Gst NO :- 09AIUPY6205D1ZR

Mobile:- 7388945503

8887886059
Akchhanshi Traders
Email:- [email protected]
91 Pachkhura Mamna Sarila Hamirpur210432
SNO :- CAMP DATE :-15/11/2022

WORK ORDER

To,

Mr.Pushpendra Singh

S/o Santhosh singh Bus Stand ke

pass 530 kailawoan Lalitpur

PIN-284402

Mob:-9621863529

Reference: Your Quotation/Letter No NIL

We are pleased to confirm our work order for carrying out Erection work of new11kv feeders for
water

treatment plant in Lalitpur district under JJM mission mahrauni tehsil as per the terms & conditions

stated here under.

Particular Amount
S.NO
1 Erection of new 11kv line on 8.5mtr long PCC /11mtr long STP
complete including Erection of PCC/STP pole in soft and hard rock, grouting of 1880.00
pole, (including material of grouting),installation of crossarm, f-clamp pin
insulator with pin ,Earthing of poles, plinth of poles,installation of danger board
,number plate, tree cutting, shifting of poles ,sagging of conductor with
commissioning of line etc. includingtransportation

2 Erection of DTR Stay with Graouting 250.00

3 Erection of DTR structure New poles complete with top 4000.00


channel, dtr base angle, Gl pipe, etc including commissioning of dtr

4 Erection of DTR structure 63kv on new poles complete with top channel, dtr 6000.00
base angle, Gl pipe, etc including commissioning of dtr

Term&Condition
1 Security Deposit
Mr Pushpendra Singh S/0 Santhosh Kumar v/p 530 kailawoan Lalitpur with PAN
NoFNFPS0898H YOU HAVE entered into an agreement with your Akchhanshi Traders,
with value 1992450.00 for which you will have to pay 10 percent security money, that is
1
199245.00 when the work is over and the goods are reconciled, then this money will be
paid to youtill that the money Deposit to Akchhanshi Traders for security Security
Purpose.
2 SCOPE OF WORK:

The entire scope of work shall include but not limited to the following:

a) Work to be carried out as per the detailed description of the work mentioned against each
item of

work and the rates thereof specified in the above schedule.

Work to be carried out as per the drawings, technical specifications issued and approved by
client.

as well as instructions of our Engineer-in-charge / Project Manager at site.

c) Work shall be subject to inspection by Site Engineer/s or Site in charge as appointed by


client.

d) Loading, unloading and transportation of material from Store to work sites, watch and `
ward of the

issued material, installation, pre commissioning testing, wiring and commissioning of the
equipment

shall be your responsibility. Any loss to property/material due to mishandling by Contractor's


workers

shall be recovered from Contractor's payable amount.

e) Liaison with customer for smooth execution of the work, arranging of Electrical shut down
as and

when necessary and getting the proper Safty…

It will be the Contractor's responsibility to settle the matters arising out of workers demands
/ trade

union activities etc. and all liabilities arising out of it will be to Contractor's account. Any

labour problem/issue resolution with workers will be Contractor's responsibility.

5) TERMS OF PAYMENT

The payment shall be made within 20 working days from the date of receipt of processable bills (only

80% of basic and GST will paid 100% in next month after submission of R1) duly verified by Engineer

In Charge/ Project Manager. All statutory deductions as per prevailing government rules/regulations

shall be deducted at the time of release of payment.

You shall be paid for certified quantity on completion of work as mentioned below;

a) 80% -On Complete Erection Of Area And Measurement By EDD Lalitpur.

Engineer In Charge/ Project Manager.

b)20% -On final Reconciliation, Rectification, Handing Over And Taking Over O & Certification 1

11kv lines Of The Same By EDD Lalitpur. Project Manager

2
All the payments shall be directly credited to your Bank Account as per details provided by you.

5) TERMINATION

We shall be at a liberty to terminate your contract with immediate effect, due to;

a) Unsatisfactory progress of work

b) Bad workmanship

c) Willful negligence to work

d) Violation to any of the provisions of above terms and conditions.

e) Breach of Trust

You shall not be eligible for any compensation whatsoever arising out of such termination.

For Akchhanshi Traders

Authoused Signatory/Approving Authority

Akchhanshi Traders

IAWe have read understood this work order with all terms & condition in full.

Accepted Unconditionally

Authorized Person of Contractor.

……………………… confirm being authorized person for… ............................... and am authorized

to accept to this work Order

Signature of Authorized Person