA Single-Effect Absorption Chillers: 120-1377 Tons (420-4840 kW)
TURBINE
Today’s environmental and energy considerations de- sure steam is considered less useful, yet more plentiful.
mand innovative chiller plant designs which save expen-
sive peak load kW-hours and eliminate CFC’s. In a Inlet Air Cooling – Use a YIA chiller to cool inlet air to
growing number of applications with waste heat or abun- a gas turbine or a compressor. The lower specific volume
dant low pressure steam, single effect absorption chill- associated with cooler air provides more combustion
ers offer an ideal means of saving on cooling costs capacity by increasing the overall efficiency of the sys-
without a significant installation cost penalty. tem.
That’s why YORK is proud to introduce the Millennium Waste Heat Recovery – Recover waste heat from print-
YIA Single Effect Absorption Chiller. The YIA Absorp- ing plants, incinerators or gas engine jacket water to pro-
tion Chiller offers the rugged, industrial-grade design vide required comfort or process cooling at little opera-
of our previous single effect model, with a whole new tional cost.
package of user-friendly microprocessor controls, de-
signed to increase reliability. Commercial Cooling/Peak Shaving – For particularly
pronounced peak loads with few operating hours, the YIA
Applications particularly well-suited for the YORK YIA absorber’s lower first cost may provide an acceptable
Absorption Chiller include the following: payback when more efficient, yet more expensive double
effect chillers cannot.
Cogeneration – For cogeneration systems, high pres-
sure steam has many valuable uses, while low pressure For these and similar money-saving designs, consider
steam is considerably less useful, yet more plentiful. In the field-proven YIA design. In over thirty-five years of
these plants, the YIA absorber can provide cooling with operation, the YORK single-effect design has proven it-
low pressure steam or hot water, freeing high pressure self in applications ranging from schools to refineries.
steam for power generation or other valuable uses. Now, with state-of-the-art controls and continual product
improvement, the YORK YIA machine is truly without
For cogeneration applications, high pressure steam is of- peer. When it comes to absorption technology, there’s
ten used as a prime mover while the remaining low pres- only one leader - YORK
4 YORK INTERNATIONAL
FORM 155.16-EG1
Reliability Features
The YORK Millennium YIA Absorption Chiller introduces machine. In this manner, the YIA unit continues its vital
a revolutionary system of unit controls and mechani- task of making chilled water, while allowing operators the
cal devices designed to keep the chiller running in even opportunity to find system deficiencies before they lead
the most extreme circumstances. Old concerns about to an actual shutdown.
crystallization are approached with a hybrid of new 6. Stainless Steel Pans – Both the pan in the evapo-
technology and older, proven methods. Additionally, the rator (which holds refrigerant) and the pan in the con-
YIA chiller contains a host of other features designed denser (which holds refrigerant) are fabricated from stain-
to give the machine a long, trouble-free life. The result: less steel, giving the machine added protection against
the smartest, safest, and most reliable single effect corrosion.
absorption chiller on the market today.
7. Hermetic Pumps – YORK’s industrial pump provides
1. Concentration Limit – YORK’s Millennium Con- a life of trouble-free operation with a recommended 55,000
trol Center actually detects the high lithium bromide hours between service inspections. Factory installed
concentrations which can endanger the unit. When high suction and discharge isolation valves provide faster and
concentrations are present, the panel limits heat input easier servicing of pumps.
until the solution reaches equilibrium at a lower con-
centration. In this manner, the machine operates only
within the safe and practical limits of the lithium bromide
absorption cycle.
2. “J” Tube – If crystallization were to occur, it would
begin in the strong solution side of the solution heat ex-
changer. This would force the strong solution to back up
into the generator. At a certain generator solution level,
the hot strong solution would over flow into the “J” tube.
This tube sends hot solution directly to the absorber, 28377A (D)
immediately warming the weak solution. The heated weak
solution would then warm the crystallized solution on the 8. Double Walled Evaporator – The Evaporator on
opposite side of the heat exchanger. This transfer of heat each YIA model is lined with a second wall, eliminating
will cause the crystallized lithium bromide to move back the need for field insulation.
into solution, allowing the unit to continue operation.
9. Purge System – YORK’s efficient purge system ex-
3. Stabilizer Valve – If minor crystallization occurs and pels non-condensable gases from the unit’s external purge
causes overflow in the “J” tube, the temperature of the chamber without the risk of spilling lithium bromide.
“J” tube will increase because of the hot solution. A spe-
10. Brass Spray Nozzles – Evaporator spray headers
cially placed sensor detects this change in temperature,
use corrosion resistant brass to ensure long life.
and the panel sends a signal to open a solenoid on
YORK’s patented Stabilizer Valve. When the Stabilizer 11. Stainless Steel Spray Nozzles – Absorber spray
Valve is open, refrigerant water is injected into the headers are fabricated from stainless steel, providing
strong solution immediately before the heat exchanger. trouble-free operation in a particularly demanding envi-
The water serves to dilute the strong solution, allowing ronment.
the crystallized lithium bromide to become soluble at a
12. Single Power Connection – A single point power
lower concentration.
connection is all that is required for the YIA Absorption
4. Steam Supply Pressure/Temperature Limit – The Chiller, providing further reliability and ease of installa-
Millennium Control Center actually monitors the inlet tion.
steam (or hot water) temperature and steam pressure.
13. 45°F (7.2°C) Condenser Water – The YORK YIA
The panel will close the control valve to the machine if
chiller is capable of operating with entering condenser
temperatures or pressures become excessive, thus
water temperatures as low as 45°F (7.2°C). Without proper
protecting the machine from potentially harmful condi-
compensation, lower tower water temperatures cause:
tions.
low refrigerant level, potential for crystallization, and low
5. Load Inhibition – Before the YIA unit shuts down refrigerant temperature. The combination of three control
due to a given safety condition (see Controls section systems allow the YIA to maintain a stable balance of
for a complete list), it first crosses a warning threshold solution and refrigerant parameters as entering tower water
which will cause the panel to limit heat input to the temperature varies:
YORK INTERNATIONAL 5
Reliability Features
• At low refrigerant levels, the Unloader Control Valve • The Stabilizer Valve will open to dilute the absorber
opens to inject lithium bromide into the refrigerant concentration if the refrigerant temperature drops be-
line. This maintains refrigerant level preventing pump low a preset level.
cavitation and keeps flow available to dilute the con-
centrated solution. The result is a system that maintains proper balance of
machine loading, and solution and refrigerant character-
• The Steam Valve Override Control System adjusts istics to allow continuous operation with tower water tem-
the steam input regulating the concentration of the peratures as low as 45°F (7.2 °C).
lithium bromide leaving the generator to a safe level
for the operating temperature of the machine.
100 100
90 90
80 80
70 70
60 60
50 50
40 40
4.5
40 7.2
45 10
50 12.7
55 15.5
60 19.3
65 21.1
70 23.8
75 26.6
80 40 45 50 55 60 65 70 75 80
Condenser Water to Absorber (deg.. C)
F) Condenser Water to Absorber (deg. F)
10 5
1
8 6
12
13
9
7 11
2 28377A
6 YORK INTERNATIONAL
FORM 155.16-EG1
How It Works
LD00900
LD00903
YORK INTERNATIONAL 7
How It Works
LD00904(R)
8 YORK INTERNATIONAL
FORM 155.16-EG1
Control System
28342A (D)
The YORK Millennium Control Center is designed for the CAPACITY CONTROL
very best in chiller protection and overall system effi-
ciency. As standard equipment on all YIA chillers, the When automatic capacity control is desired, the Millen-
Control Center is a major development in absorption nium Control Center automatically varies the steam/hot
chiller technology, providing the most precise and reli- water flow rate with a fuzzy logic control algorithm in order
able control available in the industry. to maintain the programmed leaving chilled water setpoint
for cooling loads ranging from 10% to 100% of design.
INFORMATION DISPLAY • Digital keypad entry of setpoint to 0.1°F (0.1°C)
Vital chiller operating information can be shown on the • Verify actual vs. setpoint temperature via alphanu-
40 character alphanumeric display. All information is in meric display
the English language with numeric data provided in En- • Remote reset of setpoint (up to 20°F (11.1°C) range)
glish or metric units. Information provided standard on all with a 1 to 11 second PWM signal (optional 4-20mA,
units includes: 0-10 VDC or contact closure)
When automatic control is not desired, the input steam/
• Chilled water temperatures, entering and leaving hot water flow rate is also manually adjustable from the
• Tower water temperatures, entering and leaving Millennium Control Center panel to any setting between
• Generator pressure and temperature minimum and maximum, provided steam/water input is
• Refrigerant temperature not inhibited by a specific operating condition (e.g. safety).
• Solution temperature
• Operating hours STEAM/HOT WATER LIMITING CONTROLS
• Number of starts
• Number of purge cycles (last 7 days and lifetime total) • Manual limiting available from 10% to 100% of capacity
• Control valve position (in %) • Programmable pull down demand limiting to auto-
• Indication of each pump’s operation matically limit steam/hot water source loading at
• Inlet steam pressure and temperature start-up
• Hot water temperature • Remote limiting of steam/hot water input from 10%
to 100% with a 1 to 11 second PWM signal
• Solution concentration
In addition, all operating and setpoint information can be SYSTEM CYCLING CONTROLS
transmitted to an optional remote printer through the
RS232 port to obtain data logs: • Programmable seven day time clock for automatic
start/stop of chiller and chilled and condenser water
• At any time by pressing the PRINT button pumps
• At set time intervals by programming the panel • Separate schedule input strictly for holidays
• After a safety shutdown to list the cause of the shut down • Remote cycling contacts available for other field sup-
and the operational parameters just prior to shutdown plied signals
• For a complete history print-out of the last four shutdowns • Multi-unit cycling contact input terminals for field sup-
and operational parameters just prior to shutdown. plied signals
YORK INTERNATIONAL 9
Control System
Cycling – Those controls which automatically reset and ENERGY MANAGEMENT INTERFACE
permit auto restart of the system.
