IIA - Enginnering Final Feasibility Report

Download as pdf or txt
Download as pdf or txt
You are on page 1of 265

Lower-Dhidessa phase IIA Irrigation & Drainage

Feasibility and Detail Design and StudyProject

Sectoral Studies

Client: Federal Ministry of Water, Irrigation and Electricity

Consultant: Oromia Water Works Design and Supervision Enterprise

(OWWDSE)

February, 2017

Addis Abeba

Oromia Water Works Design and Supervision Enterprise


Tel: +251114717280/+ 251 114392162/+251114392470
Fax: +251 114392008
P.O. Box: 870/1250
Website:www.owwdse.org
E-mail: [email protected]
Table of Contents MWI&E

TABLE OF CONTENTS
TABLE OF CONTENTS ............................................................................................................................... i
LIST OF TABLES ...................................................................................................................................... vii
LIST OF FIGURE....................................................................................................................................... vii
ABBRIVATION ........................................................................................................................................... x
EXCUTIVE SUMMARY ........................................................................................................................... xii
1. INTRODUCTION .................................................................................................................................... 1
1. 1 Back Ground ...................................................................................................................................... 1
1.2. Water resources of Ethiopia ............................................................................................................... 2
1.3. General Climate of the country .......................................................................................................... 2
1.4. Location and Background Lower Dhidhessa Phase IIA Project ........................................................ 2
1.5. Objective of the Study of the Work. .................................................................................................. 4
1.5.1. The Specific Objectives of Engineering Report.......................................................................... 5
1.6. Scope of the Work ............................................................................................................................. 5
1.7. Approach and Methodology............................................................................................................... 7
1.7.1. Review of Similar designed and study of Previous Project and Initial Data Collection ............. 8
1.7.2. Collecting Primary Data from the Project Site at the Field Level. ............................................. 8
2. REVIEW OF PREVIOUS DESIGN AND STUDIES of IRRIGATION PROJECT. .............................. 9
2.1. Dinger Bereha Irrigation Project Feasibility Study Report Review ....................................................... 9
2.1.1. Dinger Bereha Main Irrigation Design Consideration ................................................................ 9
2.1.3. On Farm and Tertiary Unit Design ........................................................................................... 11
2.2. Anger Dam Irrigation and Drainage Project Final Feasibility Report review ............................... 12
2.2.1. The Development Concept of Anger Dam Irrigation Project ................................................... 12
2.2.2. Drainage System of Anger Irrigation Project............................................................................ 12
2.2.3. Irrigation Methods and Crop Water Requirement .................................................................... 13
2.2.4. System Description ................................................................................................................... 13
2.3. Arjo-Dhidhessa Sugar Cane Irrigation and Drainage Project Feasibility Study Report Review ..... 17
2.3.1 Hydraulic Design of Parameters of the Canal ............................................................................ 18
2.3.2 Furrow Irrigation System ........................................................................................................... 19
2.3.3 Capacity Determination and Canal Cross-Sections Design ....................................................... 20
2.3.4 Design criteria ............................................................................................................................ 20

February,2017 OWWDSE Page i


Table of Contents MOWIAE

2.3.5. Drainage System Design ........................................................................................................... 21


2.3.6. Surface drainage system............................................................................................................ 21
2.3.7 .Peak Run off Determination ..................................................................................................... 22
2.3.8. Design of In Field Drainage System of Structures .................................................................... 22
2.3.9. Main canal structures design ..................................................................................................... 22
2.3.10. Electro-mechanical part of the Upper Arjo -Dhidhessa project ........................................... 23
2.3.11. Road Network in Upper Arjo- Dehidhessa Irrigation and Drainage Project .......................... 24
3. WATER ABSTRACTIONS OPTIONS of PHASE IIA PROJECT ....................................................... 26
3.1. Extension of Left Side Main Canal by redesigning ......................................................................... 32
3.2 Extension Of Upper Arjo-Dhidhessa from the End of Canal ........................................................... 37
3.3 Constructing Separate Main Canal at the Dam Outlet ...................................................................... 37
3.4. Water Abstraction System by Diversion Weir and Canals .............................................................. 39
3.4.1. Possible Weir Site Options for the Proposed Command Area .................................................. 40
3.5 Diverting Water by Pumping System from Dhidhessa River. .......................................................... 54
3.6. Recommendation on Water Abstraction Options of Phase IIA ....................................................... 63
4. SURVEYING WORK ............................................................................................................................ 64
4.1 Methodology of Surveying ............................................................................................................... 64
4.1.1. Establishing of GPS Control Stations ....................................................................................... 65
4.1.2. Data Collection for Detail Surveying of Topographic Map Preparation .................................. 66
4.1.3 Bench mark setup ....................................................................................................................... 67
4.2. Data Processing and CAD................................................................................................................ 67
5. DESIGN OF DIVERSION WEIR/HEADWORK AND APPURTENANT STRUCTURES ................ 68
5.1 Design Criteria for Diversion weir /headwork .................................................................................. 68
5.1.1 Design Criteria for Selection of Diversion Weir Point. ............................................................. 68
5.1.2. Criteria for Selection of type of Diversion Weir structures ...................................................... 70
5.1.3. Design criteria for Various Components of Diversion Weir Structures ................................... 70
5.1.4. Methodology for Design of Diversion Weir Structures ............................................................ 70
5.1.5. Hydraulic Design of Weir ......................................................................................................... 73
5.1.6. Forces Acting on the Weir Structure ......................................................................................... 74
5.1.7. Design Criteria for Superstructure ............................................................................................ 75
5.1.8. Design Criteria for Substructure (floor and foundation) ........................................................... 75
5.1.9. Depth of Vertical Cutoffs/ Sheet Piles. ..................................................................................... 76
5.1.10. Floor Length and Thickness of U/S and D/S Floor................................................................. 77
Table of Contents MOWIAE

5.1.11. Type of the Weir ..................................................................................................................... 77


5.1.12. Length and Thickness of Upstream and Downstream Loose Aprons ..................................... 77
5.1.13. Freeboard ................................................................................................................................ 78
5.1.14. Water ways of the Weir .......................................................................................................... 78
5.1.15. Under Sluice Ways.................................................................................................................. 79
5.1.16. Consideration for Width and Level of Crust and Upstream Floor .......................................... 79
5.1.17. Application of Cement Grouting Technique ........................................................................... 80
5.1.18. Foundation Treatment ............................................................................................................. 80
5.1.19. Wing walls and abutment ........................................................................................................ 80
5.1.20. Divide Walls ........................................................................................................................... 81
5.1.21. River Training Works ............................................................................................................. 81
5.1.22. Approach Embankments ......................................................................................................... 82
5.1.23. Design of Guide Banks ........................................................................................................... 82
5.1.24. Planning of Layout of the Main Conveyance Systems (Canal Head Works) ......................... 83
5.1.25. Crust Level .............................................................................................................................. 84
5.1.26. Approach Road and Bridges: ................................................................................................ 84
5.1.27. Gate Operating Platforms........................................................................................................ 84
5.1.28. Piers......................................................................................................................................... 85
5.1.29. Abutments ............................................................................................................................... 85
5.2. Design of Detail Diversion Weir and Appurtenant Structures ......................................................... 86
5.2.1 Selection of Diversion Weir Points of Lower Dhidhessa project .............................................. 86
5.2.3. The Foundation Condition of the Selected Head Work Site ..................................................... 87
5.2.4. Estimation of design flood at selected weir site ........................................................................ 88
5.2.5. Determination of Diversion Weir and Appurtenant Structure Hydraulically ........................... 89
5.2.6. Design of Diversion Weir ......................................................................................................... 89
5.2.7. River Back –Water Effect Evaluation and Weir Location Determination ................................ 90
5.2.8. Determination of Water tail curve............................................................................................. 93
5.2.9. Types of Weir & selection ........................................................................................................ 94
5.2.10. Shape of the Weir Crest .......................................................................................................... 95
5.2.11. Fixing Weir Crest Level .......................................................................................................... 95
5.2.12. Design of under sluices ........................................................................................................... 95
5.2.13. Determination of Height of Weir ............................................................................................ 96
5.2.14. Crest Length of the Water Way. ............................................................................................. 97
Table of Contents MOWIAE

5.2.15. Head over the Weir and Discharge. ........................................................................................ 98


5.2.16. Determination of stilling basin weir portion ......................................................................... 100
5.2.17. Determination of retrogeration and concentration ................................................................ 102
5.2.17. Freeboard .............................................................................................................................. 104
5.2.18. Top Width of Crest ............................................................................................................... 104
5.2.19. Vertical Cut off ..................................................................................................................... 105
5.2.20. Floor Length.......................................................................................................................... 105
5.2.21. Pressure Variation Calculation.............................................................................................. 105
5.2.22. Floor Thickness ..................................................................................................................... 107
5.2.23. Protection Works Beyond Impervious .................................................................................. 107
5.2.23. Stilling basin for under sluce portion .................................................................................... 109
5.2.24. Design of Appurtenant Structures. ........................................................................................ 110
5.2.25. Design of Settling Basin. ...................................................................................................... 121
6. DESIGN OF THE IRRIGATION AND DRAINAGE SYSTEM......................................................... 122
6.1. Irrigation Efficiency (E). ................................................................................................................ 122
6.2 Design Criteria of Irrigation and Drainage System......................................................................... 123
6.2.1.Hydraulic Design of Irrigation Canals of lined and unlined canals ......................................... 124
6.2.1.1. Hydraulic design of unlined canals. ......................................................................................... 125
6.2.1.2. Canal Capacity Determination Criteria ................................................................................ 125
6.2.1.3. Determination of Velocity in Unlined Canal ....................................................................... 126
6.2.1.4. Determination of Longitudinal Slope of the Canal Criteria ................................................. 128
6.2.1.5. Side Slopes of the Canal Criteria ......................................................................................... 128
6.2.1.6. Freeboard of the canal .......................................................................................................... 129
6.2.1.7. Design of Channel Bed Width and Water Depth ................................................................. 130
6.2.1.8. Design of Berm Width ......................................................................................................... 131
6.2.1.9. Design of Canal Bank .......................................................................................................... 131
6.2.1.10. Curvature of the canal ........................................................................................................ 131
6.2.2. Design of lined canal section .................................................................................................. 132
6.2.3. Working Head in Gravity Irrigation System ........................................................................... 132
6.2.4. Design of Canal Structures Criteria ........................................................................................ 133
6.2.5. Design of Night Storage Pond Criteria ................................................................................... 141
6.2.6. Design of the Drainage System ............................................................................................... 141
6.2.7. Design criteria for Road network system ................................................................................ 143
Table of Contents MOWIAE

6.2.8. Irrigation Methods in Water Distribution System criteria ...................................................... 143


6.3. Design of Irrigation and Drainage System ..................................................................................... 153
6.3.1. Description of phase IIAproject command area...................................................................... 153
6.3.2. Geotechnical,hydrogeology , Hydrology, Soil and Land Suitability Description of the Area 154
6.3.3. General System Layout of Design .......................................................................................... 158
6.3.4. Water for the irrigation ........................................................................................................... 169
6.3.5. Design of water conveyance system ....................................................................................... 174
6.3.6 Design of drainage system. ...................................................................................................... 188
6.3.7. Road network design............................................................................................................... 190
6.3.8. Design of water distribution system........................................................................................ 191
7. DESIGN OF ELECTRO MECHANICAL SYSTEM........................................................................... 195
7.1 Design Criteria of Electromechanical System ................................................................................ 195
7.1.1. Design life time ....................................................................................................................... 195
7.1.2 Pumping Cost ........................................................................................................................... 196
7.1.3 Simplicity of Operation and Maintenance ............................................................................... 197
7.1.4 Standardization ........................................................................................................................ 197
7.1.5 Hydraulic Design ..................................................................................................................... 197
7.1.6. Pump Station ........................................................................................................................... 198
7.1.7 Selection of Pumps................................................................................................................... 199
7.1.8. Emergency Operation ............................................................................................................. 201
7.1.9. Water Hammer ........................................................................................................................ 201
7.1.10. Miscellaneous ....................................................................................................................... 202
7.1.11. Electrical System................................................................................................................... 204
7.2. Design of the elector mechanical system ....................................................................................... 210
7.2.1..Intake channel and well........................................................................................................... 211
7.2.2. Wet well .................................................................................................................................. 211
7.2.3 Trash rack................................................................................................................................. 212
7.2.4. Sliding Gate ............................................................................................................................ 212
7.2.5. Selection of Pipe Sizes ............................................................................................................ 212
7.2.6. Selection of Pumps.................................................................................................................. 214
7.2.7. System head ............................................................................................................................ 214
7.2.8. Calculation For Electric Power for LLMC discharge ............................................................. 217
7.2.9 Calculation for electric power of LLUB1 ............................................................................... 218
Table of Contents MOWIAE

7.2.10 Calculated for electric power of LLUB2 ............................................................................... 218


8. COST ESTIMATION OF PHASE IIA PROJECT ............................................................................... 221
10. LIST OF REFERENCES .................................................................................................................... 230
11. ANNEXES .......................................................................................................................................... 232
Annex-1 Detail GPS data........................................................................................................................ 232
List of Table MOWIAE

LIST OF TABLES
Table 1: Average depth of water that can be applied on different slopes ................................................... 20
Table 2 : Left Main Canal main data of upper Arjo-Dhidhessa project ...................................................... 28
Table 3: Topographic map of phase IIA & other related data .................................................................... 29
Table 4: Estimated cost of upper Arjo-dhidhessa Left main canal ............................................................. 32
Table 5: Cost of extension canal including structures by redesigning of Upper arjo ................................. 34
Table 6: cost of extension canal after the end of upper arjo canal including structures ............................. 36
Table 7: Cost of canal and related structures for the canal option from the dam outlet.............................. 39
Table 8: Weir site locations options ............................................................................................................ 41
Table 9: Discharge required for LMC, LGC , and LLGC .......................................................................... 43
Table 10: Cost of Left main canal and related structure ............................................................................. 44
Table 11: Cost of left Gravity canal and related structures ......................................................................... 45
Table 12: Cost of left lifted gravity canal and related structures ................................................................ 46
Table 13: cost of lifted canal pumping system and accessories .................................................................. 47
Table 14: Cost of left upper canal systemand related acceries for LLUB1 ................................................ 48
Table 15:Cost of left lifted upper pumping and related accesserries for LLUB2 A,B .............................. 49
Table 16:Cost of left lifted upper canal pumping system and related accesseries for LLUB2C,D ............ 50
Table 17: Cost of diversion weir and appurtenant structures ...................................................................... 52
Table 18: Cost of total water abstraction system by diversion weir and canals.......................................... 54
Table 19: cost of water abstraction by pumping system of the electro-mechanical part ............................ 56
Table 20: Cost of water abstraction by pumping system of civil work....................................................... 57
Table 21: Summary of options of water abstraction system for phase IIA ................................................. 59
Table 22 : flood design at weir project site ................................................................................................. 88
Table 23: freeboard depending design flood discharge ............................................................................ 104
Table 24: hydraulic calculation of left side barrel .................................................................................... 118
Table 25: hydraulic calculation of right side barrel .................................................................................. 119
Table 26: Efficiency of the irrigation system............................................................................................ 123
Table 27: Recommended value of CVR ................................................................................................... 127
Table 28: Maximum permissible velocity and n values for different materials ........................................ 127
Table 29: Suitable side slopes for channel built in various material (chow,1959) ................................... 129
Table 30; the Freeboard recommended by USBR for channel ................................................................. 130
Table 31: discharge versus freeboard of main canals design of chewaka ................................................. 130
Table 32: General criteria of canal parameter for PC, SC, Tc, TD, CD, .................................................. 131
Table 33: Unit weight of material ............................................................................................................. 136
Table 34: Internal angle of (ɸ) of the soil ................................................................................................. 137
Table 35: allowable bearing capacity........................................................................................................ 137
Table 36: permissible concrete structure .................................................................................................. 137
Table 37: permissible Reinforcing steel stresses ...................................................................................... 138
Table 38: constant for design section ........................................................................................................ 138
Table 39: Drainage system of water duty versus years of return period ................................................... 142
Table 40: suggested furrow length for different soil type ......................................................................... 148
Table 41: Average depth of water that can be applied on different slopes ............................................... 149
Table 42: type of Major soils of the command area.................................................................................. 155
Table 43: Crop and land suitability for surface irrigation ......................................................................... 157

