Hydraulic Structure Handout (Complete)
Hydraulic Structure Handout (Complete)
Hydraulic Structure Handout (Complete)
1.1. INTRODUCTION
Def: A dam is a barrier constructed across a river or a natural stream to create a reservoir for
impounding water (for irrigation, water supply, flood protection), or to facilitate diversion of
water from the river, or to retain debris flowing in the river along with water.
The construction of dams ranks the earliest and most fundamental of civil engineering activities.
All great civilizations have been identified with the construction of storage reservoirs appropriate
to their needs, in the earliest instances to satisfy irrigation demands arising through the
development and expansion of irrigated agriculture.
Examples:
1. Dam built at Sadd-el-kafara(Egypt, around 2600 B.C.) the oldest known dam
Height 14m
Construction - Earthfill central core
- Rock shoulders
- Rubble masonry face protection
Breached - probably due to flood over topping after a relatively short
period of service.
2. Marib embankment dam – (Yemen, completed around 750 B.C.)
Height- 20m
Purpose – for Irrigation
Others were also constructed in Middle and Far East countries
Dams are individually unique structures. Irrespective of size and type they demonstrate great
complexity in their load response and in their interactive relationship with site hydrology and
geology. In recognition of this and reflecting the relatively intermediate nature of many major
design inputs dam engineering is not a stylized and formal science. As practiced it is a highly
specialist activity which draws up on many scientific disciplines and balances them with a large
element of engineering judgment; dam engineering is a uniquely challenging field of endeavor.
i) Storage Dams
Storage dams are constructed to create a reservoir to store water during the periods when the
flow in the river/stream is in excess of the demand, for utilization later on during the period when
the demand exceeds the flow in the river/stream.
1
ii) Detention Dams
Constructed to temporarily detain all or part of flood water of a river and gradually release the
stored water at controlled rates so that the entire region on the d/s side of the dam may be safe
guarded against the possible damage due to floods. Detention dams are also constructed to trap
sediment. Theses are often called debris dams.
i) Overflow Dams
They are designed to pass the surplus water over their crest. They must be made of materials
which will not be eroded by such discharges.E.g. Concrete, masonry etc…
i) Rigid dam
It is a dam constructed from rigid materials such as masonry, concrete, etc…Examples are
Gravity, arch and buttress dams.
Concrete gravity Dam: Resists the forces exerted up on it by its own weight. Its cross section is
approximately triangular in shape.
Arch Dam: Is a curved concrete dam, convex u/s, which resists the forces exerted up on it by
arch action. It is structurally more efficient than the gravity or buttress dams, greatly reducing the
volume of concrete required.
Buttress dam: It consists of water retaining sloping membrane or deck on the u/s which is
supported by a serious of buttresses or counter forts. The sloping membrane is usually R.C.slab.
In general the structural behavior of buttress dam is similar to that of gravity dam. It may be
considered as a lightened version of gravity dam.
A dam which is constructed from non-rigid materials such as earth, rockfill etc…. are called non-
rigid dams. Earthfill and rockfill dams are non-rigid dams. They are usually called embankment
dams.
2
Earthfill embankments: An embankment may be categorized as Earthfill dam if
compacted soils account for over 50% of the placed volume of material.
Rockfill embankments: In rockfill embankment the section includes a discrete impervious
element of compacted Earthfill or a slender concrete or bituminous membrane. The
designation ‘rockfill embankment’ is appropriate where over 50% of fill material may be
classified as rockfill, i.e. course grained frictional material.
It is rare that for any given site only one type of dam is suitable. It is only in exceptional
circumstances that the experienced designer can say that only one type of dam is suitable or
most economical. Thus, it would be necessary to prepare preliminary designs and estimates
for the several types of dams before one can get the best solution from the point of view of
direct costs and all other factors. Some the physical factors which affect the choice of the
type of dam are discussed below.
1.3.1. TOPOGRAPHY
Topography dictates the first choice of the type of dam and the most important factor in this
respect is the shape of the valley.
i. A narrow V-shaped valley with sound rock in abatements has an arch dam as the first
choice. However, for economic arch dam it is preferable to have the top width of the
valley less than about four times its height. It is also suitable for rockfill dam.
ii. A narrow or moderately wide U-shaped valley with sound rock foundation is best
suited for gravity or buttress dam.
iii. Wide valley with foundation of soil material to a considerable depth (deep over
burden) favor Earthfill embankment dam.
The foundations have to carry the weight of the dam. The dam site must be thoroughly
surveyed by geologists, so as to detect the thickness of the foundation strata, presence of
faults, fissured materials, and their permeability, slop and slip etc…
The common types of foundations encountered are:
Because of high bearing capacity and resistance to erosion and percolation, any type of dam
can be built on such foundations. However, the choice of the type of dam will be governed
by economy of materials or overall cost. The removal of disintegrated rock together with the
sealing of seams and fractures by grouting will frequently be necessary.
3
ii. Gravel Foundations (and course sand)
If well compacted such foundations are suitable for earthfill, rockfill and low concrete
gravity dams (<15m). As these foundations are frequently subject to water percolation at high
rates, special precautions must be taken to provide effective water cut offs or seals.
These foundations suggest the adoption of earth dams or very low gravity dams (up to 8m
high), but they are not suitable for rockfill dams. The main problems are settlement, the
prevention of piping, excessive percolation losses, and protection of the foundation at the d/s
toe from erosion.
Clay foundations are can be used to support Earthfill dams after special treatment to
consolidate clay. Since there may be considerable settlement, if the clay is unconsolidated
and the moisture content is, clay foundations ordinarily are not suitable for the construction
of concrete gravity dams, and should not be used for rockfill dams. Tests of the foundation
material in its natural state are usually required to determine the consolidation characteristics
of the material and its ability to support the supper imposed load.
At certain places, a uniform foundation of the types described above may not be available. In
such a case, a non uniform foundation of rock and soft material may have to be used if the
dam is to be built. Such unsatisfactory conditions have to be dealt with by special designs or
appropriate foundation treatment.
The spillway is a vital appurtenance of dam. Frequently its size, type and natural restrictions
in its location will be the controlling factors in the choice of the type of dam. Spillway
requirements are dictated primarily by the runoff and stream flow characteristics,
independent of site conditions or type of dam. The selection of a specific spillway types will
be influenced by the magnitudes of the floods to be bypassed. Thus, it can be seen that, on
4
streams with large flood potential, the spillway selection of the type of dam could become a
secondary consideration.
The cost of constructing a large spill way is frequently a considerable portion of the total cost
of the development. In such cases, combining the spillway and dam in to one structure may
be desirable, indicating the adoption of a concrete overflow dam.
In certain instances, where excavated material from separate spillway channel may be
utilized in dam embankment, an earthfill dam may prove to be advantageous. Small spillway
requirements often favor the selection of earthfill or rockfill dams, even in narrow dam sites.
1.3.5 ERATHQUAKE
If the dam lies in area that is subject to earthquake shocks, the design must include provisions
for the added loading and increased stresses. Although by including the provisions for the
added loading due to earthquake in the design of any type of dam may be adopted in these
areas. Earthfill and concrete gravity dams are the best suited types in this respect.
Dam site investigation requires careful planning and a considerable investment of time and
resources. Where possible, in situ and field test techniques should be employed to
supplement laboratory testing progarmmes. Proper interpretation of geological and
geotechnical data demands the closest cooperation between the engineering geologist, the
geotechnical specialist and the dam engineer.
Extensive investigations are conducted to confirm that, the site can be developed on the
desired scale and at acceptable cost. The nature of soil and rock formations present, critical to
foundation integrity must be proved by subsurface exploration. Foundation competence is
determined by stability, load carrying capacity, deformability, and effective impermeability.
All are assed in relation to the type and size of dam proposed.
In the case of a difficult site, the site evaluation programme can be protracted and expensive.
Expenditures may be of the order of 1% up to, exceptionally, 2.5 or 3% of the anticipated
cost of the dam. The scope of individual aspects of an investigation reflects circumstances
unique to the site.
In parallel with these investigations, extensive and detailed surveys are required to establish
the location and extent of potential sources of construction materials in reasonable proximity
to the site.
Generally site investigation may be broadly classified under three categories, viz
5
i) Reconnaissance
ii) Preliminary investigation
iii) Final investigation
Reconnaissance: Involves visiting all available sites which have a possibility of being
utilized and gathering information which will be useful for planning the detailed surveys and
investigations. The information to be collected may include geological data without any kind
of subsurface exploration, approximate estimate of stream flow data, storage capacity and
head available, etc….
a) Less precise site survey with the resulting topographic site map
b) Some investigation of the overburden
c) Few borings, say from 6 to 50, according to the size of the dam
d) Preliminary geologic investigation and corresponding report
e) Investigations of construction materials, e.g. earth, gravel, concrete aggregate etc…
f) Determination of public utilities such as road, telephone lines etc… that may be
affected by the construction of the dam
g) Hydrologic studies
h) Determination of sediment load of the stream
i) Checking of high water marks for their use in determining spillway capacity
requirements.
Final Investigation: One of the several possible dam sites investigated in preliminary
investigation is elected for final, precise investigation. Final investigation involves the
following items.
a) Sufficiently precise site survey and preparation of topographic maps to serve all
purposes of design and construction of the dam
b) Accomplishment of necessary borings, test pits subsurface explorations, geologic
studies and tests on the materials in foundation and in the proposed borrow lands.
c) Determination of the type of dam to be constructed
d) Planning for the foundation treatment on the basis of subsurface investigation
e) Determination of the extent of land which would be submerged in the reservoir
and the arrangements for rehabilitation of the residents of that area.
f) Obtaining sufficient information for accurate estimate of cost
g) Determination of the final location of the dam, construction equipment, labor and
other staff members, probable source of construction materials and all other
information needed to the construction Engineer.
It may, however, be mentioned that there is no distinct line of demarcation between the
preliminary and the final investigations of dam sites.
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
6
II GRAVITY DAM
A concrete gravity dam is entirely dependent up on its own weight (mass) for stability. The
gravity profile is essentially triangular to ensure stability and to avoid over-stressing of the
dam or its foundation. A gravity dam is mostly straight in plan and thus known as straight
gravity dam. However, in some cases it may be curved in plan (slightly).
In plan the axis of the dam is defined as the horizontal trace of the u/s edge of the top of the
dam and it is also called the BASE LINE OF THE DAM. In the cross section of dam the
vertical line passing through the u/s edge of the top of the dam is considered as the axis of the
dam.
The length of the dam is the length measured along the axis of the dam at the top of the dam
from one abutment to the other abutment.
The maximum base width of the dam is the horizontal distance the outer points of the heel
and the toe of the cross section of the dam.
The maximum height of the dam or structural height of dam is the vertical distance between
the lowest point in the foundation and the top of the dam.
The first consideration in designing a dam is the determination of the forces acting on the
structure. These forces may be considered as consisting of the following:
I. PRIMARY FORCES: These are of major importance to all dams, irrespective of type.
They are:
1. Water pressure
2. Self weight of dam
3. Uplift(seepage) pressure
II. SECONDARY FORCES (or LOADS): are universally applicable although of lesser
magnitude, or alternatively, are of major importance only to certain types of dams (e.g.
thermal effects with in concrete dams). They include:
III. EXCEPTIONAL FORCES (or LOADS): They have limited general applicability or
have a low probability of occurrence. They are:
1. Earthquake(or seismic) forces
7
Fig 1 Schematic of principal forces on gravity dams
WATER PRESSURE: Water pressure is the major external force acting on gravity dam.
When the u/s face is vertical its intensity is zero at the water surface and equal to H at
the base. The resultant force due to this pressure is
FH
FH’
8
SELF WEIGHT OF DAM: The weight per unit length of the dam is given by the
product of the area of cross section of the dam and the unit weight of the construction
material, i.e., concrete or stone masonry, and it acts vertically downwards at the centeroid
of the cross sectional area, Ap, of the dam profile.
Pm = Ap [kN/m]
= Unit weight of concrete, assumed as 23.5 KN/m3
For a gravity dam the weight of the dam is the main stabilizing force, and hence the
construction material should be as heavy as possible. Thus in order to get heavier, the
course aggregate should have greater specific gravity.
UPLIFT (OR SEEPAGE) FORCE: Is the force exerted by the water penetrating
through the pores, cracks and seams with in the body of the dam, at the contact between
the dam and its foundation, and with in the foundation.
It acts vertically upwards at any horizontal section of the dam as well as its foundation
and hence causes a reduction in the effective weight of the portion of the structure lying
above this section.
The percentage of area on which the uplift pressure acts is defined as the area factor, η.
Several investigations have been made and some of the earlier investigators
recommended, for both concrete and rock, a value of area factor ranging from 1/3 to 2/3,
i.e. only 1/3 to 2/3 of the area may be considered as effective area over which the uplift
pressure acts.
A’h = ηAh ( A’h = effective area)
However, Terzaghi and Leliavsky, have indicated that, for both concrete and rock, the
value of area factor is nearly unity. As such the present practice in dam design is that the
up lift pressure is assumed to act over 100% of the area with in the body of the dam and
its foundation (i.e., η = 1).
Uplift pressure can be reduced by forming drains through the concrete of the dam and by
drilling drainage holes in to the foundation rock. In modern dams internal up lift is
controlled by the provision of vertical relief drains close behind the u/s face. Formed
drains raise the full height of the dam from an inspection gallery located as low as
practicable in relation to the tail water level.
At the line of drains, in the body of the dam as well as the contact plane between the dam,
and its foundation and with in the foundation, uplift pressure is assumed to have an
intensity, Pdu, equal to
9
Fig 3 Internal up lift and assumed pressure envelopes
The uplift pressure at the contact of the dam with the foundation may also be reduced by
constructing a cut off wall or grout curtain close to the u/s face of the dam and extending
it for considerable depth in the foundation. The reduction in the up lift pressure intensity
due to the provision of the cut off wall is expressed in terms of intensity factor. The
intensity factor is the ratio of the actual intensity of uplift pressure developed when cut
off wall is provided to the intensity of up lift pressure, which would be developed with
out cut off wall. The values of intensity factor ( ) given in table 1 may be used with
judgment. However, in designs of dams theses reduction factor are generally disregarded
or are considered to be unity. This is because:
10
Height of Dam** Type of rock foundation Grouting and
Drainage
Moderate Horizontally stratified None 1.00
-Do- Fair, Horizontally stratified Yes 0.67
High - Do- -Do- 0.75
Moderate Good, Horizontally stratified -Do- 0.5
High -Do- -Do- 0.67
Moderate Fair, massive None 0.67
-Do- -Do- Yes 0.50
High -Do- -Do- 0.67
Moderate Good, massive None 0.50
-Do- -Do- Yes 0.50*
High -Do- -Do- 0.50
and acts at h/3 from the bottom of deposit. = - where is the sediment
WAVE PRESSURE AND HEIGHTS: The upper portions of dams are subject to the
impact of waves. The magnitude of the wave pressure mainly depends on the dimensions
of waves, which in turn depend on the extent, configuration of the water surface, the
velocity of wind and the depth of water in the reservoir. Knowledge of wave height is
important if overtopping wave splash is to be avoided. The most significant dimension of
wave is the height of the wave in terms of which the wave pressure exerted on the dam
can be expressed.
11
Wave height may be determined (Moliter) by the following formula:
Pw = 2.4
= 23.544 [kN/m2]
The wave pressure diagram is of a curvilinear form which for present purposes may be
approximately represented by the triangle 1-2-3 in fig 4.