By connecting with the YORK Integrated Systems Net-
• Loss of condenser water flow work, the Millennium Control Center can communicate
• Low leaving chilled water temperature [2°F (1.1°C) all data accessible from the keypad (including all tem-
below setpoint] peratures, pressures, alarms and operating data) to a
• Power failure (when automatic restart is selected) remote DDC processor through a single shielded cable.
In remote mode, the DDC processor may issue all oper-
Safety – Those controls which (when employed)require ating commands available at the keypad to the control
a manual operation to restart the system. center through the same shielded cable. With a Millen-
nium translator panel, other BAS systems can receive
• Solution pump thermal or current overload this same information.
• Refrigerant pump thermal or current overload
• Low refrigerant temperature The Millennium Control Center also provides direct hard
• Generator high temperature or pressure wire interface capability with other building automation
• Loss of chilled water flow systems. Remote chilled water temperature reset and/or
• Power failure (when automatic restart not used) remote steam/hot water input limit interface via a 1-11
• High inlet steam temperature or pressure second PWM standard signal (4-20mA, 0-10 VDC or con-
• High inlet hot water temperature tact closure optional). Remote unit start/stop and/or re-
• High solution concentration mote status including “unit ready to start,” “unit operat-
• Incomplete dilution cycle due to any of the following: ing,” “unit safety shutdown,” and “unit cycling shutdown”
• Power failure interface via relay contacts.
10 YORK INTERNATIONAL
FORM 155.16-EG1
Mechanical Specifications
The YORK Millennium YIA Absorption Liquid Chiller is pass arrangements. Stub-out water nozzle connections
completely factory-packaged, including upper and lower with Victaulic grooves are welded to the water boxes;
shell assemblies, solution heat exchanger, hermetic these nozzles are suitable for Victaulic coupling, welding
solution and refrigerant pumps, microprocessor con- or flanges, and are capped for shipment. Lifting lugs are
trols and all interconnecting piping and wiring. provided on each water box cover, and plugged vent and
drain connections are provided for each water box.
Models YIA-1A1 through YIA-10E3 are shipped as a one
piece assembly, charged with nitrogen. Models SOLUTION HEAT EXCHANGER
YIA-12F1 through YIA-14F3 are shipped as two pieces
(upper and lower shells), each charged with nitrogen, The solution heat exchanger is a shell and tube design
for field reassembly. The purge pump, chilled water flow with carbon steel tubing. The shell is formed from carbon
switch, modulating control valve, and the lithium bro- steel plate with fusion welded seams. Tubes are
mide charge are shipped loose for field installation or roller-expanded into carbon steel tube sheets.
charging.
PUMPS
SHELL ASSEMBLIES
Solution and refrigerant pumps are hermetically sealed,
The shell assemblies consist of a generator, condenser, self-lubricating, totally enclosed, factory-mounted, wired
evaporator and absorber housed in upper and lower shells. and tested. Motor windings are not exposed to LiBr or
The shells are constructed of rolled carbon steel plate water. The suction and discharge connections for each
with fusion welded seams. Carbon steel tube sheets, pump are fully welded to the unit piping to minimize the
drilled and reamed to accommodate the tubes, are welded opportunity for leaks. Suction and discharge connec-
to the end of the shells. Intermediate tube supports are tions are also equipped with factory installed isolation
fabricated of carbon steel plates. Each tube is roller ex- valves to permit quick and easy servicing of pumps.
panded into the tube sheet to provide a leak tight seal Pumps are designed to operate for a total of 55,000 hours
and each tube is individually replaceable from either end between service inspections.
of the unit.
STABILIZER VALVE
The lower shell houses the low pressure section of the
machine which includes the evaporator and the absorber. A solenoid actuated valve sends refrigerant water into
Both the evaporator and the absorber use 3/4" O.D. (19.1 the solution heat exchanger circuit in order to combat
mm), 0.028" (0.71 mm) wall, copper tubing. The evapora- any minor crystallization.
tor tubes are externally enhanced, while the absorber
tubes are prime surface. The evaporator shell is UNLOADER VALVE
double-walled, enhancing unit reliability and eliminating
the need for insulation. Spray nozzles in the absorber A solenoid actuated valve sends lithium bromide solution
are stainless steel, while those in the evaporator are made into the refrigerant circuit, allowing the unit to operate at
of brass. The evaporator and absorber are separated by condenser water temperatures as low as 45°F (7.2°C).
finned eliminator baffles designed to allow only water in
the vapor state to pass to the absorber. SOLUTION AND REFIGERANT
The upper shell contains the high pressure section of the Each YIA unit is charged with lithium bromide solution
machine, which includes the generator and the condenser. with lithium chromate used as a corrosion inhibitor. The
The generator uses 3/4" O.D. (19.1 mm), 0.035" (0.89 refrigerant is water. A small amount of 2-ethyl, hexanol is
mm) wall, 90/10 cupro-nickel tubes with external en- included as a heat and mass transfer enhancer. Lithium
hancements. The condenser tubes are 3/4" (19.1 mm) bromide charge ships to the job site directly from YORK’s
or 1" (25.4 mm) O.D., .028" (0.71 mm) wall prime sur- vendor.
face copper tubing. The condenser and generator are
separated by a finned eliminator which prevents liquid PURGE SYSTEM
carryover into the condenser.
The purge system continuously removes non-condensible
Water boxes are fabricated of carbon steel. The design gases from the unit and collects them in the absorber
working pressure is 150 PSIG (1.0 MPa)[tested at 225 water cooled purge chamber. Gases are removed from
psig (1.5 MPa)]. Integral steel water baffles are located the chamber through periodic operation of the electric
and welded within the water box to provide the required -motor-driven vacuum pump.
YORK INTERNATIONAL 11
Mechanical Specifications
Steam – The valve is a cage type (for low steam Warning Conditions – The Millennium Control Center
mass flow) with a cast iron body or butterfly-type (high limits heat input and provides a warning annunciation
steam mass flow) with a carbon steel body. Cage under the following conditions: low refrigerant tempera-
valves are supplied with 125 psig ANSI (0.86 MPa) ture, high generator pressure, high entering condenser
raised face flanges. Butterfly valves are wafer-type water temperature, purge pump current overload, faulty
valves and are supplied with 150 psig (1.0 MPa) ANSI solution dilution temperature sensor, and high steam tem-
raised face flanges. perature or pressure or high hot water temperature. Spe-
cial instrumentation measures the solution concentra-
Hot Water – The valve is a 3-way diverting type. tion and limits heat input as necessary to keep the unit
Valves are available in 125 psig (0.86 MPa), 250 psig from the crystallization region.
(1.7 MPa), and 300 psig (2.0 MPa) ratings. All valves
are supplied with ANSI raised face flanges. Safety Controls – The Control Center includes unique
safety logic designed to protect the YIA chiller from dam-
POWER PANEL aging malfunctions. Complete safety annunciation is dis-
The power panel enclosure includes the following: single point played for each shut-down by pressing the status key.
wiring connection for the incoming power supply; non-fused This information includes day, time, reason for shutdown
disconnect switch; motor starters, complete with current and and type of restart required. These include: solution or
thermal overload protection for the solution pump, refrigerant refrigerant pump thermal or current overload, low refrig-
pump, and purge pump (current overloads only); 115VAC 50/ erant temperature, generator high pressure or tempera-
60 Hz control power transformer. ture, loss of chilled water flow, power failure, high steam
supply pressure or temperature, high hot water supply
MILLENNIUM CONTROL CENTER temperature, auxiliary safety shutdown, high solution con-
centration, incomplete dilution cycle, and power failure
The microprocessor control center is factory mounted, (if manual restart after power failure is selected).
wired and tested. The electronic panel automatically con-
trols the operation of the unit in meeting system cooling
requirements while minimizing energy usage. Chiller op- Operating Controls – Background messages are dis-
erating parameters are sensed by either thermistors or played while the unit is running to signal operator of con-
transducers and displayed on the keypad display. trolling conditions such as: steam limit in effect, leaving
chilled water temperature control, and non-critical sensor
The operating program is stored in non-volatile memory error. System cycling messages are displayed in regard
(EPROM) to eliminate chiller failure due to AC power to day, time, cause of cycling shutdown, and auto-start
failure/battery discharge. In addition, programmed indication, These include loss of condenser water flow,
setpoints are retained in lithium battery-backed RTC low leaving chilled water temperature, and power failure
memory for a minimum of 5 years. (when auto-start is selected).