February,2017 OWWDSE Page vii


List of Table MOWIAE

Table 44: Land holding ownership of the community of the command area ........................................... 159
Table 45: slope class and area size for gravity block ................................................................................ 160
Table 46: slope class and area for lifted block .......................................................................................... 162
Table 47: Different blocks of net irrigable area under gravity and lifted system .................................... 165
Table 48: scheme supply for lower arjo phase IIA full irrigation ............................................................. 170
Table 49: Annual water required for proposed crops................................................................................ 171
Table 50: water required and electric city charge in pumping system ...................................................... 172
Table 51: Requirement of monthly water volume and electricity cost for lifted system .......................... 174
Table 52: Left main canal (LMC) designed dimension ............................................................................ 177
Table 53: Left gravity canal (L G C) designed dimension........................................................................ 177
Table 54: Left lifted gravity canal Designed dimension ........................................................................... 180
Table 55: Summary of canal length designed for farm work.................................................................... 185
Table 56: Canal Structures on LMC, LGC, & LLGC ............................................................................... 187
Table 57:farm structures on gravity canals of PC,SC&TC ....................................................................... 187
Table 58: farm structures on lifted gravity canals of PC, SC, &TC ......................................................... 187
Table 59: farm structures on upper lifted gravity of PC, SC, and TC....................................................... 188
Table 60: Summary of drainage canals for farm work, LMC, LGC& LLGC .......................................... 189
Table 61: Farm structures on drainage canals of gravity block ................................................................ 189
Table 62: farm structures on drainage canals of lifted block .................................................................... 189
Table 63: farm structures on drainage canals of upper lifted block .......................................................... 190
Table 64: Road network designed in irrigation and drainage system ....................................................... 190
Table 65; Irrigation interval and depth of application for full irrigation .................................................. 192
Table 66: Different crops and irrigation depth of application in 5 days interval ...................................... 193
Table 67: design of life for major components ......................................................................................... 196
Table 68: Design Data for electro mechanical part ................................................................................... 210
Table 69: left side pump station piping calculation .................................................................................. 213
Table 70; Left Side pump station , valve factor k ..................................................................................... 214
Table 71: Head loss in valve, fittings and lines ........................................................................................ 214
Table 72: Required data to select pump .................................................................................................... 215
Table 73: Model Pump Data ..................................................................................................................... 216
Table 74 Cost estimation of Head work, main canals and related structures............................................ 222
Table 75: Cost estimation of farm work canals and related structure phase IIA project .......................... 223
Table 76: Cost estimation of farm work drainage canals and related structures....................................... 225
Table 77: Cost estimation of road network and related structures of phase IIA project ........................... 226
Table 78: Cost summary of head work, gravity and lifted blocks of irrigation and drainage phase IIA
project ....................................................................................................................................................... 228
Table 79: Cost summary of gravity, lifted, head work and LMC Of phase IIA versus area of project ... 229

February,2017 OWWDSE Page viii


List of Figur MWI&E

LIST OF FIGURE
Figure 1: map of location of lower dedesa phase IIA project ....................................................................... 4
Figure 2: map of upper and lower Arjo (chewaka) Phase IIA Irrigation and drainage projects ................. 27
Figure 3: phase IIA gravity and lifted command area................................................................................. 31
Figure 4: Command area of phase IIA and weir option .............................................................................. 42
Figure 5: Pump option at near command area from Dhidhessa River ........................................................ 55
Figure 6: Water abstraction options with required cost. ............................................................................. 58
Figure 7: photo of diversion weir site ......................................................................................................... 87
Figure 8: water surface profile without weir ............................................................................................... 91
Figure 9: Water surface profile with weir at 4.3km (option1) .................................................................... 91
Figure 10; water surface profile with weir at 3.3km (option2) ................................................................... 92
Figure 11: Photo of Bedele-Nekemte Road Bridge over Dedesa river ....................................................... 93
Figure 12: tail Water curve ......................................................................................................................... 94
igure 13: river cross-section of head work. ................................................................................................. 96
Figure 14: longitudinal section of designed diversion weir ...................................................................... 103
Figure 15: Level and length of left D/S floor............................................................................................ 113
Figure 16: level and length of D/s right floor ........................................................................................... 116
Figure 17: diagram showingLeft side barrel ........................................................................................... 118
Figure 18: Diagram showing right side barrel .......................................................................................... 120
Figure 19 proportional off take with one off take on left side, one of take with right side , and off take on
either side .................................................................................................................................................. 140
Figure 20: photo of furrow system directly from the field canal .............................................................. 150
Figure 21: furrow method of irrigation using siphons .............................................................................. 151
Figure 22: method of siphon flow in furrow ............................................................................................. 152
Figure 23: photo of proposed command area of phase IIA /Chewaka ...................................................... 154
Figure 24: map showing soil and land suitability for irrigation ................................................................ 158
Figure 25: map showing gravity block command area with slope class ................................................... 160
Figure 26: map showing lifted block command area with slope class ...................................................... 162
Figure 27 Command area with gravity and lifted blocks .......................................................................... 164
Figure 29:graph showing monthly water volume requred ....................................................................... 172
Figure 30: Graph showing water required for lifted Irrigation block ....................................................... 173
Figure 31 : layout of left main canal, gravity canal and lifted canal ......................................................... 176
Figure 32: six types of canal cross-section of main canal. ........................................................................ 184
Figure 33Graph showing head versus capacity of pump .......................................................................... 217

February,2017 OWWDSE Page vii


Abbrivations MWI&E

ABBRIVATION
ADIDP Anger Dam Irrigation Development

AMSL/amsl Above Mean Sea Level

BGL Below Ground Level

BIU Basic Irrigation Unit

BM Bench Mark

CD Collective Drain

DGPs Diffrential Global Positioning System

DTM Digital Terran Model

ENSAP Eastern Nile Subsidiary Action Plan

ENTRO Eastern Nile Technical Regional Office

FD Field Drain

FDs Field Distributions

FSL Full Supply Level

GDP Growth Domestic Product

Ha/ha Hacter

ID Interceptor Drain

KW Kilo Watte

LGC Left Gravity Canal

LGB Left Gravity Block

LLGB Left Lifted Gravity Block

LMC Left Main Canal

LLGC Left Lifted Gravity Canal

MCE Meterfrea Consulting Engineer

February,2017 OWWDSE Page x


Abbrivations MWI&E

MoWE Ministry of Water Irrigation and Energy

MoWIAE Ministry of Water Irrigation and Electricity

MCN Main Canal North

MCS Main Canal South

MNDC Main Natural Drainage Canal

NGS National Grid System

NPSHA Net Posetive Suction Head Admissable

OWWDSE Oromia Water Works Design Supervision Enterprise

PCA Project Command Area

PC Primary Canal

PS Pump Station

RMC Right Main Canal

SC Secondary Canal

SD Secondary Drain

SMU Soil Mapping Unit

TC Tertiary Canal

USBR Unite Statae Bureau Reclamation

UTM Universal Transverse Mercator

WGS58 World Geodetic System

February,2017 OWWDSE Page x


Executive Summary MWI&E

EXCUTIVE SUMMARY
The economy of Ethiopia is primarily based on agriculture. Almost three-fourth of its population
is directly or indirectly dependent on agriculture. Nearly 46% of the G.D.P. of the country, 70%
of the export earnings and 85% of the employment opportunities are derived from the
agriculture. Still the role of agriculture in supplying and supporting the manufacturing sector in
establishing agro-industry is very high. Despite the fact of agriculture playing such an important
role in the economy of the country and the availability of abundant water resources in the
country, the facility of irrigation has so far been only very minimal leaving the agriculture to be
mainly dependent on the rainfall.

In many parts of Ethiopia the increased population pressure and frequency of droughts has
exceeded the ability of traditional strategies to cope up and global climatic change resulting in
food insecurity and wide spread animal deaths. To meet the demand of the steadily growing
population and to increase foreign export of the county, the government of Ethiopia embarked on
different water resources development studies. Accordingly, all the main river basins of the
country have been extensively surveyed to prepare a master plan for development of the water
resources of the country and to identify a number of potential schemes for irrigation project. In
order to alleviate the situation of food insecurity , countries like Ethiopia have no choice but to
aggressively switch their development endeavors towards effective and efficient use of their
natural and human resources .Development strategy that could help is use of country‟s water and
land resource endowment. As a result, development of different irrigation scheme (small to large
scale) can play a major part not only in solving the current food insecurity, but also in enhancing
the economic development of the country through the earning of more foreign currency and
creating employment opportunities.

The irrigation development in Ethiopia is one of the causative sectors for the economic
development of the country. From this Dhidhessa river due to the construction of dam the
potential contributor for the irrigation developments is expected 80,000 ha.

The country has an extensive network of rivers and streams. There are thirteen major rivers
basins; eight of these have large potential rivers with an average flow of 30 to 50 m3/sec. These
are: Abay (Blue Nile), Tekezi, Mereb, Baro, Omo, Awash and Wabe shebeelle. The Most
impressive basin of Ethiopia plateau, Blue Nile, is an immense river system served by a number

February,2017 OWWDSE Page xii


Executive Summary MWI&E

of important tributaries. The rich water resources are the result of favorable climatic condition.
The country has diverse rainfall and temperature pattern..

Lower Dhidhessa Irrigation and drainage project Phase IIA is located at 398 km west of Addis
Ababa in Oromia regional state Illubabur zone specifically in Chewaka Wereda . The project
land covers one urban and twenty six rural kebeles of Chewaka Woreda. Administratively the
project area is bounded by east Wellega zone from the east, west wellega zone and Leka woreda
from west, by west Wellega from the north, and Dabo Hana wereda from south.

 The Structure of Draft Feasibility Engineering Report


This draft engineering report contains eight chapters in the following detail report.The executive
summary gives very brief description of the main highlight of each chapter to give a bird‟s eye
view of the following chapters.

Under the first chapter of introductory part contains mainly water resource, climate and
agriculture system of the country. Objective, scope, approaches, and methodology of the
consultancy service based on TOR the agreement done with client are included.

The second chapters contains review of similar large scale irrigation project especially the
projects found surrounding phase IIA lower Dhidhessa like Dinger Berha, Anger dam, and
upper Arjo irrigation projects of detail feasibility and final engineering design and study report
has been made in order to get additional knowledge.

In the third chapter detail water abstraction systems or development options of the project are
discussed considering estimation of the required costs of each options and evaluating other
merit and de-merits factors, so that select the best option in order to continue the detail study
and design of the project.

Under chapter four surveying work report including the methodology and scope of the whole
surveying work of the command area, head work and main canal routes data collection and
topographic map preparation are included.

Under chapter five the report included based on the selected water abstraction options set detail
design criteria of head work and appurtenant structure including the design of head work and
appurtenant structure.

February,2017 OWWDSE Page xiii


Executive Summary MWI&E

Under chapter six the detail criteria and design of Irrigation and drainage system like layout
design, conveyance system of main canal and branch canals, drainage system, irrigation methods
, and road network of the project were included.

Under chapter seven the report contains the electro-mechanical system of the project. In the
project out of 11326.70 ha of net area, 7368.83 ha will be used the conveyance system of lifted
gravity canal system. Therefore, in this chapter design criteria and detail design of the
electromechanical system of the project pump and electric system are included.

Finally in chapter eight it included costestimation. Even though detail BOQ is not prepared at
this stage but , major cost estimation report was done for the future implementation of the
project. Currently estimation cost was made due to the fact that major works like diversion weir,
Left main canal, gravity and lifted canal including detail system layout of farm work and
discharge required were known.

 Reviewing of Large Scale Project Documents


In reviewing the large scale irrigation projects like Dinger Berha, Anger Dam, and Upper Arjo
projects feasibility report were done so that some knowledge is acquired for our design and
study of phase IIA project. It also identifies the consideration of important formula, data,
methodology, and scope which can be used in our design as additional information for further
analysis.

 Water Abstraction System


The determination of water abstraction system is paramount for the project cost and continuing
of further design of the irrigation and drainage of the project. This has been made by considering
upper Arjo-Dhidhessa design document, topo map of lower Arjo Dhidhessa phase IIA project,
and the discussion made with the client and other partners suggestion during inception report
presentation. Therefore, five options of different alternatives of water abstraction system for
Chewaka command area have been proposed for the detail analysis. These five options are as the
following.

1. Extension of left side main canal from Upper Arjo project by redesigning the canal.
2. Extension of Upper Arjo left side main canal starting from the end without redesigning

February,2017 OWWDSE Page xiv


Executive Summary MWI&E

3. Constructing separate main canal at the dam outlet.


4. Water abstraction option by diversion weir and canals.
5. Diverting water by pumping system from Dhidhessa River near the command area.

Evaluations have been made on the advantages and disadvantages of different factors like
the future management system, water availability , size of irrigable command area, requirement
of redesign ,future operation, and the least total cost required for investment and operation and
maintenance cost of infrastructures of the above options. Finally based the analysis of these
alternatives, water abstraction option using diversion weir and gravity and lifted canal system
for phase IIA project was selected as the best water abstraction system or development option
of the project.

 Surveying Work
As per our TOR topographic survey of the command area, head work site and main canal route
were done by the establishment of DGPS Control Points so that detailed topographic survey of the
whole command area data was collected.

After data was processed 24,000ha of the command area topographic data has been collected
with all artificial and natural features and topo map was ready for design and system layout.