The total pressure Pw per unit length of the dam is given by the area of the triangle 1-2-3
and given by
[KN/m]
Its center of application is above the still water surface at height 3/8 (or 0.375 )
12
ICE PRESSURE: Ice load can be introduced in circumstances where ice sheets form to
appreciable thickness and persist for lengthy periods. In such situations, ice pressure may
generate a considerable horizontal thrust near crest level.
An acceptable initial provision for ice load, Pice, where considered necessary is given by
Pice = 145kN/m2 for ice thickness in excess of 0.6m (USBR, 1976). Where ice thicknesses
are unlikely to exceed 0.4m and/or will be subject to little restraint, as on sloping face ,
ice load may be neglected.(Contraction and expansion due to change in temperature
causes ice pressure).
WIND PRESSURE: Wind pressure is seldom a factor on the design of dams. Such
structures are usually in sheltered locations. Even in exposed locations, the wind has
access to only the d/s face of a loaded dam. The maximum possible pressures are small
when compared to the loads for which the dam is designed, and it acts against the water
load. The superstructure of dams carrying very large sluice gets may need to be
proportioned to resist wind loads of 1 kN/m2 to 1.5 kN/m2.
Due to the horizontal acceleration imparted to the foundation and dam the following two
forces act on the dam.
i. Inertia force
ii. Hydrodynamic pressure
13
Under reservoir full conditions the most adverse seismic loading will occur when the
ground shock is associated with foundation acceleration operating upstream, i.e. form d/s
to u/s. This will cause the inertia force to act on the dam in the direction from u/s to d/s.
However, for reservoir empty conditions the acceleration in the direction from u/s to d/s
would produce the worst combination. In general, the inertia force is equal to the product
of weight of the dam and seismic coefficient.
[kN/m]
And the inertial force is considered to operate through the centeroid of the dam section.
Due to horizontal acceleration the foundation and dam are accelerated either towards the
reservoir or away from it depending on the direction of the acceleration being from u/s to
d/s or vice versa. However, this movement of the dam is restricted by the water in the
reservoir owing to its inertia, on account of which there is an instantaneous
hydrodynamic pressure (or suction) exerted on the dam. The direction of hydrodynamic
pressure is opposite to the direction of earthquake acceleration.
For dams with vertical or sloping u/s faces, the hydrodynamic pressure, p e, in kN/m2, at
any elevation y below the water surface is given by the following equation. (Ref Fig 5)
14
Fig 5 Hydrodynamic pressure and inertia forces
The value of the coefficient C may be obtained for dams with u/s face either vertical or
having constant slope for the entire height by the following expression:
Where Cm = maximum value of C for a given constant slope of the face of the dam
y = depth of horizontal section under consideration below the water surface
in the reservoir, m
Value of Cm may be obtained from a plot of Cm Vs , where is the angle (o) that the
face of the dam makes with the vertical. However, approximate value of Cm may be
calculated from:
For dams with u/s face partly vertical and partly sloping the value of C may be obtained
as follows: (Ref Fig 6).
a) If the height of the vertical portion of the u/s face of the dam is equal to or greater
than half of the total height of the dam, then the entire face is considered as
vertical.
b) If the height of the vertical portion of the u/s face of the dam is less than half of
the total height of the dam, then the slope of the u/s face is considered to be equal
to the slope of the line joining the point of intersection of the u/s face of the dam
and the water surface in the reservoir; and the point of intersection of the u/s face
of the dam and foundation (i.e. the heel of the dam).
Fig 6
The total hydrodynamic force, Pe, above any elevation y distance below the reservoir
surface, and the resulting total overturning moment, Me, above the elevation are given by:
15
The corresponding values of Pe and Me for the dam above its base may be obtained by
substituting h for y as
The hydrodynamic pressure acts normal to the face of dam. As such if the u/s face of the
dam is sloping, then it will have horizontal and vertical components. The horizontal
component is given by equation:
The vertical component for part of the dam above a horizontal section x-x at a depth y
below the water surface is given by:
Pe1 = horizontal component of total hydrodynamic pressure for a part of the dam at a
horizontal section at which the slope of the face commences;
= Angle between face of dam and vertical
Under reservoir full condition the most adverse seismic loading will occur when the ground
shock is associated with vertical acceleration operating downwards. Foundation acceleration
downwards will effectively reduce the mass, and hence the stability of the structure. The inertia
force is exerted on the dam as well as the water in the reservoir in the direction opposite to that of
acceleration.
If W is the weight per unit length of the dam and is the vertical seismic coefficient then
the inertia force exerted per unit length of the dam is given by:
Thus for an upward acceleration the inertia force P emv would be acting downwards and hence it
would result in an increase in the weight of the dam from W to W (1+ ). On the other hand,
if the acceleration is acting downwards, the inertia force Pemv would be acting upwards
which would result in reduction of the weight of the weight of the dam from W to W (1-
). Similar expressions may be obtained for water in the reservoir.
16
It is commonly assumed that = (1.5 – 2.0) for the purpose of analysis.
Representative seismic coefficients, , applied in design are listed in table 2.
Table 2 Seismic acceleration coefficients,
Coefficient Modified General damage
Mercalli Scale Level
0.0 - Nil
0.05 VI Minor
0.10 VII Moderate
0.15 VIII-IX Major
0.20 Great
Note that uplift pressure is normally assumed to be unaltered by seismic shock. This is so
because the duration of the earthquake is too short to permit the building up of pore
pressure in the concrete and rock foundation.
A concrete gravity dam should be desired with regard to the most rigorous adverse
groupings or combinations, which include transitory loads of remote probability, and
therefore have a negligible livelihood of occurrence in service, are not considered a valid
basis for design. Such combinations may be investigated when verifying the design of the
most important dams, but are generally discounted in the analysis of lesser structures.
The design of gravity dam should be checked for two cases, i.e.,
USBR has classified the ‘Normal Load Combinations’ and ‘Extreme Load Combinations’
as below.
17
Case II Empty Reservoir
A concrete gravity dam must be designed to resist, with ample factor of safety. There
are three tendencies of destruction.
1. Rotation or overturning
2. Translation or sliding
3. Overstressing or material failure
OVERTURNING STABILITY
The overturning of the dam section takes place, if tension is ignored; when the
resultant force at any section cuts the base of the dam d/s of the toe. The factor of
safety with respect to overturning can be expressed in terms of the moments about the
d/s toe of any horizontal plane. The factor of safety against overturning is defined as
the ratio of the summation of all restoring forces/moments (i.e. positive) to the
summation of all overturning moments (i.e. negative).
Values of F.S. in excess of 1.25 may generally be regarded as acceptable, but F.S.
should not be less than 1.5 (i.e. F.S.> 1.5 is desirable.)
SLIDING STABILITY
A dam will fail in sliding at its base, or any other level, if the horizontal force causing
sliding are more than the resistance available to it at that level. The resistance against
sliding may be due to friction alone, or due to friction and shear strength of the joint.
The planes of weaknesses are the necessary horizontal construction joints, including
the joint at the base. The shearing and frictional resistance of the joint must be
sufficient to with stand the tendency to slide.
If the shear strength is not taken in to account, the factor of safety is known as factor
of safety against sliding. If is the summation of all the horizontal forces
18
causing the sliding and are sum of the all vertical forces, factor of safety
against sliding is given by:
If f represents the coefficient of static friction of the material above and below the
joint, will be frictional resistance to sliding. For equilibrium, >
resultant. Values of f for masonry on masonry and masonry on rock foundation varies
b/n 0.6 and 0.75; F.S. >1.
It is considered that a low gravity dam should be safe against sliding considering
friction alone. However in large dams, shear strength of the joints should also be
considered for an economical design. The factor of safety in this case is, therefore,
known as Shear Friction Factor (S.F.F.) and is defined by the equation
OVERSTRESSING
A dam may fail if any of its part is overstressed and hence the stresses in the dam
should be with in the specified limit (allowable working stresses) for the dam body
and in the foundation.
The stresses at any point at the base of the dam or with in the dam body can be
obtained from the following equation.
19
Positive sign is used to calculate normal stress at the toe.
Negative sign is used for calculating normal stress at the heel.
20
Fig 7 Normal stress distribution at the base
Evidently, the maximum compressive stress occurs at the toe and for safety this
should not be grater than allowable compressive stress ( ) all the foundation
material; i.e.
Concrete gravity dams are usually designed in such a way that no tension is
developed anywhere; since concrete cannot withstand sustained tensile stresses.
Hence, the maximum value of eccentricity that can be permitted on either side of
the center is equal to B/6; which leads to the famous statement:
21
Fig 8 Principal stresses at the toe and heel of gravity dam.
The stress intensities are assumed to be uniform on the faces of the element.
Since the tail water pressure acts normal to the face and there is no shear
stress, BA is a principal plane. Since principal planes are at right angles to each
other BC is perpendicular to AB.
22
For to be maximum, should be zero, i.e. no tail water and
=
Since is always more than 1 will be greater than
Therefore, this maximum normal stress produced anywhere in the body of the
dam must be calculated and compared with the allowable compressive stress.
= =
Where, is the angle the u/s face makes with the vertical.
P and Pe are water pressure and hydrodynamic pressure respectively
But at the heel, water p[pressure P is always more than and hence P will be
the major principal stress and is the minor principal stress.
A shear stress also acts on plane AC. No shear stress on AB and BC (principal
planes). Resolving all forces in the horizontal direction, we get
The elementary profile of a gravity dam, subjected only to the external water
pressure on the u/s side will be a right angled triangle, having zero width at top
water level and a base width B at the bottom.
23
Fig 10 Elementary profile of a gravity dam
For reservoir empty condition the elementary profile provide the maximum possible
stabilizing force against overturning w/o causing tension in the base. This is so
because the weight of the dam (the only force) acts at a distance B/3 from u/s
face.
Considering the elementary profile of the gravity dam (fig. 10) of height H and
base width B;
i. Weight of dam,
24
ii. Water Pressure,
For no tension at any point in the base of the dam, the resultant must pass through the
middle third of the base.
Thus for reservoir full condition the outer middle third point A is the limiting position of
the point at which the resultant may meet the base for no tension at any point in the base
of the dam. Thus taking moments of all forces about A, and equating it to zero, we get;
…………..(a)
Hence, if B is taken equal to or greater than , then no tension will develop at the
heel (full reservoir).
When = 1 (usually ) ……. Full uplift is considered.
For no sliding to occur, the force resisting sliding must exceed the force causing sliding
and in the limiting case these forces must be equal. Assuming sliding is resisted only by
friction, and then the force resisting sliding is equal to f(W-Pu) and the force causing
sliding is equal to P and in the limiting case we have;
25
………………(b)
Therefore, the minimum base width to be provided for the elementary profile of a gravity
dam should be the greater of the base widths given by equations (a) and (b).
Limiting Height of Elementary Profile of Gravity Dam- High and Low Gravity
Dams
In the limiting case of no tension at any point in the base of the dam, e = B/6, and hence
Therefore, ………………………………(c)
26
Equation (d) shows that the value of varies only with H as all the other terms are
constant for any dam. In order to avoid failure of the dam, due to crushing the value of
(at toe) should not exceed the allowable working stress fall for the dam material and
the limiting case.
Thus, this value of H is the maximum height which may be provided for an elementary
profile of a dam w/o exceeding the allowable working stress for the dam material.
However, a lower value of H will be obtained when uplift pressure is not considered (i.e.
=0). Hence to be on the safer side to determine the limiting height of a dam having
elementary profile, the uplift pressure is neglected. This height is given by:
………………………………………………………(e)
If the height of the dam is more than given by equation (e),the maximum compressive
stress will exceed the permissible stress. This condition is undesirable.
Equation (e) defines the distinction b/n a low and high gravity dam. Low gravity dam is
one in which H is less than that given by equation (e) and maximum compressive stress is
not more than the allowable stress.
If the height of the dam to be constructed is more than that given by equation (e), the dam
is a high gravity dam. For such a dam, the section has to be given extra slopes at the u/s
and d/s sides, below the limiting height to bring the compressive stress with limits.
27
Fig 11 Low and High gravity dams
The elementary profile of a gravity dam is only a theoretical profile. Certain changes will
gave to be made in this profile in order to cater to the practical needs. These needs are:
i. Providing a straight top width, for road construction over the top
of the dam and/or at least to resist the impact action of the
floating debris
ii. Providing a free board above the top water surface so that water
may not spill over the top of the dam due to wave action, etc…
The addition of these two provisions will cause the resultant force to shift towards the
heel. For reservoir empty condition, the resultant shift more towards to the heel, crossing
the inner middle third point, and consequently, tension will be developed at the toe. In
order to avoid the development of this tension some concrete have to be added on the u/s
side of the dam.
Top Width: The concrete added to provide the top width affects the cross section of the
dam.
28
Fig 13 Effect of top width on the profile of a gravity dam
In fig(13a) M1 and M2 are the inner and outer third points on the base. Thus AM 1 and
AM2 are the inner and outer third point lines, respectively. Let ADE be concrete added to
provide top width with AD = a and MI will be the line passing through the centeroid of
the added triangle ADE. This line when produced intersects AM1 and AM2 at points G
and J respectively.
For Reservoir Empty Condition, due to the additional concrete ADE, the resultant force
will intersect at a point to the right of AM1 outside, the middle third for all the sections
above plane FGH and on the left of AM1 outside the middle third for all the sections
below plane FGH. Hence tension will develop at the d/s face of the dam below plane
FGH. Therefore, to avoid this tension, concrete will have to be added at the lower levels
on the u/s side of the dam by providing u/s batter FC1shown in fig (13a).
This would result in increasing the total volume of concrete in the dam.
To find the depth h’ of the plane FGH below which u/s batter is required, we have
FG = AM = 2/3 a
FH = 3FG = 3x(2/3)a = 2a
But
For reservoir full condition, due to the additional concrete ADE, for all sections below
plane KJE, the resultant force will intersect at a point on the left of AM2within the
middle third (because of added wt, since before ADE is added R was at outer middle
third).
However, for the sake of economy the resultant force must intersect at the outer third
point line at all sections. As such in order to make the resultant force to intersect at the
outer third point at all sections the d/s face of the dam may be shifted from EB to EB1,
resulting in the reduction of concrete. Thus, due to the provision of some top width the
modified dam section will be ADEB1C1F shown in fig 13b.
Thus an increase in top width, will increases the concrete in the added element and also
increase it on u/s face, but shall reduce it on the d/s face. It has been further observed that
29
within limits the concrete added for providing the top width decreases rather than
increase the total concrete volume in the dam. Thus it is so b/c the increased volume of
concrete in the upper portion of the dam is compensated by reduction in the lower levels.
Hence, the most economical top width is a function of height of dam. Without
considering earthquake forces, the most economical top width, has been found by
Creager to be equal to 14% of the dam height. However, for low dams the top width is
usually greater than that provided on the bases of economy, b/c of minimum roadway
requirement & capacity of top width to withstand shock of floating objects. Its useful
value varies b/n 6m and 10 m.
FREE BOARD: Free board is generally provided equal to 3/2hw where hw is wave
height. However modern practice is to provide a maximum free board equal to 3 to 4% of
the height of dam, though free board equal to 5% or more might prove economical.
In this method the section of the dam is considered to be divided into a number of zones.
(The face slopes are altered at suitable interval). Design commences from crest level, and
descends through profile stages corresponding to predetermined elevations. Each zone is
designed in such away that all requirements of stability are satisfied (i.e. stress levels are
maintained with in acceptable limits e.g. no tension under any condition of loading).