12 YORK INTERNATIONAL
FORM 155.16-EG1
YORK INTERNATIONAL 13
Optional Features
WATER FLANGES For applications with working pressures which exceed 150
psig (1.0 MPa), high pressure water boxes with flanges are
150 lb. (1.0 MPa) ANSI raised-faced flanges for the available. These compact water boxes are rated for 300
evaporator and/or absorber/condenser water connec- psig DWP (2.1 MPa) and tested at 450 psig (3.1 MPa).
tion as well as the generator connection are factory
welded to water nozzles. Companion flanges, bolts,
nuts and gaskets are not included. MARINE WATER BOXES
TOWER WATER FLOW SWITCH Marine water boxes allow service access for cleaning of
the heat exchanger tubes without the need to break the
This is a paddle-type, vapor-proof water flow switch water piping. Bolted-on covers are arranged for conve-
suitable for 150 psig DWP (1.0 MPa) (300 DWP (2.1 nient access. Victaulic nozzle connections are standard;
MPa) available) for the absorber/condenser water cir- flanges are optional. Marine water boxes are available
cuit (chilled water flow switch is standard). for the evaporator or absorber/condenser circuits. Ma-
rine water boxes are only available for circuits with 150
REMOTE RESET CONTROLS psig (1.0 MPa) working pressures.
Two optional boards allow for continuous reset of ei-
ther leaving chilled water temperature or remote steam/ INDUSTRIAL GRADE PAINT
hot water limit using a 4 to 20mA, 0 to 10 VDC, or
contact closure as opposed to the standard 1 to 11 A factory-applied coating of industrial-strength Amerlock
second PWM signal. These signals may be wired di- 400 epoxy primer and Amershield finish is applied to
rectly to the panel terminal block on the card file with- exterior chiller surfaces for harsh environments.
out any external interfacing.
The chiller can be shipped knocked down into two ma- Chiller micropanel and power panel are enclosed in NEMA
jor sub-assemblies (generator and main shell) as re- 4 rated enclosures for industrial applications. This op-
quired to rig into tight spaces. This is particularly con- tion includes waterproofing of control and power connec-
venient for existing buildings where equipment room tion wiring.
access does not allow rigging a factory packaged
chiller. Shipment in the knock-down configuration is
standard on units YIA-12F1 through YIA-14F3. HIGH TEMPERATURE OPTION
14 YORK INTERNATIONAL
FORM 155.16-EG1
Application Data
The following discussion is a guide for the application exist which cannot be corrected by proper water treat-
and installation of Millennium YIA Single-Effect Absorp- ment, it may be necessary to provide a larger allowance
tion Chillers to ensure reliable, trouble free life for which for fouling, and/or specify special materials of construc-
this equipment was designed. tion.
YORK INTERNATIONAL 15
Application Data
must be electrically connected to the chilled water inter- shutdown. The valve should be located a distance of 4 to
lock position in the unit control center. A water strainer, 10 feet (1.2 m to 3.0 m) from the absorption unit genera-
of maximum 1/8" (3.18 mm) mesh should be tor inlet flange.
field-installed in the chilled water inlet line as close as
Automatic control valves are sized according to job spe-
possible to the chiller. If located close enough to the chiller,
cific full load steam or hot water parameters. For applica-
the chilled water pump may be protected by the same
tions with low steam mass flows, the cage valve pro-
strainer. The flow switch and strainer assure chilled wa-
vides the best control. However, at higher mass flow, the
ter flow during unit operation. The loss or severe reduc-
cage valve pressure drops are prohibitively high. Thus, a
tion of water flow could seriously impair the YIA unit per-
butterfly valve is used. Hot water valves are three-way
formance or even result in tube freeze-up.
diverting valves which bypass hot water that is not
needed to maintain capacity.
Condenser Water – Like the chilled water circuit, the
tower water circuit requires a means of proving flow. The
recommended method of proving flow is a tower water SOUND AND VIBRATION CONSIDERATIONS
flow switch (not in standard supply scope, but available
Since the YIA unit generates very little vibration, vibra-
from YORK) installed in the tower water piping in the same
tion eliminating mounts are not required. However, when
manner as the chilled water flow switch (above).
the machine is installed where even mild noise is a prob-
The YIA chiller is engineered for maximum efficiency at lem, pads can be used. The use of anchoring bolts on
both design and part load operation by taking advantage the machine legs is not normally necessary.
of the colder cooling tower water temperatures which
naturally occur in the winter months. For standard air STEAM AND CONDENSATE THEORY
conditioning applications, YIA absorbers can tolerate
entering tower water temperatures as low as 45°F (7°C) Saturation Temperature
without a cooling tower bypass. The YIA unit, by a sys- The temperature at which a fluid changes from the liquid
tem of internal controls which regulate the solution con- phase to the vapor phase, or conversely, from the vapor
centration, can operate continuously and automatically phase to the liquid phase is called the saturation tempera-
with entering cooling water temperature as low as 45°F ture. A liquid at the saturation temperature is called a satu-
(7°C). In order to safely accept such low cooling water rated liquid and a vapor at the saturation temperature is
temperatures, the YIA machine actually measures solu- called a saturated vapor. It is important to recognize that
tion concentration leaving the generator. If the solution the saturation temperature of the liquid (the temperature
concentration is too high, the Millennium Control Center at which the liquid will vaporize) and the saturation tem-
will begin to close the steam valve until the concentra- perature of the vapor (the temperature at which the vapor
tion reaches an acceptable level. Thus, the full load ca- will condense) are the same for any given pressure.
pacity of the machine may decrease as the temperature
of the cooling water falls. In normal air conditioning appli- For any given pressure, the saturation temperature is
cations, this is not significant because chilling load gen- the maximum temperature the liquid can have and the
erally decreases with lower wet bulb temperature. minimum temperature the vapor can have. Any attempt
to raise the temperature of a liquid above the saturation
For process applications which have strict requirements temperature will only result in vaporizing some part of
for leaving chilled water temperatures, a three way cool- the liquid. Similarly, any attempt to reduce the tempera-
ing tower bypass valve is recommended. The bypass ture of a vapor below the saturation temperature will only
valve should maintain entering cooling water tempera- result in condensing some part of the vapor.
ture at +2.5°F (1.4°C) of the design temperature.
Superheated Vapor
At the initial start-up, entering tower water temperature
may be as low as 45°F (7°C). Vapor at any temperature above the saturation tempera-
ture corresponding to its pressure is referred to as super-
CONTROL VALVES heated vapor. Once a liquid has been completely vapor-
ized, the temperature of the resulting vapor can be fur-
An automatic control valve is furnished with the unit by ther increased by adding energy. When the temperature
YORK for field mounting and wiring. The valve will be of a vapor has been increased above the saturation tem-
electrically actuated and will automatically close on unit perature, the vapor is said to be superheated and the
16 YORK INTERNATIONAL
FORM 155.16-EG1
energy supplied to superheat the vapor is commonly re- absorber should be kept close to dry saturated steam so
ferred to as superheat. valuable generator heat transfer area is not used for
desuperheating steam.
Before a vapor can be superheated, the vapor must be
removed from contact with the vaporizing liquid. Also, Steam Purity
before a superheated vapor can be condensed it must
first be cooled to the saturation temperature correspond- Boiler water treatment is an essential part of any mainte-
ing to its pressure. nance program. If the water is not properly treated, cer-
tain chemicals may exceed tolerable limits and damage
Subcooled Liquid the generator, control devices and adjoining piping. It is
the customer’s responsibility to test the condensate to
If, after condensation, the resulting liquid is cooled (con- make sure it is within certain limits. These limits are listed
stant pressure) so that its temperature is reduced below in the service manual.
the saturation temperature, the liquid is said to be
subcooled. If the steam carries entrained air or other gases, this will
have a tendency to reduce the steam temperature. Air
The Effect of Pressure on Saturation Temperature will also reduce the heat transfer properties of a unit be-
cause it migrates to heat transfer surfaces causing an
The saturation temperature of a fluid depends on the pres- insulating effect.
sure of the fluid. Increasing the pressure raises the satu-
ration temperature, while reducing the pressure lowers Carbon dioxide in steam is probably the most destruc-
the saturation temperature. tive form of contaminant. CO2 will dissolve in the con-
densate forming carbonic acid, which is extremely corro-
Condensation sive to pipes and system components.
Steam Supply •
Input (Btu/hr or W/hr) = (h1 - h2) X m
Dry steam (no water droplets) or slightly superheated
steam should be supplied to the unit to maximize the Where:
heat content in the steam. The steam temperature and h1 = enthalpy of steam entering the unit (saturated
pressure must not exceed the maximum allowable as vapor)
this may cause damage to system components. h2 = enthalpy of condensate leaving the unit
(subcooled liquid)
•
The maximum steam temperature includes any super- m = mass flow rate of steam (lb./hr or kg/hr)
heat. Minimal superheat can be desirable to prevent con-
densation in supply lines, but excess superheat must be h1 can be determined by reading the pressure at the Steam
avoided. Superheated steam must be cooled to satura- Inlet Pressure Indicator.Then refer to steam tables to find the
tion temperature before useful heat transfer can occur in enthalpy of the saturated vapor at this pressure. This value
the absorption chiller generator. Steam supplied to an assumes that dry steam is entering the unit.
YORK INTERNATIONAL 17
Application Data
Refer to subcooled liquid tables to determine enthalpy of rated vapor value to the saturated liquid value. Since en-
the condensate leaving the unit. Both temperature and thalpy is an indication of the heat in the steam, available
pressure must be measured to determine this value. heat is reduced if liquid water is contained in the steam.