 Design of Head work and appurtenant structure


A weir can be defined as a barrier with a crest to raise the water level in order to take it by
gravity to an area for irrigation development. A weir structure is generally constructed across the
river for:

 Diversion of water into the canals


 Raising of water level to feed canals
 Storing the excess flow received from upstream storage sites; and
Regulation of desired supplies

 Methodology for the Design of Diversion Weir Structure.


The design of the diversion structure is carried out in two parts i.e., hydraulic design and
structural design. In the hydraulic design, overall dimensions and profiles of the main structure

February,2017 OWWDSE Page xv


Executive Summary MWI&E

and a few of the components are worked out, so that satisfactory hydraulic performance of the
structure can be ensured.

In the structural design, the various component of the diversion structure (Weir) shall be
designed. Details are then worked out to have a structure, which will be safer under any possible
and probable combination of loadings. In both the cases, the diversion structure has to be
properly designed for both the surface and subsurface flow conditions.

The surface design includes the fixing up of waterway, top profile of various structures, energy
dissipation arrangements, protection works, scour depths, length & protection of divide walls,
levels and protection of guide bunds, afflux bunds etc. The sub-surface design will include
fixing of the depth and section of cut-offs, uplift pressure calculations, exit gradient etc.

The basic parameters which were considered and selected before taking up detailed hydraulic
designs were the following;

i) Design flood discharge


ii) Afflux
iii) Pond level
iv) Crest level and profiles
v) Rating curve & downstream retrogression of water levels.
vi) Safety against Sub-surface Flow & Uplift

 Hydraulic Design of Weir Criteria


Broad crest weir is selected the calculation was done by the following formulae.

The flow state through weir is considered for modular and unmodular flow, respectively.When
Upstream head (total head over the crest) = H1 and downstream head (total head over the crest)
=H2, it is for modular flow if H2/H1<0.75 and for unmodular flow if H2/H1>0.75.

Following formulae can be applied according to cases.

For modular flow

Q1 = CLHe3/2 modular flow;

Q1 = calculated discharge (m3/s)

L= length of the weir (m)

He = total head over the crest (m)

February,2017 OWWDSE Page xvi


Executive Summary MWI&E

C = coefficient of discharge 1.7

For non-modular flow

C1L 2 g  H 2 - h a 2   C2 DL 2 gH
2 3 3
Q2 
3  

Where;

Q2 = calculated discharge (m3/s)

L =effective length of the pass (m)

H = difference of u/s and d/s water level (m)

ha =approach velocity head (m)

D =Downstream head (m) 6.12m

C1 = coefficient of discharge 0.577

C2 = coefficient of discharge 0.8

 Specific Diversion Weir Site Selection of Lower Dhidhessa Project


The main objective of constructing diversion weir for phase IIA project along Dhidhessa river as
it was discussed with the above water abstraction system water will be diverted to the left and
right side of main canal intake in order to irrigate the command area available at phase IIA
(Chewaka) and phase IIB (Beneshangul area) for a total estimated about gross are of 30,000Ha
each project has. It means both project totally has agross area of 60,000ha.

In the water abstraction system analysis of different options the diversion weir point below the
main road of Nekemte-Bedele bridge over Dhidhessa River has been selected as the best option.
It is located on the point 4.3km and 3.3km to the downstream from the new bridge crossing the
Dhidhessa River on Nekamte-Bedelle road. Their coordinates are X=214497.7532
Y=965480.7351, X=214400.6990 Y=964560.0315, respectively. Finally the location at 4.3km
weir site was selected as the best location due to back water effect. The span of river width is
estimated 150-200m length. The river bank is totally covered by forest to the left and right side
as you go further the elevation will increase.

 Designof Diversion Weir.

February,2017 OWWDSE Page xvii


Executive Summary MWI&E

Therefore, from the hydrological analysis the peak design discharge at the selected weir site
location with the assumption of with the dam availability at the Upper Arjo project is estimated
as for 100 years return period is 1200m3/sec.The 100 year return period was selected considering
other experience large scale project of Ethiopia.Free board is to be checked using flood of 1000
year frequency.

Hence, a diversion weir was designed with a mass concrete glacises broad crusted weir type with
a total length of 100m span ,a height of 4m above the river bed of 1265m elevation, top width
of the weir crust is 3m and the maximum base width 22.6m. With upstream slope of glacises
weir 1V:1H and downstream1V:3H respectively. It has right and left side of under sluice with
20m and 10m span width respectively.

 Design of the Irrigation and Drainage System


The proposed Lower Dhidhessa Irrigation Development Project is based on the Diversion weir
which will be constructed on river Dhidhessa proposed at the downstream of Arjo- Bedele
Road.The available water in the Arjo Dhidhessa storage dam is sufficient for irrigating an area of
80000 hectares based on the previous study.

Upper Arjo Dhidhessa sugarcane development Irrigation project is one of the projects presently
being under construction for an area of 32,000ha for sugarcane development.

The first Phase of the project (phase-IIA) which is found in Oromia Regional State originally
planned for 30,000 ha, but after making detail investigation by different sectors like soil and
land suitability which was covered 28,883.94 ha land and taking topographic map by surveyor
of the area in phase IIA project covered 26,000 Ha to the left side and 11,000ha to the right side.
The area has a gross irrigable area of 30,391.57 Ha in engineering system layout design so that
a net area of 17,101.70 Ha has decided to be developed. But from this area of phase IIA
10,500ha of gross area and net area of 5775ha will be separately prepared at right side.In this
report from 19,891.57ha a net area of 11,326.70 ha was prepared.

 General system layout design


The total command area of the project lies inside the valley of the Dhidhessa River. The major
slope of the area is from west to east direction to the center of the River. The elevation in the

February,2017 OWWDSE Page xviii


Executive Summary MWI&E

command area varies between El.1310 to 1165m.The topographic of the area estimated for
gravity block out of gross 5891.12Ha 0-2 % , 2-5%, 5-8%, 8-16% slopes have 4.25%,
21.82%, 28.59% and 9.39% of area size respectively. The other part of the command area has
0.01%, 0.02%, 0.27%, 0.78%, and 1.96% areas covered by forest, grave, rock surface, towns,
and villages respectively. For lifted block out of 12000.45Ha, 0-2 % , 2-5%, 5-8%, 8-16% and
>16 % slopes have the area size of 3.87%, 27.11%, 33.03% , 24.54% and 6.54 %. The other
part of command area have 1.56%, 3.11%, 0.05% and 0.25% has town, village, grave and RS
(rock surface) respectively
The gross command area is in general having undulating topography. In system layout design the
maximum slope considered under irrigation is 11-12% considering the past experience of local
farmers in surface irrigation living at Phase IIA project farmers can work by constructing
terrace and other erosion protection method. The area above 11-12% slope of the command area
was not considered as suitable for surface irrigation system.
There are also some isolated hills rising above the average level of the plain and very marshy
areas which actually will be excluded from irrigation suitability except some pocket area can be
used during dry season. Since, due to the lifted head to be determined maximum 60-65m from
the gravity elevation to lifted system and considering the slope of canal the command area by
gravity system with maximum elevation of 1310m.The command area above 1310m is left out
from system layout of the irrigation system.
Therefore, from gravity block of the whole total gross area 5891.12Ha, in system layout and the
net irrigable area of 3957.86ha were designed. In phase IIA irrigation and drainage system of the
project based on the proposed water abstraction system, in the addition of gravity block, lifted
gravity blocks of area is considered to irrigate the whole recommended area of the project. The
system layout has been done to develop the area by lifted pumping system for the gross area of
14,000.45 Ha and a net area of 7368.83 Ha.
 Design Criteria of Irrigation and Drainage System
A diversion weir is proposed at the downstream of Arjo Bedele road for both command area
found in phase IIA and IIB. The estimation of canal capacity to meet water requirement for
proposed cropping pattern is the most important input for irrigation in project. Provided that in
the project for design of canal the cropping pattern is proposed in different phases, for design of

February,2017 OWWDSE Page xix


Executive Summary MWI&E

canal the requirement of water is considered for the maximum water requirement. The maximum
duty of water recommended by agronomist is in the month of March is 1.05lit/sec/ha.

 Canal capacity determination criteria


The capacity of the canal should be sufficient to fulfill the maximum of the peak demand of all
the crops that are required to be irrigated at any one time amongst all season as the agronomist
determined cropping pattern in sectors study.

All types‟ canals capacity MC, PC, SC, and TC were determined using the following manning
formula criteria. With continuity equation of Q= AV, where, A= Area of water cross-section and
V= velocity of water
Manning formula
1
V= 𝑛 * R2/3 * S1/2 (Kumar, 2005)
Where, V= velocity of flow in m/sec
R= Hydraulic mean depth in meters
S= Bed slope of the channel
n = Rugosity coefficient
The values of n in both these equations depend upon a channel condition and upon discharge
size.
Capacity required for the canal to irrigate the command depends on the crop pattern, irrigation
intensity, rotation period, water required during critical period, transmission losses, etc. For
fixing the canal capacity, a design statement, or capacity statement should be separately
prepared, reach by reach.

Main, Primary, Secondary and tertiary canals sections are getting reduced from head to tail reach
with discharge getting reduced. The flow in the main, primary, secondary and tertiary and field
canals will be maintained continuous throughout the year during application except where no
irrigation required during wet season. As in case of surface irrigation method, water application
is planned to be in rotation in the farm units the capacities of field canals will be the same and
kept its dimension constant from head to tail reach.

Concerning velocity;minimum permissible velocity refers to the smallest velocity which will
prevent sedimentation and vegetative growth. An average velocity of (0.4-0.9) will prevent
sedimentation when the silt load of the flow is low. In small canals it can take upto 0.27m/sec.

February,2017 OWWDSE Page xx


Executive Summary MWI&E

Maximum permissible velocity entirely depends on the material that is used and the bed slope of
the channel which is upto 0.9m/sec. All freeboard, bed width, depth, longitudinal slope, berm
have been calculated according to design criteria of the material recommended by geotechnical
study report.

 Design of Main Canals (LMC, LGC& LLGC)


Based on the above design criteria and maximum water requirement the following canals were
designed. Left main canal has designed with a length of 46.6km beginning from the diversion
weir for a discharge of 23m3/sec, 13.20m base width , water depth of 2.14m, fb = 0.75 and
velocity is 0.66m/sec. The canal cross-section is the same from head to the tail.

The left gravity canal at the beginning it has a designed discharge 8.39m3/sec with a dimension
of 84.57km length, depth of water 1.59m velocity of water 0.62m/sec bed width 6.12m and
longitudinal slope 1:5000. The cross-section of the canal is decreasing from head to the tail.

The left lifted gravity canal has a length of 57.25km with at the beginning of the canal has
discharge of 12.2m3/sec dimensions of bed width 11m depth of water 1.61m, a freeboard 0.70m
side slope 1.5H: 1Vand longitudinal slope 1:7000. And velocity has 0.57m/sec.

 Design of canal structures and night storage pond


In the canal structures design like cross drainage, flumes, siphon, escape, foot bridge, cross and
head regulators along the main canals were also designed. Night storage ponds also designed for
lifted block of block 1, 5, and 6 and upper lifted blocks of 1and 2 . The size of night storage pond
for block1 eleven in number between size 5084m3 and 21364m3. For block 5 it has five numbers
between 2743.3m3 and 10910.83m3. And for block six it has a volume of storage between
5084m3 to 21364m3. The size Upper lifted blocks are 4 and it has a useful capacity of 8463,
12711,8148, and 6948m3.

All the other detail farm work system of PC, SC,TC, TD, CD, MD and farm structure were
designed according to the standard well known typical drawing and set the criteria of the above
canals.
Under farm work from the system layout of gravity block of net 3957.86Ha of the total length of
canals of PC, SC and TC estimated the length of 6.526km, 48.762km and 197.418km

February,2017 OWWDSE Page xxi


Executive Summary MWI&E

respectively. In the same block of gravity the drainage canals have CD, SD; TD has a length of
each 9.223, 26.72, and 142.3km respectively. Under lifted system of block net 6264.25Ha the
total lengths of canals of PC, SC, and TC have a length of 56.65, 71.66, and 285.95km
respectively. In the same block of lifted system have CD, SD, and TD have 15.377, 14.87 and
180.84km and upper lifted blocks have respectively. For 1104.58ha upper lifted block has
6km,56 km and 32.8km length of Sc, TC, and TD.

 Irrigation Methods and Water Distribution System


There are three major types of irrigation methods. These are Surface irrigation, Sprinkler or
overhead irrigation, and Drip or trickle irrigation.Each method has certain limitations but most of
the methods can be adapted to a fairly wide range of conditions. Different methods of water
application are adopted because of variations in soil type, topography, water supply, crops and
other management practices.

Due to the topographic condition of the area considering most of the command area‟s slope is
high and undulating nature it seems overhead or sprinkler irrigation is better. But, the sprinkler
or overhead irrigation system will not be appropriate due to high technical capacity requirement
and the initial investment cost is high considering the irrigation scheme is intended to the
farmers. Hence, surface irrigation was considered for this particular project for the area both
under left gravity and lifted blocks. Furrow and basin water application system were proposed.

 Design of Electro Mechanical System


In LowerArjo- Dhidhssa irrigation phase IIA project there are two types of conveyance system
used for the command area irrigation systems. The conveyance systems designed were the
gravity and lifted gravity canal system as based on the proposed water abstraction system. Out of
11326.70 Ha , 3957.87ha and 7368.83 ha will be used gravity canal and lifted gravity canal
system respectively.

For the design of suction and discharge piping and the rising main pipeline from PS to NSR,
flow velocity limits described in the design criteria section were adopted. In the design using
Hazen William formula was used and 28 numbers of pumps including standby were designed
for 560lit/sec discharge. The pumps capacities were designed with total head of 70m for lifted

February,2017 OWWDSE Page xxii


Executive Summary MWI&E

block . The total electric energy consumption required is 15.7MW for lifted block and For
upper lifted block of 1104.58 ha it needs 982.5KW.

 Cost Estimation of the Irrigation Development of phase IIA Project.


Though at this draft feasibility report stage the cost estimation is not detail, but the total cost
estimation was made for the whole project implementation.

It is possible to estimate the cost since major work of areas were identified like the water
abstraction system, the diversion head work and its‟ major quantity of work, the three big main
canals like left main canal, left gravity canal and left lifted gravity canal with numbers of
structures (inverted siphons, flume, Cross regulators, escape etc,). All the required farm work
also identified from the design of system layout. From the electro-mechanical design part the
number of pumps and electric energy consumption were also determined.

Based on this, the detail cost of area of work for the development of irrigation of phase IIA
project including both lifted and gravity system of irrigation of investment cost for a net
irrigable area of 11,326.70 Ha was estimated , so that the total implementation cost including
VAT is Eth birr 3,677,675,318.22.