Figure 14 below shows a typical dam section with seven zones in a non-overflow gravity
dam.
ZONE I: This is the portion above the maximum water surface (1-2-3-4) or if there is
ice, it is the one above the bottom of the ice sheet.
If there is no ice, the height of zone-I is controlled by free board requirements and the
width is determined by practical consideration or economy for the section as a whole. In
case of ice sheets the height of zone I is fixed on the consideration of sliding of the zone
due to ice pressure.
ZONE II: For a limited distance below the bottom of zone I, the resultants, reservoir full
and empty, lie well with in the middle third (or kern). Both u/s and d/s faces, therefore,
may remain vertical until, at some plane 5-6, the resultant, reservoir full, intersects the
joint at the exact extremity of the middle third. That portion of the dam b/n the bottom of
zone I and the plane 5-6 constitutes zone II.
30
ZONE III: Below the bottom of zone II, the u/s face continues to be vertical while the d/s
face must begin to batter.
The line of the resultant continues to coincide with the d/s extremity of the middle third
when the reservoir is full. The resultant, reservoir empty, still being with in the middle
third, the u/s face may remain vertical until at some plane 7-8, where it intersects at the
u/s extremity of the middle third. Therefore, zone III is the portion b/n 5-6 and 7-8,
determined by tension criteria, reservoir full.
ZONE IV: In this zone, the u/s face also begins to batter so that the lines of the resultants
for reservoir empty lie along the corresponding extremities of middle-third. The position
of lower limit plane 9-10 of this zone is governed by the criterion that the maximum
inclined stress (principal stress) at the d/s toe, for reservoir full condition is just equal to
the allowable limit, (which thus fixes the lower limit of zone IV).
31
The design of zone IV especially the height and d/s and u/s slopes, are determined by
trial, by dividing zone IV into a number of convenient blocks till the bottom of zone IV is
reached. It should be noted that Low Dams lie with in the limits of zone IV. Zones V, VI
and VII are applicable only for high dams.
ZONE V: - Below the plane 9-10 for some distance the inclination of the d/s face of the
dam will have to be so adjusted that for reservoir full condition the principal stress at this
face does not exceed the max allowable limit. In this case the resultant for reservoir full
condition will remain well within the middle third. On the other hand the inclination of
the u/s face is so adjusted that for reservoir empty condition the resultant continues to
intersect just at the u/s extremity of the middle third. However, at some plane 11-12 for
reservoir empty condition the principal stress at the u/s face may reach the maximum
allowable limit, which thus fixes the limit of zone V. (B/n 9-10 & 11-12).
ZONE VI: In this zone the conditions of the design are determined by the maximum
pressures (principal stresses) at both u/s and d/s faces under reservoir empty and reservoir
full conditions, respectively (the inclinations are adjusted that 1 should not to exceed the
limit). The line of the resultants under both the conditions lies well with in the middle
third. The position of the bottom plane 13-14 is reached when the inclined pressure at d/s
toe just reaches its maximum value.
ZONE VII: As the height of the dam increases, the batter of both u/s and d/s faces
increases. Consequently, at some plane the value of sec 2 (for d/s face) may become so
great that the principal stress at the d/s face may exceed the maximum allowable limit.
The portion of the dam in which this condition prevails constitutes zone VII. However,
this zone should be eliminated by revision of the entire design.
If the height of the dam is so large that it is more than the position of plane 13-14 of zone
VI, various changes are made in the upper zones so that the height of the dam lies with in
zone VI. If this is not possible, then the height of the dam is reduced or superior material
is utilized so that the height is accommodated with in zone VI.
For high dams, going beyond zone IV, it is found that the shape of u/s and d/s slopes is
sometimes unusual shape. The u/s face has a relatively flat slope while the d/s face has
outward convex shape. A convexed face under compression, whether smoothly covered
or polygonal, may be subject to tensile stress on surface parallel to the face. Such a shape
for the d/s face of the dam is not desirable b/c the outer layer of such a section tends to
buckle outward and unless the buckling forces is cancelled by the weight component
normal to the face, tension results. The dam section will have to be then redesigned so
that such a curvature for the d/s face of the dam is avoided. Alternatively the dam section
may be designed by SINGLE STEP METHOD.
32
In the single step method of design a section of the dam is suitably assumed and the
entire dam is considered as a single zone.
In the assumed section of the dam the u/s face is kept vertical for some depth to be
determined by trial. As a first trial, the vertical portion of the u/s face may be assumed to
be extended up to the plane FGH shown in fig 13 (a), below which it is given some slope.
The slope given to the u/s and d/s face of the dam are so adjusted that the principal
stresses at the u/s face for reservoir empty condition and at the d/s face for the reservoir
full condition reach their maximum values simultaneously. This may be accomplished by
trial and error. The dam section is then checked for all stability requirements for reservoir
empty and full conditions, which will normally be satisfied at all the points above the
base of the dam when the slopes for the u/s and d/s faces are adjusted as indicated above.
Fig 15 shows the sections of a high dam designed both by single-step method and
multiple step- method. It is quite clear from the two sections that the multiple-step design
is more economical for the upper portion of the dam. The single step method section is
under stressed at all the points except at the base. Hence, if the height of the dam is less,
multiple step design method would give substantial saving in material.
33
Fig 15 Comparison of zone method (multiple-step) and single step for design of high
dams
Depending upon the location and purpose served, joints provided in dams may be
classified under two heads:
a) Construction joint (or horizontal joints)
b) Contraction joints.
Construction joints: usually called horizontal joints are necessary since the entire work
of concreting the whole dam cannot be completed in one stretch. They are the joints
introduced b/n successive lifts. (The lift is the height by which the dam is raised in one
continuous operation by pouring concrete (or laying masonry).
For solid gravity dam lifts of about 1.5m is adopted. The concrete of the next lift is
placed after sufficient time is allowed for the previously placed concrete to cool and
attain its initial set and become hard. As such horizontal joints are provided to allow
sufficient cooling b/n the successive lifts of concrete.
Prior to the placement of concrete of the next lift, the surface of the previous placed
concrete is thoroughly cleaned by the use of high velocity jet of water and air as well as
wet- sand blasting process. Further, immediately before the concrete placing of the next
lift begins, a 12.5mm thick layer of mortar should be applied to permit a proper bond
between the previously placed concrete and the new concrete. Such treatment of the
34
surface and the use of good concrete create tight horizontal joints for which no provisions
to ensure water tightness, such as water stops, keys, etc, are necessary.
Contraction Joints: are mainly provided to avoid cracks caused by shrinkage of concrete
due to temperature changes. They are vertical joints. The cracks may be the result of
tensile stresses produced when the volumetric changes of concrete is restrained.
Volumetric change results in shrinkage from drying concrete & from temperature
variations. The major change, however, results from temperature variation. Surface
cracks may develop due to high daily temperature difference b/n the surface and near the
surface areas of the dam. Cracks adversely affect water tightness, durability, appearance
and internal stresses of concrete.
Transverse Joints: They are provided normal to the axis of the dam. They extend
vertically from the foundation to the top of the dam and are continuous from the u/s to the
d/s face of the dam, thus divide the dam into separate blocks. They are provided to allow
contraction of concrete on the two sides and thus prevent development of transverse
cracks in the dam.
The spacing of transverse joints is governed by physical factors of the dam site; details
of the structures associated with the dam such as spillway gates, outlets, penstocks,
spillway bridge piers, etc, results of temperature studies and probable plant capacity. For
concrete dams these are usually spaced 15 to 20m.
Longitudinal Joints: are provided parallel to the axis of the dam. They are provided to
prevent longitudinal cracks.
Longitudinal joints run b/n two adjacent transverse joints and are thus not continuous all
along the length of the dam. Spacing of these joints varies b/n 15 and 30m.
35
The longitudinal joints subdivide each block formed by transverse joints in to several
smaller blocks, but since each block must be monolithic block, these joints are provided
with horizontal keys over the entire surface of the joint ground. These joints are usually
provided in the core of high dams b/c as the height of the dam increases the base width
also increases & it approaches limit beyond which vertical cracks parallel to the axis of
the dam may develop if longitudinal joints are not provided. Thus these joints serve the
same purpose in each block of the dam as the transverse joints serve in the dam as a
whole.
Keys: are the regular projections provided in contraction joints of a dam for transfer of
load from one block to the other through shear. In transverse joints vertical keys are
provided which are designed to transfer horizontal shear and to assist in minimizing
leakage of water through the joints.
In longitudinal joints horizontal keys are provided which are designed to take vertical
shear.
36
Water Stops (or water seals): - Provided across transverse joints, adjacent to the u/s face of
the dam, to prevent the leakage of water from the reservoir through the transverse joints if
the transverse joints are not grouted.
Water ways: - are the openings provided for obtaining water from the reservoir for various
purposes such as irrigation, water supply, power generation, etc as well as for allowing
the excess water which cannot be stored in the reservoir during floods to over flow to the
d/s side. These include outlets, penstocks, spillways etc.
Fig 17 Water
stops
GALLERIES
A gallery is an opening provided for obtaining access to the interior of the dam for
various purposes. It may run in transverse or longitudinal direction and may run
horizontally or on a slope.
37
Shape:- Usually rectangular with its top and bottom either flat or semi-circular. For flat
top and bottom all corners are rounded to reduce stress concentration.
Size:Large enough to provide working space and access for equipment for normal
maintenance. Its size in general varies from 1.5m to 1.8m in width and 2.2 to 2.4m in
height.
Fig 18 galleries
Purposes of a Gallery
1. To provide drainage of the dam section. Water seeping from u/s face of the dam
is drained off through galleries.
2. To provide facilities for drilling and grouting operations for foundation of the
dam.
3. To provide space for the piping system and equipment used for grouting of the
contraction joints as well as for the post cooling of concrete blocks.
4. To provide access to the interior of the dam for inspection and also for installing
various instruments to study structural behavior of the dam after completion.
5. To provide access to, and room for mechanical and electrical equipment required
for the operation of gates for outlet conduits, power penstocks and spillway crest.
6. To provide access routes for visitors; to provide access through the dam for
control cables and/or power cables.
Depending upon the purposes served the galleries can be classified as follow:
i) Foundation gallery
ii) Drainage gallery
iii) Grouting gallery
iv) Inspection gallery
v) Gate gallery
38
Foundation Gallery: Provided at the foundation level and follows the configuration of the
valley. It extends over the entire length of the dam and it normally runs parallel to the
axis of the dam. Always it is provided very close to the u/s face of the dam. Minimum
distance from u/s face (for structural safety) should be either 10%of the maximum head
water on u/s side or 6m which ever is more. There should be a minimum of 1.5m
concrete b/n foundation and floor of the gallery. Its purpose is drainage of water seeping
(percolating) through u/s face of the dam. Hence it is also called drainage gallery.
They are also used to drill and grout the holes for grout curtain on the u/s edge of the
gallery.
If proper temperature control is not exercised, the large concrete blocks b/n the joints
may crack due to high temperature gradient b/n the interior and the surface. These large
blocks of concrete are subject to deep as well as surface cracking. The cracks in the
interior of the blocks are produced due to heat of hydration liberated by cement thus
giving rise to high temperature gradient. The surface cracks may appear due to daily
variations of temperature at the surface. The surface cracks are more harmful, since the
disintegration starts through them by wedge action. Water inters these surface cracks,
accumulates there and then solidifies; at 4oc it expands resulting in widening and
deepening of cracks.
Following methods are employed to check or minimize the development of the cracks in
mass concrete.
39
4. Using Lower percentage of cement in concrete for interior of the blocks, say about
80% of that of the exterior.
5. restricting the height of the lift, say 1.5m
6. Allowing considerable time b/n lying of two successive vertical lifts. The usual time
is about 4 days.
Foundation Treatment: - The foundation must be strong enough to withstand the entire
load acting up on it.
Methods of Treatment: First surface has to be prepared. This is done by removing all
loose overburden of weathered rock as well as any decayed or weak rock till sound bed
rock is exposed. In this process the underlying sound rock should not be damaged.
Further, the final rock surface should be excavated to develop stepped or benched
foundation to increase the sliding resistance of the dam. The surface should also be
thoroughly cleaned with wet sand blasting and washing before concrete is laid.
In order to rectify the deficiencies in deep foundation as well as the water tightness of the
foundation, the following methods of treatment are employed.
i) Excavation of seams of decayed or weak rock by tunneling and back filling tunnels
with concrete.
ii) Excavating for and making concrete cutoff walls across leakage channels in the dam
foundation where the water channels are too large or too wet for mining and grouting.
iii) Grouting the foundation to increase its strength and tender it impervious.
Foundation Grouting: This consists of injecting under pressure a mixture of cement and
water (called grout) in to holes drilled in the foundation rock for the purpose of sealing
seams, cracks and fissures or filling voids present in the rock. Foundation grouting
classified on the basis of pressure used for grouting may be either (i) low pressure
grouting (ii) high pressure grouting and when classified on the basis of the purpose
served by the grouting, it may be (i) consolidation grouting or (ii) curtain grouting.
40
Consolidation grouting is low pressure grouting and curtain grouting is a high pressure
grouting.
Consolidation Grouting: Done to consolidate the entire rock foundation and thus to
increase its strength. Shallow holes of depth ranging from 3 to 15m (also called B-holes)
are drilled through the foundation rock on a grid pattern at spacing of 6 to 30m. Before
grouting operation starts the holes are thoroughly washed with water and compressed air
to remove all loose material and drill cuttings. Then the holes are tested for tightness by
injecting water under pressure, which helps to decide on the consistency of the grout to
be used and to locate seams and other openings in the rock which are to be plugged. The
grout is then injected in to these holes at a relatively low pressure which is usually less
than about 392.4KN/m2 (4kg f/cm2). This grouting results in the consolidation of the
foundation in to more or less monolithic mass by bonding together the jointed rock.
Moreover this grouting serves as cutoff against the leakage of the grout of the high
pressure grouting which may be required to be done later.
Curtain Grouting: - Done to create a deep curtain or a barrier in the foundation rock at the
heel of the dam which will prevent leakage from the reservoir and thus reduce the uplift
pressure on the dam. Deep holes (called A hole) which are either vertical or inclined are
drilled. Inclined holes are drilled to intercept the principal joints in the rock to develop an
effective curtain, the primary series of holes being spaced 4.5 to 7.5m depending on the
nature of the rock. A second series comprises an equal number of intermediate holes.
This one is repeated for a third series but reducing the spacing of holes to quarter of that
of the first series (i.e. spacing 1.2 to 1.5m). The depths of holes depend on nature of the
rock and in general vary b/n 30-40% of the head water depth on dense foundation to 70%
of head water depth for poor foundations.
3. ARCH DAM
3.1 General
41
An arch dam may be defined as a solid wall curved in plan standing a cross the entire
width of the river, in a single span. It is one type of concrete dam.
Unlike a concrete gravity dam which carries the entire load by its self weight an arch
dam obtains its stability by both the self weight and to a great extent by transiting the
imposed loads by arch action in to the valley walls. The geometry of the dam site is
therefore the most basic consideration in the selection of an arch dam. As a general
rule an arch dam requires a site with abutments of sufficient strength to support the
arch trust. Concrete saving in such dams relative to gravity dam is 50-85% &
abutment stability is critical to the structural integrity & safety of an arch dam.
