APP037 Curtain Wall

Download as pdf or txt
Download as pdf or txt
You are on page 1of 16

Practice Note for Authorized Persons,

Buildings Department Registered Structural Engineers and APP-37


Registered Geotechnical Engineers

Curtain Wall, Window and Window Wall

Structural Submission of Curtain Wall Plans

Curtain wall should be designed to meet the performance requirements set


out in sections 29 to 31 of the Building (Construction) Regulation (B(C)R). Attention
should be paid to the requirements for wind loads, horizontal imposed loads specified in
section 9 of and Table 3 in the Schedule to the B(C)R on curtain wall when there is no
protective barrier provided, protection of openings, protection against corrosion and the
quality of materials.

2. The following details are required to be included in the curtain wall plans
for submission to the Building Authority (BA) for approval:

(a) structural framing and key structural details and the installation
procedures excluding any unnecessary shop fabrication details;

(b) structural calculations comprising design check on the parent


structure, analysis on the structural adequacy and stability of the
proposed curtain wall, element design for aluminium alloy, fixing
components, glazing, and deflection check on major load carrying
members;

(c) workmanship specifications for welding, galvanisation measures


to overcome bi-metallic effects, and corrosion prevention;

(d) elevations including pane arrangements;

(e) typical and non-typical sections showing structural members and


supports;

(f) typical and non-typical connections;

(g) specifications on allowable tolerance of the positioning of curtain


wall supports and any remedial arrangements in cases where such
tolerance is exceeded;

(h) the mode of support from and connection to the load-bearing


structure of the building (anchorages in structural concrete
members or welded connections to structural steel members) and
any justification and application for modification of section 31 of
the B(C)R for using other mode of support, e.g. drilled or bolted
fixings;

/(i) …
-2-

(i) the projection of the curtain wall from the outer face of the
structural elements, e.g. beams, columns and floor slabs, for
consideration of exemption from gross floor area and site coverage
calculations;

(j) standards or codes of practice;

(k) material specifications for structural steel, aluminium alloy,


cast-in anchors, fixing screws, structural sealant, and glazing; and

(l) sections showing compliance with section 35 of the B(C)R and the
Code of Practice for Fire Safety in Buildings 2011 on such relevant
aspects as the protection against spread of fire and smoke between
floors, between different fire compartments on the same floor, and
between the accommodation of a storey and the required staircase
or its protected lobby.

Structural Submission of Window or Window Wall Plans

3. In general, window and window wall should satisfy the performance


requirements stipulated in the B(C)R, the requirements on lighting and ventilation
stipulated in the Building (Planning) Regulations and relevant codes of practice.

4. If a window or window wall forms wholly or partly the external wall of a


building, have a structural opening with the least dimension exceeding 1.8m or an area
exceeding 6m2, and is at 100m or more above adjoining ground level or where the wind
reference pressure, Qo,z 1 , is 2.86 kPa or more, structural framing and key structural
details, excluding any unnecessary shop fabrication details should be submitted for
approval. The submission should contain the following information to demonstrate that
the window or window wall is of adequate strength and stability:

(a) information described in items (b) to (g) and (j) to (l) of paragraph
2 above;

(b) structural adequacy in resisting horizontal imposed loads specified


in section 9 of and Table 3 in the Schedule to the B(C)R for the
window or window wall that functions as a protective barrier; and

(c) deflection checks to ensure that the maximum deflection of the


structural elements does not exceed the deflection limits stipulated
in the Code of Practice for Structural Use of Glass 2018 (Glass
Code).

5. Structural details of a window or window wall (including glass shop front)


with the design span of its structural elements (i.e. mullion, glass fins, etc.) exceeding 6m
should be submitted for approval. The structural information mentioned in items (a) to
(c) of paragraph 4 above should be included in the submission.