February,2017 OWWDSE Page xxiii


Introduction MWI&E

1. INTRODUCTION
1. 1 Back Ground
The economy of Ethiopia is primarily based on agriculture. Almost three-fourth of its population
is directly or indirectly dependent on agriculture. Nearly 46% of the G.D.P. of the country, 70%
of the export earnings and 85% of the employment opportunities are derived from the
agriculture. Still the role of agriculture in supplying and supporting the manufacturing sector in
establishing agro-industry is very high. Despite the fact of agriculture playing such an important
role in the economy of the country and the availability of abundant water resources in the
country, the facility of irrigation has so far been only very minimal leaving the agriculture to be
mainly dependent on the rainfall.

In many parts of Ethiopia the increased population pressure and frequency of droughts has
exceeded the ability of traditional strategies to cope and global climatic change resulting in food
insecurity and wide spread animal deaths. To meet the demand of the steadily growing
population and to increase foreign export of the county, the government of Ethiopia embarked on
different water resources development studies. Accordingly, all the main river basins of the
country have been extensively surveyed to prepare a master plan for development of the water
resources of the country and to identify a number of potential schemes for irrigation project. In
order to alleviate the situation of food insecurity , countries like Ethiopia have no choice but to
aggressively switch their development endeavors towards effective and efficient use of their
natural and human resources .Development strategy that could help is use of country‟s water and
land resource endowment. As a result, development of different irrigation scheme (small to large
scale) can play a major part not only in solving the current food insecurity, but also in enhancing
the economic development of the country through the earning of more foreign currency and
creating employment opportunities.

The irrigation development in Ethiopia is one of the causative sectors for the economic
development of the country. From this Dhidhessa River the potential contributor for the
irrigation developments is expected 80,000ha.

February,2017 OWWDSE Page 1


Introduction MWI&E

1.2. Water resources of Ethiopia


The country has an extensive network of rivers and streams. There are thirteen major rivers
basins; eight of these have large potential rivers with an average flow of 30 to 50 m3/sec. These
are: Abay (Blue Nile), Tekezi, Mereb, Baro, Omo, Awash and Wabe shebeelle. The Most
impressive basin of Ethiopia plateau, Blue Nile, is an immense river system served by a number
of important tributaries. The rich water resources are the result of favorable climatic condition.
The country has diverse rainfall and temperature pattern.

1.3. General Climate of the country


Diverse rainfall and temperature pattern and altitude induced climatic conditions form the basis
for three environmental zones: cool, temperate and hot. The cool zone consists of the central
parts of western and eastern section of north western plateau generally above an altitude of
2400m.The temperate zone consists of lower areas of plateau between 1500m and 2400m amsl
and hot zone consists of areas where the elevation is lower than 1500m amsl.

The country has five agro-climatic zones which are broadly delineated mainly for two reasons:
rainfall and temperature because of (altitude).

1.4. Location and Background Lower Dhidhessa Phase IIA Project


Lower Dhidhessa Irrigation and drainage project Phase IIA is located at 398km west of Addis
Ababa in Oromia regional state Ilu Ababur zone and east welloga zone, specifically in Chewaka
Wereda and Diga wereda respectively. The project land covers one urban and twenty six rural
kebeles of Chewaka Woreda and nine kebeles in Diga wereda and one kebele from
Benishangule regional state . Administratively the project area is bounded by east Wellega zone
of wereda from the east, west Wellega zone and Leka woreda from west, by west Wellega from
the north, and Dabo Hana wereda from south. Geographically the project site is found between
UTM co-ordinate y= 974630 to 997585 North and x= 177285 to 202883 east for chewaka and
With the current road system the project area is located 380km far on the way of using Addis
Ababa –Gimbi main asphalt road and immediately bend just below a well known Efreme Hotel
to the left side using all weather road of 18km far at small town of Chewaka.

One of these studies which is currently under construction is the feasibility study and detail
engineering design of Arjo Dhidhessa Sugarcane irrigation Development project conducted by

February,2017 OWWDSE Page 2


Introduction MWI&E

OWWDSE in 2014 to develop a net 32,000ha irrigable area for sugarcane production on
Dhidhessa River with construction of a dam. The previous plan also indicates that the dam being
constructed for Upper Arjo is sufficient enough to irrigate an area of 80,000ha of land.

The main target of the Lower Dhidhessa Irrigation and drainage development project is to
expand the potential of the upper project dam and reservoir radius to the lower end so that gross
irrigable land of 60,000ha could possibly be obtained in two different regions of Oromia and
Benshangule Gumuze National Regional State. The study is going to be conducted in two
different phases phase IIA and Phase IIB.

During detail study in Ilubabur zone Ilu Harere Woreda soil and land suitability evaluation
which was covered 28,883ha land and taking topographic map by surveyor of the area
covered 26,000Ha in engineering system layout has a gross irrigable area of 19,891.57Ha and
net area 11,326.70Ha has decided to be developed at chewaka to the l;eft side the rest will be
covered at right side estimated a gross area of 10,500ha and 5775ha of net area.

At the project inception period effort has been made to identify efficient water abstraction
techniques to command the irrigable command area either from the river or by extending the
upper Arjo left side main canal and it has been recommended to extend the upper Arjo left main
canal.

February,2017 OWWDSE Page 3


Introduction MWI&E

Figure : map of location of lower dedesa phase IIA project

1.5. Objective of the Study of the Work.


The main Objectives of Lower Arjo Dhidhessa Phase IIA project is as follows:

 Based on TOR the main objective is to develop a gross area of 30,000Ha of land after
identifying the exact suitability of the land for the community to produce different crops
and sugar cane through irrigation of Chewaka area
 To implement series of study steps to determine whether the project appears technically,
economically, socially and environmentally feasible,
 To conduct a study on the suitability of the proposed land and its demarcation for
irrigable crops and pasture land,
 To plan, study and design efficient irrigation infrastructure development systems that
could be easy to manage,

February,2017 OWWDSE Page 4


Introduction MWI&E

1.5.1. The Specific Objectives of Engineering Report


 To study and design the diversion weir to irrigate gross command area of 30,000Ha
found to the left side of Dhidhessa River and right side of phase IIA future project.
 To design an efficient irrigation system which ensures reliable delivery of irrigation
water at the right time and to the required amount of Chewaka command area.
 To design an efficient drainage system that ensures removal of excess rain and
irrigation water.
 To estimate the required cost of Irrigation and drainage system of Chewaka area
based on the designed drawing prepared.

The main objective of our study is to undertake feasibility study and detail engineering design on
a total of gross 30,000 Ha by appropriate water abstraction system at the proposed command
area

1.6. Scope of the Work


In the design and study of lower Dhidhessa irrigation phase IIA project the following main
activities will be performed.

In the following sections the scope of the work for Lower Arjo Dhidhessa phase IIA the whole
irrigation and drainage system are described after exactly identifying suitable area of the project.

 Determine appropriate water abstraction system for supplying the irrigation of net
command area of17,101.70ha and gross 30,000ha of phase IIA.

Selection of Appropriate water abstraction is very important for irrigating 17,101.70ha of the
net command area as it will determine all the design and the future cost of the whole project
implementation.

 Design of the diversion head work and its appurtenant structures

Both hydraulic and structures determination of head work and appurtenant including the
feasibility study will be determined as per the design criteria set. The following main diversion
weir structures will be considered.

February,2017 OWWDSE Page 5


Introduction MWI&E

 Normal diversion weir portion.


 Under sluice portion of the weir.
 Divide wall.
 Upstream and downstream floors/aprons/ of the diversion weir.
 Determine cut off walls depth based on score depth at the design flood discharge and safe
exit gradient consideration which the latter is dependent on natural river bed material soil
particle size at the proposed weir site.
 Energy dissipating system design for hydraulic jump for both the diversion weir and
canal head regulator and check the safety marginal against the downstream effects to
considerable distance.
 Canal head work/ head regulator/ intake/ design.
 Silt control devices (silt excluder and/or silt ejector).
 Guide banks.
 Marginal bund.
 Determine diversion work and associated structures design parameters such as main
diversion weir height & cross sectional shape, scouring sluice sill level, diversion
headwork sill level, intake gate size, divide wall location and dimensions etc.
 Structural design of river diversion work and appurtenant.

 Upstream and downstream floor thickness determination of the weir and head regulator
systems based on the uplift pressure encountered for different critical flow conditions.
 Stability analysis of the main body of the weir portion against
o Over turning, sliding and overstressing

 Stress level check at critical sections near the toe portion of the weir.
 The various forces and acceptable combinations of these forces are considered in the
process of stability analysis and allowable stress level checks. The forces involved for the
analysis are:-
 Water pressure
 Uplift pressure
 Pressure due to earthquake forces ( if available in the area)

February,2017 OWWDSE Page 6


Introduction MWI&E

 Silt pressure
 Stabilizing force ( Weight of the Weir Body)
 Prepare detail drawings of section of diversion weir with album
 Prepare detail BOQ and estimation of cost breakdown of the structures of diversion weir
and appurtenant structuers.
 Design the irrigation system of chewaka command area and all the canals system
 Based on the topographic map surveyed proposed command area of Chewaka prepare
detail system layout by dividing the command area under different blocks, options of the
irrigation system, soil map, slope of the land , crops to be grown etc.
 Design main canals system as per the design criteria, system of the irrigation and
different recommendation given by sectors study like geo-technical, agronomy,
watershed, hydrogeology etc both under the gravity and lifted system according to
proposed finalized water abstraction system.
 Design all canals like main canal, primary canals, secondary canals, tertiary canals, as per
the design criteria and sectors study recommendation given.
 Design all the drainage system of Chewaka command area of tertiary drain, collective
drain and main drainage canals based on the topographic area, and others sectors study
recommendation of hydrology, soil, and watershed etc.
 Design all the required irrigation canals structures like culvert, division box , drop , off
take , super passage, flume as per the design criteria and others sectors like, hydrology ,
geo-technical study recommendation.
 Prepare detail system of layout, canals ,and farm structures of sections, profiles of
drawings , of Irrigation and drainage system.
 Prepare detail BOQ and estimation of cost breakdown of the farm structures, canals, and
others structures of the irrigation and drainage system.

1.7. Approach and Methodology


Review of similar big projects of already designed projects in the same area or other places and
collecting initial necessary data for project area by different sectors study and preparing
topographic map from field data collection of surveying are very important.

February,2017 OWWDSE Page 7


Introduction MWI&E

1.7.1. Review of Similar designed and study of Previous Project and Initial
Data Collection
All information pertinent to the irrigation project under consideration shall be thoroughly
revised. Available information includes, but not limited, to the following,

 Review of reports written by different consultants for the study and design of Arjo
Dhidhessa.
 Review of Available reports regarding large scale irrigation and drainage project.
 Review available base map showing topography, roads, paths field boundaries and
drainage channels.
 Review the available reports with regard to flood hazard in the project area. Study of
social and environmental safeguard.
 Identifying constraints and recommend procedures to be adopted during execution of the
design.
On the bases of our assessment to the available information, the required data collection
shall be defined, which will be the bases for further detail design of the project.
 Review of previous study and design of engineering of the available documents.
 Review of all sectors studies conducted and collecting important parameters which is
related to the engineering design like irrigation agronomy, hydrogeology, geo-technical.
soil, environmental impact assessment , watershed management , socio-economic study.

1.7.2. Collecting Primary Data from the Project Site at the Field Level.

Preparing detail head work and command area of topographic map by conducting and
collecting surveying data

February,2017 OWWDSE Page 8


Review of Previous Design and Studies of Irrigation Project MWI&E

2. REVIEW OF PREVIOUS DESIGN AND STUDIES of


IRRIGATION PROJECT.
Reviewing different similar previous designed Irrigation and drainage projects were done before
proceeding designing of Dhidhessa phase IIA projects. It is very important to reviewing the
previous similar projects for the following reasons.
 To include scopes of designed irrigation and drainage projects considered in
similar projects so that applying in the current projects.
 Increase our knowledge on all important factors in design and study of the current
projects based on similar irrigation and drainage projects.
 Identify major challenges, strengths and weakness in designing other similar
projects so that improving the current project.
 To take some important and common irrigation and drainage data, formula and
others factors in order to apply in our current project.
 To compare some important parameters , data so that to evaluate its different and
magnitude

2.1. Dinger Bereha Irrigation Project Feasibility Study Report


Review
Dinger Bereha irrigation Project is situated in Oromia regional state, Ilu Ababur zone at a
distance of 60 km north beadle town . The study was conducted by Eastern Nile Technical
Regional Office (ENTRO) under Eastern Nile Subsidiary Action Program (ENSAP) with joint
venture of consultant MCE (Metafere Consulting Engineers), BRL and SHORACONSULT Co.
in 2010. The proposed Irrigation project is intended to irrigate net area of about 7500ha of land
diverting part of base flow of Dhidhessa River. The command area lies on the left bank of
Dhidhessa River. The weir site is located at a grid of 203671Eand 983650N.

2.1.1. Dinger Bereha Main Irrigation Design Consideration


At Dinger Bereha the peak flood discharge computed by statistics of Abay master plan is
1582.8m3/sec for 100 years return period and 1959m3/sector 1000years return period
respectively. In the project types of crops recommended are sorghum, maize, rice, seasam,
beans, vegetables, and citrus

February,2017 OWWDSE Page 9


Review of Previous Design and Studies of Irrigation Project MWI&E

The hydrological study recommended adopting value of1160m3/sec and 1735m3/sec for a flood
discharge of return period of 100 years and 1000 years return period respectively.

In the Dinger Berha project oggee type weir is selected as the discharge coefficient of ogee type
is efficient. Mass concrete weir is recommended. The foundation is sound base rock. The
minimum height of the weir is 3m. The length of the weir determination is considered discharge
per unit width not exceeded 15m3/sec is taken 110m length.

For the structure to stable the following condition must be fulfilled. 1, the structure must safe
against sliding, overturning, and the resultant force must lie within the middle thired.2, there
should not be tension under the base.3, the maximum toe and heel pressure on foundations
should not exceed the prescribed safe limits. factor of safety against sliding, overturning were
considered and safe, but for the problem of foundation on sliding 24mm anchor bars per linear
grouted into hole drilled to the foundation. Under sluice also provided for the left side. Based on
the design report the weir has a flushing channel at the left end, whereas the off take to the
primary canal will be at right angles to the flushing canals. To minimize the amount of sediment
in the water diverted to the primary canal the crust of off take will be one meter above the bed of
the flushing canal.

Downstream of the canal off take a 150m long settling basin will be constructed. And the
settling basin will be angled towards the river and it will have a gate at the downstream end to
allow flushing of the settled sediment back to the river. In design of embankment, because of the
weir across the river, the water level will rise upstream which case the geo textile can be
avoided. The canal outlet is proposed to take off at an angle 90with diversion weir axis. The
canal bed width is 4.5m it is proposed to provide with two bays of 1.5m by 1.9m width one
0.5m thick pier and the discharge is determined by drowned weir formula by neglecting the
approach velocity head.