The concepts of overturning and sliding stability applicable to gravity or buttress
analysis have little relevance to the arch. An arch represents a stable structural form
and given that the integrity of the supporting abutments is assured, failure can occur
only as a result of overstress. Arch dam design is therefore centered largely up on
stress analysis & the definition of an arch geometry which avoids local tensile stress
concentrations and /or excessive compressive stress. In a achieving this objective it is
frequently necessary to adopt varying curvatures & thicknesses b/n arch crown &
abutments & also from crest level to base.
The horizontal component of Arch trust must be transferred in to the abutment at a
safe angle, i.e., one which will not promote abutment yielding or instability. At any
elevation the arch trust may be considered to enter the abutment as shown in fig 1.
42
Fig 2 Valley shape and Dimensions
In constant radius Arch dam, the arch center for the u/s face d/s face and the
centerline of horizontal arch rings, at various elevations lie on a straight vertical line
that passes through the center of the horizontal arch rings of the u/s face at the crest.
Hence it is also known as Constant center arch dam.
43
In this type of dam the central angles of arch rings of the intrados vary at various
elevations, the maximum being at the top of the dam and a certain minimum at the
bottom of the dam. Due to reduction in central angle and the central rise of arch rings
at the lower elevations near the base of the dam, considerably low arch action will be
developed for these arch rings. Hence relatively large proportion of the water load at
the lower elevations will be carried by cantilever action for which the arch rings at the
lower elevations will have to be made considerably thick.
This will result in uneconomical design. For U–shaped valleys the constant radius
arch dams are found suitable since there is a relatively less reduction in the central
angle and the central rise of the arch rings at the lower elevations. Reduction at the
central angle at the lower elevations would be considerable in the case of narrow V-
shaped valleys and would result in uneconomical design for such types of dams.
Constant angle arch dam: - The central angle of the horizontal arch rings is of the
same magnitude at all elevations. Theoretically, for economical design of constant
angle arch dams central angle of arch rings equal to 133 0 34’ may be adopted.
However, the practical range of central angle from 100 0 to 1500 depending on the
valley shapes. Due to large central angle greater arch action will be developed for the
arch rings at all elevations. Hence water load at all elevations is carried by arch
action. In general, the thickness of constant angle arch dam is smaller than that of
constant radius arch dam. As a result, under same condition it requires only about
70% of concrete as compared to constant radius arch dam.
The radii of arch rings of constant angle arch dam decreases as the depth below the
crest increases since the central angle at all elevations has the same magnitude.
Moreover, the curvature of each arc ring will be different and the various arch rings
may be arranged to have the crowns of either extrados or intrados of all arch rings
flushing. These arrangements will result in an overhang of the u/s face near the
abutments and that of the d/s face near the crown of the arch. Hence, the formwork
required is complicated and costly than that of constant radius arch dam.
Constant angle arch dams are suited to narrow V-shaped valleys with large central
angle fairly large arch action will be developed even at lower elevations & hence the
design will be economical.
44
Fig 4 Constant angle Arch dam
Variable Radius Arch Dam: Neither the radius nor the central angle is constant.
Radius is maximum at the top & minimum at the base. The central angle of the arch
rings usually vary b/n 80 to 1500 & these are so adjusted that large arch action is
developed even for arch rings at lower elevations. The radii at various elevations are
also so adjusted that the over hangs are avoided or minimized. Further in this dam,
centers of the arch rings at various elevations do not lie on the same vertical line.
This type of arch dam is suited to u-shaped valleys as well as for narrow V-shaped
Valley b/c by adjusting the radii & the central angles a fairly large arch action may be
developed even for arch rings at lower elevations.
This type of arch dam is suited to U-shaped valleys as well as V-shaped valleys since
large arch action will be developed at lower elevations for arch rings having smaller
spans by adjusting the radii and the central angles.
As compared to the constant angle arch dam a variable radius arch dam is less
economical since under the same conditions a variable arch dam requires about 17%
more concrete than constant radius arch dam since under the same conditions the
concrete required for a variable radius arch dam is only about 82% of that required
for a constant radius arch dam. Hence it is a compromise b/n constant radius &
constant angle arch dams.
FLOW
45
Fig 5 Variable Radius Arch dam
Thin cylinder theory: - In this theory the horizontal section of the arch dam is
assumed to behave as part of thin cylinder ring at the corresponding elevation. Further
it is assumed that the horizontal water load is carried entirely by arch action. The
pressure on the arch ring equal to the hydrostatic pressure at the corresponding
elevation and the stress distribution across the arch ring is uniform.
The figure shows a section of a thin arch ring having extrados radius r e, subtended
angle of arch ring and thickness t
If the arch ring is at a depth of h below reservoir water surface, then P = (the
hydrostatic pressure acting in the radial) direction.
46
And the total hydrostatic pressure force p is given by:
P= ×2 re sin
P= 2 h re sin
If R is the abutment reaction its component in the upstream direction which resists the
pressure force P is equal to R sin / 2
2Rsin/2 =2h re sin/2
R = h re (Abutment Reaction)
If the thickness (t) of the arch ring is small compared with r e it may be assumed that
uniform compressive stress is developed in the arch ring.
If is the compressive stress developed in the arch ring at the abutments then
(Average Stress) ( )
If f is the allowable compressive stress for the arch material then in the limiting case
f and
t=
This equation indicates that the thickness t of the arch ring increases linearly with
depth below the water surface and for a given pressure the required thickness is
proportional to its radius.
Thickness relation in terms of intrados, ri and mean radius r, can be derived as
follows.
ri = re-t re = ri+t
t=
r = re-1/2 t re = r+ t/2
The concrete volume of any given arch is proportional to the product of the arch
thickness and the length of the center line arc. For a fixed combination of span,
loading and permissible cylinder theory stress, the follwing can be shown.
Where A = tx1 = cross sectional area of arch ring for unit height
= in radians
47
If L is the span of arch ring, then
L/2 = rsin /2 L = 2rsin /2 r =L/(2sin /2) --------------------(a)
And
= 133034’ ---------------------------------------(b)
Thus, on the basis of thin cylinder theory, the volume of concrete required for arch
dam would be minimum if the central angle is 133034’. By substituting /2 in
equation (a) we get
--------------------(c)
L = the arch span and the radius may be re,r or ri if L is the corresponding span.
In a site with a variable span length, a constant radius dam can have the correct
central angle only at one elevation.
The smallest concrete volume for the whole dam, with constant radius, is obtained by
increasing the top angle to get the best average angle. The top angle which gives the
best average can be found by trial and topography seldom permits value greater than
1500 for at the top of the dam.
Improvement in thin cylinder theory was made by considering the arch as thick cylinder.
The stresses at the extrados and intrados are given by
48
The thickness is given by the relation
4. BUTTRESS DAMS
Efforts have been made from time to time to innovate methods for affecting economy in
the use of concrete, by cutting down concrete from concrete gravity dam’s portion where
it remains unstressed. Attempts have therefore been made to provide hollow gravity
dams. Buttress dams are an improvement innovation over the hollow concrete gravity
dams in which solid wall of specified thickness & section are constructed parallel to the
flow at some suitable intervals called buttress & include slabs which are supported on u/s
side on these buttresses.
49
Road
50
6) Cutoff (Concrete): - is provided at the upstream end of the dam to reduce/prevent the
seepage & up lift.
51
the foundation is weak. The main disadvantage of this type is that it requires a thicker
slab as compared to the fixed (continues) slab.
Fig 2
b) Fixed (or continuous) Deck Slab Type Buttress Dams
The deck slab is cast monolithic with the buttresses and it acts as a continuous slab.
Reinforcement is provided both on upstream & down stream faces of the slab. This
type of deck can be used only when the foundation is strong; where it will be more
economical than the freely supported slab b/c the deck slab is thinner.
Fig 3
Cantilever Deck slab type Buttress Dams
The deck slab is cast monolithically with the buttresses in such a manner that it over
hangs on either side of the buttress and acts as cantilever.
52
Fig 4
53
C) Tee head buttress dams
54
3) Semi - rigid buttress Dams: - It is neither as rigid as rigid buttress dam nor as
flexible as a flexible buttress dam. It is therefore in b/n that of rigid buttress dam
& a flexible buttress dam.
E.g. The massive head type buttress dam
They are the same as those on gravity dams. Uplift pressure acting on a buttress dam
depends on the type of the dam and type of foundation provided for buttresses. If
separate spread footings are used for each buttress then the uplift pressure is relieved
by the gap b/n the buttresses.
Buttress dams on rock foundation are subject to the uplift pressure due to head water
is usually neglected and only the uplift pressure due to TW (if any) is considered for
the entire footing. However, in the same case if the foundation rock is such that uplift
pressure due to head water cannot be neglected, then under the deck and haunch
section full uplift pressure due to head water is considered and the remaining portion
of the footing full uplift pressure due to tail water is considered. If a mat foundation is
provided for all buttresses, uplift pressure may be computed in a similar manner as in
the case of gravity dam.
Buttress dams should full fill stability requirements as that of gravity dams. Further in
the case of a buttress dam the total force acting per buttress unit must be considered
instead of force per unit length of dam as in the case of gravity dam.
55
Height of dam:-Economic buttress spacing increases with the height of the dam; whereas
for low dams the buttress spacing will be proportionally less.
For buttress dams on sound rock foundations the most economical buttress spacing for
deck slab buttress dams are given below.
Height of dam (m) Economical spacing c/c of buttress (m)
15 to 30 5 to 6
30 to 45 9 to 12
Above 45 12 to 15
Type of Footing: it is not economical to have very large spacing of buttresses b/c the
quantities of material required for spread footing (or mat foundation) & for the apron of
spillways increase with an increase in the buttress spacing and hence it will be
economical to have a smaller spacing for buttresses.
Upstream slope: Varies from 350 to 450 and is governed by the requirements of sliding
factor, i.e., H/v resistance against sliding is achieved from the vertical component of
the water pressure since self weight of the buttress dam is relatively small. Vertical
component of the water pressure varies with the upstream slope.
Further, for constant buttress spacing, small variation in the u/s slope results in an
appreciable change in the quantity of concrete and hence it affects economy. Likewise for
constant u/s slop the variation in the buttress spacing also results in change in the quantity
of concrete and hence affects economy.
Thus for each value of u/s slop there would be an economical buttress spacing which may
be determined from a master curve which may be prepared as indicated below. Further
from the same curve, a combination of the most economical buttress spacing and the u/s
slope may also be determined.
A master curve is extremely useful for determining the most economical spacing for d/t
upstream slopes.
56
Fig 7 Simplified diagram of buttress dam
Taking
1
Cq 0.2083H 2 cot
f
The equation shows that for a given height h and a given value of f the quantity of
concrete depends up on cot . Thus for a given value of h and f the quantity of concrete
Cq, obtained are independent of the buttress spacing and hence this will plot as vertical
lines on the plot of buttress spacing vs quantity of concrete. Next choosing certain value
of , the dam is designed by considering a number of buttress spacing and the quantity
of concrete required per unit length of the dam for each buttress spacing is determined.
The value of the quantity of concrete so obtained are plotted against the corresponding
buttress spacing on the same graph to obtain a curve for the chosen value of . By
repeating the same procedure for d/t values of a series of such curves are obtained as
57
shown by joining the points of intersections of the curves and the vertical lines
corresponding to each value of which is shown by a solid line. The master curve gives
the value of economical buttress spacing for each value of for the given height of dam.
Further, the apex of the master curve gives the value of the most economical buttress
spacing as well as the corresponding value of and the quantity of concrete per meter
length of dam.
The deck slab is designed as a simply supported slab by using the standard methods of
R.C.C/ design. The slab thickness is controlled by bending moments at higher levels and
shear at lower levels. (Refer any R.C.C. text)
Design of A Haunch
58
The width of the bearing face of the haunch is determined from the permissible bearing
pressure and the assumed load distribution on the face. The load distribution on the
bearing face is usually assumed to be triangular with the maximum at the outer edge and
zero at the inside corner of the haunch.
a) Width (B). The actual load distribution on the bearing surface is indeterminate.
However the triangular distribution is usually assumed, with the maximum pressure p at
the outer edge and zero pressure at the inner edge of the haunch. Thus the total reaction R
is Given by
R = 0.5pB
b) Depth The depth dm and ds are as per the design requirements respectively, for
bending moment and shear. These depths are so proportioned that the bracket profile
adequately envelopes the theoretical minimum depth profile for moment and shear.
The depths D1 and D2 are the actual depths provided.
Fig 9
Though the conventional formulae of the design of RCC beams and cantilevers are not
strictly applicable for trapezoidal brackets of the haunch, approximate depth profile can
be determined from the conventional RCC design formula ( see any text on RCC
DESIGN).
59
For preliminary design of buttress only water pressure on the deck slab, weight of deck
slab and buttress are considered. The final design is checked for other forces such as
earthquake, uplift pressure, wave pressure, silt pressure etc…
Preliminary design of buttress is carried out on the bases of Unit column theory, in which
the buttress is assumed to be made of a number of unit columns.
Assumptions:
1) Each column transfers the load from the top of the column to the foundation
independently of the adjacent columns above or below it.
2) Each column is so proportioned that at every section of the column uniform
compressive stress is developed and it is curved to avoid eccentric loading.
The magnitude of the initial load Po depends on the type of joint b/n deck slab and the
buttress. Thus if the joint is frictionless then Po = Pw + Wdn (total water pressure on the
deck and component of the weight of the deck slab normal to the buttress face (fig 10).
On the other hand if the joint is monolithic then Po is equal to the resultant of the total
water pressure on the deck slab Pw and the weight of deck slab Wd. In this method in
general, five columns distributed over the entire buttress will be adequate.
60
For each unit column, the value of the initial thickness to is obtained from:
------------------------------------(1)
Where fc is the permissible compressive stress in concrete
The thickness t at any point in the unit column at a vertical distance y from the origin o is
given by --------------------------------------(2)
Since the width of the column is constant (i.e. unity), the thickness of the column
increases from the deck to foundation.
By substituting value of from equation (4) in to equation (3), the coordinates (x,y) of
any point on the column axis with respect to origin o may be obtained from
-----------------------------------(5)
The minimum thickness of buttress determined on the bases of unit column theory is
usually much less than the minimum thickness required from practical considerations.
Thus the minimum thicknesses to be provided are given below.
61
The design of the unit column should therefore be carried out with actual thickness
provided as per the requirements of the minimum thickness (as given above).
Downstream Slope of Buttress: The unit column theory gives a curved d/s face for the
buttress. However, a buttress with a curved d/s face is difficult to construct and hence
from practical point of view a buttress a plane sloping d/s face is usually provided. The
slop of the d/s face should satisfy overall stability requirements. Usually the base length
of the buttress varies from 1.2 to 1.5 times the depth below the maximum water level in
the reservoir.
After determining the dimensions, the buttress has to be checked for overall stability
against overturning g and sliding. Using the same formula as that of the gravity dam
analysis, the direct stress sliding factor and S.F.F. are computed.
After the buttress has been found adequate for the axial loads, it should be investigated
for column ration (slenderness ratio) and massiveness factor.
Column Ratio: Is the ratio of unsupported length of buttress measured along lines of
principal stress to the thickness of the buttress. Low buttresses having no lateral support
may have a column ratio of b/n 12 and 14, but for high buttresses which require lateral
support the column ratio should be limited to the range 7 to 10.
Massiveness factor: Is the ratio of spacing of buttress to the thickness of the buttress. In
general its value varies b/n 2.5 and 3.
Finally after calculating foundation pressure (of the design deck slab and buttresses)
spread footings and mat foundations are designed depending on magnitude of foundation
pressure.