/6. …
1
In case the preceding Code of Practice on Wind Effects in Hong Kong 2004 is adopted for the design of
window or window wall, design wind pressure, qz, should be regarded as the wind pressure criterion.
-3-

6. Where the structural details of a window and window wall are not required
to be submitted for approval, the Authorized Person (AP) and Registered Structural
Engineer (RSE) should ensure that the design, fabrication and installation of the window
and window wall would achieve the required safety standard. Attention should be given
to the requirements on horizontal imposed loads, protection of openings, function of
protective barriers, corrosion protection, quality control of materials and protection
against the spread of fire and smoke between floors.

Minor Works Relating to Curtain Wall, Window or Window Wall

7. Under the Minor Works Control System, certain minor works relating to
repair or replacement of curtain wall, and construction, alteration, repair or replacement
of window or window wall in an existing building are designated as minor works, which
may be carried out under the simplified requirements as an alternative to obtaining prior
approval and consent under the Buildings Ordinance (BO). Reference can be made to
Schedule 1 of the Building (Minor Works) Regulation and Practice Note for AP, RSE
and Registered Geotechnical Engineers (PNAP) APP-147 regarding the list of minor
works items and the simplified requirements respectively.

Design and Construction Standards

8. Standards commonly used for the design and construction of curtain wall,
window and window wall, which are acceptable to the BA, are given in Appendix A and
PNAP APP-53.

Separate RSE

9. In view of the specialty of curtain wall, window and window wall works, a
separate RSE may be appointed to prepare the design and supervise the carrying out of
such works. Under such circumstances, the specified Forms BA4 and BA5 indicating
the appointment of the separate RSE and the scope of works for which he/she is
responsible are required to be submitted together with the plans submitted for approval.
Upon completion of the works, the separate RSE so appointed is required to certify
satisfactory completion of the works in accordance with regulation 25(3) of the Building
(Administration) Regulations (B(A)R).

10. Where structural details for proposed curtain wall, window or window wall
works are submitted by the separate RSE, the submission should be accompanied by an
assessment report prepared by him/her giving an account of the effect of the proposed
works to the parent structure. The assessment report should be appended with a statement
signed by the project RSE to confirm that he/she is fully aware of the connection details
and the effect of the works on the parent structure.

11. The separate RSE appointed for the curtain wall, window or window wall
works shall be responsible for the supervision of the construction of such works,
including the installation of any cast-in anchorage, e.g. anchor plates, cast-in embeds and
through bolts, etc., in the parent structure except in the event where the cast-in anchorage
has been pre-installed in the parent structure prior to his/her appointment. For such cases,
the structural details and layout of the pre-installed parts should be given in the

/superstructure …
-4-

superstructure plans to be submitted for approval by the project RSE who shall then be
responsible for the supervision of the installation of such parts. The separate RSE should
refer to the pre-installed connection details when designing the curtain wall, window or
window wall works and should co-ordinate with the project RSE for any necessary
amendments if different connection details are to be used.

Use of Tempered Glass

12. Where tempered glass is used, the RSE and the registered contractor (RC)
should ensure that an acceptable Quality Assurance Scheme (QAS) is adopted by the
glass manufacturer to minimise the risk of spontaneous breakage of tempered glass.

13. To ensure that the tempered glass panes are of good quality, proper
supervision and adequate quality control are necessary during the production processes
of the tempered glass panes. In this connection, the following conditions/requirements
will be imposed when giving approval of plans:

Quality assurance

(a) the tempered glass should be manufactured by a factory with ISO


9001 quality assurance certification as required under item 6 of
section 17(1) of the BO;

(b) a copy of the QAS of the manufacturer should be submitted at least


14 days before the commencement of the production works in the
factory as required under regulation 10 of the B(A)R. Such
submission should be appended with a statement signed by the
RSE to declare that he/she has studied the QAS and confirm that
there are adequate measures incorporated in the QAS to ensure the
quality of the tempered glass products in compliance with the
provisions of the BO and the approved plans. The items to be
included in the QAS are listed in clause 9.1.3 of the Glass Code;

(c) the compliance reports for heat soak process 2 issued by the glass
manufacturer and endorsed by the RSE should be submitted prior
to the application for occupation permit or the submission of Form
BA14 as appropriate under regulation 10 of the B(A)R. The
compliance reports for heat soak process should be in accordance
with clause 9.3 of the Glass Code;