Q= (2/3C1L2g(h)3/2 + C2LH2gh )*2

Where, Q= Discharge required for irrigation

C1&C2= Discharge coefficient, C1=0.557, C2=0.80

B=width of the gate= 1.5

February,2017 OWWDSE Page 10


Review of Previous Design and Studies of Irrigation Project MWI&E

h= Head difference= 0.21

H= depth of water at downstream =1.61

2.1.2. Operation of the Project and Night Storage Irrigation System


Irrigation will take place during 12 hours of the day light but the primary canal and pump station
will operate at constant flow, appropriate to the irrigation demand for the whole 24 hours period.
During the night the night storage reservoir will be emptied. For the farm distribution the method
adopted for the project gravity type. To determine crop water requirement the dependable rainfall
was calculated on the basis of rainfall that is equally or exceeded three years out of four (75%
dependablity). In the project consider after assessment of the potential performance
characteristics of the adopted irrigation system.

2.1.3. On Farm and Tertiary Unit Design


Different factors have been used in the design of on farm and tertiary units

 The topographical condition of a general slope of the area


 Numerous gullies and streams cutting the project area
 the present social structure and land organization based on small farms and family labour
without mechanization
 The actual farmers knowledge of water use and management of surface irrigation , when
water is available\

Concerning the efficiency after the assessment of the potential performance characteristics of the
adopted irrigation system (all lined canals, night storage reservoirs , closed buried pipe
Distribution systems and pipe work for on farm distribution ) the overall efficiency was at 60-
65% (that is on farm: 75%, distribution through pipe network that are emptied regularly: 80-
90%,main connivance :95%.

In general from the review of this project the main lesson are the maximum flood discharge
from the hydrological study the design discharge are 1160m3/sec and 1730m3sec for 100 years
and 1000 years respectively this is which important to compare with lower Dhidhessa project
design discharge . Under sluce also provided at both left and right side of the weir and for the
problem of the foundation 24mm anchor bars per linear grouted into hole drilled to the

February,2017 OWWDSE Page 11


Review of Previous Design and Studies of Irrigation Project MWI&E

foundation. Downstream of the canal off take 150m length of settling basin considered if it is
nessery it is possible to consider in lower Dhidheesa project according to the situation.

2.2. Anger Dam Irrigation and Drainage Project Final Feasibility


Report review
The project area is located within two zones (East wellega and Horo Wellega) in the Oromia
National Regional state. The dam and the reservoir area lie within Abe Dongoro and Gida
Ayyanaa woredas in the Horo Wellega and east Wellega zone respectively. The Project
command area (PCA) lies in three woredas Abedongoro, Gida Ayyana and Limu. Access to the
Anger dam site is along the main road between the zonal capital Nekemte and Ayyana (or
Baherdar ) After approximately of north of Nekemete , another 14 km east (4wdvehicles) and 2-
3 km by foot.

2.2.1. The Development Concept of Anger Dam Irrigation Project


The anger dam is planned to supply water for domestic and riparian needs with 100% reliability
and the irrigation system planned for reliability of over 80% -85%. After erection of the dam, the
project will be developed in two main stages. In the first stage the southern (MCS) will be built
and agricultural production will proceed. In the second stage, the northern area will enter
production. Agricultural planning to accommodate mixed small farming operations is adopted
and cropping patterns and crops are selected accordingly. Engineering and on farm development
of irrigation have considered cropping on small individual plots of 2ha each, subdivided into 8
irrigation units of 0.25ha each. Although land will be re-divided and re allocated amongst
growers, based on engineering designs, and on location and routing of water channels , growers
will continue to cultivate small multiple plots at different locations , based on fertility traditional
land tenure.

2.2.2. Drainage System of Anger Irrigation Project


The main natural drainage channel in the area is Anger River. The river flows from east to west,
below the dam site, for about 7km. and then flows south till the end of PCA(about 19km). There
are many big and small streams outfall in the left and right sides of Anger River. The peak
discharge value (at m3/sec) of the anger river for 5,10,25,50 and 100 year return periods are
133.7, 203.8, 319.3, 389.8- and 493 respectively

February,2017 OWWDSE Page 12


Review of Previous Design and Studies of Irrigation Project MWI&E

2.2.3. Irrigation Methods and Crop Water Requirement


Due to various reasons both surface gravity and pressurized irrigation methods were selected for
different geographical areas within the PCA. The area on the south side of the anger river is
intended for the gravity irrigation on permanent basis. The northern main canal (MCN) will
developed during the second stage. It will mainly serve for pressurized irrigation. The water
requirement and the irrigation intervals were determined according to the selected cropping
pattern and the soil properties. The maximum water requirement is based on the irrigable area is
183.44Mm3 with water demand of 5.3mm/day. The Irrigation application time is 12 hours for
surface irrigation. Pressurized irrigation is planned for (net) 22 hours.

2.2.4. System Description


Because of the area topography and irregularities, secondary canals, and tertiary canals need to
run across slope. Consequently, these canals may need intensive drop structures and may be far
too expensive. For slops more than 1% the alternative of using close pipes was considered. The
four conveyance systems were studied on the basis of topography and land suitability maps.
These alternatives are

 Open gravity canal


 Pipe canal
 Forced pipe (gravity led pressurized pipe)
 Pressured pipe by pump

The selected irrigation method for ADIDP comprises surface irrigation through earthen canal,
surface irrigation through pipe canal, pressurized irrigation through gravity head and pressurized
irrigation through pumps.

2 .2.4.1 Water Conduits


The BIU is planned to be of uniform size and dimensions: 200mby 100m, an area of 2ha. These
dimensions should be kept as much as possible, to allow for furrows of uniform length of 100m.
The BIU of 2ha consists of eight farms units each of 0.25ha or 100m by 25m

The FDs in the PCA run in steep slopes, generally exceeding 4%. Detailed analysis of a
comparison of two alternatives: earth FD and field pipe was carried out. The use of field pipes is

February,2017 OWWDSE Page 13


Review of Previous Design and Studies of Irrigation Project MWI&E

recommended for a surface slope of more than 2%. The water is delivered to the furrows by
siphons, in case of earth canals or by overflow valves in case of field pipes.

Tcs Fcs and BIU operate for 12 hours hence the area designed for double discharge capacity. The
MCs operate 24hours hence night storage reservoirs are needed at the inlet of SCs.

2.2.4.2 Delivery in Closed Pipes


Because of steep slopes the canal need to employ many drops. Consequently, the option of using
pipelines was considered. The use of pipes for pressurized irrigation is proposed as an alternative
for each canal at secondary level.

In case of pressurized irrigation, in above areas, the main pipes, the sub mains pipes and valve
line are equivalent to SCs, TCs and FDs, respectively.

Regulation of water flow uses either the natural gravity head or external mechanical means of
pumping. From the main canal, a main pipe runs along the slope (perpendicular to the contours).
From the main pipe, sub main pipes run about along the counters. However, the sub main pipes
can follow the surface features as required in order to cover maximum area. The sub main pipes
can be of curvature and meanders as may be necessary. Use of pumps is proposed for irrigation
of the higher elevated areas as well as the areas adjacent to the steep slopes along the mc, to
provide the required pressures in the pressurized irrigation distribution system at different
locations. A lift canal system is also included to irrigate higher elevation area through a provision
of a single pumping station.

2.2.4.3. On farm irrigation


The net irrigation water requirement for the system design and operation derived from the
cropping pattern and for combined crops by small holders: 5.3mm/day and for sugar cane:
5.7MM/day. The gross application water requirement is calculated with irrigation application
efficiency and the delivery efficiencies of the water delivery system. For surface irrigation
application efficiency considered 65%, pressurized irrigation for basket crops 90%, Pressurized
irrigation for sugar cane 86%.In all delivery efficiency FD=92%, TC=92%, SC=94% and MC
90% for all pipes = 100%. The per ha figure of water application to the field for surface irrigated
area and pressure irrigated area are 2.07l/sc/ha and 0.93l/sec/ha, respectively.

February,2017 OWWDSE Page 14


Review of Previous Design and Studies of Irrigation Project MWI&E

The irrigation interval is calculated in consideration with the soil type and crops effective root
zone. Considering also the practical simplicity of the irrigation interval, an interval of 8 days is
planned for the application of the peak water requirement. The irrigation interval of 8 days is
well in accordance with the layout of the plots arrangement and the on-farm system of FDs and
Tcs.

In the irrigation system four possible irrigation method were analyzed at the stage of typical
arrangement adapted to the specifically of the area under study. These are Surface (furrow
irrigation), Pressurized (Center pivot, drip irrigation, sprinkler irrigation).

In surface irrigation system the topography of the area makes surface irrigation extremely
difficult because of the steep slopes and irregularity of the surface. However, if a budget
limitation governs the decision and low irrigation efficiency is accepted with risk of erosion, the
only surface irrigation method that can be employed is furrow irrigation. Any other surface
irrigation method such as borders or basin, require and expensive works for land preparation and
leveling is required.

The designed area allocation will enable simple and efficient operation of on the farm irrigation
system. The regular layout of the 8area units of 2ha each also enables a straight field ditch of
minimal length. Due to the ground slope, most of the field ditch (6 out of 8) serve one side and
only a limited number of field ditch (2 out of 8) can serve two sides ,thus being more efficient.
Surface irrigation planned for daily irrigation of 12 hours, where by the full flow of the tertiary
canal is diverted to one field ditch for one day of the 8 irrigation interval days, and the flow is
rotated during the 12hours among the 8 farm units

2.2.4.4. Drainage and flood protection works


The main natural drainage channels (MNDC) will form the core of the planned system to drain
excess runoff during the rainy season and avoid inundation and water logging in the PCA. The
system will also serve as the outlet for on farm drainage system.

The layout of the drainage system will be based on the following elements.

 The MNDCs
 Incoming sources (Watershed upstream of the proposed main canals and direct rainfall
over the PCA)

February,2017 OWWDSE Page 15


Review of Previous Design and Studies of Irrigation Project MWI&E

 Land use (crop type and layout ,and field management)


 planning irrigation systems

Additional drains will be constructed upstream and parallel to the main canals interceptor drains,
to reduce crossings on the main canals and protect them. These drains will divert flood water, as
topography permit, to the MNDCs entering the PCA.

For protection of the proposed main canals, the design discharge values of 5-year and 50 year
return periods were adopted for design of interceptor drains and drainage crossing, respectively

In MNDC which includes the Anger River and other main natural streams in the PCA. Anger
River, being the main drainage channel for PCA will be designed for discharge of a 10 year
return period. Other main streams will be designed for a discharge of 5-year return period. The
drainage crossing on this river will be designed for a discharge corresponding to a25-year return
period in PCA

The main drains ,which are natural streams flowing from outside the PCA collecting flood water
from much wider basins, will be designed for peak discharge values calculated using the SCS
method (U.S soil Conservation Service). In design of typical structures for the drainage two
types of outfall structures are proposed on these MNDC, wherever required( i) piped inlet deep
outfall (drain outfall structure type 2) and deep drain outfall (drain outfall structure Type-3)

Field drains are designed for a minimum of 2ha (the basic irrigation unit )of the surface irrigated
areas, considering the one in five year 24 hour rainfall even , i.e to remove the volume of runoff
from 1-in-5 year ,24 hours storm, in 24 hours . The drainage coefficient required to drain this
volume of water in 24 hours, is 4.4lit/sec/ha. The maximum irrigation surplus runoff for the 2ha
area is 4.06lit/sec while the average rainfall runoff is 8.8 l/sec. This value of average rainfall
runoff is approximately 2.2 times higher than the irrigation surplus runoff; hence the drainage
system will be designed for the average rainfall runoff value considering the irrigation during
this rainfall event is unlikely, similarly the discharge value were calculated for field drains ,for
various options of irrigation plot layout and on farm system. All tertiary drains and collector
drain are designed based on the same principle

Maintenance of drainage system is very important to avoid silt, weeds and other impediments
routine maintenance of drains before rainy season is essential.

February,2017 OWWDSE Page 16


Review of Previous Design and Studies of Irrigation Project MWI&E

2.2.4.5 .Road Infrastructure


The main objective of the road system study is to facilitate the proper performance and operation
of the irrigation scheme on the one hand, and make social service more accessible to the farmers.
On existing road situation the Nekemte-Bure road provides the primary access to the command
area, however, there is a poor networking of all whether road. Most part of the command area
have difficult accessibility because of somewhat uneven topography elevation between 1400-
1800masl. The roads were built by several community with in the project area which built by the
community using labor intensive techniques.

Using the road functional classification selection, the design traffic flow and the expected traffic
loads and movement in the irrigation project, the standard used for community feeder roads
would be appropriate for design in the initial phase. The design of feeder roads essentially
consists of the following components. Geometry, pavement, hydrology, hydraulic, major and
minorstructure, consideration of local needs, and requests.

In the above project reviewing some important point‟s lesson have taken as the following:

 Due to the topographic condition in irrigation method combining gravity and pressurized
irrigation methods were used.
 For the conveyance system due to topography and land suitability four conveyance
system were studied like open gravity canal, pipe canal, pressurized pipe and forced pipe
and finally selected surface irrigation through earthen canal, pipe canal and pressurized
irrigation through gravity head and pressurized irrigation through pumps.
 In design of the drainage system for protection of the proposed main canals, the design
discharge values of 5-year and 50 year return periods were adopted for design of
interceptor drains and drainage crossing, respectively.
 In farm road network design. The design of feeder roads essentially consists of the
following components. Geometry, pavement, hydrology, hydraulic, major and minor
structure, consideration of local needs, and requests.

2.3. Arjo-Dhidhessa Sugar Cane Irrigation and Drainage Project


Feasibility Study Report Review
Arjo Dhidhessa sugar cane irrigation project is located about 360km far from Addis Ababa and
it is found in Oromia National Regional State at Illuababore and Jimma zone in both Gechii

February,2017 OWWDSE Page 17


Review of Previous Design and Studies of Irrigation Project MWI&E

and Lemmu district which is 40 km far from Bedele town. The main objective of the project was
to develop sugarcane on 50,000 ha for 28,000 TCD plant but after the designed only 31918.6 ha
was net decided to be developed. The main project components are rock fill with impervious clay
core dam with 47m height and 502m length, and spillway. The irrigable area is found to the left
and right side of the river of Dhidhessa is 31,918.6 ha at the 1 st stage using to irrigate by both
surface and sprinkler irrigation system.

The Arjo Dhidhessa command area feature has a combination of level to flat and almost
flat, rugged and undulating topography. The project area can be conveniently categorized
into Kola agro –climatic zone.

The total 31,918.6 ha of irrigable area of Arjo-Dhidhessa project 17,259 ha, 10,612.5 ha and
4047.31 ha size will be used the irrigation system of by sprinkler, surface gravity and lifted
gravity system respectively. The total available designed command area to the left side with
gravity, lifted gravity and sprinkler system of irrigation of command area is 15,809.9 ha and the
total available designed command area to the right side with gravity, lifted gravity and sprinkler
system of irrigation is 16,108.9 ha.