18 YORK INTERNATIONAL
FORM 155.16-EG1
ç
CHECK
VALVE
è
TO CONDENSATE
RETURN
PRESSURE
TO CONDENSATE
RELIEF
RETURN
VALVE STEAM STEAM
ç
SEPARATOR STRAINER
STOP VALVES PRESSURE
DRAIN SOLENOID VALVE REDUCING
CONDENSATE COOLER(S)
(SUPPLIED BY YORK) VALVE
LD00697
two gauges increases to an unacceptable level, the excess of 100 psi (690 kPa). The noise generated in a
strainer should be removed and cleaned. single step of reduction may be objectionable.
Steam Separator – The steam separator is installed in Automatic Shut-Off Valve – This valve should shut-
the steam supply line and is used to separate any liquid off 100% of the steam flow during a cycling/safety shut-
present in the steam. This condensate liquid would nor- down or a power failure. The YORK supplied steam con-
mally be piped through a steam trap back to the conden- trol valve will remain in whatever position it happened to
sate tank. The steam trap will prevent any steam from be in at the time of a power failure. A valve that will
blowing through the separator into the condensate return completely shut-off steam flow to the unit during such a
system. The use of a steam separator and trap will allow failure is required. This steam valve should be bubble
dry steam to enter the unit at all times. tight.
The system requirement is to have dry steam into the Pressure Relief Valve – A 15 psig (103 kPA) pressure
generator of the absorption chiller. If dry steam can be relief valve should be installed to protect the steam gen-
supplied without the use of a steam separator then it is erator vessel. The vessel is not ASME stamped and
not necessary to install one. therefore must be protected from pressures above 15
psig (103 kPa). The vessel can be ASME stamped for
In cases where the chiller is located close to the boiler or 150 psig (1034 kPa) as an option, but the operating pres-
is supplied with superheat, the steam reaching the chiller sure will still be limited to 15 psig (103 kPa).
may already be dry. However, since any liquid present in
the steam entering the chiller will reduce the heat input, To prevent nuisance blowing of the relief valve, it should
it is important to include a steam separator unless it is be set 2 or 3 psi (14 to 21 kPa) above the generator
truly not necessary. operating pressure and within code requirements. The
relief valve should be sized for maximum steam flow
Pressure Reducing Valve – A pressure reducing valve and vented in accordance with local codes. A relief valve
must be used if the steam pressure to the chiller is greater is not required if there is a properly sized relief valve
than 15 psig (103 kPa). For applications where the steam elsewhere in the system, which will keep the system
supply pressure is known to fluctuate, it is recommended below 15 psig (103 kPa).
that a steam pressure regulating valve be used.
Steam Control Valve (York Supplied) – The steam con-
When needed, a steam pressure reducing valve suitable trol valve as found in the ship-loose-items, should be
for dead-end service must be provided in the steam sup- installed as shown in Fig. 4. This valve should be con-
ply piping ahead of the steam control valve. This pres- nected to the appropriate wiring harness and is used to
sure reducing valve should be sized on the basis of the control the amount of steam that enters the unit. It will
pressure drop and absorption unit full load steam flow modulate from 10% to 100% depending on the leaving
requirements, not on the basis of steam supply pipe size chilled water temperature. The minimum value of 10% is
(which can result in an oversized valve). The pressure set in the field. This is explained in detail in the installa-
reducing valve should be provided with stop valves on tion manual.
both inlet and outlet and a full size bypass with a globe
valve to permit manual operation during maintenance. Steam Inlet Pressure Indicator (If Desired) – A pres-
sure gauge can be installed to allow the operator to de-
Two pressure reducing valves, one large and one small, termine the inlet steam pressure to the unit. The inlet
piped in parallel may be desirable for those applications steam pressure is indicated by the micropanel, but an
with continued operation at low loads or where highly vari- additional pressure gauge may be desired.
able upstream pressures exist. The smaller valve would be
set at a slightly higher pressure than the large valve so it Drain Solenoid Valve (York Supplied) – Factory sup-
will stay open at low flow rates while the large valve closes, plied device used to insure zero steam flow through the
thus protecting the seat of the larger valve. unit during shut down. This valve should be installed in a
horizontal run of pipe within 2 feet (0.6 m) of the chiller
The use of two steps of steam pressure reduction may condensate outlet. This valve works in conjunction with
be desirable on applications with pressure differentials in the Automatic Shut-Off Valve.
20 YORK INTERNATIONAL
FORM 155.16-EG1
Vacuum Breaker (If Desired) – A vacuum breaker will possible elevation between the generator outlet and the
often not be necessary, but they can prevent conden- trap should be used.
sate build up in the generator section of the chiller at part
load. A discussion of the chillers operation and the func- The condensate outlet line should be sized in accordance
tion of the vacuum breaker follows: with good engineering practice for condensate at the flash
If an atmospheric return system is used, the generator will point and should be kept as short and simple as pos-
not operate in the vacuum region, but will operate at atmo- sible. Stop valves should be provided ahead of the
spheric pressure at the low load conditions. Throttling of strainer and after the trap for necessary maintenance;
the steam valve at low load results in steam condensate and a full size bypass provided with globe valve for
back-up into the generator tubes. As the load increases, manual operation during maintenance. A full trap outlet
the steam valve will open and the rising steam pressure will line size connection and valve should be provided for
force the condensate out of the generator. The accumula- blow-off and test purposes.
tion of condensate in the generator at reduced loads and The steam trap should be selected for about 1.5 times
subsequent drainage will have no adverse effect on ab- the design full steam flow rate, at the design operating
sorption unit efficiency. However, the cyclical drainage of pressure differential. The operating full load pressure dif-
condensate from the unit will require that the main system ferential: PD = SP – P1 – P2 – P3
condensate receiver be sized with sufficient additional ca-
where:
pacity to accommodate this fluctuation (assumed to be equal
to the absorption unit generator volume as a maximum -see PD = Trap pressure drop, psi.
Table 2 on page 22). SP = Steam pressure, psig, at generator flange nor-
mally 3 psi less than the design pressure to the
To avoid fluctuation in condensate return or water ham- control valve.
mer in the generator tubes, a vacuum breaker swing check P1 = Condensate line pressure drop losses, psi.
valve can be added as shown in Fig. 5 on page 24. A 3/
P2 = Check valve pressure drop loss, psi.
8-inch size is sufficient to prevent condensate build-up.
For safety, a pipe should be installed from the check P3 = Condensate cooler pressure drop loss, psi.
valve to a location close to the floor or other safe place.
The use of the check valve to permit air entrance into Select float capacity from manufacturer’s ratings per
the generator tubes has the disadvantage that this air above recommendations.
must later be purged through the thermostatic element
The line from the steam trap to the condensate receiver
of the float trap and tends to entrain air in the conden-
will contain some flash vapor flowing with the conden-
sate return.
sate. This line should be as short as possible, preferably
Strainer(s) – A fine mesh strainer with blow-off valve not more than 30 feet (9 m) in equivalent length. As a
should be provided ahead of the steam trap(s) to protect general rule, it should be sized according to the number
it from damage. of traps used and one or more sizes larger in the case of
longer piping runs.
Float and Thermostatic Steam Trap(s) – Fig. 4 shows
a typical condensate steam trap piping arrangement as Check Valve – A check valve should be provided in the
used on an absorption unit. The trap serves the purpose of trap outlet line to prevent any possible air or condensate
passing condensate, but preventing the loss of steam. A leakage back to the generator under reduced load oper-
float and thermostatic steam trap is recommended for this ating conditions.
application. It should be applied in accordance with the
manufacturer’s recommendations. The trap should be lo- Condensate Cooler – The use of a condensate cooler
cated as close to the generator condensate outlet as pos- between the trap and the condensate receiver to cool the
sible in the horizontal plane. In the vertical plane, the trap condensate below its flash is required for vacuum return
should be located below the generator condensate outlet, systems and may be desirable, though not required, for
a minimum of 12 inches (0.3 m). Preferably, the maximum atmospheric return systems.
YORK INTERNATIONAL 21
Application Data
22 YORK INTERNATIONAL
FORM 155.16-EG1
The variations in condensate flow must be recognized down to pressures well into the vacuum region at part
and the cooler selected to cool the maximum flow of load. As the cooling load decreases, the chilled water
condensate 5-10°F (3-6°C) below the saturation tempera- controller will start closing the steam control valve, re-
ture of the lowest pressure in the system (atmospheric ducing both steam flow and steam pressure to the gen-
pressure for an atmospheric return or the lowest pres- erator. At some part load point, say 75% for illustration,
sure in a vacuum return system). Sufficient coolant must the steam pressure will be 0 psig, or atmospheric. With
be provided to cool the maximum condensate flow to the further reduction in load, the steam valve will continue to
desired temperature. Coolers may be air or evaporatively close, resulting in generator steam pressures below at-
cooled, providing they can produce the desired leaving mospheric pressure (providing a vacuum condensate
condensate temperature. The flow of coolant should be return system is used). If an atmospheric return system
automatically controlled to provide the desired leaving is used or if a vacuum breaker is installed at the outlet of
condensate temperature. Coolant flow could be manu- the chiller then the generator pressure will not drop below
ally set for maximum load and allowed to operate con- atmospheric. The use of a vacuum breaker is discussed
tinuously at that level with no operating difficulties, but in the component details section above.
the poor economics of such an arrangement make auto- Three basic types of return systems are possible: (1) a
matic control preferable. completely atmospheric system; (2) a system that al-
lows the chiller and steam traps to function at atmospheric
Auxiliary Condensate Receiver – An auxiliary conden- pressure, but the remainder of the condensate system/
sate receiver must be used if the main condensate re- boiler feed to operate in a vacuum; (3) and a system that
ceiver is located a great distance from the chiller or above operates entirely in a vacuum. Reference Figs. 5, 6, and
the chiller. An auxiliary condensate pump is used to 7 for typical diagrams.
send condensate from the auxiliary receiver to the main System (1) – For an entirely atmospheric system, a
condensate receiver. vacuum breaker may be installed at the outlet of the chiller
(see component details section). Also in this system both
The auxiliary condensate receiver should be located at the auxiliary condensate receiver (if needed) and the main
floor level as close to the absorption unit as possible. A condensate receiver must be vented to atmospheric pres-
check valve in the auxiliary condensate pump discharge sure. The auxiliary condensate receiver should be used
line is recommended where condensate backflow may on completely atmospheric systems when the main con-
occur. densate receiver is located at some distance from the
condensate outlet or above the condensate outlet. This
Auxiliary condensate receivers with condensate pumps system requires a float controlled pump to move conden-
are available as a package. They include a float or other sate from the auxiliary receiver to the main condensate
control to cycle the pump to suit the condensate flow. receiver in addition to the main condensate pump/boiler
Manufacturers’ recommendations concerning selection and feed pump.
application of these packages should be followed.
