Pipeline Crossings
Pipeline Crossings
Pipeline Crossings
Pipeline Crossings
Version 1.0
Supporting Documents
General BMPs & Standard Project
Considerations
Regional Timing Windows
Contact List
B.C. Ministry of Environment Contacts
Fisheries and Oceans Canada (DFO) Contacts
Glossary
MOE/DFO Notification, Approval &
Authorization Instructions & Forms
Introduction
Disclaimer
Information in this document is provided for guidance only. Users must apply appropriate legisla-
tion and regulations as applicable to the works in and about a stream that are being considered. It is
strongly recommended that an appropriately Qualified Professional(s) (QP) be consulted as part of
project development. Legislation and regulations should be consulted and applied as they pertain to
your project. If a discrepancy arises between this document and legislation, the legislation takes prece-
dence. Neither the Province of British Columbia nor Government of Canada guarantee the accuracy
or completeness of the information referenced herein and in no event are liable or responsible for
damages of any kind arising from its use. Note that other legislation and regulations (e.g., municipal)
may also apply to such activities and should be consulted.
The following five (5) steps will help guide you through the provincial and federal Notification, Approval
and/or Authorization process for Pipeline Crossing Construction or Maintenance works:
Step
1
Step
2
Step
Step
4
Step
5
Pipeline Crossings – Standards and Best Practices for Instream Works 3
How to proceed with your Pipeline Crossing Project
3 • pipeline and associated works are installed in a dry stream channel at a depth
so that the top of the pipe is at least 1 m below the lowest elevation of the
Addendum bed of the stream; and,
• the crossing is constructed in accordance with the requirements prescribed
in paragraph 44(b) of the Water Act for clear span crossings in the case of an
aerial crossing:
-- the crossing and approach roads do not produce a backwater effect
or increase the head in the stream;
-- equipment used for construction, including site preparation,
maintenance or removal of the crossing, is situated in a dry stream
channel or operated from top of bank;
-- the hydraulic capacity of the crossing is equivalent to the hydraulic
capacity of the stream channel or is capable of passing the 1 in 200
year maximum daily flow and that, for suspended pipelines the
height of the underside of the crossing is also adequate to provide
free passage of flood debris and ice flows; and,
-- crossing materials meet the standards of the Canadian Standards
Association, as applicable.
Step
The following Best Management Practices (BMPs) are methods, that if followed, will
4 help ensure your project minimizes potential impacts to fish and fish habitat and will
provide a standard level of protection to the aquatic and terrestrial environment poten-
tially affected by your project.
It is the responsibility of the proponent/developer to ensure that they are in compliance with all applicable
legislation.
To reduce impacts on fish and wildlife habitats and populations, your Pipeline Crossing construction and
maintenance activities must consider:
Operational
PL08 install effective erosion and sediment control measures prior to works to prevent entry
of sediment into the watercourse and inspect these measures regularly during the course
of construction to ensure they are functioning properly. Make all necessary repairs if any
damage occurs or effectiveness is compromised;
PL09 avoid disturbing the bed and banks of the stream by ensuring operational activities and set
up remain outside the bankfull width of the stream;
PL10 minimize right-of-way clearing by limiting impacts to on-site and adjacent riparian areas
and only work where using directional drilling setbacks from shore. Use existing trails,
roads or cut lines as access routes to avoid disturbance to the riparian vegetation, wherever
possible;
A. Directional Drilling
Design
PL12 conduct geotechnical evaluations for directional drilling and boring operations where
channel and surficial morphology indicate a high risk of crossing failure (e.g. known debris
or buried construction material);
PL13 design the drill path to an appropriate depth below the watercourse to minimize the
risk of frac-out and prevent the line from becoming exposed due to natural scouring of
the stream bed;
PL14 locate drill entry and exit points far enough from the banks of the watercourse to minimize
impact on these areas;