The irrigation project area is planned to be developed through the abstraction of Water from an
upstream dam constructed across Dhidhessa River. The main Canal route has two directions that
are to the right and left side of Dhidhessa River. The total length of the Main Canal Route for the
right side is 92.5 Km and for the left side 104.4 Km which is in total 196.4 Km. the canal of left
and right side was designed 17.9m3/sec and 25m3/sec respectively. The discharge from the left
and right dam outlet also 56 m3/sec. The left side full supply level is 1337.50 m and the end left
side main canal coordinate is x=981050 and y=201951

2.3.1 Hydraulic Design of Parameters of the Canal


The hydraulic design parameters used to design canal sections, per given design criteria are
described under.
The dimension of the channel can be calculated using the general formula of Manning‟s
equation, which is given by:

1
Q * AR 2 / 3 S 1 / 2
n

February,2017 OWWDSE Page 18


Review of Previous Design and Studies of Irrigation Project MWI&E

Where, Q = discharge of the channel

R = Hydraulic radius = A/P

A = Wetted cross-sectional area = CBWxFSD+mxFSD2

CBW = Canal Bed Width

FSD = Canal Full Supply Depth

m = side slope

P = wetted perimeter = CBW +2x(mxFSD)

s = bed slope

n = Manning‟s roughness coefficient

(“n” value consider for the design of the main canal are 0.025 & 0.018 for unlined and
lined canals respectively).

The velocity of flow ranges adopted for Arjo Dhidhessa Sugar Development irrigation project
varies from 0.95m/sec to 0.39 m/sec. which the geotechnical investigation of the canal route
prevails that this range of flow velocity will not cause erosion of the side canal materials.

2.3.2 Furrow Irrigation System


Furrow shape, spacing and length are determined before and based on the soil and slope of the
command area relating with experience value.
Accordingly all the furrow length in the quaternary unit of the block is approximately 200.00m.
The slope of furrow in all quaternary units except adjacent to the secondary natural drains are
level (0-1%). The stream size and method of feeding the furrows will be described under.
The size of the furrow stream is the one factor, which can be varied after the furrow irrigation
system has been installed.
The maximum non-erosive flow rate in furrow is estimated by the following empirical formula
equation:
qm= 0.6D/s

February,2017 OWWDSE Page 19


Review of Previous Design and Studies of Irrigation Project MWI&E

where; qm : Maximum non-erosive stream,(l/s)


s : Slope offurrow expressed
The average depth of water applied during irrigation can be calculated from the
following relationship:
𝑞∗360∗𝑡
D= ,
𝑤𝑙

where; D : Average depth of water applied in cm


q : Stream size,l/s
t : Duration of irrigation (elapsed )
w : Furrow spacing in m
ttimetime),hours
L : Furrow length in m

Therefore, based on the above relation the following values are derived:
Table : Average depth of water that can be applied on different slopes
Furrow length = 200m Furrow spacing = 1.0m
S (%) 0.5 1 1.5 1.8 2 2.2 2.5 2.75 3 3.25 3.5
qm (l/s) 1.2 0.60 0.40 0.33 0.30 0.27 0.24 0.22 0.20 0.18 0.17
d(cm) 51.84 25.9 17.3 14.4 13.0 11.8 10.4 9.4 8.6 8.0 7.4
type dominates the area.

2.3.3 Capacity Determination and Canal Cross-Sections Design


The total water requirement of each canal system has been determined before and the peak
design duty at tertiary level is 1.59l/s/ha. Therefore, the estimation of design discharge capacity
per reaches area coverage with duty of water required.

2.3.4 Design criteria


The following main design criteria have been considered in the design of tertiary canals cross-
sections:
 The minimum size of the canals is imposed by the construction possibilities; a
hand-made canal has a minimum width of 0.3m and a minimum depth of 0.15m.
 For any given flow Q and slope so the permissible velocities should not exceeded.
 The dimensions of the canals are calculated with Manning formula.

February,2017 OWWDSE Page 20


Review of Previous Design and Studies of Irrigation Project MWI&E

2.3.5. Drainage System Design


Drainage has been considered as an integral part of the irrigation system. Lack of proper
drainage system or inadequate and deficient drainage system may result into very serious adverse
consequences. In this background, drainage system should be carefully studied and designed as a
complementary system in any irrigation schemes, because no irrigation method produces wetting
exactly matching to the plant roots i.e. some part of the field may receive little water and the
other may be over irrigated. Generally two types of drainage system can be provided these are
surface drainage and sub-surface drainage system.
According to previous soil survey, land suitability and hydrological studies finding currently
static ground water table in the project area is at deep depth, hence water logging is not a
problem for well-managed surface and sprinkler irrigation system. Moreover, since there is no
problem of salinity no water is required to leach undesirable salts from the soil. Taking these
facts in to account surface drainage system is proposed, so that excess irrigation and storm water
unwonted for the crop growth would be safely evacuated.
In general there is no drainage problem from topographic point of view in almost all part of the
command area.

2.3.6. Surface drainage system


It is proposed to provide detailed surface drainage system as an integral part of the irrigation
system. In view of the above discussion, it transpires that there is no necessity of sub-surface
drainage. However, it suggests the need and necessity for providing elaborate surface drainage
system. Therefore, the surface drainage system for the project has been planned and designed
which should be constructed and maintained properly so that it functions efficiently and
effectively. In this way, if proper surface drainage system is implemented and its proper
functioning is ensured, and a good ground water management policy is adopted, then there will
be no appreciable rise in ground water necessitating implementation of sub-surface drainage
system. With this end in view detailed planning and design of surface drainage system has been
done.
The main objectives of provision of this surface drainage system are:-
• To safely remove storm from the farm land.
• To collect and dispose excess irrigation run-off.

February,2017 OWWDSE Page 21


Review of Previous Design and Studies of Irrigation Project MWI&E

2.3.7 .Peak Run off Determination


Peak runoff is normally used for design of drainage channels and related structures. Drainage
capacity is determined based on either instantaneous peak discharge from the catchment or
average surface runoff over a period of hours. For the design under consideration the latter case
has been chosen to attain optimum design discharge. In field drainage system is designed for 1 in
5 year 24 hour rainfall event, i.e. the drains are designed to remove the volume of runoff from a
1in 5 year 24 hr storm. For the quaternary and tertiary drains this result in short term flooding,
although this should care within 24 hours for all but the most extreme events (with return periods
in excess of 1 in 5 year). The short term flooding will not lead to significant problems for either
the crops or drainage channels. However, any structures on the drainage network could be
damaged by the higher flows that are generated. Accordingly, a different criteria has been used
to establish the required capacity of drain structures, namely 1 in 5 years 15 minute storm. The
runoff formulas commonly used is:

2.3.8. Design of In Field Drainage System of Structures


Different types of drain canal structures have been provided on the different components of the
drainage system. These include:
 Drop structures
 Road crossings
 Outfalls

2.3.9. Main canal structures design


The Appurtenant structures so provided in the Main Canal can be categorized in two basic
grouping which the first one is the canal regulating structures comprise of Cross Regulators ,
Head Regulators (Off take Structures), Escapes and Drop Structures.
The second group of structures is provided solely for the crossing of river valley, stream and
Gully crossings. This cluster of structures is of different type depending on the technical and
economical appropriateness of the specific crossing point.

The type of regulating and crossing structures provided for Arjo Dhidhessa irrigation Project is
as listed here in below.

 Cross Regulator
 Head Regulator

February,2017 OWWDSE Page 22


Review of Previous Design and Studies of Irrigation Project MWI&E

 Main canal escape and rejection outlet structures


 Vertical drops
 Inverted Siphon Drainage Crossing
 Flume Drainage Crossing
 Superpassage Drainage Crossing
 Box culvert Drainage crossing
 Pipe Culvert drainage Crossing

The above structures of detail hydraulic and structural analysis were considered in the design as
per the design criteria.

2.3.10. Electro-mechanical part of the Upper Arjo -Dhidhessa project


Arjo-Dhidhessa sugar cane development irrigation project has four main categories of locations
for pump stations. These are the Upper-Right Irrigation site, Upper Left Irrigation site, Lower
Right Irrigation, Lower Left Irrigation Site.

The right irrigation site is the command area which is located at the right side of Dhidhessa
River, and similarly the left command is located at the left side of the Dhidhessa River. On the
other hand the lower commands are located below (at the Southern) part of Arjo-Bedele Road.

In each of the above irrigation sites there are different irrigation methods. These are Sprinkler,
Lifted Irrigation Command areas. These four command areas have their own respective station
design capacities.

The design of the pumping stations was performed in three phases mainly:

 Data collection
 Evaluation of alternative options
 Detail design of pumping stations based on the selected option

The detail design and calculations of the major components of the electromechanical system are
described in detail and include:

 Intake chamber or sump design


 Pipe sizing

February,2017 OWWDSE Page 23


Review of Previous Design and Studies of Irrigation Project MWI&E

 Pump selection

Surge analysis

There are more than twenty eight pump stations which are designed for gravity and sprinkler
irrigation systems. The station design capacity, head, power requirement, and discharge at
channels and calculated

The design criteria used as a guideline during the design process. Criteria is set out for

 Hydraulic design
 Pumping equipment
 Electrical equipment
 Accessories

2.3.11. Road Network in Upper Arjo- Dehidhessa Irrigation and Drainage


Project
In the project of Irrigation and drainage system road networks were designed to facilitate all the
irrigation water management operation and agricultural activities including inputs and outputs
management. All the agricultural machineries like tractor, vehicles, agricultural harvesting and
equipments and other inputs of agricultural crops have to be contentiously transported in the
irrigation system to the market access. The roads were designed considered the maximum load
and its width the machines can be moved in the system. At the crossing point of the field
crossing bridges and culverts were also considered.
The roads were divided into four main divisions. These roads are main road, secondary road,
tertiary road and field roads.

Reviewing the upper Arjo-Dhidhessa project is very important as lower Arjo-Dhidheesa project
is a continuation of upper Arjo Dhidhessa project. Many important data like the left side canal
discharge, type and number of structures, the end canal bed elevation and the discharge at the
dam outlet are required for lower Dehidhessa project of phase IIA. Using the very common
manning formula for the determination of the canal capacity and considering the minimum and
maximum velocity within the range of 0.39m/sec and 0.95m/sec. The combination of the
irrigation system like pressurized and surface irrigation system, designing of the drainage system

February,2017 OWWDSE Page 24


Review of Previous Design and Studies of Irrigation Project MWI&E

for internal and external system like using I in 5 years for 24 hours of storm rainfall can be used
based on the condition in lower Arjo-Dhidhessa project.

February,2017 OWWDSE Page 25


Water Abstractions Options MWI&E

3. WATER ABSTRACTIONS OPTIONS of PHASE IIA


PROJECT
In order to divert water from the dam and Dhidhessa River to the command area of phase IIA of
project different options were proposed as the following:

1, Extension of left side of main canal from the Upper Arjo- Dhidhessa project by redesigning
the Canal

2. Extension of upper Arjo-Dhidhessa left side main canal starting from the end without
redesigning the canal

3. Constructing separate main canal at the dam and taking water from the dam outlet

4. Water abstraction option using diversion weir and canals.

5. Diverting water by pumping system from Dhidhessa River.

The methodology was done by collecting appropriate data of like topographic map, discharge,
elevations, cost estimation and other related data, so that evaluating different options of the
above alternatives of water abstractions system and to decide the best option in order to continue
the detail design. Using the following table 2 and table 3 main data on the Upper Arjo-Dhidhessa
and Lower Dhidhessa topo map analysis was done to estimate others cost of the following
tables. For the following cost estimation tables VAT is considered for all types of water
abstraction systems. Additionally operation and maintenance and running cost for 15 years was
considered. The purpose of cost estimation is to compare the different alternatives and select the
best minimum cost.

February,2017 OWWDSE Page 26


Water Abstractions Options MWI&E

Figure : map of upper and lower Arjo (chewaka) Phase IIA Irrigation and drainage projects

February,2017 OWWDSE Page 27


Water Abstractions Options MWI&E

Table : Left Main Canal main data of upper Arjo-Dhidhessa project

NO Description unit Qty Remark

1 Left dam outlet discharge m3/sec 56

2 Left main canal discharge upper arjo M3/sec 17.9-8.99

3 Total length of upper main canalupper Arjo km 104.4

4 Total length of upper main canal below Nekmte- km 39.22


Bedele road

5 Average depth of water upper Arjo m 1.85

6 Average width of the canal upper Arjo m 4.12-5.59

7 Free board of the canal Upper Arjo m 0.75

8 Side slope of the canal upper arjo M 1.5/1

9 Bed slope of upper Arjo S 0.0002-


0.0001

10 Concrete lined main canal part km 25

11 Number of escape NO 7 2.5by---6m

12 Number of siphon NO 3 With average


length 613.3m

13 Number of flume NO 9 24m length by


2.16 width

14 Super passages NO 7 3.42 by


10.14m

15 Cross drainage NO 35 26.55m

February,2017 OWWDSE Page 28


Water Abstractions Options MWI&E

16 Cross Regulator NO 11

17 Full supply level at the end M 1317.50

18 End of left side main canal coordinate position X=981050

Y=201951

Source: Upper Arjo Detial design and study engineering report, OWWDSE,2014

Table : Topographic map of phase IIA & other related data

NO Description unit Qty Rem


ark

1 Length of extension of canal from the end of km 89.6


Upper Arjo upto phase IIA end

2 Length of extension from end of upper Arjo upto km 18.593


begging of phase IIA command area

3 Length of gravity canal from the weir upto km 46.6


beginning of command area

4 Length of gravity canal from the weir upto the end km 131.16
of command area of phase IIA

5 Command area elevation under gravity m 1249-1146

6 Command area elevation under lifted m 1309-1218

7 Elevation between gravity to lifted canal m 1250-1309

8 Elevation between lifted canal to upper lifted m 1310.03-1399


block
9 Net command area under gravity canal Ha 3957.87

10 Net command area under lifted gravity canal Ha 6264.25

February,2017 OWWDSE Page 29


Water Abstractions Options MWI&E

NO Description unit Qty Rem


ark

11 Net command area under upper lifted block Ha 1104.58


12 Total length of canal from dam outlet upto end of km 191.36
command area is (104.4+86.96km)

13 Water duty at maximum for Chewaka/ Phase IIA lit/sec/ha 1.05


command area for 24 hours

14 Left main Canal length from Diversion weir km 46.6

15 Length gravity canal length after junction km 84.56

16 Left lifted gravity canal after junction km 57.25

17 Left main canal discharge M3/sec 23

18 Left Gravity canal discharge m3/sec 8.39

19 Left Lifted Gravity canal discharge m3/sec 12.20

Source: System layout design of lower Arjo Phase IIA project, OWWDSE, 2016

February,2017 OWWDSE Page 30


Water Abstractions Options MWI&E

Figure : phase IIA gravity and lifted command area

February,2017 OWWDSE Page 31


Water Abstractions Options MWI&E

3.1. Extension of Left Side Main Canal by redesigning


Extending Left main canal starting from the coordinate point x= 201951E and y= 981050N,
which run from main dam and rich after 104.4km length and at the end it has a full supply level
of 1317.5m amsl that can irrigate the lower Dhidhessa project which comprise a gross area of
19,891.57Ha by gravity irrigation system.

