Sample Bom
Sample Bom
and Construction
Renovations/Improvement, Property Management
November 19, 2022
I. Title of the Project / Work
2 Storey Residential
Cagayan Valley
II. Work to be accomplished
A. Tarpaulin
B. Mobilization and Temporary Structures
C. Earth Works
D. Reinforced Concrete
E. Trusses and Roofings
F. Doors and Windows
G. Painting Works
H. Plumbing Works
I. Electrical Works
J. Tile Works
K. Staging and Scaffolding
L. Formworks
M. Clearing & Demobilization
N. PPE
III. Bill of Materials
d.3. Concrete Slab and Slab on Fill
40 kgs. Portland cement bags 265 290.00 116.00 76,850.00 30,740.00 107,590.00
fine sand cu.m. 23 950.00 380.00 21,850.00 8,740.00 30,590.00
gravel 3/4" cu.m. 39 1,350.00 540.00 52,650.00 21,060.00 73,710.00
12 mm dia. RSB pcs 479 215.00 86.00 102,985.00 41,194.00 144,179.00
# 16 tie wires kgs. 29 65.00 26.00 1,885.00 754.00 2,639.00
Sub Total 256,220.00 102,488.00 358,708.00
d.4. Girders, Beams, Roof and Cantilever Beams
40 kgs. Portland cement bags 167 290.00 116.00 48,430.00 19,372.00 67,802.00
fine sand cu.m. 12 950.00 380.00 11,400.00 4,560.00 15,960.00
gravel 3/4" cu.m. 13 1,350.00 540.00 17,550.00 7,020.00 24,570.00
16 mm dia. RSB pcs 193 380.00 152.00 73,340.00 29,336.00 102,676.00
10 mm dia. RSB pcs 188 150.00 60.00 28,200.00 11,280.00 39,480.00
# 16 tie wires kgs. 35 65.00 26.00 2,275.00 910.00 3,185.00
Sub Total 181,195.00 72,478.00 253,673.00
d.5. Concrete Gutter, Canopy and Stair
40 kgs. Portland cement bags 94 290.00 116.00 27,260.00 10,904.00 38,164.00
fine sand cu.m. 3 950.00 380.00 2,850.00 1,140.00 3,990.00
gravel 3/4" cu.m. 9 1,350.00 540.00 12,150.00 4,860.00 17,010.00
12 mm dia. RSB pcs 162 210.00 84.00 34,020.00 13,608.00 47,628.00
10 mm dia. RSB pcs 54 150.00 60.00 8,100.00 3,240.00 11,340.00
# 16 tie wires kgs. 15 65.00 26.00 975.00 390.00 1,365.00
d.6. Masonry works with Plastering Sub Total 85,355.00 34,142.00 119,497.00
I. DIRECT COST
a.) MATERIALS 2,276,217.00
b.) LABOR 737,497.20
3,013,714.20
II INDIRECT COST (OCM) 210,959.99
III PROFIT 301,371.42
IV TOTAL CONSTRUCTION COST (I+II+III) 3,526,045.61
Prepared by:
NAME OR ARCHITECT/ENGR
Architect/engineer/contractor
Approved:
NAME OF OWNER
Owner