Quality supervision plan

(d) a quality supervision plan for the quality supervision of


manufacturer’s heat soak process of the tempered glass to be used
in the works shown in the approved plans prepared by the RSE and
the RC should be submitted as required under regulation 10 of

/the …

2
As one of the quality control measures for tempered glass used in curtain wall, window and window
wall works, heat soak process conforming to BS EN 14179-1:2016 and complying with the Glass Code
should be carried out to all tempered glass panes.
-5-

the B(A)R at least 14 days before the commencement of the


tempered glass production in the factory. A standard form of
supervision plan together with a list of typical items for quality
supervision and a sample of the inspection record are provided in
Appendix B for reference.

Qualified supervision

(e) the required qualified supervision under item 6 of section 17(1) of


the BO should be provided as follows-

(i) the RSE should assign a quality control supervisor (QCS)


to supervise a certain number of tempered glass panes
undergoing the heat soak process. The RSE should
determine the necessary frequency of supervision, which
should cover at least 30% of the number of tempered glass
panes used in the project. The minimum qualifications and
experience of the QCS are to be the same as grade T3
technically competent person (TCP) under the RSE’s
stream, as stipulated in the Code of Practice for Site
Supervision 2009 (2021 edition) (Supervision Code). As
an alternative, the RSE’s QCS may employ
videotelephony3 to conduct supervision. In this connection,
the QCS should work with his/her assistant in the factory
who is not a member of the team of supervisory personnel
of the RC stream providing the required continuous
supervision;

(ii) the RC should assign a quality control co-ordinator (QCC)


to provide full time continuous supervision of the heat soak
process of all tempered glass panes in the factory. The
minimum qualifications and experience of the QCC are to
be the same as grade T1 TCP under the RC’s stream, as
stipulated in the Supervision Code. To ensure the heat soak
process is properly conducted by the glass manufacturer,
the QCC should measure the glass surface temperature
independently by using his/her own data logger. The
information recorded by the data logger should be set at
one-minute intervals and kept in the factory; and

(iii) the names and qualifications of the QCS and QCC of the
RSE and the RC respectively should be recorded in their
inspection log books. The details of heat soak process for
tempered glass panes should also be recorded in their log
books and kept in the factory. If the alternative
arrangement of employing videotelephony as described in

/paragraph …

3
Videotelephony means two-way simultaneous communication with both audio and video in real time
through telephone or computer network connections. The video should be recorded in colour with
resolution of not less than 480p in a non-rewritable DVD-ROM.
-6-

paragraph 13(e)(i) above is adopted, all supervision items


covered in the videos taken should be recorded
contemporaneously in QCS inspection log book and should
be submitted together with the DVD-ROM discs of the
videos taken to BD within 14 days after completion of the
heat soak process for each batch of tempered glass panes.
The RSE should certify on each disc with a permanent
marker signifying that his/her QCS personally use
videotelephony for compliance with the approval
conditions; and

Quality supervision report

(f) a quality supervision report should be submitted by the RSE as


required under regulation 10 of the B(A)R, prior to the application
for occupation permit. The report should include a statement
signed by the RSE to confirm that adequate supervision has been
provided in accordance with the quality supervision plan, a copy
of the inspection log book of the QCS and QCC of the RSE stream
and RC stream respectively for the heat soak process required in
paragraph 13(e)(iii) above, and a soft copy of the record of the data
logger required in paragraph 13(e)(ii) above.

Structural Sealant

14. For better aesthetic appearance, structural sealant may be used in the curtain
wall, window or window wall works. The proposed structural sealant should be
compatible with the glazing system and the structural frame with which it is in contact.
Compliance certificates comprising sealant compatibility test report, sealant adhesion test
report and print review report in accordance with the Glass Code together with deglazing
test report are required to be submitted prior to the application of an occupation permit or
the submission of Form BA14 as appropriate. The compliance certificates and deglazing
test report should be made by sealant manufacturer and be also appended with a statement
signed by the RSE who has prepared the plans to confirm the acceptance criteria
appropriate to the test have been complied with.