From the above Table 3 the intake capacity from the dam outlet is designed to convey a
discharge of 56m3/sec, but the left main canal for upper project will take 17.9 m3/sec at peak
requirement. The remaining 38.1m3/sec can be utilized for the development of Lower Dhidhssia
irrigation project by modifying the canal carrying capacity. The upper canal dimension was
designed to accommodate a discharge range between 17.9- 8.99m3/sec. The Lower Dhidhessa
irrigation main canal for phase IIA start after the end point of the Upper- Dhidhessa project and
only travel 18.5km to find the command area. All the above Upper Arjo-Dhidhessa designed
structures like 25 km concrete lined canal length, seven escapes, three big inverted siphons
with average each length of 613.3 m , nine flume with average length each 24 m , seven super
passage length with each 10.42 m and 35 cross drainages

Table : Estimated cost of upper Arjo-dhidhessa Left main canal

NO Type of irrigation Unit QTY Estimated cost Remark


structures
(birr)

1 Main canal excavation km 104 798,442,950

2 Main canal lined km 25 331,609,658

3 Cross regulators NO 11 19,772,203.12 -

4 Head regulators with NO 51 9,690,332.73 -


off take

5 Inverted siphon NO 3 123,621,620.4 -

6 Flume NO 9 124,730,994 -

February,2017 OWWDSE Page 32


Water Abstractions Options MWI&E

7 Super passage NO 7 11,782,572.54 -

8 Outlet rejection/escape NO 7 6,756,359.58 -

9 Cross drainage NO 35 13,449,438.8 -

10 Investment cost 1,655,834,549


including VAT

11 Operation 320,155,610
&maintenance 15 year

12 Total 1,975,990,159

Source: Upper Arjo-Dhidhessa detail technical report by OWWDSE, 2014

As per the recommendation of agronomist during the maximum water requirement in the month
of March is 1.05li/sec/ha for phase IIA command area based on the given cropping pattern. The
gross area of Phase IIA is 30,391.57Ha and net irrigable area from system layout is 17101.7Ha to
the left and right side. But for the left side The discharge required is 11,326.70*2.1lit/sec/ha will
be 23.786m3/sec

The total water discharge at main canal of outlet is equal to 23.786 m3/sec. But for the lower
Arjo-Dhidhessa project in the future it will be expected to consider for water supply scheme and
other allowance from 4-5m3/sec to the people and livestock hence the design capacity of the
canal for the extension lower Arjo- Dhidheesa project considering night storage it will require
23m3/sec.

The total discharge required to use in the extension system both upper Arjo and lower Arjo-
Dhidhessa is 23 +17.9=40.9m3/sec.This means current capacity of canal will be increase by 2.28
times the Upper Arjo-Dhidhessa canal capacity and to modify the entire canal dimension also
required starting from the dam outlet.It will also require modifying, since it was designed with a
discharge range of 17.9-8.99m3/sec. Therefore, all the canal and structures capacity need to
increase its capacity.

February,2017 OWWDSE Page 33


Water Abstractions Options MWI&E

Considering the upper Arjo- Dhidhessa cost estimation in table 4 and the detail cost estimation
for the extension of canal from dam outlet can be estimated in the following table 5.

This means the discharge is 2.28 times increase the upper Arjo-Dhidhessa design discharge. The
above canal dimension, canal lining, and all the above listed structures will be increased its
capacity and its cost at least 1.75 times of the original design.(This is based by comparing
different discharge amount and related dimension and cost of structure of previous work).
Redesigning, and operational and maintenance cost has to be considered. The redesigning cost is
estimated about 6,200,000 birr. In the following table 5 cost estimation of initial investment cost
and operational and maintenance cost of 15 years are considered. Another disadvantage is the
Upper Arjo-Dhidhessa project is totally assigned for sugar cane but phase IIA areais for the local
community in order to produce different crops, which the management in both case are different,
so that, this will also bring some complication. The main advantage of using extension of the
canal will be about 11,326.70Ha of irrigation area can be irrigated without using any energy
power system like electricity by the gravity system.

The cost estimation unit rate is based on the current price of the Upper Arjo-Dhidhessa detail
BOQ work and increased as per the discharge increments.

Table : Cost of extension canal including structures by redesigning of Upper arjo

NO Type of irrigation Unit QTY Estimated cost Remark


structures
(birr)

1 Main canal excavation km 104 1,397,275,163

2 Main canal lined km 25 580,316,901.30

3 Cross regulators NO 11 34,601,355.46 -

4 Head regulators with off NO 51 16,958,082.28 -


take

5 Inverted siphon NO 3 216,337,835.70 -

February,2017 OWWDSE Page 34


Water Abstractions Options MWI&E

6 Flume NO 9 218,279,239 -

7 Super passage NO 7 20,619,501.95 -

8 Outlet rejection/escape NO 7 11,823,629.27 -

9 Cross drainage NO 35 23,536,519.90 -

Investment cost 2,897,710,460


including VAT

10 Operation &maintenance 560,272,317.4


15year

11 Cost of redesign NO 1 7,130,000


including VAT

Total cost 3,465,112,777

Source: Upper Arjo-Dhidhessa BOQ technical report by OWWDSE, 2014 &calculation

In the water abstraction system of lower Arjo-Dhidhessa extension canal by redesigning of


Upper Arjo-Dhidhessa capacity of canal and related structures increases in order to
accommodate both the upstream 17.9m3/sec and lower Arjo left side 11,326..70ha supply of a
discharge of 23 m3/sec. Due to this reason the upper stretch of 104km canal and related
structures are increasing with cost of Eth birr 1,489,122,618.00 comparing to when it was only
designed for 17.9 m3/sec.

Cost of the extension of canal and related structures after the end of the Upper Arjo-Dhidhessa
canal of 89.6 km for a discharge of 23 m3/sec and the detail cost is described in the following
table 6

Since the length of lower Arjo-dhidhessa canal is 89.6 km which is lower than 104 km of Upper
Arjo project but its discharge is increasing to 23 m3/sec than17.9m3/sec from which is larger
than the Upper Arjo-Dhidhessa canal capacity by 1.45 times and the dimension of the canals and

February,2017 OWWDSE Page 35


Water Abstractions Options MWI&E

related structures increased by 1.15 times the Upper Arjo-Dhidhessa. The number and types of
structures can be easily determined from the system layout of prepared topo map.

Table : cost of extension canal after the end of upper arjo canal including structures

NO Type of irrigation Unit QTY Estimated cost Remark


structures
(birr)

1 Main canal km 89.6 611,090,326


excavation& filling

2 Escape NO 3 3,007,428.31 -

3 Head regulators NO 5 5,509,008.16 -

4 Inverted siphon NO 10 134,421,183.76 -

5 Foot bridge NO 7 5,411,038.75 -

7 Off take NO 31 6,477,946.89 -

8 Cross drainage NO 40 122,039,189 -

Investment cost 1,021,149,539


including VAT

10 Operation 197,439,263.4
&maintenance 15 years

Total cost 1,218,588,802.0

Hence, if we use to extend the Upper Arjo-Dhidhessa canal the total investment cost required is
birr (3,465,112,777+1,218,588,802) = 4,683,701,579) by considering the sugar development
project cost previous estimation 1,975,990,159.00 which had already separate budget by sugar
corporation and it needs additional extra cost for lower phase IIA of water abstraction system

February,2017 OWWDSE Page 36


Water Abstractions Options MWI&E

birr 2,707,711,420. This means due to extension the total cost required for phase IIA alone
considering sugar development cost deduction it will requir considering operational and
maintenance cost Eth birr 2,707,711,420.

3.2 Extension Of Upper Arjo-Dhidhessa from the End of Canal


At the end of Upper Arjo-Dhidhessa command area extension of canal is possible directly to
irrigate the downstream of Chewaka area or Phase IIA without redesigning and modification of
the Upper Arjo-Dhidhessa canal and its canal structure. At the end of Upper Arjo-Dhidhessa the
canal discharge capacity was designed for a discharge of 8.9 m3/sec, but the discharge of peak
requirement of Chewaka area or phase IIA project left side is estimated 23 m3/sec, which is 2.6
times greater capacity required. Another reason also the cropping calendar time for Upper Arjo-
Dhidhessa project and the peak requirement of water is almost the same as with phase IIA
project. Had it been the cropping calendar and the peak requirement demand is at different time
in the two projects it is possible to use the end discharge of 8.9m3/sec capacity dimensions
directly to Chwaka command area, even if the discharge is lower than the required one which is
enough for some plot of the area. In general it is impossible to use directly without redesigning
and modification of canal capacity and related canal structure due to the above reasons.
Therefore, this option is totally not working and rejecting from the options.

3.3 Constructing Separate Main Canal at the Dam Outlet


At the Upper Arjo- Dhidhessa Dam outlet of the left side the discharge was designed 56m3.
/sec and the maximum peak design discharge at the beginning of left side main canal is
17.9m3/sec. The water discharge left from the Upper Arjo-Dhidhessa project is estimated about
38.1m3/sec. This is more than the required downstream of phase IIA of 23 m3/sec.

Considering the Upper Arjo-Dhidhessa project canal crossing drainage, the catchment
characteristic, flood magnitude, the soil, all the geotechnical material are similar to all the layout
of Upper Arjo-Dhidhessa. The layout of the canal for phase IIA is in the same pattern for upper
Arjo-Dhidhessa.

All the above Upper Arjo-dhidhessa canal length of 104.4 km, concrete lining of 25 km length,
with different appurtenant structures of inverted siphons, flumes, cross drainage ,super passage
and escape except head , and cross regulators structures will be required on the same of the

February,2017 OWWDSE Page 37


Water Abstractions Options MWI&E

above stretch of length of the canal. The canal also crosses the Upper Arjo-Dhidhessa command
area, because of the command area extends above the gravity canal to the left side due to the
layout of command area included lifted and sprinkler or pressurized system of irrigation to the
left side.

In order to irrigate the whole phase IIA project command area, after 104.4 km canal length, it
required an estimated length of additional 86.6 km of canal with all canal structures. The
discharge required for Lower Arjo Dhidhessa Phase IIA project is 23 m3/sec. The water
abstraction option from the dam outlet as the required discharge is increased from upper Arjo-
Dhidhessa command area with 1.45 times and the capacity of related dimension also will be
increased by 1.15 times. The number and types of structures can be known from topo map both
upper Arjo and lower Arjo project. The cost of structures also estimated based on this amount in
the following table 7.

If we need this option of canal from outlet of the dam we will not have any problem of discharge
for the downstream but we need the total cost including 15 years operation and maintenance Eth
birr 3,700,031,945.00

The main advantage of this option is, it will not have a shortage of water as the required
discharge is greater than the available one and irrigation system also possible with gravity
system without any electric or other power requirement.

February,2017 OWWDSE Page 38


Water Abstractions Options MWI&E

Table : Cost of canal and related structures for the canal option from the dam outlet

NO Type of irrigation structures Unit QTY Estimated cost Remark

(birr)

1 Main canal excavation& km 193.6 1,320,391,597


filling

2 Main canal lined km 25 480,834,004.31

3 off take NO 31 6,477,946.88 -

4 Inverted siphon NO 13 350,754,015.7 -

5 Flume NO 17 358,502,699 -

6 Super passage NO 7 20,095,549 -

7 Outlet rejection/escape NO 3 3,007,428.31 -

8 Cross drainage NO 75 156,060,344.25 -

9 Investment cost+VAT 3,100,542,122

10 Operation maintenance for 599,489,819.30


15 years

11 Total Cost 3,700,031,941

Source: Upper Arjo-Dhidhessa Detail BOQ preparation, OWWDSE, 2014 And Detail system
layout of Phase IIA

3.4. Water Abstraction System by Diversion Weir and Canals


This alternative of water abstraction is diverting water from the same Dhidhessa River at
appropriate location to command the downstream phase IIA project by a diversion weir or any
appropriate head work structure.

February,2017 OWWDSE Page 39


Water Abstractions Options MWI&E

The Weir site selection was conducted based on natural physical flowing character of the
Dhidhessa River, geological condition, and the availability head sufficient enough to irrigate the
proposed command area. After delineating the command area by EMA topo prepared contour
map to find possible options weir site and on site visiting along the river course were also
conducted.

3.4.1. Possible Weir Site Options for the Proposed Command Area
Along the river course of Dhidhessa River based on the command head, river flow stream, and
other geotechnical characteristic of the bed condition the following two options were evaluated
for determination of the appropriate weir location.

3.4.1.1. On the river course between Ephrem Hotel and the bridge on the road Nekemte via
Arjo to Bedele crossing on Didessa River
Ephrem Hotel is a well known Hotel located at coordinate 187292E and 999316N just at the
crossing of Dhidhessa river and Nekemte Gimbi Road with elevation of 1135m amsl and the
bridge on the road Nekemte via Arjo to Bedele on Dhidhessa river located at coordinate
215361E and 961658N with elevation 1275 m amsl

At 4.3 km downstream of the bridge on the road Nekemte via Arjo to Bedele on Dhidhessa
River, diverting water from Dhidhessa River at a location of 214368.8E and 965596N with
elevation of river bed 1265m amsl was selected. The selected weir site is located at 45 km far
upstream from the command area. The length of weir crest depends on physical feature of this
selected weir site and it is around 100-150 m wide. In this case diversion is possible to irrigate
net are 3957.9 ha with gravity canal system the rest 7368.83 ha can be irrigated by lifted pump
system.

3.4.1.2. On the river course above the bridge on the road Nekemte via Arjo to Bedele on
crossing Dhidhessa River
Diverting water from Dhidhessa River site at location of 221751.8E and 953403.39N with
river bed elevation of 1290 m amsl, which has a river width of 100-150 m at distance 8km
upstream from bridge. And it is located 48 km far from command area, which, it seems ideal site
for weir location. In this case canal alignment crosses the existing sugarcane irrigation farm
structures, it also cross the main asphalt road, on top of that the diversion weir constructed also
has to serves both phase IIA and Phase IIB or the left and right side command area but the right

February,2017 OWWDSE Page 40


Water Abstractions Options MWI&E

side above the bridge has sugar cane factory infrastructure. In this weir location canals also
irrigate the command area partially by gravity and partially by pumps.

Table : Weir site locations options

No Options Location of weir River bed Weir crust Command area


Elevation(M) length (m)
(Ha) net

Easting Northing Gravity Lifted

1 Option I 214383.6 965614.1 1275 100-150 3964.25 7368.83

2 Option II 221790.8 953496.4 1290 100-150 7368.83 3957.9

Therefore, based on the above different options of diversion weir site selections, option I is better
than option II due to various reasons, as option II is located above the asphalt road and it crosses
many infrastructures of Sugar cane factory and farms to the right side, even though it has better
gravity irrigated area than lifted canal system.