Disadvantages
i) Needs reinforcement and expensive shuttering
ii) Additional skilled labor is required to create form work
iii) Threat of deformation of concrete from impounded water is more likely than
from a thick gravity section
iv) More susceptible to damage by sabotage.
===============================================================
62
5. EMBANKMENT DAMS
The embankment dam can be defined as a dam constructed from natural materials
excavated or obtained near by. The materials available are utilized to the best advantage,
in relation to their characteristics as bulk fill zones with in the dam section. The natural
fill materials are placed and compacted with out the addition of any binding agent, using
high capacity mechanical plant.
An embankment dam is therefore a non rigid dam which resists the forces exerted up on
it mainly by its shear strength. These dams usually provide the most economical and
most satisfactory solution for sites at which suitable foundation at reasonable depth may
not be available for a dam of concrete or masonry.
63
The two main forms of embankment dams are (1) Earth (earth fill) dams made
predominantly of earth or soil. (2) Rock fill dams made predominantly of quarried rock.
However a composite earth and rock fill type of embankment dams are also being widely
used.
The design of an earth dam involves both a hydraulic and structural analysis. The
hydraulic analysis deals with the determination of the seepage patterns and the magnitude
of seepage as well as the internal hydrostatic seepage forces for both the dam body and
the foundation. Of particular importance is the investigation for possible removal of fine
particles near the toe by emerging seepage water (piping). The structural analysis
involves the study of the stability of the embankment under the given conditions of
seepage and other forces. Settlement and stability studies of the foundation are also
important.
64
In the case of hydraulic-fill dam the materials are transported from borrow pits to their
final position (dam site) placed through the agency of water. Thus in this case, at the
borrow pits the material is mixed with water to form a slurry which is transported through
flumes or pipes and deposited near the faces of dam. The courser materials of the slurry
stay near the faces of the dam while the finer ones move towards the center and get
deposited there. This would provide a dam section with shoulders of the course free
draining particles and an impervious central core of fine grained material such as clay and
silt.
In the semi-hydraulic fill dam construction, the material is dumped near the upstream and
down stream face of the dam to form rough levees as in the case of rolled fill dam w/o the
use of water. Then the space b/n the levees are filled with water and the material placed
in or upon the levees is washed to wards the center of the dam. For this jets of water are
directed on the dumped fill which cause the finer material from the fill near the faces of
the dam to be washed away. The finer material moves towards the central portion of the
dam and is deposited there thus forming an impervious central core while course material
stays near the faces of the dam. However, in the absence of proper jetting action the
dumped fill at the faces of the dam may be more dense and impervious than the material
immediately below it on the inside of the dam which may result in the failure of the dam.
Out of these three types, the rolled-fill earth dams are the most common. This is so b/c
in the case of other two types of dams lack of control in placing the material may result in
the failure of the dam.
Rolled Fill dams are of three types
a) Homogenous type
b) Zoned type
c) Diaphragm type
65
The material comprising the dam must be sufficiently impervious to provide an adequate
water barrier & the slopes must be relatively flat for stability. To avoid sloughing the
upstream slope must be relatively flat if rapid draw down of the reservoir is anticipated.
Although formerly very common in the design of small dams, the purely homogenous
section has been replaced by a modified homogeneous section in which small amounts of
carefully placed pervious materials control the action of seepage so as to permit much
steeper slopes. The modified homogeneous section is the one provided with internal
drainage filter system in the form of a horizontal drainage blanket or a rock toe or a
combination of both.
Fig
5.1 Homogeneous dam Section B.
Zoned embankment type: These are the most common for high dams of rolled fill type.
They are provided with a central impervious core, covered by a relatively pervious
transition filter which is finally surrounded by a more pervious outer zones or shells.
The core thickness should not be less than 3 m or the height of the dam above the section.
The central core checks the seepage; the transition filter zone prevents piping through
cracks which may develop in the core. The outer zones (shells) provide stability to the
core and also distribute the load over a larger foundation area. The core is usually a
66
mixture of clay and sand or gravel or silty clay. Pure clay that shrinks and swells
excessively is not suitable .Freely draining materials such as coarse sands and gravels are
used as the outer shells. This is necessary b/c the down stream pervious zone should act
as a drain to control the line of seepage.
I f a variety of soil are readily available, the choice of type of earth fill dam should
always be the zoned embankment type b/c its inherent advantages will lead to economies
in cost of construction.
C. Diaphragm type
In this type of section the bulk of embankment is constructed of pervious materials
(Sand, grave, or rock) and a thin diaphragm of impermeable material is provided to form
the water barrier. The position of this barrier may vary from a blanket on the up stream
face to central vertical core. If the diaphragm is provided as an impervious blanket on the
u/s face of the dam it needs to be protected against shallow sloughs and slide during
draw down and from erosion by wave action. For this the diaphragm is held buried below
a thin layer of pervious material over which the up stream slope protection is provided.
The diaphragm may be of earth, Portland cement or asphalt concrete or other material.
If the core thickness at any elevation is less than 3m or less than the embankment height
above the corresponding section then the dam embankment is considered to be the
diaphragm type.
67
Fig 5.3 Diaphragm type
Foundation Requirements
The essential requirements of a foundation for an earth dam are that it provides support
for the embankment under all conditions of saturation and loading and that it provides
sufficient resistance to seepage to prevent excessive loss of water. Although the
foundation is not actually designed certain provisions for treatment are made in designs
to assure that essential requirements will be met.
Foundations are grouped in to three main classes according to their predominant
characteristics as rock foundation, Foundation of coarse-grained material (pervious
foundation) and foundations of fine grained materials (Impervious foundation).
Impervious foundation Foundations of fine silt and clay are impervious and have very
low shear strength. Shear failure may occur in such foundations: If the foundation
material is impervious and comparable to the compacted embankment material in
structural characteristics, little foundation treatment is required. The minimum treatment
for any foundation is stripping of the foundation area to remove the topsoil with high
content of organic matter & other unsuitable material which can be disposed of by open
excavation. In many cases where the over burden is comparatively shallow the entire
foundation is stripped to bed rock.
Rock foundation: - foundations of rock including hard shale do not present any problem
of bearing strength for small earth fill dam. The principal considerations are dangerous
erosive leakage and the excessive loss of water through joints, crevices, permeable strata
and along fault planes. Ordinarily, the design and estimate for a storage dam should
provide for the injection of grout under pressure to seal seams, joints & other opening in
68
the bed rock to a depth equal to the reservoir head above the surface of the bed rock.
Grouting is usually done with neat cement and water starting with a ratio of 1:5 pressures
usually applied are (0.25 D kg/sq cm) where D is the depth of grouting below the surface.
Pervious foundations: - often the foundations for dams consist of recent alluvial
deposits composed of relatively pervious sand and gravel over lying impervious
geological formations. Two basic problems are found in pervious foundations. One
pertains to the amount of under seepage and the other is concerned with the forces
exerted by the seepage.
Quantity of under seepage and seepage forces: - To estimate the volume of under
seepage, it is necessary to determine k, by Darcy’s formula, the accuracy of which
depends on the homogeneity of the foundation and the accuracy with which the
coefficient of permeability is determined.
Seepage forces are caused as a result of the friction b/n the percolating water and the
walls of the pores of the soil through which it flows. The forces are exerted in the
direction of flow and are proportional to the friction loss per unit distance. As the water
percolates up ward at the d/s toe of the dam, the seepage force tends to lift the soil
resulting in piping.
An earth dam must be safe and stable during all phases of construction and operation of
the reservoir. For this the following must be met.
i) The embankment must be safe against over topping during occurrence of the
inflow design flood and also by action of wave, by provision of spillway of
sufficient capacity and of sufficient free board.
ii) The slope of the embankment must be stable during all stages of construction
and under all conditions of operation including rapid draw down in case of
storage dam.
iii) The embankment must be designed in such away that it will not impose
excessive stress up on the foundation.
iv) Seepage flow through the embankment, foundation and abutments must be
controlled so that no internal erosion takes place so that no sloughing takes
place where the seepage emerges
v) The upstream slope must be protected against erosion by wave action, and the
crest & down stream slope must be protected against erosion due to wind and
rain ( by growing grass on it and /or putting riprap but not good for aesthetic).
vi) The seepage line should be well with in the down stream face and there should
be no opportunity for the free passage of water from the u/s to the d/s face.
For any dam of homogenous material, seepage will pass trough the dam and appear at
the downstream face regardless of the tightness of the material. The line of saturation
i.e. the upper boundary of the flow line below which the flow is under hydrostatic
pressure is called the phreatic line. If this line of saturation is allowed to intersect the
69
d/s slope above the toe, a serious sloughing will always occur unless prevented by
construction of toe drains or filters or rock fill toe.
Location of the position of the phreatic line is desirable for determination of the
amount of through seepage and for construction of the flow nets as it represents one
flow boundary.
Fig 5.4
Kozeny has shown that the phreatic line in this case coincides with the base parabola
ADC except at the entrance. The base parabola has its focus (F) at the starting point
of the horizontal drainage blanket & intersects the water surface at A (0.3L from B).
The basic property of parabola which is utilized to draw the base parabola is that the
distance of any point P from the focus is equal to the distance of the same point from
the directrix.
I) Graphical Method
i) With center at A & radius AF draw an arc. The arc cuts the line AB
when produced at E. Draw a vertical line GE through point E which is
the directrix of the base parabola.
ii) The intermediate points are located by utilizing the above mentioned
basic property of the parabola.
iii) Join all intermediate points by a smooth curve. The last point C on the
parabola will be midway b/n F & G as FC = CG
II) Analytical Method
Let us take the origin (O) at the focus with X- positive u/s & Y-positive up
ward.
From the basic property of parabola: distance PF = distance PR
…………………………………………(i)
Squaring both sides & rearranging
…………………………………………….(ii)
70
Where yo is the distance from the focus to the directrix, also called focal
distance (f) Thus FG = Yo. The value of Yo can be obtained from the known
coordinates ( X = b, Y = h) of the starting point A.
Substituting the values in equation (i) we have
For different values of X the corresponding values of Y can be computed
using the parabola equation (II). The intermediate points are plotted from the
known coordinates to obtain a smooth curve.
As the actual phreatic line starts from point B and not from point A, a short
transition entry correction curve is sketched free hand by eye judgment such
that it is perpendicular to the u/s face & meets the basic parabola tangentially.
After the phreatic line is determined, then it is also possible to draw the flow
net, considering the phreatic line as the first/top most flow line. And thus, one
can compute the quantity of seepage through dam. Discharge through dam can
also be quantified using analytical approach for this particular situation.
v = ki
k = Coefficient of permeability
i = the hydraulic gradient
The the seepage discharge per unit length can be given by:
q = vA= kiA
Where A is area of flow per unit length
For steady flow, the discharge through all vertical planes across the dam
section will be the same.
Considering the discharge through the vertical section PQ passing through the
point P (x.y),
q = kiA
71
PHREATIC LINE FOR A HOMOGENEOUS DAM SITH OUT ANY
DRAINAGE SYSTEM
Fig 5.5
In this case the phreatic line cuts the d/s faces at point J above the toe. In
addition to the entry correction an exit correction is also required.
The focus (F) of the base parabola is located at the d/s toe of the dam & its
starting point A is located at a distance of 0.3L from B.
Casagrande has shown that the exit correction ( depends up on the slope
of the discharge face and he has given the values ) for different
values of angle as follows.
Fig 5.6
The value of (a+ ) may be obtained from the figure by measuring FK from the toe
after the base parabola has been drawn or by using the following polar equation of the
parabola.
72
Where
Variation of the slope angle is measured clockwise from the horizontal. The
above equation for fig 5.4, cannot be applicable for determining for <
30 Approximate analytical solutions for such case are:
0.
i) Approximate analytical solution for the determination of the distance a for the slope angle <
300
For the slope angle < 300, Sceffernak and Van Iterson gave the analytical solution
for the determination of the distance a. In this case it is assumed that the hydraulic
gradient (i) is equal to the tangent of the angle.
Thus
This assumption is true for small values of the angle
A vertical line is drawn through the point J to cut the base at J’ (Fig ). The discharge
through the vertical section JJ’ per unit length is given by:
Simplifying,
73
ii) Approximate analytical solution for the determination of the distance a for the slope angle30 0<
< 600
Casagrande suggested that in this case the hydraulic gradient should be taken as sin
instead of tan .That is it should be taken as (dy/ds) instead of (dy/dx), where s
is the distance measured along the phreatic line.
or
or
For a slope angle up to 600, the length of the phreatic line So can be taken
approximately equal to the straight distance FA = , thus the above equation
becomes
74
The figure below shows an earth dam with rock toe. The u/s face of the rock toe is
usually inclined downstream i.e., > 900 as shown in figure below (fig 5.7).
However, sometimes the u/s face of the rock toe is kept vertical. The drawing
procedure for phreatic line is the same as previous cases but the exit correction is
somewhat d/t.
Rock Toe
Exit Correction of Phreatic line for earth dam with rock toe
The u/s face of the rock toe acts as the discharge face. It makes an angle with the
horizontal. The base parabola cuts the discharge face at point K. The value of
) may be obtained by measuring the distance FK or from equation given above for a
given value of and calculated value of yo
For the known value of , the value of can be obtained from fig 5.6. The
exit correction, , is then found from the values of the equations. The joint J is then
marked on the u/s face of the rock toe at a distance of from K. The phreatic line
is drawn by making a transition curve by eye judgment from the point J to the point
M on the base parabola. The transition curve is tangential to the vertical line at J, and
it meets the base parabola tangentially at M. It may be noted that the phreatic line
drops vertically in to the rock toe.
PHREATIC LINE FOR ZONED ERATH DAM WITH A CENTERAL CORE
For zoned earth dam the phreatic line construction depends mainly on the geometry
and thickness of the core section. B/c the permeability of shell material (example
75
sand) is quite large as compared to core material (example clay), the effect of outer
shells on the phreatic line in the core is negligible. As such the u/s shell has
practically no effect on the position of the phreatic line. The phreatic line can just
start from point B where the extension of the water level cuts the core. The d/s shell
in this case acts as a drain. Thus the usual practice is to draw the phreatic line for the
core section only.
For drawing the phreatic line, the focus F is to be located at the d/s toe of the core and
assuming the u/s shell as a reservoir. Then the core section is treated as a
homogeneous dam and the same of constructing phreatic line for homogeneous dam
is considered.
However, in this case, the phreatic line at the exit end will be slightly above the base
of the core so that the seepage water can flow under gravity through the d/s shell
which acts a drain (fig 5.8).
IN DAM:
The only measure is provision of impervious core within the body of the dam called
embankment zonation.
Embankment zonation : -for reducing seepage through the body of the dam, a core
of impervious material such as silt clay or clayey silt is generally provided. For most
effective control of through seepage and seepage during reservoir draw down, the
permeability should progressively increase from the core out towards each slope.
Sometimes flat slopes without drains are provided for some dams constructed with
impervious soils having flat embankment slopes & infrequent, short duration , high
reservoir levels, the phreatic surface may be contained well with in the d/s slope &
escape gradients may be sufficiently low to prevent piping failure.
IN FOUNDATION:
76
If the foundation consists of alluvial deposits of pervious sand and gravel with
impervious stratum at a great depth measures to be adopted are cut-off, u/s
impervious blanket and d/s berm.
Cutoff trenches: This is the most positive means of controlling the amount of
seepage and insuring that no difficulty will be encountered by piping through the
foundation or by uplift pressure at the down stream toe. Whenever economically
possible, seepage through a pervious foundation should be cut off by a trench
extending to bed rock or other impervious stratum.