Design of Spider Fixing

15. The design of metal spider fixing as the fixing device for supporting glass
panes should be verified by means of proof load test. In addition, attention should be
given to its detailing at the interface connection with the glass panes, which should be
designed to accommodate all anticipated movements. The mechanical properties,
dimensions, load capacities and specific proprietary model number/series of metal spider
fixing should be shown in the relevant plans submitted for approval.

16. Proof load test on metal spider fixing should be conducted in accordance
with the test criteria specified in Appendix C upon completion of the works. The test
report should be endorsed and submitted by the RSE prior to the application of an
occupation permit or the submission of Form BA14 as appropriate. Proof load tests of

/metal …
-7-

metal spider fixing may not be required if the type of the proposed metal spider fixing is
already included in the Central Data Bank promulgated in PNAP ADM-20 and uploaded
to the Buildings Department (BD) website.

Locking Devices of Openable Sashes/Sub-frames

17. Locking devices are used to restrain openable sashes/sub-frames of windows,


window walls and curtain walls in locked positions. All components of locking devices
should be made of durable and non-combustible materials.

18. Locking devices should be evenly distributed along the sash/sub-frame to


allow even load distribution on the window frame/curtain wall. The locations and the
ultimate design strength of the locking points should be shown on structural plans for
approval 4. The ultimate design strength should be the characteristic strength divided by
a factor of safety (FOS) of 1.8. The characteristic strength should be verified by means
of a proof load test in accordance with the test criteria set out in Appendix D and the test
report should be endorsed by RSE and submitted to BD prior to the application for an
occupation permit or the submission of Form BA14 as appropriate. Proof load tests of
locking devices may not be required if the type of the proposed locking devices is already
included in the BD’s Central Data Bank.

19. In order to ensure all locking points can be triggered effectively, a single
handle bar should not be connected to more than 8 locking points.

20. Hinges for openable sashes/sub-frames should be adequate in holding its own
weight. In general, the size of a top-hung sash should not exceed 2.5m2. Similarly, the
width of a side-hung sash should not exceed 700mm.

21. AP/RSE should ensure the openable sash/sub-frame and the locking devices
are properly designed and assembled to meet the performance requirements and
construction tolerance. In normal circumstance, the FOS of 1.8 is considered adequate
for covering construction tolerance. Improper assembly may cause additional moment
on the components of the locking devices. Adequate site supervision should also be
provided to ensure that the works are properly assembled.

Safety Test for Curtain Wall

22. Safety test for a curtain wall should be conducted as required under item 6
of section 17(1) of the BO. The test should be carried out by an independent laboratory
accredited by the Hong Kong Laboratory Accreditation Scheme (HOKLAS) or by other
laboratory accreditation bodies which have reached mutual recognition
agreements/arrangements with HOKLAS. The test carried out by an accredited
laboratory should be within its scope of accreditation. The test reports should be made
on a HOKLAS endorsed certificate or equivalent certificate/report and be also appended
with a statement signed by the RSE who has prepared the plans to confirm the acceptance
criteria appropriate to the test have been complied with. They should be submitted prior

/to …

4
The requirements on locking devices are applicable to all new or major revision of structural plans for
development proposals or alteration and addition works submitted to the BA for approval on or after
1 August 2020.
-8-

to the application of an occupation permit or the submission of Form BA14 as appropriate.


However, such safety test is not required for the curtain wall repair or replacement works
carried out under the fast track processing procedures as stipulated in paragraphs 30 and
31 of PNAP ADM-19 or minor works item 1.61 of the Minor Works Control System.

23. As a curtain wall may comprise various pane sizes subject to a wide range of
design wind pressure, the test panes should be selected based on engineering judgement
and with justification of mathematical computation models where appropriate. It is
desirable to specify the representative test panes in the curtain wall plans. Detailed
requirements of the safety test are given in clause 8.3.1 of the Glass Code.