System (2) – Since the condensate will be at atmo-
spheric pressure until it leaves the auxiliary condensate
Condensate Return Systems receiver, a vacuum breaker can still be used if desired
(see component details in the previous paragraph). The
Steam condensate return systems should be designed auxiliary condensate receiver must be used in this sys-
in accordance with good engineering practice for the gen- tem. The main condensate tank will no longer be vented
eral purpose of removing condensate from the absorp- to atmospheric pressure. A float control is still used in
tion unit’s generator and returning it to the boiler. Either the auxiliary condensate receiver, however, it controls a
an atmospheric or a vacuum condensate return system valve instead of a pump. The low pressure, in the main
may be used with absorption units, as discussed earlier tank, will draw the condensate through when the valve is
in this section. opened.
A general understanding of the YORK single-effect ab- For system (2), a condensate cooler must be provided in
sorption unit operating requirements and characteristics the line between the steam trap and the auxiliary receiver,
is necessary before discussion of condensate return as detailed under condensate cooler in the component
systems. The absorption chiller will operate at full load details section. It must be sized to cool the maximum
steam pressures in the 9-12 psig (62 to 88 kPa) range, flow to a temperature 5-10°F (3-6°C) below the saturation
point of the vacuum return system.
YORK INTERNATIONAL 23
Application Data
System (3) – When the low pressure steam for a YIA at a steam pressure in the vacuum region can improve a
unit comes at or below atmospheric pressure (i.e. steam steam turbine’s economy and efficiency.
turbine exhaust), the entire system can run at a higher
efficiency by using a vacuum pump on the condensate In this system a vacuum breaker can not be used.
return system. At low load, when the absorption system
is operating in the vacuum region, this vacuum can only A condensate cooler must be provided in the line be-
be obtained if the condensate return system similarly op- tween the steam trap and the auxiliary receiver, as de-
erates in a vacuum. With a vacuum condensate return tailed under condensate cooler in the component details
system, the steam supply can be at vacuum steam pres- section. It must be sized to cool the maximum flow to
sure, rather than at a minimum steam pressure of 0 pounds temperature 5-10°F (3-6°C) below the saturation point of
gauge (as it is limited by systems (1) and (2). Discharging the vacuum return system.
LD00684(R)
24 YORK INTERNATIONAL
FORM 155.16-EG1
LD00685(R)
LD00947(R)
FIG. 7 – SYSTEM 3: VACUUM CONDENSATE RETURN SYSTEM WITH STEAM INLET AND CONDENSATE
OUTLET UNDER VACUUM.
YORK INTERNATIONAL 25
Application Data
A hot water supply of 240°F (116°C) will provide suffi- allows YORK units to enjoy a longer life than competitive
cient heat for the YIA chiller. Lower hot water tempera- units, and further reduces the risk of crystallization.
tures may not achieve the nominal capacity for a given
Applications with hot water should use the following
size. A sample hot water piping arrangement is shown in
guidelines:
Fig. 8 below. YORK recommends that shut-off valves be
installed in the hot water supply and return piping for
1. Use the maximum permissible entering hot water tem-
serviceability. On hot water unit shutdown, the water in
perature to the generator for a standard selection (avail-
the generator contracts as it cools. This may form a
able from your local YORK office for specific applica-
vacuum. This can be prevented by installing a check
tions).
valve in the return hot water piping with a 3/4" (19.1 mm)
bypass around the check valve. It would be piped be- 2. In cases where hot water supply temperature exceeds
tween the generator outlet and the hot water bypass. Refer the maximum allowable, 240°F (116°C), the high tem-
to the figure below. perature option must be included with the chiller. Note
The YIA unit’s high performance standards use a maxi- that the hot water supply temperature can not exceed
mum entering hot water temperature of 266°F (130°C) 266°F (130°C) for chillers with the high temperature
(based on rating from your local YORK office). This limit option.
LD00690B
FIG. 8 – TYPICAL HOT WATER PIPING
26 YORK INTERNATIONAL
FORM 155.16-EG1
INSULATION
No appreciable operation economy can be gained from the Tables 2 and 3 below give the heat loss and ventilation
insulation of YORK YIA chillers. However, insulation may requirements for a 10°F ambient temperature rise for the
be desirable to prevent sweating of cold surfaces or to pre- various YIA units and further reduces the risk of crystalliza-
vent overheating of the mechanical equipment room due to tion. Tables 4 and 5 on page 28 provide approximate insula-
heat gains from the high temperature surfaces of the unit. tion areas.
TABLE 3 – GENERATOR HEAT LOSS (ENGLISH) TABLE 4 – GENERATOR HEAT LOSS (METRIC)
YORK INTERNATIONAL 27
Application Data
TABLE 5 – APPROXIMATE INSULATION FOR HOT AND COLD SURFACES – ENGLISH MEASURE
TABLE 6 – APPROXIMATE INSULATION FOR HOT AND COLD SURFACES – METRIC MEASURE
28 YORK INTERNATIONAL
FORM 155.16-EG1
Ratings
TABLE 7 – NOMINAL RATINGS, STEAM MACHINES – ENGLISH
NOTES:
1. All IsoFlow Chillers are rated according to ARI 560-92. Ratings in Tables above represent unit performance at
nominal conditions. For full and part load conditions at specific conditions, contact your local YORK office.
2. For proper selection of cage-type steam valve, use Fig. 17 on page 40. For butterfly type and hot water valves,
contact YORK Marketing.
PERCENT DESIGN ENERGY INPUT
YORK INTERNATIONAL 29
Ratings
TABLE 8 – NOMINAL RATINGS, STEAM MACHINES – METRIC
EVAPORATOR ABSORBER/CONDENSER
CAPA- CON-
MODEL CITY SUMP- PRESS. PRESS.
YIA-ST
(KW) TION INLET OUTLET FLOW # OF DROP INLET OUTLET FLOW # OF DROP
(KG/H) (°C) (°C) (GPM) PASS (K/PA) (°C) (°C) (L/S) PASS (K/PA)
NOTES:
1. All IsoFlow Chillers are rated according to ARI 560-92. Ratings in Tables above represent unit performance at
nominal conditions. For full and part load conditions at specific conditions, contact your local YORK office.
2. For proper selection of cage-type steam valve, use Fig. 17 on page 40. For butterfly type and hot water valves,
contact YORK Marketing.
30 YORK INTERNATIONAL
FORM 155.16-EG1
110
100
95
90
40 42 44 46 48 °F
4 6 7 8 9 °C
Leaving Chilled Water Temp. (°F)
Leaving Chilled Water Temp
100
% of Full Load (in tons)
Chiller Cooling Capacity
95
90
85
80
75
0 1 2 3 4 5 6 7 8 9
Steam Inlet Pressure (in psig)
FIG. 12 – TYPICAL CHILLER COOLING CAPACITY FOR AVAILABLE STEAM INLET PRESSURE
105
Consumption
% of Nominal Full Load Consumption
Chiller Steam Consumption
Consumption
Load
100
Chiller
% of Nominal Steam
Full
95
40 42 44 46 48 °F
4 6
Leaving Chilled7Water Tem p.8(°F) 9 °C
LeavingChilled
Leaving ChilledWater
Water Temp
Temp
32 YORK INTERNATIONAL
FORM 155.16-EG1
Nozzle Arrangements
LD00686
LD00687
YORK INTERNATIONAL 33
Nozzle Arrangements
NUMBER NOZZLE
IN OUT
PASSES ARRANGEMENT
E1 C E
E2 D F
1,3
E3 E C
E4 F D
E5 C D
E6 D C
2,4
E7 E F
E8 F E
NUMBER NOZZLE
IN OUT
PASSES ARRANGEMENT
1 HW1 L K
2 HW2 L M
3 HW3 L K
34 YORK INTERNATIONAL
FORM 155.16-EG1
Physical Data
G
CONTROL
PANEL
YORK INTERNATIONAL 35
Physical Data
PHYSICAL DATA
UNIT APPROX. SHIPPING APPROX. OPERATING
MODEL WEIGHT, POUNDS WEIGHT, POUNDS
“YIA”
TOTAL MAX. RIG TOTAL #/PAD
1A1 8900 8700 10900 2725
1A2 9800 9700 12100 3025
2A3 10800 10600 13500 3375
2A4 11700 11500 14500 3625
2B1 13400 13300 17400 4350
3B2 14800 14600 18800 4700
3B3 16200 16000 20900 5225
4B4 17600 17400 23100 5775
4C1 18500 18200 25100 6275
5C2 20200 19900 27800 6950
5C3 21800 12500 30000 7500
6C4 23500 23200 32500 8125
7D1 28700 28400 39400 9850
7D2 32200 31900 43700 10925
8D3 35700 35400 48000 12000
8E1 39000 38600 53100 13275
9E2 43400 43000 59100 14775
10E3 48500 48100 65600 16400
12F1 55100 44400 † 65600 19575
13F2 59700 48100 † 86000 21500
14F3 63700 50600 † 90600 22650
† When unit is shipped in two sections, maxiumum rigging weight (including skids) of lower section (evap. and abs.) is approx 75% of total
shipping weight.