Partial cutoff trenches The partial cut offs are effective only when they extend down
into an intermediate stratum of lower permeability. This stratum must be continuous
across the valley foundation to ensure that three- dimensional seepage around
discontinues stratum does not negate the effectiveness of the partial cutoff. Such type
of measures is effective when the foundation material is stratified alluvial deposit.
Sheet pilling cut offs: - A steel sheet pile cut off consists of interconnected sheet
piles to form a continuous impervious barrier. It is relatively expensive and leakage
through the interlocks b/n the individual piling is considerable. It is used occasionally
77
78
in combination with a partial cutoff trench as a means of increasing the depth of the
cutoff. Sheet piling cutoffs are practically limited to use in foundations of silt, Sand
and fine gravel.
Slurry trench cutoff: - is an important method of constructing positive cut offs when
wet conditions or deep cutoffs in alluvial valleys make conventional constriction
methods uneconomical.
q’ = pq
78
79
Fig 5.8
Some water always seeps through the dam and foundation even after adopting several
seepage control measures discussed earlier. The seeping water should be safely
drained through the dam and foundation without causing ill effects.
IN DAM:
Horizontal drainage blanket Rock toe
Chimney drain Strip drain
79
80
it is not effective if the embankment material has stratifications and the horizontal
permeability is greater than the vertical permeability.
Fig 5.9
ii) Rock toe: The rock toe is provided at the d/s toe of the earth dam and it forms part
of the dam. It consists of stones of size varying from 15 to 20 cm. The u/s face of the
rock toe may be vertical or inclined. A graded filter may be provided between the
rock toe and the soil mass as well as b/n the foundation and the rock toe to avoid
migration of materials.
The rock toe is suitable for low to moderate height of dams. The height of the rock
toe is generally b/n H/3 to H/4, where H is the height of the dam. Rock toe can also
be used in conjunction with horizontal drainage blankets.
Fig 5.10
iii) Strip drain: A strip drain is provided instead of a horizontal drainage blanket if
there is scarcity of pervious materials in the area. Transverse drains are provided to
carry water from the strip drain to another parallel drain located at the d/s toe of the
dam (refer figure).
80
81
Fig 5.11
iv) Chimney drain: A chimney drain is a vertical/nearly vertical drain located inside
the dam so that it intercepts all layers of the dam in the seepage zone. Thus it is
helpful in stratified embankments. A chimney drain renders the d/s portion of the dam
free from seeping water and it increases the stability of the d/s slope. It also helps in
reducing the pore water pressure during construction and sudden draw down
condition.
Chimney drains are rarely provided in homogeneous dams and they are provided d/s
of the impervious core in zoned earthfill dams. From the chimney drain water is
carried to d/s by a horizontal drainage blankets. The chimney drain should be
accompanied with proper filters.
Fig 5.12 81
Chimney Drain
82
IN FOUNDATION:
In general, the drainage systems provided for the dam can also serve for the purpose
of drainage of foundation. Additional measures such as mentioned below can be
taken in to account.
i) Toe drain and drainage blanket: The purpose of toe drains is to collect the seepage
water from the horizontal drainage blanket (construction in conjunction with it –fig)
and foundation to carry it to an outfall pipe which then discharges the water in to the
river or spillway stilling basin.
Toe drain pipes are usually of verified clay or perforated asphalt dipped corrugated
metal pipes placed in trenches excavated to the required depth below the ground
surface to ensure effective interception of seepage flow. Filters are provided as usual.
82
83
ii) Drainage trenches: Drainage trenches are used when a thin impervious top
stratum overlies a shallow pervious stratum of the foundation so that the trench can be
built to penetrate the pervious stratum substantially. They are similar in arrangement
with that of toe drains, but in this case there is no pipe provided to drain. The trenches
are excavated to the required depth and backfilled with properly graded layers in
accordance with the filter criteria such that the coarser materials are at the inner side.
Drainage trenches, however, are not effective if the underlying pervious stratum is
quite deep and stratified.
Drainage
Trench
Fig 5.14
iii) Relief Wells: Are generally used for drainage of the foundation if it consists of a
deep pervious stratum which is stratified and whose permeability increases with
depth. Relief wells are provided at or near the d/s toe of the dam to collect water
seeping through the foundation and to reduce the pore pressure in the foundation.
Relief well consists of an interior perforated pipe or a well screen with a minimum
diameter of 15 cm. The well screen is surrounded by a small thickness of gravel pack
which is properly graded so as to meet the filter criteria for the surrounding soil. (Fig.
). Seepage from the relief wells is usually discharged at the toe of the dam in the river
channel through the horizontal overflow pipe and a lined drainage ditch. The spacing
of the relief wells is usually b/n 15 to 30m.
83
84
iv) Vertical Sand drains: These drains consist of vertical holes drilled in the
foundation all along the base of the dam. These holes are filled with clean, course
sand of high permeability to form sand columns (Fig 12). These sand drains reduce
the path of drainage in the horizontal direction and help in the drainage of the
foundation. They also accelerate consolidation of the foundation soil by providing
drainage.
Vertical sand drains are quite effective for the drainage of soft clay foundation which
can not be easily drained by other methods. Vertical sand drains can also act as relief
wells and thus help in reducing the pore pressure and controlling under seepage.
84
85
Soft clay
stratum
The design of an earth dam essentially consists of determining such a cross sections
of the dam which, when constructed with the available materials, will fulfill its
required function with adequate safety.
Thus there are two aspects of the design of an earth dam, viz.
i) To determine the X-section of the dam and
ii) To analyses the stability of the proposed x-section.
For determining the X-section of an earth dam there are no mathematical analyses or
formula as in the case of rigid dams.
The design of slopes of earth fill embankments depends on the nature of the materials of
construction and the type of dam (i.e. zone, homogeneous & diaphragm). It depends on
the nature of the material used for the core and the shells and in the case of zoned
embankment on the relative proportion of them.
i) crest width:- The crest width of an earth fill dam depend on several
considerations such as:-
Sufficiency to keep the top flow line well with in the dam body when the
reservoir is full.
sufficiency to provide the embankment mass for resistance to earth quake
shock
Satisfactory for secondary requirement such as minimum road way width.
85
86
The additional safety provision generally various from 0.6 to 3m depending up on the
size of the reservoir, the height of the dam the reliability of the flood computation etc.
The free board should not be less than 2m in any case.
iii) Embankment slopes: - The design slopes of an embankment may vary
widely depending on the character of the materials available for construction,
foundation conditions and the height of the structure. The upstream slope may
vary from 1:2 to as flat as 1:4 (V:H) for stability usually it is 1:2.5 or 1:3. Flat
upstream slopes are sometimes used in order to eliminate expensive slope
protection.
The usual down stream slopes for small earth fill dams are 1:2 where a down stream
pervious zone is provided in the embankment and 1:2.5 where the embankment is
impervious. Theses slopes are stable for soil types commonly used when drainage is
provided in the design so that the down stream slope of the embankment does not be
come saturated by seepage.
The table below shows slopes recommended by Terzaghi.
iv. Slope protection: - usual types of surface protection for the upstream slope
against destructive wave actions are riprap and concrete pavement. The upstream
slope protection should extend from the crest of the dam to a safe distance below
minimum water level and ordinarily terminate on a supporting berm.
86
87
Usual type of surface protection of the upstream slope is stone riprap, either dumped
or hand placed. For thin layers, hand placed riprap may be economical than dumped
riprap.
V. Surface drainage: - may be necessary to prevent gull eying at the contact of the
embankment and valley slopes. This is done by providing a gutter concrete or stone
pavement.
Vi. Filters: - filers are always provided between any two dissimilar materials when the
difference in their particles is so great that the particles of the finer material can migrate
in to the voids of coarser material with seepage water & can cause piping.
There fore filters are provided:-
B/n the drainage system & the adjoin soils to prevent the migration of the soil
particles in to the drains.
B/n impervious zones (cores) of fine-grained soils and the pervious zones (shells)
of the coarse -grained soils for the same purpose.
D15 of the filter = 5 to 40 provided that the filter does not contain
D15 of base material more than 5 percent of material finer than 0.074 mm
Failure of an embankment dam can result from instability of either the upstream or down
stream slopes. The failure surface may lie with in the embankment or may pass through
the embankment and the foundation soil. The critical stages in u/s slope are at the end of
87
88
construction & during rapid draw down. The critical stages for the d/s slope are at the end
of construction & during steady seepage when the reservoir is full.
Stability of an embankment is determined by its resistance to shearing stresses that may
result from external loads (such as reservoir pressure & earth quake) and internal or body
force.
Various methods of slope stability analysis are available but the Swedish slip -circle or
slices method is the most common. In this method the factor of safety against sliding is
defined as the ratio of resisting moments to actuating moments (or the ratio of resisting
forces to actuating forces). The forces are computed taking a trial slip surface and
dividing the soil mass above the assumed failure surface in to some number of slices.
The potential surface of rupture is taken to be any cylindrical surfaces.
The figure shows a trial slip surface AB which is circular; the radius of the circle, r and
its center o.
The trial failure wedge is divided in to vertical slices (or strips) by drawing vertical lines.
The slices are usually of equal width, but not necessary so. The number of slices is
usually kept 5 to 15. The greater the number the more is accuracy. It is convenient to
have all the slices of equal width b, but not necessarily. In the case of the zoned section,
the slicing should be in such a way that the base of each slice is resting on only one type
of the material.
88
89
Fig 5.18 Slicing and consideration of forces and the direction of application (SWEEDISH CIRCLE
METHOD)
89
90
In the conventional Swedish circle method, it is assumed that the reactions E R and EL are
equal and opposite in direction and cancel each other. Like wise the U L and UR. Thus
there are four forces which are normally considered in the analysis viz, W4, C4, R4 and UB.
Resolving the Vector W in to its tangential and Normal components by drawing a
perpendicular from the tip of the vector W to the normal direction,
Where , is the angle which the normal makes with the vertical
Thus resolving all the forces in the normal and tangential direction,
On any trial surface, the safety factor against sliding is given by:
The resisting force is the internal frication resistance plus cohesion, if any
i.e. Resisting force = (N- ) tan + c L and T is the driving force
Where: - N= Normal force along the arc
90
91
Therefore
Various centers and radii are used and those computations are repeated until the arc
which gives the minimum safety factor is established. The slip surface which gives
minimum factor of safety is the critical. The minimum Fs should be greater than the
allowable one (1.5).
Summary of procedure for earth dam stability analysis
1. Take a trial slip surface and divide the wedge above the slip surface into 8 to 15
vertical slices.
3. Measure the angle which the normal makes with the vertical and compute N and T.
4. Determine the pore water pressure, u, at the base of the slice or otherwise. Compute the
force UB due to the pore water pressure as:
5. Determine the cohesive force,
6. Determine the factor of safety for slip surface from equations given above.
91
92
7. Repeat the procedure for a number of other trail surfaces. The trail surface which gives
the minimum factor of safety is the most critical circle. The minimum factors of safety
should be greater than the specified safe value.
But how to determine the most critical circle???? Fellenius suggested something……
In the course of stability analysis, it is quite cumbersome to take so many trial surfaces
and hence Fellenius has shown, to reduce number of trials, suggested a line called
Fellenius line (line AB) for a homogeneous slope (see fig below) on which the most
critical circle lies.
Fig 5:19 Fellenius Line for determining the most critical circle
To draw the Fellenius Line AB, point B is located at a depth of H below the toe and 4.5H
from it (Fig 5 :19). Point A is then located by drawing two lines PA and QA. The line PA
makes an angle with the slope line and PQ and the line QA makes an angle with
the horizontal line drawn through the point Q. The values of and are given in table
along with fig 5: 19 above.
The center of the most critical circle may lie anywhere on the line AB or its extension.
However the exact position of critical circle is obtained after conducting the stability
analysis for different points. The center O with minimum factor of safety is the center of
92
93
the most critical circle. The above procedure of drawing Fellenius line is applicable for
soils. For a purely cohesive soil, the point A itself represents the center of the
most critical circle.
For Zoned dams, taking point A and go with successive trials may help at arriving the
most critical failure circle. The so called nine point matrix method may help a lot with
this regard (Refer Arora, pp 403-405).
Earth dam failures are caused by improper design, frequently based on insufficient
investigation and lack of control and maintenance. The various causes may be grouped in
to the following three broad categories:-
i) Hydraulic failure
ii) Seepage failure
iii) Structural failure
93
94
Foundation Slide: - When the foundation of soft soil such as fine silt, soft
clay etc. the entire dam may slide over the foundation. Partial failures of
embankment may also occur over part of the foundation where seams of
fissured rock, shale’s or soft clay may occur.
Embankment Slide: - When the embankment slopes are too steep for the
strength of the soil, they may slide causing dam failure. For the upstream
slope the critical condition is during sudden draw down and for the down
stream slope the full reservoir and steady seepage condition is the most
critical.
The cost producing large quantities of rock for the construction of rock fill
dams makes this type of dam economical only in remote areas where the cost
of concrete would be high or in areas where there is a scarcity of earth fill
materials and the only material for construction of the structure consists of
durable hard rock.
A rock fill dam is an embankment which uses variable sizes of rock to provide
stability and an impervious membrane to provide water tightness.
The watertight membrane for a rock fill dam should be constructed on the
upstream slope where its condition can be inspected when the reservoir is
drawdown. And repairs made as necessary. Usually the membrane will consist
of Portland cement concrete although steel plates and wood planking have
been used to the limited extent of the life of those materials.
Rock fill dams can prove economical when any of the following conditions
exist.
94
95
Impermeable membrane
Rock fill
U/S cut-off
Rock cushion/rubble masonry
The membrane is usually placed on the u/s face, and in some instances it is
placed in the center of the rock fill. The material of the membrane could of
concrete, asphalt, steel, timber or impervious soil.
The rock fill usually owns the natural slope at the d/s face. The dry rubble
masonry/well compacted rock is provided b/n u/s impervious membrane and
the rockfill to make smooth compact bedding for the impervious membrane.
95
96
96
97
Foundation requirement: - The foundation requirement for a rock fill dam is less sever
than for a concrete gravity dam. But more sever than earth fill dams. Rock fill dams
require foundations which will result in a minimum of settlement.
Generally rock foundations consisting of hard, durable rock which can not be softened or
eroded appreciably by percolating water is recommended.
To prevent seepage, the foundation must be grouted.
Cutoff wall: - A watertight seal must be provided along the contact of the impervious
membrane with the foundation and abutment at the upstream toe of the dam to prevent
seepage under the dam. In existing dams, this seal has been in the form of a concrete
cutoff wall which extends from the upstream toe of dam to the bed rock. The cutoff wall
must provide adequate support for the weight and thrust of the membrane in addition to
its function of preventing under seepage.
Dowell slab cut-offs have the advantage of not requiring extensive excavation in rock,
thereby allowing grout operation to begin earlier saving time and reducing design costs.
The depth of penetration of the cutoff wall in to bedrock depends up on the character of
the foundation rock. If the rock is sound, the cutoff wall should extend in to the
foundation rock not less than 1 meter. A deeper wall or special treatment such as
grouting may be required if the rock is not sound or if open joints or broken rock
structure exists.
Embankment Design
Selection of embankment material: - The rock must be hard & durable to resist
excessive breakdown during the hauling and placing operation and must be located near
the dam site for economy .The rock also should with stand disintegration under the action
of freezing and thawing.