Inspection, Maintenance and Repair

24. In view of the special requirements for the design and construction of curtain
wall, window and window wall, the inspection, maintenance and repair of such works
shall follow Annex D of the Glass Code. The BA recommends all APs and RSEs to
adopt the guidelines and requirements given in the Glass Code. They are also requested
to offer help and advice as appropriate to their clients who have curtain walls, windows
or window walls in their buildings.

Aluminium Windows

25. Reference may be made to PNAP APP-116 in respect of the design and
installation guidelines on aluminium windows.

Concurrent Processing of Approval and Consent Applications

26. For curtain wall works, the application for approval of plans and consent to
the commencement of works may be made concurrently under PNAP ADM-19.

( YU Po-mei, Clarice )
Building Authority

Ref. : BD GP/BREG/C/6(V)

This PNAP is previously known as PNAP 106


First issue September 1984
Last revision May 2020
This revision April 2022 (AD/NB2) (Paragraphs 1, 2, 4, 7, 13, 16, 18 and 22 amended
and Appendix B added)
Appendix A
(PNAP APP-37)

Standards Commonly Used for the


Design & Construction of
Curtain Wall, Window and Window Wall
Acceptable to the Building Authority

Reference Standards

The standards listed in this appendix and PNAP APP-53 are intended to
provide reference information only for the purpose of design and construction of curtain
wall, window and window wall systems. It should be noted that:

(a) the standards listed are not meant to be exhaustive;

(b) national standards and codes of practice of various countries,


though similar in major aspects, do not have exact equivalence
to one another;

(c) should a certain design standard be adopted, it should be applied


to the design consistently; and

(d) Building Regulations shall always take precedence over other


design standards should there be a conflict between them.

A. Material & Workmanship

Standard Title/Description
Glass Hong Kong Code of Code of Practice for Structural Use of
Practice Glass 2018

Stainless BS EN 10029:2010 Hot rolled steel plates 3 mm thick or above


Steel - Tolerances on dimensions, shape

BS EN ISO 9445:2006 Continuously cold-rolled stainless steel.


Tolerances on dimensions and form.

BSEN ISO 9445-1: 2010 Part 1. Narrow strip and cut lengths

BSEN ISO 9445-2:2010 Part 2. Wire strip and plate/sheet

BS EN 10048:1997 Hot rolled narrow steel strip. Tolerances on


dimensions and shape

BS EN Continuously hot-rolled uncoated plate,


10051:1991+A1:1997 sheet and strip of non-alloy and alloy
steels. Tolerances on dimensions and shape

BS EN 10095:1999 Heat resisting steels and nickel alloys

/B. …
-1-
B. Design

Standard Title/Description
Glass Hong Kong Code of Code of Practice for Structural Use of
Practice Glass 2018

C. Testing

Standard Title/Description
Glass Hong Kong Code of Code of Practice for Structural Use of Glass
Practice 2018

Curtain Wall, Hong Kong Code of Code of Practice for Structural Use of Glass
Window, Practice 2018
Window wall

(Rev. 5/2020)

-2-
Appendix B
(PNAP APP-37)

Heat Soak Process of Tempered Glass Supervision Plan

To the Building Authority,

In accordance with the conditions of approval imposed in your letter of


for works,
we submit this supervision plan for the heat soak process of the tempered glass to be used at
(address of site) on
(Lot No.) (BD ref. ________________________).

2. We undertake that the supervision of the above heat soak process will be carried
out in accordance with this supervision plan, PNAP APP-37 and the Code of Practice for
Structural Use of Glass 2018 (Code). We also undertake that the management and execution
of quality supervision of the works covered by this supervision plan will be carried out in the
manner prescribed by the provisions of the Buildings Ordinance and Regulations.

3. The quality control supervisor (QCS) and quality control co-ordinator (QCC)
assigned by the registered structural engineer (RSE) and the registered contractor (RC)
respectively to supervise the above heat soak process are:

I.D. No.^/ Frequency of


Name in English^ Name in Chinese^
TCP No.** Quality Supervision

at least 30% of the


number of tempered
RSE’s QCS# glass panes

Signature of QCS for confirmation of appointment*: ____________________


Full time
RC’s QCC#
Signature of QCC for confirmation of appointment*: ____________________

The contact information and CVs showing their relevant experience and academic qualifications are
attached at the Annexes. If more than one supervisor/co-ordinator is proposed for a QCS/QCC post,
the demarcation of their responsibility should be provided.