NOTES:
1. All dimensions are approximate. Certified drawings are available upon request.
2. Minimum clearances are: Front 3'–0"; End opposite service clearance only requires enough room to suit piping, except for
Models YIA10E3, YIA13F3, & YIA14F3, which require 7'–0".
36 YORK INTERNATIONAL
FORM 155.16-EG1
PHYSICAL DATA
UNIT
APPROX SHIPPING APPROX OPERATING
MODEL
WEIGHT, KG WEIGHT, KG
“YIA”
TOTAL MAX. RIG. TOTAL KG/PAD
1A1 4040 3950 4950 1240
1A2 4450 4410 5500 1380
2A3 4910 4820 6130 1540
2A4 5310 5220 6590 1650
2B1 6090 6040 7900 1980
3B2 6720 6630 8540 2140
3B3 7360 7270 9490 2380
4B4 7990 7990 10490 2630
4C1 8400 8270 11400 2850
5C2 9170 9040 12620 3160
5C3 9900 9760 13620 3410
6C4 10670 10540 14760 3690
7D1 13030 12900 17890 4480
7D2 14620 14490 19840 4960
8D3 16210 16080 21800 5450
8E1 17710 17530 24110 6030
9E2 19710 19530 26830 6710
10E3 22020 21840 29790 7450
12F1 25020 16270 † 35550 8890
13F2 27110 17620 † 39050 9770
14F3 28920 18800 † 41140 10290
† When unit is shipped in two sections, maxiumum rigging weight (including skids) of lower section (evap. and abs.) is approx 75% of total
shipping weight.
NOTES:
1. All dimensions are approximate. Certified drawings are available upon request.
2. Minimum clearances are: Front 1m; End opposite service clearance only requires enough room to suit piping, except for
Models YIA10E3, YIA13F3, & YIA14F3, which require 2.2 m.
YORK INTERNATIONAL 37
Valve Selection Curve
10,000
9,000
8,000
PRESSURE DROP - PSI
7,000
LVE 6,000
VA
6"
A LVE USE 4" VALVE 5,000
4" V
4,000
LVE 3,000
3" VA
E
VALV 2 4 6 8 10 12 13
5 2 1/2" 2,000
1,000
IG
RE AM
PS
SU TE
4
ES T S
3
EXAMPLE
2
LD01890
FIG. 17 – CAGE TYPE STEAM VALVE PRESSURE DROP FOR LOW STEAM FLOW APPLICATIONS
NOTE: BUTTERFLY-TYPE STEAM VALVES MUST BE USED FOR HIGH STEAM FLOW APPLICATIONS.
38 YORK INTERNATIONAL
FORM 155.16-EG1
60 70
50
40
S
30
AS
S
4P
S
AS
AS
20 20
4P
3P
S
AS
S
AS
3P
2P
S
AS
10 2P 10
S
AS
6
S
AS
1P
5
1P
4
1 1
1000
1600
100
200
300
400
500
700
200
100
400
600
1000
1600
800
GPM GPM
LD01506 LD01509
CHILLED WATER CHILLED WATER
50
40
SS
PA
20 SS 20 3/1
PA D SS
3/1 SS ON PA
D PA S/C 2/1
ON 2/1 AB D
S/C D 10 ON
10 AB ON S/C
S/C AB
AB 7
7
ER
5 E NS
5 ER ND
S
EN CO
D 3
CON
1
200
300
400
500
600
700
1
200
300
400
500
600
700
GPM LD01511
GPM
TOWER WATER *
LD01508 TOWER WATER *
30
20
20
SS
PRESSURE DROP–FT. WATER
SS
PA
PA
3
10
10
SS
SS
PA
PA
7
2
2
5
5
S
SS
AS
PA
1P
3
2
2
1
1
90
100
200
300
400
500
90
100
200
300
400
500
GPM
GPM
HOT WATER LD01507 LD01510
* See Note on page 49. HOT WATER
YORK INTERNATIONAL 39
Pressure Drop Curves
MODEL YIA – 2A3 MODEL YIA – 2A4
80 80
60 60
S
40
AS
40
S
4P
AS
S
30
AS
4P
30 S
3P
AS
20
3P
20
S
S
AS
AS
2P
2P
10 10
S
AS
S
7
1P
7 AS
1P
5 5
4
3 3
2 2
1 1
1600
1000
100
200
300
400
500
700
1000
1600
100
200
300
400
500
700
50 60
40 SS
PRESSURE DROP–FT. WATER
SS
PRESSURE DROP–FT. WATER
30 PA PA
3/1 30 3/1
D ND
20 ON SS 20 CO SS
S/C PA BS/ PA
AB 2/1 A 2/1
D D
ON ON
10 S/C 10 S/C
AB 8 AB
7
6
5 R
ER 4 N SE
S
EN NDE
3 ND 3
CO
CO
2 2
1 1
1000
200
300
400
500
600
800
1000
200
300
400
500
600
700
800
GPM GPM
LD01514 TOWER WATER *
TOWER WATER * LD01517
30 30
20 20 SS
SS
PA
PA
3
PRESSURE DROP–FT. WATER
SS
PA
10 2
SS
10
PA
8
2
7 6 SS
PA
SS
5 1
PA
5
4
1
4
3
3
2
2
1
90
100
200
300
400
500
1
90
100
200
300
400
500
GPM
GPM LD01513
HOT WATER LD01516
* See Note on page 49.
HOT WATER
40 YORK INTERNATIONAL
FORM 155.16-EG1
80 80
60 60
PRESSURE DROP–FT. WATER
S
S
AS
AS
S
30
S
30
4P
AS
4P
AS
3P
3P
S
S
20
AS
20
AS
2P
2P
S
S
AS
10
AS
10
1P
1P
7 7
5 5
3 3
2 2
1 1
1000
2100
120
200
300
400
500
600
800
1000
2100
120
200
300
400
500
600
800
GPM LD01518 GPM LD01521
60 60
40 40
SS SS
PA 30 PA
30 3/1
3/1 D
ND SS SS ON SS
20 CO PA PA 20 S/C PA
/ /1 /1 AB /1 SS
S 2 1 2 PA
AB ND D ND 1/1
CO ON S/C
O D
10 S/ S /C 10 AB ON
AB
AB S/C
AB
7 7
5 5
4 ER
4
3 NS 3 ER
E NS
ND ND
E
2 CO 2 CO
1 1
1500
375
500
600
700
800
900
1000
1000
1100
200
300
400
500
600
700
800
GPM LD01520
GPM
LD01523
TOWER WATER * TOWER WATER *
40 40
30 30
SS
PA
SS
20 20 3
PA
PRESSURE DROP–FT. WATER
SS
PA
SS
10 10 2
PA
2
8 8
6
SS
6
SS
PA
5 5
PA
1
1
4 4
3 3
2 2
1 1
100
200
300
400
500
650
100
200
300
400
500
650
80 80
60 60
S
S
40 40
AS
AS
S
S
4P
AS
4P
AS
30 30
3P
S
3P
AS
S
AS
2P
20 20
2P
S
AS
S
AS
10
1P
10
1P
7 7
5 5
3 3
2 2
1 1
1000
2100
120
200
300
400
500
600
800
1000
2100
120
200
300
400
500
600
800
GPM GPM
LD01524 LD01527
CHILLED WATER CHILLED WATER
60 65
40 SS SS
PA 40
PRESSURE DROP–FT. WATER
/1 PA
30 D3 3/1
/CON 30
ON
D SS
S SS S/C PA
20 AB PA SS 20 AB 2/1
SS
/1 PA D PA
D 2
1/1 /CON /1
ON D S D 1
S/C ON AB ON
10 AB S/C 10 S/C
AB A B
7 7
5 5
4 ER ER
E NS 4 E NS
3 ND 3 ND
CO CO
2 2
1 1
1500
375
500
600
700
800
900
1000
375
500
600
700
800
900
1000
40 40
30 30
S
AS
20
AS
PRESSURE DROP–FT. WATER
3P
PRESSURE DROP–FT. WATER
3P
20
S
AS
S
AS
2P
2P
10
10
8
8
S
S
AS
AS
6
1P
1P
6
5 5
4 4
3 3
2 2
100
200
300
400
500
650
100
200
300
400
500
650
GPM GPM
LD01525 LD01528
* See Note on page 49. HOT WATER HOT WATER
42 YORK INTERNATIONAL
FORM 155.16-EG1
S
40
S
AS
AS
S
S
4P
30
AS
4P
30
AS
3P
3P
S
S
AS
AS
20 20
2P
2P
S
S
AS
AS
10 10
1P
1P
7 7
5 5
3 3
2 2
1 1
1000
2000
3000
200
300
400
500
600
800
1000
2000
3000
200
300
400
500
600
800
GPM GPM
LD01530 LD01533
CHILLED WATER CHILLED WATER
65 65
SS
PRESSURE DROP–FT. WATER
1 1
1000
1600
1000
2000
2200
400
500
600
700
800
900
500
600
700
800
900
GPM GPM
LD01532 LD01535
TOWER WATER * TOWER WATER *
40 40
30 30
S
S
AS
AS
20
PRESSURE DROP–FT. WATER
20
PRESSURE DROP–FT. WATER
3P
3P
S
AS
S
AS
2P
2P
10 10
8 8
S
6
AS
S
6
AS
1P
5
1P
5
4 4
3 3
2 2
1000
150
200
300
400
500
600
800
1000
150
200
300
400
500
600
800