Un-weathered igneous and metamorphic rocks are of satisfactory quality for rock fill.
Sedimentary rocks should be avoided. The rock should be abrasion resistant.
The rock produced in the quarry or obtained from natural sources should be well graded
from 0.014 - 0.73 cubic meters in size and should contain less fine than sufficient to fill
the voids.
97
98
dams, the downstream slope should be equal to the angle of repose of dumped rock fill
(about 1.4 to 1) & the u/s slopes should be 2:1 to facilitate construction of the u/s
impervious facing. The u/s and d/s slopes depend up on the type of impervious membrane
and its location. Central core/sloping membrane slope ranges from 2:1 to 4:1 u/s and d/s
slope. For u/s membrane type rockfill dam, u/s slope ranges from 1.3: 1 to 1.4:1 and d/s
slope approximate the natural slope of the rock fill.
Asphalt or concrete faced dams have u/s slopes of range 1.6:1 to 1.7: 1 to facilitate the
construction of the membrane whereas steel and concrete faced dams could have slopes
in the range of 1.3: 1 to 1.4:1. D/s slopes usually range from 1.3: 1 to 1.4:1 for both above
cases.
Rock fill zone: - The placement of the rock fill is one of the most important operations in
the construction of a rock fill dam as it is essential to minimize total settlement and the
possibility of damage to the impervious membrane. Settlement of rock fill takes place in
two stages. The first major settlement occurs during the construction of the rock fill. This
stage of settlement has a minor bearing on the security of the impervious membrane,
provided the membrane is not placed concurrently with the rock. The second major stage
of settlement occurs as the reservoir fills and the thrust due to water load is transmitted to
the rock fill.
For small rock fill dams placement of rock in relatively thin layers is considered to be
advisable. The rock should be dumped on the embankment and spread in layer with a
maximum thickness of 1 meter. The spreading operation will assure a minimum number
of large voids and provide a compact rock fill.
Preparation of upstream facing: - for small dams a zone of graded sand and gravel or
quarry fines when well compacted present smooth bedding for the impervious membrane.
This zone should have a minimum horizontal width of 1 meter to facilitate compaction. It
should be constructed in 30 cm layers thoroughly wetted and compacted. The material
98
99
used in this zone should be pervious and well graded from 0.6 cm to 7.5 cm. After
placing the upstream face can be dressed smooth to accept any type of membrane.
Design of upstream facing: - Reinforced concrete pavement is the most common type
although asphaltic concrete. Steel and timber planking may serve the purpose.
For low dams, a reinforced concrete slab with a minimum thickness of 20 cm should be
provided. Horizontal and vertical expansion joints are not required b/c of low reservoir
head and minor amount of settlement expected. However, vertical joints may be
required to compensate for horizontal expansion on low dams of considerable length.
Reinforcement should be provided: areas of steel equal to 0.5% and 0.7% of the concrete
area, vertically and horizontally is considered good practice.
Timber planking is not recommended for general use, although it is often the cheaper
type of membrane to construct. The principal objections to this type of construction are
the danger of loss by fire at low water and the relatively short life of timber construction
when alternately exposed to wetting and drying.
Zone C: The larger d/s zone of the dam consists of best quality, larger sized compacted
rock. This zone provides high stability to the section.
Zone B: Rock of lesser quality than such as excavated from spillway, used to minimize
total dam cost.
Zone A: well graded small sized rock gravel; this is used to provide bedding to the u/s
membrane and to retard excess water losses when the membrane cracks.
In general, materials in zones B and C should grade from fine rock u/s to course rock d/s
with the largest and strongest material placed in the lower d/s portion of zone C.
For central earth core, rockfill dams, the larger and the stronger rock should be placed in
the d/s rock fill zone and grade from fine rock next to the filter to course rock near the d/s
slope.
The u/s rock fill zone may be rock of lesser quality than the d/s zone and grade from fine
at the filter to course at the u/s face.
99
100
Fig 5.24 Typical section of decked type rockfill dam with zones
100
101
VI. SPILLWAYS
6.1 Introduction:
Spillways are provided for storage dams to release surplus or flood water, which cannot
be contained in the allotted storage space, and at diversion dams to bypass flows
exceeding those, which are turned into the diversion system.
There are several spillway designs. The choice of design is a function of the nature of the
site, the type of dam and the overall economics of the scheme. The importance of a safe
spillway cannot be overemphasized; many failures of dams have been caused by spillway
of insufficient capacity. Ample capacity is of paramount importance for earthfill and
rockfill dams, which are likely to be overtopped, whereas concrete dams may be able to
withstand moderate overtopping. Usually, increase in cost is not directly proportional to
increase in capacity. Very often, the cost of a spillway of ample capacity will be only
moderately higher than that of one which is obviously too small.
A spillway may be located either within the body of the dam or at one end of the dam or
entirely away from the dam as an independent structure.
The required capacity of a spillway, i.e. the maximum outflow rate through the spillway,
may be determined by flood routing and requires the following data:
i) Inflow hydrograph (plot of rate of inflow vs. time)
ii) Reservoir capacity curve (plot of reservoir storage Vs water surface
elevation)
iii) Discharge curve (plot of rate of outflow Vs reservoir water surface
elevation).
By flood routing, corresponding to a particular inflow hydrograph, the maximum outflow
rate and maximum rise in the water surface may be determined.
101
102
i) Control Structure: Major component, which regulates and controls the outflow
from the reservoir. It prevents outflow from a reservoir below a fixed level and
allows the flow when the water surface in the reservoir rises above the level. In
most of the cases, the control section consists of a weir, which may be sharp
crested, ogee, or broad crested. Gates may also be provided on the crest of the
control structure to regulate the flow of water from the reservoir.
ii) Discharge channel (or waterway, or conveyance structure): Its main function
is to convey the water safely from the reservoir downward to the river. Located
next to the control structure. The conveyance structure may be the d/s face of the
spillway, an open channel excavated along the ground surface, a closed conduit
placed through or under the dam, or a tunnel excavated through an abutment.
iii) Terminal structure or energy dissipator: Provided to dissipate the high energy
of flow from spillway before the flow is returned to the river. It is provided on the
downstream of the spillway.
iv) Entrance or approach channel and outlet channel: Entrance channels may be
required to draw water from the reservoir and convey it to the control structure.
Similarly outlet channels may be required to convey the spillway flow from the
terminal structure to the river channel below the dam. The entrance and outlet
channels are not required where a spillway draws water directly from the reservoir
and delivers it directly back into the river; e.g. overflow spillway. However, in the
case of spillways placed through abutments or through saddles or ridges, the
entrance and outlet channels may be required.
1. According to their function (or based on the time when the spillway comes into
operation) as
102
103
(a) Service (or main) spillways: Designed for frequent use in conveying flood
releases from the reservoir to a watercourse downstream from a dam. It is
designed to pass the entire design flood.
(b) Auxiliary Spillways: - Designed for infrequent use and may sustain limited
damages when used. Some damages of the structure from passage of
infrequent flood is permissible. It is provided as a supplement to the main
spillway and its crest is so located that it comes into operation only after the
floods for which the main spillway is designed are exceeded. It is provided in
conjunction with the main spillway. The total capacity of the spillway is then
equal to the sum of the capacities of the main and auxiliary spillways.
This is the simplest type of spillway, which is constructed in the form of low height weir
having d/s face either vertical or nearly vertical. Water drops freely from the crest, and
the underside of the falling nappe is ventilated sufficiently to prevent a pulsating,
fluctuating, jet. Occasionally, the crest is extended in the form of an overhanging lip to
direct the small discharge away from the face of the overfall section.
103
104
Since vacuum gets created in the underside portion of the falling jet, sufficient ventilation
of the nappe is required in order to avoid pulsating and fluctuating effects of the jet.
If no artificial protection is provided on the d/s side of the over-fall section, the falling jet
usually causes the scouring of the stream bed and will form a deep plunge pool.
The free over fall spillway is suitable for thin arch dams and for those dams with nearly
vertical downstream face and would permit free fall of water. Free over-fall spillways are
used where the hydraulic drops from head pool to TW are not in excess of about 6m.
Spillway crest
Overhanging lip
Free overfall
Overflow spillways are by far the most widely adopted. They are mainly used on
masonry or concrete dams, and if used with earth fill and need a separate concrete
structure.
An overflow spillway is an improvement upon the free overfall spillway. The essential
difference between the free overfall spillway and the overflow spillway is that in the case
of the former the water flowing over the crest of the spillway drops as a free jet clearly
away from the downstream face of the spillway, while in the case of the latter the water is
guided smoothly over the crest of the spillway and is made to glide over the downstream
face of the spillway.
The shape of the crest or the upper curve of the ogee profile of this spillway is made to
conform closely to the profile of the lower surface of the nappe (or lower nappe) or sheet
of water flowing over a ventilated sharp-crested weir when discharging at a head equal to
the design head of the spillway.
104
105
At the design head (H = Hd) the water flowing over the crest of the spillway will remain
in contact with the surface of the spillway as it glides over it and optimum discharge will
occur. In this case no pressure is exerted on the spillway by the flowing water, as there
will be atmospheric pressure along the contact surface between the flowing water and the
spillway.
At head less than the design head (H < H d) the overflowing water will remain in contact
with the surface. The natural trajectory of the nappe falls below the profile of the spillway
crest, then there will therefore be positive gage pressures over the crest, as the nappe
tends to be depressed. In this case, as the spillway is supporting a sheet of flowing water
backwater effect will be created and the discharge will be reduced.
At a head greater than the design head (H < H d), the nappe trajectory is higher than the
crest profile, and the overflowing water tends to break contact with the spillway surface
and zone of separation will be formed in which negative or suction pressure will be
produced. The effect of negative pressure will be to increase the effective head and
thereby increase the discharge. This may result in cavitation. However, in practice, this
pressure reduction is not normally a serious problem unless H > 1.5 H d. Indeed recent
work suggests that separation will not occur until H approaches 3 Hd.
The shape of the nappe shaped profile depends upon the head, the inclination of the
upstream face of the spillway and the height of the spillway above the streambed or the
bed of the entrance channel (which influences the velocity of approach to the crest of the
spillway).
Several standard ogee shapes have been developed by U.S. Army Corps of Engineers at
their Waterways Experimental Station (WES). Such shapes are known as 'WES' standard
spillway shapes. The downstream profile can be represented by:
105
106
(6.1)
Where:x, y = Co-ordinates of the points on the crest profile with the origin at the highest
point of the crest called APEX.
Hd = Design head excluding head due to velocity of approach,
K, n = Constants depending on the slope of the upstream face.
The crest equation gives the crest shape downstream from the origin of coordinates. This
equation is applicable to positive values of x and y.
HD
106
107
a b R1 R2
U/s Face K n Hd Hd Hd Hd Crest Equation
slope
Vertical 2.000 1.850 0.175 0.282 0.200 0.500
1H: 3v 1.936 1.836 0.139 0.237 0.210 0.680
2H: 3v 1.936 1.810 0.115 0.214 0.220 0.480
3H: 3v 1.873 1.776 0.000 0.119 (Straigh 0.450
t line)
According to U.S. Army Corps of Engineers, the u/s curve of the ogee spillway (u/s of
origin, though in the form of compound circular curve) having a vertical u/s face, should
have the following equation:
(6.2)
Where the upstream profile extends up to
The corresponding y value is equal to 0.126 Hd.
The curved profile of the crest section is continued tangentially along the straight sloping
surface, which forms the d/s face of the spillway. The location of the point of tangency
(P.T) depends on the slope of the straight portion of the d/s face of the spillway, which in
turn depends on the stability requirements and on the features of the stilling basin at toe
of the spillway. The slope of the straight portion varies between 1V: 0.6H to 1V: 0.8H. At
the end of the sloping surface a curved bucket is provided to create a smooth transition of
flow from the spillway to the outlet channel or the river on the d/s side and prevent
scoring.
(6.3)
V= velocity of flow at to e of spillway [m/s
H = head excluding head due to velocity of approach (m)
Neglecting energy loss over the spillway, velocity of flow v at the toe will be
(6.4)
Where Z = the fall, m
Ha = head due to velocity of approach, m
y = depth of flow at the toe, m
107
108
C = coefficient of discharge
Le = effective length of crest of spillway, m
HD = total head over the crest including that due to velocity of approach.
HD = Hd + Ha
For high ogee spillway Ha is very small, and HD ≈ Hd
a) Effect of Depth of Approach: With increase in the height of spillway the velocity of
approach decreases and the coefficient of discharge increase. Model tests have shown
that the effect of approach velocity is negligible when the height of the spillway above
the streambed is equal to or greater than 1.33 Hd (P ≥ 1.33 Hd) where Hd is the design
head excluding the head due to velocity of approach
A plot of C versus P/H D is shown below, where HD is the design head including head due
to velocity of approach (i.e. HD = Hd + Ha). It may be observed from this plot that there is
a marked increase in the value of C till the height of the spillway (P) becomes equal to
108
109
twice the design head HD. With further increase in P there is no much increase in the
value of C.
(b) Effect of heads differing from the design head: The plot of (C/C’) versus (H e/HD)
for a spillway of height P above stream bed greater than 1.33 H d, where C is coefficient
of discharge corresponding to the actual head of flow H and C’ is the coefficient of
discharge corresponding to the design head H D. It may be observed from this plot that
with increase in the value of (H e/HD) the value of (C/C’) increases. In other words, with
increase in the head H the coefficient of discharge increases. However, for H e< HD, C <
C’; and for He > HD, C > C’.
109
110
Since for heads of flow higher than the design head higher will be the coefficient of
discharge, if the spillway crest is designed by assuming a lower design head, for most of
the range of heads of flow higher coefficient of discharge will be obtained.
However, the design head should not be less than about 80% of the maximum head in
order to avoid the possibility of cavitation.
Model tests have shown that for P > 1.33 H d the head due to velocity of approach is
negligible and when the total head of flow is equal to the design head, i.e. H e = HD, the
coefficient of discharge is equal to 2.2.
When the actual operating head is less than the design head, the prevailing coefficient of
discharge, C, tends to reduce, and is given by
(6.6)
(c) Effect of upstream face slope: For small values of the ratio (P/H D) a spillway with
sloping upstream face has a higher coefficient of discharge than a spillway with vertical
upstream face. However, for large values of the ratio (P/H D) the coefficient of discharge
for spillways with sloping upstream face tends to decrease.
110
111
111
112
For flow at design head the average values of Kp may be assumed as follows:
Pier coefficients, Kp:
1. Square nosed piers with corners rounded on a radius equal to about 0.1 of pier
thickness → Kp =0.02
2. Round-nosed piers → Kp = 0.01
112
113
113
114
The water flowing over the spillway acquires a lot of kinetic energy by the time it reaches
near the toe of the spillway due to the conversion of potential energy into kinetic energy.
If arrangements are not made to dissipate this huge kinetic energy of the water, and if the
velocity of the water is not reduced, large-scale scour can take place on the downstream
side near the toe of the dam and away from it. These arrangements are known as energy
dissipation arrangements or energy dissipators.
For the dissipation of the excessive kinetic energy possessed by the water the two
common methods adopted are:
Hydraulic jump can form in a horizontal rectangular channel when the following relation
is satisfied between the pre-jump depth (y1) and post – jump depth (y2).