^ In accordance with the Hong Kong Identity Card


** CV is not required if TCP No. is provided.
#
The minimum qualification and experience of QCS and QCC should fulfill the requirements
specified in PNAP APP-37.
* Signature of QCS/QCC for the confirmation of appointment under RSE/RC stream indicates that the
QCS/QCC has read, understood and agreed with the notes on “Personal Data” of this supervision
plan.

/4. …
-1-
4. The quality supervision will cover all items of works to be inspected as devised in
Annex 1. The record of quality supervision in Annex 2 will be completed contemporaneously
by the QCS/QCC with a copy of these documents to be kept in the factory.

Prepared by:

Signature Signature
Name of RSE Name of AS
Date RGBC
Date
Enclosure : Annexes 1 to 3

Personal Data

Purposes of Collection

1. The personal data provided by means of this supervision plan will be used by the
Buildings Department for the following purposes:

(a) activities relating to the processing of your submission in this supervision plan;

(b) activities relating to the above proposed building works; and

(c) facilitating communication between the Buildings Department and yourself.

2. It is obligatory for you to provide the information as required in the supervision plan. If
you fail to provide the required data, delay may be caused in processing of your submission or even
result in rejection of the application.

Classes of Transferees

3. The personal data you provided by means of this supervision plan may be disclosed to
other government departments, bureaux, organisations or any persons for the purposes mentioned in
paragraph 1 above.

Access to Personal Data

4. You have the right of access and correction with respect to the personal data as provided
under the Personal Data (Privacy) Ordinance. The Buildings Department has the right to charge a
reasonable fee for the processing of any data access request. Request for personal data access and
correction should be addressed to the New Buildings Division 2 of the Buildings Department.

(4/2022)

-2-
Annex 1 to Appendix B
(PNAP APP-37)

Typical Items for Quality Supervision of Heat Soak Process of Tempered Glass

Item Description

(a) General
H1 Ensure that the names of quality control supervisor (QCS) under RSE and quality control
co-ordinator (QCC) under RC recorded in an inspection logbook and kept in the factory agree
with the supervision plan.
H2 Ensure the respective QCC/QCS’s inspection frequency and items are in accordance with the
requirements of PNAP APP-37 and Code of Practice for Structural Use of Glass 2018 (Glass
Code).
H3 Check that the calibration reports (as detailed in clause 9.3.2 of the Glass Code) of the ovens
are in accordance with BS EN 14179-1:2016 and kept in the factory.
H4 Check that all thermocouples are calibrated at 6-month interval as recommended in the
HOKLAS Supplementary Criteria No. 2.
H5 Check that all essential details (e.g. quantity and size of glasses, reading of data logger, etc.)
of heat soak process for tempered glass panes are recorded in the logbook and kept in the
factory.
(b) Heat Soak Process

H6 Check that a minimum of 8 thermocouples are installed and monitored by the factory in
accordance with clause 9.3.3 of the Glass Code.
H7 Check that an additional thermocouple is installed and measured independently by using the
QCC’s own data logger.
H8 Check that a minimum clearance of 20mm is provided to separate the glass panels and ensure
heated air circulation between the glass panels.
H9 Check that heating phase is commenced with all the glass panels at ambient temperature.
H10 Check that heating phase is concluded when surface temperature of the last glass reaches
250°C; the glass surface temperature should not be allowed to exceed 290°C; the period of
glass surface temperature in excess of 270°C shall be minimised. The maximum heating
rate is 3°C per minute.
H11 Check that holding phase is commenced when surface temperature of all glass panes has
reached 250°C; the duration of the holding phase is at least 120 minutes; the oven should be
controlled so that the glass surface maintains in range of 260°C ±10°C during the holding
phase.
H12 Check that doors of oven are not opened until the reading of the control element dropped to
70°C.
H13 Check that number of broken glass after heat soak process is recorded.
H14 Check that fragmentation test is carried out after heat soak process.
Hn Any other items considered essential for quality supervision of the heat soak process.