GPM GPM
LD01531 LD01534
* See Note on page 49. HOT WATER HOT WATER
YORK INTERNATIONAL 43
Pressure Drop Curves
MODEL YIA – 5C3 MODEL YIA – 6C4
80 80
60 60
PRESSURE DROP–FT. WATER
S
AS
AS
S
S
4P
30
4P
AS 30
AS
3P
3P
S
S
AS
AS
20 20
2P
2P
S
S
AS
AS
10 10
1P
1P
7 7
5 5
3 3
2 2
1 1
1000
2000
3000
200
300
400
500
600
800
1000
2000
3000
200
300
400
500
600
800
GPM GPM
LD01536 LD01539
CHILLED WATER CHILLED WATER
65
70
SS
40 PA 50 SS
PRESSURE DROP–FT. WATER
3/1 PA
PRESSURE DROP–FT. WATER
30 D 3/1
ON SS 30 ON
D
SS
S/C PA
S/C PA
20 AB 2 /1 SS B /1
D PA 20 A 2 SS
O N 1/1 ND PA
S/C ND S /CO D 1/1
AB /CO AB ON
10 S
S/C
AB 10 AB
7
7
5
R 5 ER
4 SE 4 NS
3 D EN E
ON 3 ND
C CO
2 2
1 1
1000
2000
2200
500
600
700
800
900
500
600
700
800
900
1000
2200
GPM GPM
LD01538
TOWER WATER * TOWER WATER * LD01541
40 50
40
30
30
S
AS
S
PRESSURE DROP–FT. WATER
AS
3P
20
3P
PRESSURE DROP–FT. WATER
20
S
S
AS
AS
2P
2P
10 10
S
8
AS
8
1P
S
AS
6 6
1P
5 5
4 4
3 3
2
2
1000
150
200
300
400
500
600
800
1000
150
200
300
400
500
600
800
GPM
GPM LD01537 HOT WATER
* See Note on page 49. LD01540
HOT WATER
44 YORK INTERNATIONAL
FORM 155.16-EG1
80 80
60 60
PRESSURE DROP–FT. WATER
S
AS
AS
S
S
4P
4P
30 30
AS
AS
3P
3P
S
S
AS
AS
20 20
2P
2P
S
S
AS
AS
10 10
1P
1P
7 7
5 5
3 3
2 2
1 1
1000
2000
3000
4200
1000
2000
3000
4200
250
400
500
600
800
250
400
500
600
800
GPM GPM
LD01542 LD01545
CHILLED WATER CHILLED WATER
70 70
50 50
SS SS
PA PA
3 /1 30 L3
30 D TA
ON SS TO SS
20 BS/C PA SS 20 PA SS
A 2/1 PA L2 PA
ND 1/1 TA L1
C O D TO TA
S/ ON TO
10 AB S/C 10
AB
7 7
5 5 ER
R NS
4 E 4 NDE
D
NS ON
3 E 3 CCO
ND
CO
2 2
1 1
1000
2000
3100
1000
2000
3100
800
900
800
900
GPM GPM
LD01557
LD01544
TOWER WATER * TOWER WATER *
50
40 40
30 30
S
S
AS
AS
3P
3P
20 20
S
S
AS
AS
2P
2P
10 10
8 8
S
S
AS
AS
6 6
1P
1P
5 5
4 4
3 3
2 2
1000
1200
200
300
400
500
600
700
800
1000
1200
200
300
400
500
600
700
800
GPM LD01543
GPM LD01546
* See Note on page 49.
HOT WATER HOT WATER
YORK INTERNATIONAL 45
Pressure Drop Curves
MODEL YIA – 8D3 MODEL YIA – 8E1
80 80
60 60
PRESSURE DROP–FT. WATER
40
S
AS
AS
S
S
4P
30
4P
AS
30
AS
3P
3P
S
S
AS
AS
20 20
2P
2P
S
S
AS
AS
10 10
1P
1P
7 7
5 5
3 3
2 2
1 1
1000
2000
3000
4200
250
400
500
600
800
1000
2000
3000
4000
5500
300
400
500
600
800
GPM GPM
LD01547 LD01550
CHILLED WATER CHILLED WATER
70 70
50 SS 50
PA
PRESSURE DROP–FT. WATER
/1
D3
30 ON SS 30 SS
S/C
PA PA
AB SS /1
20 2/1 PA 20
2 SS
ND 1/1 ND PA
O D /CO 1/1
S/C ON AB
S D
AB S/C ON
10 AB 10 S/C
A B
7 7
5 R 5
4 SE 4
EN
3 ND ER
CO 3 ENS
2 ND
2 CO
1 1
1000
2000
3100
800
900
1000
2000
3000
4000
4500
GPM GPM
LD01549 LD01552
TOWER WATER * TOWER WATER *
50 40
40
30
30
S
S
AS
PRESSURE DROP–FT. WATER
AS
3P
3P
20
PRESSURE DROP–FT. WATER
20
S
AS
S
2P
AS
2P
10
AS
1P
10 8
S
AS
8
6
1P
6 5
5 4
4
3
3
2
1000
1700
300
400
500
600
700
800
2
1000
1200
200
300
400
500
600
700
800
GPM
GPM LD01548 HOT WATER LD01551
* See Note on page 49.
HOT WATER
46 YORK INTERNATIONAL
FORM 155.16-EG1
80 80
60 60
40
S
40
AS
AS
S
S
4P
4P
30
AS
30
AS
3P
3P
S
S
AS
AS
20 20
2P
2P
S
S
AS
AS
10 10
1P
1P
7 7
5 5
3 3
2 2
1 1
1000
2000
3000
4000
5500
300
400
500
600
800
1000
2000
3000
4000
5500
300
400
500
600
800
GPM GPM
LD01553 LD01494
CHILLED WATER CHILLED WATER
70 70
50 50
PRESSURE DROP–FT. WATER
1 1
1000
2000
3000
4000
4500
1000
2000
3000
4000
4500
GPM GPM
LD01555 LD01496
TOWER WATER * TOWER WATER *
50 50
40 40
30 S
SS
30 AS
PA
3P
PRESSURE DROP–FT. WATER
PRESSURE DROP–FT. WATER
20 20
SS
SS
PA
SS
PA
PA
S
2
AS
10
1
10
1P
8 8
6 6
5 5
4 4
3 3
2 2
1000
1700
300
400
500
600
700
800
1000
1700
300
400
500
600
700
800
GPM GPM
LD01554 LD01595
* See Note on page 49. HOT WATER HOT WATER
YORK INTERNATIONAL 47
Pressure Drop Curves
MODEL YIA – 12F1 MODEL YIA – 13F2
80 80
60 60
PRESSURE DROP–FT. WATER
S
AS
40
AS
3P
30
3P
30
S
S
AS
AS
2P
20
2P
20
S
AS
AS
10
1P 10
1P
7 7
5 5
3 3
2 2
1 1
1000
2000
3000
4000
5000
7000
500
700
1000
2000
3000
4000
5000
7000
500
700
GPM GPM
LD01497 LD01500
CHILLED WATER CHILLED WATER
70
50
PRESSURE DROP–FT. WATER
30 SS
PA
2/1 SS
20 D PA
ON 1/1
BS/C D
A ON
BS/C
10 A
7
5 ER
4 ENS
ND
3 CO
2
1
1500
2000
3000
4000
5000
6000
LD01499 GPM
LD01502
TOWER WATER *
50 50
40 40
S
S
AS
AS
30 30
3P
3P
20 20
S
AS
2P
S
AS
2P
10 10
S
AS
1P
SS
8 8
PA
1
6 6
5 5
4 4
3 3
2 2
1000
2000
2500
1000
2000
2500
400
500
600
700
800
400
500
600
700
800
80
60
PRESSURE DROP–FT. WATER
S
40
AS
3P
30
S
AS
2P
20
S
AS
10
1P
7
5
3
2
1
1000
2000
3000
4000
5000
7000
500
700
GPM
LD01503
CHILLED WATER
70
50
PRESSURE DROP–FT. WATER
SS
PA
30 2/1
D SS
ON PA
20 S/C 1/1
AB D
ON
S/C
10 AB
7
5 R
N SE
4
NDE
3 CO
2
1
1500
2000
3000
4000
5000
6000
GPM
LD01505
TOWER WATER *
60
50
40
S
AS
3P
30
PRESSURE DROP–FT. WATER
20
AS
2P
10
AS
1P
8
6
5
4
3 * Pressure drop curve for the condenser water circuit
2 only is shown as a dotted line. For total tower water
pressure drop through the chiller use the appropriate
1000
2000
2500
400
500
600
700
800
YORK INTERNATIONAL 49
Electrical Data
TABLE 14 – ELECTRICAL DATA
50 YORK INTERNATIONAL
FORM 155.16-EG1
YORK INTERNATIONAL 51
Guide Specifications
kW), 3-Phase TEFC motor, and all required accessories. sors, pressure transducers, and other control devices
The purge pump shall be shipped mounted on the chiller necessary to sense unit operating parameters to be
and connecting hose shall be field installed by installing factory mounted and wired to panel. The control center
contractor at the job site. panel shall include a 40 character alphanumeric dis-
play showing all system parameters in the English lan-
guage with numeric data in English (or Metric) units
LITHIUM BROMIDE AND REFRIGERANT CHARGE
(°F, PSIA, or °C, kPa, respectively).