PL15 develop a frac-out response plan that includes measures to stop work, contain drilling mud,
prevent further migration into the watercourse and notify all applicable authorities;
Operational
PL16 ensure operators do not remove riparian vegetation between drill or bore entry and exit
points in preparation of trenchless stream crossing operations;
Operational
PL31 ensure operators do not remove riparian vegetation between drill or bore entry and exit
points in preparation of trenchless stream crossing operations;
PL32 excavate bell holes beyond the top of bank, a minimum of 30 m from any watercourse
to preserve riparian vegetation and allow containment of any sediment or deleterious
substances;
PL33 treat water and divert uncontaminated water into a vegetated area or settling basin to
remove suspended solids and prevent sediment and other deleterious substances from
entering the watercourse, when dewatering bell holes;
PL34 stabilize any waste materials removed from the work site (including bell holes) above the
ordinary high water mark (HWM), to prevent them from entering any watercourse;
PL35 contain spoil piles with silt fence and ensure it is compacted, covered with biodegradable
mats or tarps and/or plant native grass or shrubs;
PL36 monitor the watercourse to observe signs of malfunction during all phases of the
work;
PL37 keep on-site and readily accessible all material and equipment needed to contain and
clean up releases of sediment-laden water and other deleterious substances for the
duration of the work;
Operational
PL39 ensure sediment or other deleterious substance(s) do not enter any watercourse as a
result of open cut pipeline construction or maintenance activities;
PL40 install open cut pipeline stream crossings in naturally dry stream channels (no water
flow present) or in isolation of any stream flow to prevent downstream sedimentation.
If dewatering, water diversion hoses must be screened as per the Freshwater Intake
End-of-Pipe Fish Screen Guideline (DFO, 1995) and MOE Temporary Diversion
works Standards and BMPs must be applied.
PL41 fish salvage, where fish are present in any part of the watercourse, is necessary prior
to dewatering during Temporary Diversion activities. An appropriately Qualified
Professional(s) must complete the salvage and acquire necessary collection permits
from MOE and DFO and comply with applicable regulations and legislation;
PL42 pump wastewater from project dewatering activities to stable, well-vegetated areas
above the high water mark (HWM) of the stream so that fine sediment and other
particulate matter can settle out prior to re-entry into the watercourse. These locations
must be monitored to ensure that neither erosion nor icing occur;
PL43 all instream pumps should have capacities that exceed expected flows and backup pumps
and generators must be on site and operational should they be required;
PL44 maintain natural stream flows upstream and downstream of the worksite during the
construction period;
PL45 limit disturbance of the streambed and banks to that necessary to place the pipeline;
PL46 place any materials generated from the open cut pipeline construction or maintenance
activities outside the riparian area of the stream to prevent bank erosion and sedimentation
of the watercourse during spring melt or periods of increased precipitation;
PL47 backfill excavated sites with appropriate, compacted fill material. Do not backfill with
vegetation, debris or mud;
General Considerations
Pacific Region Operational Statements
http://www-heb.pac.dfo-mpo.gc.ca/decisionsupport/os/operational_statements_e.htm
Develop with Care: Environmental Guidelines for Urban and Rural Land Development
in British Columbia
http://www.env.gov.bc.ca/wld/documents/bmp/devwithcare2006/DWC%202006%20Sec%201%20Introducti
on.pdf
Land Development Guidelines for the Protection of Aquatic Habitat (Section 5 and 6)
http://www-heb.pac.dfo-mpo.gc.ca/publications/pdf/165353.pdf
Pipeline-Stream Crossings
http://www.wildsalmoncenter.org/pipeline-stream-english.pdf
Guide to the Code of Practice for Pipelines and Telecommunication Lines Crossing a
Water Body, Including Guidelines for Complying with the Code of Practice
http://www3.gov.ab.ca/env/water/Legislation/CoP/PipelineGuide.pdf
Step
If you determine that your project requires notification and/or approval from MOE or DFO,
5 please ensure that MOE and/or DFO application instructions are followed and forms com-
pleted and sent to the appropriate agency.
The latest application instructions and forms for MOE and DFO can be found at
http://www.env.gov.bc.ca/wld/BMP/