(4/2022)
Annex 2 to Appendix B
(PNAP APP-37)

Record of Quality Supervision Carried Out by


QCS / QCC* under RSE / RC* Stream

BD Ref.: BD 3/1234/22
Project Location: ABC Street
Type of Works: Heat Soak Process of Tempered Glass for Curtain Wall Works
Name of QCS / QCC* : (1)
Mr. Lee Tai-man
Frequency of Inspection: Full time / at least 30% of the number of tempered glass panes*

Date 4/1/2022 (Tue)


Inspection Findings
Batch No. and Photos
Item Quantity Inspected Result (if any)
Remedial / Remark
No.(2) (S(3)/NS(4)/NA(5))
Batch 2, 8 nos. of glass
H1 panes S

H2 Ditto S

H3 Ditto S

H4 Ditto S

Record of some glass panes’ size


H5 Ditto NS incomplete. It has been rectified and
recorded in logbook

H6 Ditto S

𝐻𝐻7 Ditto S

Clearance less than 20mm. It has been


H8 Ditto NS
rectified and recorded in logbook.

H9 Ditto S

H10 Ditto S

H11 Ditto S

H12 Ditto S

Broken glass not recorded. It has been


H13 Ditto NS
rectified and recorded in logbook.

H14 Ditto S

Signature

* Delete if inappropriate
Note (1) : Full name of the QCS/QCC as provided in the supervision plan.
Note (2) : According to the checklists devised by the RSE and AS of the RC.
Note (3) : “S” denotes “Satisfactory”.
Note (4) : “NS” denotes “Not satisfactory”
Note (5) : “NA” denotes “Not Applicable”.
(4/2022)
Appendix C
(PNAP APP-37)

Proof Load Test for Spider Component

Reference Standards

The design of metal spider fixing can be verified by means of proof load
test, which are required to be carried out in accordance with the test criteria specified in
the Code of Practice for the Structural Use of Steel 2011.

2. The requirements and procedures for the test are:

(a) Sampling rate should be at least 1% or 3 numbers, whichever is more,


of each representative type of the spider components concerned, and
the test specimens should be set up in such a manner that is compatible
with the proposed fixing details given in the approved plans;

(b) Test loads should be determined in accordance with clause 16.2.1.2 of


the Code of Practice for the Structural Use of Steel 2011. ‘Actual dead
load present during the test’ may be taken as the weight of the spider
component. ‘Remainder of dead load’ may be taken as the weight of
the attachment (e.g. glass panes) to the spider component;

(c) A test load should be applied and released in at least 5 increments and
decrements respectively;

(d) A reading on deformation should only be taken when it has become


completely stable, and readings on deformation should be taken at
three 5-minute intervals at least on attainment of the test load until
there is no significant increase in the deformation;

(e) There should be no creep for a period of at least 15 minutes under the
test load;

(f) A running plot in respect of loading increment/decrement against


deformation should indicate substantial linear behaviour under the test
load; and

(g) On removal of the test load, the recorded residual deformation should
not exceed 5% of the maximum deformation recorded.

(5/2012)
Appendix D
(PNAP APP-37)

Proof Load Test for Single Locking Devices of Openable Sashes / Sub-frames

The characteristic strength of each type of single locking devices should be


verified by means of proof load test. The testing specimens should fully represent the
actual arrangement of the single locking devices to be installed on site.

2. The requirements and procedures for the test are:

(a) Sampling rate should be at least 0.1% or 5 numbers, whichever is


more, of each type of the locking devices concerned. The test
specimens should be set up in such a manner that they are compatible
with the proposed fixing details given in the approved plans;

(b) Test load should be applied at a constant rate; and

(c) The characteristic strength should be evaluated as follows:

Characteristic strength = Average test load at failure – K x σ

where

K is the K-factor for at least 5 test specimens and may be taken as


3.41 (K-factor corresponding to larger numbers of test
specimens may be used if appropriate); and

σ is the standard deviation.

(5/2020)

You might also like