Lithium bromide shall contain a lithium chromate corro-
sion inhibitor additive to minimize the rate of copper and The operating program shall be stored in non-volatile
ferrous metal corrosion on both the solution and refriger- memory (EPROM) to eliminate chiller failure due to AC
ant sides of the unit, even in the presence of air. power failure/battery discharge. In addition, programmed
setpoints shall be retained in lithium battery-backed RTC
memory for a minimum of 5 years.
STEAM/HOT WATER VALVE
Chiller shall be furnished with a steam or hot water con- 115V control voltage will be supplied through a 1 KVA
trol valve, linkage, and actuator motor. This assembly power transformer located in the power panel and will be
shall be shipped loose for installation by others. Valve/ factory wired to the microcomputer control panel. Termi-
linkage/actuator motor assembly to be sized by the unit nal blocks will be provided for all external safety and
manufacturer in accordance with the specified pressure control interlocks.
and flow requirements.
System Operating Information – During normal op-
The steam valve shall be a cage or butterfly type valve eration the following operating parameters shall be ac-
incorporating a cast iron or carbon steel body. The hot cessible via the microcomputer control panel:
water valve shall be a 3-way diverting type valve incor-
porating a cast iron or carbon steel body. Valve/linkage/ • Return and leaving chilled water temperatures
actuator motor assembly shall be capable of modulating • Return and leaving condenser water temperatures
steam/hot water flow in a linear fashion from 10% to 100% • Inlet steam pressure
of maximum design chiller capacity. Valve shall be • Refrigerant temperature
equipped with a minimum of 125 psig (862 kPa) ANSI • Solution temperature
flanged connections. • Solution concentration
• Indication of refrigerant/solution/purge pump operation
The actuator motor shall be 120V/1-Ph/60Hz, and shall • Operating hours Number of starts
be powered from the chiller’s MicroComputer Control • Number of Purge Cycles (last 7 days and total cumu-
Panel. Actuator motor position to be communicated to lative)
the MicroComputer Control Panel through a feedback con- • Inlet steam or hot water temperature
trol signal. • Steam or hot water valve actuator potentiometer po-
sition (in %)
• Generator shell pressure
UNIT CONTROLS
• Automatic decrystallization or hot water temperature
Each unit shall be furnished complete with a factory
mounted and pre-wired control system. Unit controls to Capacity Control – The control panel shall automati-
be furnished shall include a total of two (2) enclosures; a cally control the input steam or hot water flow rate to
power panel and a microcomputer control panel. maintain the programmed leaving chilled water setpoint
for cooling loads ranging from 10% to 100% of design.
Power Panel – The power panel enclosure shall be
The input steam or hot water flow rate shall also be manu-
NEMA 1 and shall house the following components: single
ally adjustable from the microcomputer control panel to
point wiring connection for incoming power supply; non-
any setting between minimum and maximum when auto-
fused disconnect switch; motor starters, complete with
matic operation is not desired and when steam or hot
current and thermal overload protection, for solution
water input is not being inhibited by a specific operating
pump(s), refrigerant pump, and purge pump (current over-
condition.
loads only); and a 115 VAC 50/60 Hz control power trans-
former.
Safety Shutdowns – Panel shall be pre-programmed
MicroComputer Control Center – The control panel to shut the unit down and close “safety shutdown” con-
enclosure shall be NEMA 1 and be equipped with hinged tacts under any of the following conditions:
access door with lock and key. All temperature sen-
YORK INTERNATIONAL 53
Guide Specifications
• Refrigerant or solution pump thermal or current over- Cycling shutdowns shall permit unit to automatically re-
load start when pre-programmed thresholds are reached. Fol-
• Low refrigerant temperature lowing a cycling shutdown, cycling shutdown contacts
• Generator high pressure shall close and cycling shutdown message shall be dis-
• Loss of chilled water flow played and recorded in a similar fashion as safety shut-
• Power failure (when “Automatic Restart after Power down messages.
Failure” option is not utilized)
• High inlet steam or hot water temperature Programmable Setpoints – The following parameters
• High inlet steam pressure shall be programmable directly from the key pad:
• Incomplete dilution cycle operation due to one of the
following conditions: • Leaving chilled water temperature in 0.1°F (°C) in-
• Power failure crements
• Solution/refrigerant pump overloads • Remote reset chilled water temperature range (see
• Low refrigerant temperature details below)
• Loss of chilled water flow • 7 day schedule for unit start/stop (see details below)
• External auxiliary safety shutdown • Holiday schedule for unit start/stop (see details be-
• High solution concentration low)
• Pull down demand (see details below)
All safety shutdowns will require the unit to be manually • Time clock/calendar date
restarted.
Remote Reset signal for leaving chilled water tempera-
Whenever a safety shutdown occurs, the microcomputer
ture setpoint shall be 1 to 11 second pulse width modu-
control panel shall record the following information and
lated (PWM) as standard. An optional field installed card
store it in memory (or communicate it to a remote printer):
file and card shall be available to permit the following
reset signals to be used in lieu of a 1 to 11 second PWM
• Day and time of shutdown
signal: 4-20mA DC, 0-10 VDC, contact closure.
• Reason for shutdown
• Type of restart required (automatic restart is dis-
played, manual restart is implied) 7 Day Scheduling shall permit one unit start and stop to
• All system operating information displayed just be made each day at discrete times as desired over a
prior to shutdown seven day calendar basis through the use of an integral
time clock. In addition, a separate holiday schedule shall
Warning Conditions – microcomputer control panel be programmable up to one week in advance. All major
shall close warning contacts and generate a unique warn- system components such as chilled water pumps and
ing message whenever one of the following operating condenser water pumps shall be able to be controlled
conditions is detected: from the control center panel to start and stop with the
chiller (except as required for safety shutdowns) to mini-
• Low refrigerant temperature mize system energy usage.
• High generator pressure
• High inlet hot water temperature The Pull Down Demand feature shall permit ramp load-
• High inlet steam pressure ing of input steam or hot water flow rate upon unit start-
• High entering condenser water temperature up. Programmable inputs include initial input steam/hot
• Purge pump current overload water flow rate, final input steam/hot water flow rate, and
• Faulty strong solution dilution temperature sensor duration of pull down demand period (0 to 255 minutes).
Cycling Shutdowns – Control panel shall be pre-pro- Remote Steam Limit or Hot Water Input – The remote
grammed to shut unit down whenever one of the follow- steam limit input feature shall permit the limiting of input
ing conditions is detected: steam flow rate when the unit is operating in the remote
mode at any time based upon a remote 1 to 11 second
• Loss of condenser water flow pulse width modulated (PWM) signal. An optional field
• Low leaving chilled water temperature (2°F below installed card file and card shall be available to permit
setpoint) the following remote steam or hot water demand signals
• Power failure (when “Automatic Restart after Power to be used in lieu of a 1 to 11 second PWM signal: 4-
Failure” option is selected) 20ma DC; 0-10 VDC; contact closure.
54 YORK INTERNATIONAL
FORM 155.16-EG1
Data Logging – The microcomputer control panel shall play of operator information. The single shielded cable shall
contain an RS-232 port to enable the transmission of all also allow the remote integrated DDC processor to issue
operating, setpoint, and shutdown information to a re- operating commands to the control center including but
mote printer (printer supplied by others). This transmis- not limited to the following:
sion can occur as needed or automatically at predeter-
• Remote unit start/stop
mined intervals (0.1 to 25.5 hr). In the case of a safety
• Remote chilled water temperature reset
or cycling shutdown, the RS-232 port shall transmit all
operating data detected prior to the shutdown as well as • Remote steam limit input
the time and cause of the shutdown to a remote printer The Microcomputer Control Panel shall also be capable
(printer supplied by others). In addition, a history of the of providing a limited interface to other building automa-
last four safety or cycling shutdowns and operating data, tion systems which are not provided by the chiller manu-
with the exception of power failures, shall be retained in facturer in order to permit the following operations:
memory and can be printed as well.
• Remote unit start/stop
Energy Management Interface – When connected to a • Remote chilled water temperature reset
BAS interface provided by the chiller manufacturer, the • Remote steam limit input
microcomputer control panel shall be able to communi- • Remote readout of status including:
cate all data accessible from the keypad to a remote inte- • Unit ready to start
grated DDC processor through a single shielded cable. • Unit operating
This information will include all unit temperatures, pres-
• Unit safety shutdown
sures, safety alarms, and status readouts for complete
• Unit cycling shutdown
integrated plant control, data logging, and local/remote dis-
YORK INTERNATIONAL 55
P.O. Box 1592, York, Pennsylvania USA 17405-1592 Subject to change without notice. Printed in USA
Copyright © by York International Corporation 1997 ALL RIGHTS RESERVED
Form 155.16-EG1 (597)
Supersedes: 155.16-EG1 (1096)