(7.1)
(7.1)
Where y1 = pre-jump (initial) depth
y2 = post- jump (sequent) depth
Fr1 = Froude number of the incoming flow
For a given discharge intensity q over a spillway, y1, will be equal to q/v1; and v1 (mean
velocity of incoming flow) is determined by the drop H 1 , if head loss is
neglected, (see fig. 7.1)
114
115
Hence, for a given discharge intensity and given height of spillway, y 1 is fixed and thus y2
is also fixed. But the availability of a depth equal to y 2 in the channel on the downstream
cannot be guaranteed as it depends upon the tail water level y0 which depends on the
hydraulic conditions of the river channel on the downstream side. The values of y o
corresponding to different values of q may be obtained by actual gauge discharge
observations and plot of yo versus q prepared, known as Tailwater Rating curve
(T.W.R.C.). The post-jump depth (y2) for all those discharges, are also computed from
equation (7.1) and a plot of y2 versus q may be made which is known as jump height
curve (J.H.C.). If J.H.C. and T.W.R.C. are plotted on the same graph, five possibilities
exist regarding the relative positions of these curves.
The energy dissipation arrangement that can be provided is dependent upon the relative
positions of T.W.R.C. and y2 curve.
Condition 1: In this case for the entire discharges jump will develop close to the toe of
the spillway. In such a case, a simple horizontal concrete apron may be provided whose
length is equal to the length of the jump corresponding to the maximum discharge over
the spillway.
Condition 2: The jump forming at toe will be drowned out by tailwater, and little energy
will be dissipated.
115
116
Water may continue to flow at high velocity along the channel bottom for a considerable
distance. The problem can be solved:
i) By constructing a sloping apron over the riverbed extending from the
downstream surface of the spillway. The jump will form on the sloping apron
where depth equal to y2 (lesser than the tailwater depth at toe) is available.
The slope of the apron is made in such a way that proper conditions for a jump to occur
somewhere on the apron at all discharges.
ii) By providing a roller bucket type energy dissipater. Also a drop provided in the
riverbed to lower the TWL can be used to dissipate the energy.(Fig 7.2c).
Condition 3: In this case the jump will develop at a certain section far downstream of the
toe of the spillway. This is the most frequent one, and shows that a stilling basin (with a
depressed horizontal apron) is required for all discharges in order to produce a jump close
to the toe of the spillway.
If the tailwater is very low, ski-jump type dissipator may be provided. But it needs sound
rock at the riverbed, since part of the dissipation takes place by impact; the rest being
dissipated by aeration and diffusion in air.
Condition 4: In this case the following measures may be taken to develop jump close to
the spillway.
i) Provide a stilling basin with an end sill for developing a jump at low discharges
and combine the basin with a sloping apron for developing a jump at high
discharges.
ii) Provide a sloping apron which lies partly above and partly below the riverbed so
that jump will develop at lower portion of the apron at low discharges and at
higher portion of the apron at high discharges.
116
117
Fig. 7.2e.Condition 4
In this case, the tail water depth is insufficient at low discharges and is greater at high
discharges.
Condition 5: This condition is just the reverse of condition (4) and the same arrangement
that was made for condition (4) will serve the purpose. (Fig 7.2e)
A stilling basin consists of a short, level apron at the foot of the spillway. It must be
constructed of concrete to resist scour. The function of the basin is to decelerate the flow
sufficiently to ensure the formation of a hydraulic jump within the basin. The jump
dissipates much of the energy, and returns the flow to the subcritical state.
The passage of water from a reservoir into the downstream reach involves a number of
hydraulic phenomena such as the transition into supercritical flow, supercritical non-
aerated and aerated flow on the spillway, entry into the stilling basin with a transition
from supercritical to subcritical flow, and echoes of macro-turbulence after the transition
into the stream beyond the basin. It is, therefore, possible to consider the energy
dissipation process in the following stages, all of which may be combined.
117
118
( 7.2)
(7.2)
Where V’ = the (supercritical) velocity at the end of the spillway
(7.3)
and taking
Hence, (7.4)
(7.4)
The ratio of the energy loss, e, to the total energy E (i.e. relative energy loss) is
(7.5)
(7.5)
For the ratio of the height P of the spillway crest above its ending and the overflow head
H, with P/H < 30, and smooth spillways (Novak & Cabelka, 1981),
(7.6)
(7.6)
For a given P, φ increases as H increases, i.e., if for a given discharge Q the spillway
width b decreases and thus q increases.
118
119
Thus, for P/H = 5, φ = 0.92 and the relative head loss (e/E) is 15%, where as for P/H =
25, φ = 0.61 and relative head loss is 62 %.
The value of head loss coefficient (ζ) could be increased (and φ decreased) by using a
rough spillway or by placing baffles on the spillway surface. However, unless aeration is
provided at these protrusions, the increased energy dissipation may be achieved only by
providing an opportunity for cavitation damage.
Referring to the notation is Fig (7.3) and to equations (7.2) and 7.4) we can write
(7.7)
(7.7)
(7.8)
(7.8)
The stilling basin depth is then given by
(7.9)
(7.9)
and the length of the stilling basin is given by
(7.10)
(7.10)
where σ´ and k are coefficients derived from laboratory and field experiments.
According to Novak and Cabelka Coefficients σ´ and k can be taken as 1.1 <
and 4.5 < k < 5.5, where the lower value of k applies for Fr1 > 10 and the higher for Fr1 ≤
3.
119
120
When applying equations (7-7) –(7-10) we start with a known discharge q and the
corresponding downstream depth y0 and apply the iterative procedure, which follows:
Take the energy (reference) datum at downstream riverbed level, and compute E
assuming an initial value of y' = 0;
Choose a suitable value of
Compute y' for qmax from equation (3.7); y2 from equation (3.8); and y' from equation
(3.9) (From a chosen value of safety coefficient,
Compute y0 (from uniform flow equation – Manning, Chezy) and compare it with y2
If y2 < y0, no stilling basin is required; if y2 y0 stilling basin is required and therefore
compute y´ with 1.1 < σ´ < 1.2 from equation (3.9);
Take new reference datum at basin bed level; and calculate new E and repeat steps 2-4 to
check that
Repeat the above steps at least for one smaller q to check whether the designed stilling
basin is adequate for lower discharges as well.
Note: Equations (3.8) and (3.10), and thus the design under discussion, apply to
basins with a horizontal floor only.
120
121
The hydraulic jump entrains a substantial amount of air additional to any incoming
aerated flow. The main significance of the presence of air in the jump region is the
requirement of higher stilling basin sidewalls due to higher depth of flow.
The major problems in spillway stilling basin are cavitation, uplift, and abrasion.
The highly turbulent nature of the flow in the hydraulic jump induces large pressure
fluctuations and is the cause of cavitation. Cavitation number can be expressed as
(7.11)
where P´ is the deviation of the instantaneous pressure P from the time average pressure.
If σ falls below a critical value, σc, then cavitation occurs.
Another serious structural problem in hydraulic jump stilling basins is the effect of uplift
pressures due to the dam drainage system or the tailwater level or the water table in the
basin bank, which is aggravated by the macro-turbulent pressure fluctuations underneath
the jump. Therefore, it is sensible to design the floor slab for the full downstream uplift
pressure applied over the whole area of the floor with the basin empty or the uplift
pressure head equal to the root mean square value of pressure fluctuations of the order of
0.12V12 /2g (V1= inlet supercritical velocity) applied under the whole full basin.
Furthermore, all contraction joints should be sealed, no drain openings should be
provided, and the floor slab should be as large as possible and connected by dowels and
reinforcement (ICOLD, 1986).
Abrasion of concrete in the basin could take place if this is also used for bottom outlets
carrying abrasive sediments (unlikely to happen for V<10m/s), or from sediment drawn
into the basin from downstream either by bad design or operation. The basin should be
self-cleaning to flush out any trapped sediment.
The prevention of vibration of basin elements (due to turbulence of the flow) also
requires massive slabs, pinned to the foundation when possible.
Although the stilling basin based purely on a simple hydraulic jump works well and
relatively efficiently, in certain conditions other types of basins may produce savings in
construction costs. Certain accessories such as chute blocks, baffle blocks (or floor
blocks), and end sills (or baffles) are usually provided in the stilling basins to reduce the
length of the jump and thus to reduce the length and the cost of the stilling basin.
Moreover, these accessories also improve the dissipation action of the basin and stabilize
the jump.
121
122
The type of stilling basin to be provided depends on the type of jump, which in turn
depends on the Froude number Fr1 of the incoming flow.
7.2.5.1.1 Stilling basin for 1.7 < Fr1 < 2.5 (Type I)
Only horizontal apron needs to be provided. The flow does not have much
turbulence and hence no accessions are required. However, the apron must be
sufficiently long to contain the entire jump. The length of the apron should be the
length of the jump (i.e. 5y2 = L, and (L 4y2) where y2 = sequent depth).
7.2.5.1.2 Stilling Basin for 2.5 < Fr1 < 4.5 (Type IV)
Type IV stilling basin is found effective. It is provided with chute blocks and end sill is
optional. The length L of the stilling basing may be obtained from the following table.
Fr1 2 3 4 5
L/y2 4.3 5.3 5.8 6
True hydraulic jump will form. Depending on the incoming velocity of flow two types of
basins are developed:
a) V1 < 15 m/s: Type III stilling basin may be adopted. This basin utilizes chute
blocks, baffle blocks and end sill (the size, spacing and location of the chute and
baffle blocks are shown in the Figure). The length of the stilling basin and the
height h3 and h4 of the baffle blocks and the end sill may be obtained for
different values of Fr1 as follows:
b)
Fr1 5 6 8 10 12 14 16
The use of chute blocks, impact baffle blocks, and an end sill shortens the jump length
and the stilling basin. This basin relies on dissipation of energy by the impact blocks and
on the turbulence of the jump phenomena for its effectiveness. Because of the large
impact forces to which the baffles are subjected by the impingement of high incoming
velocities and because of the possibilities of cavitation along the surfaces of the blocks
122
123
and floor (due to downstream suction), the use of this basin should be limited to heads
where the velocities do not exceed 15 m/s.
c) V1 > 15 m/s: Here impact baffle blocks are not employed and they are
designated as Type II stilling basin. Because the dissipation is mainly
accomplished by hydraulic jump action, the basin length will be greater than that
indicated for type III basin.
However, the chute blocks and dentated end sill (instead of solid end sill) will still be
effective in reducing the length from that which would be necessary if they were not
used. In this basin baffle blocks are not provided because.
i) due to the high velocities of incoming flows these blocks will be subjected to
excessively large impact forces, and
ii) There is a possibility of cavitation along the downstream face of these blocks
and the adjacent floor of the basin due to large negative pressure being
developed in this region.
The length L of Type II stilling basin may be obtained for different values of F r1 from the
following table
Fr1 5 6 8 10 12 14
L/y2 3.85 4.0 4.2 4.3 4.3 4.3
When the tail water depth is too great for the formation of a hydraulic jump (i.e. when
TW depth are too large as compared to the sequent depths required for the formation of
hydraulic jump), dissipation of the high energy of flow can be effected by the use of
submerged bucket deflector.
They are of two types, viz.
i) Solid roller bucket
ii) Slotted roller bucket
Solid Roller Bucket: Consists of a bucket like apron with a concave circular profile of
large radius and a deflector lip. When water flows over the bucket the entire sheet of
water leaving the bucket is deflected upwards by the bucket lip and two rollers are
developed. One of the rollers, called bucket roller, moves in counterclockwise direction
and is developed on the surface of the bucket. The other roller moving in clockwise
direction, called ground roller, is developed on the ground surface immediately
downstream of the bucket. The movement of the rollers, also with the intermingling of
the incoming flows, causes the dissipation of energy.
123
124
Figure 7.4
7.3.1 Slotted Roller Bucket: Consists of a bucket like apron with a concave circular
profile of large radius and a slotted or dentated deflector lip. Its action is, in general, same
as solid roller buckets. The two rollers are also developed in this case. However, in this
case water leaves the lip at a flatter angle and only a part of it is deflected upwards. Thus
surface boil is considerably reduced and less violent ground roller occurs which results in
a smoother flow on the downstream side.
124
125
This type of dissipater has a longitudinal profile, which resembles the submerged bucket.
However, the deflector is elevated above the tail water level, so a jet of water is thrown
clear off the dam and falls into the stream well clear off the toe of the dam. Spillways
may be arranged in pairs, and then the jets made to angle inwards so that they converge
and collide in mid – air. This breaks up the jets, and is very effective means of energy
dissipation.
The ski – jump bucket may be used where the tail water depth is less than the sequent
depth required for the formation of hydraulic jump and the riverbed is composed of stiff
rock. In this case, the energy is dissipated by air resistance, breaking up of the jet into
bubbles and the impact of the falling jet against the riverbed and tail water.
Figure 7.6
The use of ski-jump brings substantial economies where geological and morphological
conditions are favorable, and particularly where the spillway can be placed over the
power station. The head loss in the jet itself, whether solid or disintegrated, is only about
12% (Novak, 1996). But if the jet is split into several streams, which collide, substantial
energy will be dissipated. The main benefit for energy dissipation from jet spillways is in
the impact into the downstream pool. The major amount of energy dissipation occurs in
the region where the jet plunges into the tailwater.
As the flow increases, a ‘sweep-out’ discharge is attained at which point the flip-bucket
starts to operate properly wit a jet. Here, the impact zone of the jet has to be as far away
as possible from the bucket to protect the structure against retrogressive erosion. The jet
trajectory is hardly affected by air resistance for v < 20 m/s, but for velocities of 40 m/s
125
126
the throw distance can be reduced by as much as 30% from the theoretical value given by
(V2/g) sin2 θ.
(7.12)
126
127
127
128
128
129
129
130
An outlet is a closed conduit formed in the body of the dam. It may also
be in the form of a pipe or tunnel that passes through the hill side at one
end of the dam. The function of an outlet is to discharge the stored water
in to the channel d/s. For a concrete (or masonry) dam, the outlets pass
through the body of the dam and are called sluice ways.
For earthen dams, it is preferred to place the outlets outside the limits of
the embankments. But if no adjacent hill site is available & there is no
alternative left but to pass the sluiceways through the dam, projecting
collars, must be provided so as to reduce seepage along the outside of
the conduit. The seepage is thus, reduced by increasing the length of the
seepage path by at least 25 percent.
If L is the total length of sluiceways from u/s to d/s, the length of the
seepage path will be given as
L+ (2x) N or 2NX 0.25L
Where N is the number of collars, X is the projection of the collar
measured from the outer face of the conduit & L is the length of the
conduit.
Attention should be given to the design of entrance of outlet. In a square-
edge entrance, separation may occur. To reduce the loss at entry bell
mouth entrance is usually provided for high velocity outlet works.
Where Q= discharge
A= area of outlet sluice
H= differential head causing
flow i.e the difference of u/s &
d/s water level
131
132
The net effective head which is responsible for flow, should be taken
as Heff = differential head (H) – head loss
132
133
133
134
135
135
136
A dry intake tower will therefore have water inside the tower if its gates
are closed, whereas the wet intake tower will be full of water even if the
gates are closed.
When the entry ports are closed a dry intake tower will subjected to
additional buoyant force & hence must be of heavier construction than
the wet intake towers. However, the dry intake towers are useful and
beneficial in the sense that water can be withdrawn from any selected
level of the reservoir by opening the port at that level
These racks are generally bar screens, made from steel bars spaced at 5
to 15 cm center to center in both directions depending upon the
maximum size of the debris required to be excluded from entering the
conduit.
The velocity of flow through the trash rack is kept low (generally less
than 0.62m/s) so as to minimize losses.
136
137