February,2017 OWWDSE Page 41


Water Abstractions Options MWI&E

Figure : Command area of phase IIA and weir option

Hence, in lower Arjo-Dhidhessa phase IIA project the water abstraction system by diversion weir
of option has left main canal, gravity and lifted main canals including the pump system. Under
the gravity and lifted blocks from the system layout it has 3957.9 and 7368.83 Ha net irrigable
area respectively. The left main canal beginning from the diversion weir upto the junction of
lifted and gravity system has 46.6 km and it has two off takes before the junction point.

February,2017 OWWDSE Page 42


Water Abstractions Options MWI&E

Table : Discharge required for LMC, LGC , and LLGC

NO Name of main Area under Area Water duty Discharge Remark


canal Gravity block under required in required
(Ha) Lifted lit/sec M3/sec
block
(Ha)
1 LGC(Left Gravity 3957.9 - 2.1/lit/sec/ha 8.312
Canal) for 12 hours
Sub total 8.312
2 LLGC (Left lifted 7368.86 - -
gravity canal)
2.1 LLGC 3692 - 1.05/lit/sec/ha 3.88 Due to
for 24 hours night
storage
2.2 LLGC 3676.83 - 2.1 7.721
Subtotal LLGC 11.6
Add 5.25% for 0.66
future expansion
Total of LLGC 12.26
3 Total of LG C and 20.57
LLC(LMC)
3.1 Add for water 2.43
supply and other
use
Total LMC 23

Based on the above table 9 calculation the water for the left main canal (LMC) supplying
both gravity and lifted canal by the addition of future water supply and expansion of the area of
system of the canal and it has a discharge capacity of 23 m3/sec.On this left main canal from
system layout of topo map surveyed it has different structures such as 4 inverted siphons, 60

February,2017 OWWDSE Page 43


Water Abstractions Options MWI&E

drainage crossing aqueducts, 7 flume structures, 2 escapes, and 1 regulator.The unit rate of cost
estimation was done based on lower Arjo-Dhidhessa cost estimation of the current work. The
dimension of the canal also estimated based on the discharge; see the detail in the following
table10.

Table : Cost of Left main canal and related structure

NO Type of irrigation structures Unit QTY Estimated cost Remark

(birr)

1 Main canal excavation km 46.67 402,649,332.28

And filling

2 Inverted siphon NO 4 30,112,442.45

3 Flume NO 7 53,880,176.81

4 Regulator NO 1 520,088.60 -

5 Outlet rejection/escape NO 2 5,070,261. -

6 Cross drainage NO 60 122,039,189.43 -

7 Off take structures NO 2 101,818.60

8 Foot bridge NO 6 6,284,174.31

9 Investment cost with VAT 713,756,106.

10 Operation &maintenance cost 138,004,743.10


15 years

11 Total cost 851,760,849.10

Source: Lower arjo Detail Cost estimation preparation, OWWDSE, 2016 And system layout

February,2017 OWWDSE Page 44


Water Abstractions Options MWI&E

After the end of Left main canal left gravity canal system has 84.56 km length with a discharge
of 8.4 m3/sec. The gravity canal has from topo map of system layout it has 12 drop structures; 32
cross drainage structures, 70 off takes. The dimension of the canal also estimated from the
discharge requirement and the required cost of the canal water abstraction system is estimated
using the unit cost prepared. See the detail of structures and cost estimation in the table 11
below.

Table : Cost of left Gravity canal and related structures

NO Type of irrigation structures Unit QTY Estimated cost Remark

(birr)

1 Main canal excavation km 84.56 151,813,213.34

And filling

2 Drop structures NO 12 721,629.09 -

3 Off take structures NO 64 6,738,140.46 -

4 Cross drainage NO 35 71,189,527.19 -

5 Escape NO 2 1,821,680.90

6 Cross regulator NO 7 4,530,719.29

7 Foot bridge NO 7 2,523,594.92

8 Total investment cost including 275,239,281


VAT

9 Operation & maintenance cost 15 53,217,514.98


year

10 Total cost 328,456,795.9

February,2017 OWWDSE Page 45


Water Abstractions Options MWI&E

Source: Lower Arjo-Dhidhessa Detail Cost estimation preparation, OWWDSE, 2016 And
Detail system layout

Again the diversion system option has left lifted gravity canal which has 57.25 km length with a
discharge of 12.26 m3/sec. The left lifted gravity canal has from system layout 35 cross
drainage structures, 31 off takes, 2 escapes, 5 cross regulators, 5 foot bridges . See the detail of
structures and cost estimation in the table 12 below.

Table : Cost of left lifted gravity canal and related structures

NO Type of irrigation structures Unit QTY Estimated cost Remark

(birr)

1 Main canal excavationAnd filling km 57.25 260,304,473.12

2 Off take structures NO 31 4,318,631.26

3 Cross drainage NO 33 67,121,554.206

3 Escape NO 3 3,157,800.8

4 Head Regulators NO 5 3,672,677.72

5 Inverted siphon NO 8 71,691,298.01

6 Foot bridge NO 5 2,576,685.13

7 Inlet and outlet pumping structure LSM 12,094,143.31

8 Pumping house LSM 31,667,531

9 Investment cost including VAT 523,769,738.60

10 Operation &maintenance cost 15 years 101,270,8789

11 Total Cost 625,040,617.60

Source: Lower Arjo-dhihessa Detail cost estimation preparation, OWWDSE, 2016 And Detail
system layout

February,2017 OWWDSE Page 46


Water Abstractions Options MWI&E

The left lifted gravity canal system has other additional cost except civil work, like electrical
energy, transformer and substation, pumping system, pipes and related accessories cost and
others. Since there is a difference between the gravity system point at (X=192842.762,
Y=989310.97) and z=1249 m and lifted canal system beginning point (X= 192396.13,
Y=988832.88 and Z= 1314) and it has about 65m height elevation difference with horizontal
length of 655-670 m. In order to deliver water from the gravity system to lifted canal system
pumping is required. Therefore, for this it needs 15.748 MW electric power, 28 numbers of
pumps with stand by, pipes, transformer and substation, and other accessories are considered. On
the left side for the upper blocks of lifted system of 1104.58 ha it needs 982.5KW and 9 pump
numbers including the emergency. The left lifted gravity canal system will be used pumping
system based on monthly water demand as per the agronomy recommendation and the power
required and the cost of electricity has been estimated in table 47.

On the top of that if the irrigation is used electric system it is important to consider the future
cost of electric charge to decide the best alternatives, see the detail of table13 below.

Table : cost of lifted canal pumping system and accessories

NO Type of irrigation structures Unit QTY Estimated cost Remark

(birr)

1 Supply Pump with stand by No 28 130,394,880 With 560 lit/sec

2 Supply of pipes LSM 40,200,000

3 Supply of valve & fittings LSM 4,020,000

4 Supply of crane LSM 180,000

5 Transport of pumps &fittings, LSM 26,219,233


pipes, crane

6 Transformer and NO 1 16,911,626

February,2017 OWWDSE Page 47


Water Abstractions Options MWI&E

Substation

7 Installation LSM 8,739,744

8 Investment cost including VAT LSM 260,665,307.45

9 Operation &maintenance 15 LSM 212,910,646.2


years+ VAT

10 Running cost for 15 yearElectric KW 365,022,264.75


power for 15748kw+VAT

11 Total cost 838,598,218.40

Source: Lower arjo Detail Electro mechanical cost estimation preparation, OWWDSE, 2016

Table : Cost of left upper canal systemand related acceries for LLUB1

NO Type of irrigation structures Unit QTY Estimated cost Remark

(birr)

1 Supply Pump with stand by No 5 5,280,000 With 160 lit/sec

2 Supply of pipes LSM 7,180,000

3 Supply of valve & fittings LSM 711,000

4 Supply of crane LSM 72,650

5 Transport of pumps &fittings, LSM 1,976,045


pipes, crane

6 Transformer and NO 1 703,954

Substation

7 Installation LSM 658,682

February,2017 OWWDSE Page 48


Water Abstractions Options MWI&E

8 Investment cost LSM 16,582,331

9 VAT 2,487,349.65

10 Total investement cost 19,069,680.65

11 Operation &maintenance 15 LSM 18,270,510


years+ VAT

12 Running cost for 15 yearElectric KW 20,946,933.75


power for 577kw+VAT

13 Total cost 58,287,124.40

Table :Cost of left lifted upper pumping and related accesserries for LLUB2 A,B

NO Type of irrigation structures Unit QTY Estimated cost Remark

(birr)

1 Supply Pump with stand by No 4 2,904,000 With 160 lit/sec

2 Supply of pipes LSM 5,718,000

3 Supply of valve & fittings LSM 571,800

4 Supply of crane LSM 117,000

5 Transport of pumps &fittings, LSM 1,396,620


pipes, crane

6 Transformer and NO 2 495,911

Substation

7 Installation LSM 465,540

February,2017 OWWDSE Page 49


Water Abstractions Options MWI&E

8 Investment cost LSM 11,668,871.00

9 VAT 1,750,330.65

10 Total investement cost 13,419,201.65

11 Operation &maintenance 15 LSM 12,913,160.25


years+ VAT

12 Running cost for 15 year Electric KW 14,588,695.875


power for 406.5kw+VAT

13 Total cost 40,921,057.78

Table :Cost of left lifted upper canal pumping system and related accesseries for LLUB2C,D

NO Type of irrigation structures Unit QTY Estimated cost Remark

(birr)

1 Supply Pump with stand by No 5 7,452,000 With 160 lit/sec

2 Supply of pipes LSM 15,894,000

3 Supply of valve & fittings LSM 1,589,400

4 Supply of crane LSM 160,200

5 Transport of pumps &fittings, LSM 3,284,620


pipes, crane

6 Transformer and NO 1 702,710

Substation

7 Installation LSM 1,094,880

February,2017 OWWDSE Page 50


Water Abstractions Options MWI&E

8 Investment cost LSM 30,177,810

9 VAT 4,526,671.50

10 Total investement cost 34,704,481.50

11 Operation &maintenance 15 LSM 30,369,780.75


years+ VAT

12 Running cost for 15 year Electric KW 20,525,067.75


power for 576kw+VAT

13 Total cost 85,599,330

In the above upper lifted block of 1104.5 ha it required tottaly one pump house estimated about
5,000,000 birr is required. Therfore the total cost required for upper block is birr 189,807,512.18

In the water abstraction system of using diversion weir system for using both gravity and lifted
system the cost of diversion weir also considered.

In this case, the diversion weir serves for both the right and left command area of phase IIA and
phase IIB project so that, the cost will share into two portions of phase IIA and phase IIB
projects. See the following detail cost break down of diversion weir in table14

Hence based on table 14 cost estimation the breakdown the total cost for the diversion weir
including operation and maintenance cost of 15 years is Eth birr 396,610,923.46. Therefore, the
total cost for phase IIA share will be Eth birr 198,305,461.73

February,2017 OWWDSE Page 51


Water Abstractions Options MWI&E

Table : Cost of diversion weir and appurtenant structures

NO Description Amount (birr) Remark

1 General item and mobilization 1,126,200

2 Weir body ,apron, cut off 20,683,363.30

3 Under sluice part of left and right side 26,488,319.35

4 Under sluce gates work left and right 3,305,000

5 Divide Wall 10,868,821.29

6 Wing wall 18,161,717.90

7 Guide bund and marginal bund 17,474,842.23

8 Expansion joint 1,069,113.88

9 Right and left Head regulator 12,851,824.07

10 Right and left Barrel construction 14,267,130.76

11 Bridge work 2,627,798.11

12 Protection work 1,297,107.90

13 Temporery cofer dam work 26,471,430.00

February,2017 OWWDSE Page 52


Water Abstractions Options MWI&E

NO Description Amount (birr) Remark

14 Right and left settling basin 71,876,832.58

15 Ancillary building 2,118,835.67

16 Sub total 230,688,337.04

17 Supervision and contingency (15%) 34,603,250.56

18 Total investment cost 265,291,587.60

19 Add 15% VAT 39,793,738.14

20 Total investement cost Including VAT 305,085,325.74

21 Operation & maintenance cost 15 years 91,525,597.72 2% per annual

22 Total cost 396,610,923.46

Source: Lower Arjo -Dhidhessa , Head work lay out design, OWWDSE, 2016

Therefore, the total cost of water abstraction system with diversion weir and using both gravity
and lifted canal system is summarized as the following table15. It includes left main canal, left
gravity canal, left lifted gravity canal, electro mechanical cost, and diversion weir cost.

February,2017 OWWDSE Page 53


Water Abstractions Options MWI&E

Table : Cost of total water abstraction system by diversion weir and canals

NO Description Unit Cost including 15 years Remark


operation& maintenance

1 Left Main canal 46.6km Birr 851,760,849.10

2 Left Gravity canal 86km Birr 328,456,795.90

3 Left Lifted Gravity canal Birr 625,040,617.20


system 57.25km

4 Electro mechanical cost of Birr 838,598,218.40


pumping system for lifted
including 15 years
running& operation and
maintenance

5 Electro mechanical cost of birr 189,807,512.18


pumping system for upper
lifted block including 15
years running , opertain and
maintenance cost

5 Diversion weir cost Birr 198,305,461.73 50% allocated to


phase IIA and
50% to phase IIB

7 Total cost birr 3,031,969,454.51

3.5 Diverting Water by Pumping System from Dhidhessa River.


In the water abstraction system by pump option from Dhidhessa river near the command area
different pump site location have been analysed but the best and shortest distance is found at a
point X= 196813.272 and y= 991142.45and z= 1210 using main pipe line for a length of 767 m,

February,2017 OWWDSE Page 54


Water Abstractions Options MWI&E

which is far from Dhidhessa River and after that lifted canal system can be used to get the
command area at a point of X= 196148.87 and y= 990758.72 and z= 1320m. The height
difference between the two points is 110m. In the following table16 shows all related cost
breakdown with a pump system. The discharge required to supply the command area is the same
as the above left main canal estimated 23 m3/sec. It is 2.13 times the left lifted gravity canal then
the dimension and the cost is increasing by 1.5 times left lifted gravity canal and structure.

The main canal length of pumping system also the same as left lifted gravity canal length with
some additional stretch length and estimated 64.3 km. The length between the pump stations and
where the lifted system of canal started is estimated 7 km. The discharge of the canal is the same
as left main canal estimated 23 m3/sec. The head required is 120 m. Therefore, the detail of the
cost for both electro-mechanical and civil work of the canal system is as the following. The
electricity cost for running the power of 58.120 MW for the pumping system which was
calculated based on the monthly water demand in table 46 as per the agronomy amount of water
required recommendation.

Figure : Pump option at near command area from Dhidhessa River

February,2017 OWWDSE Page 55


Water Abstractions Options MWI&E

Table : cost of water abstraction by pumping system of the electro-mechanical part

NO Type of irrigation structures Unit Estimated cost Remark

(birr)

1 Supply of pumps LSM 467,712,000 58 number of pumps

2 Supply of pipes LSM 80,400,000

3 Supply of valves & fittings NO 8,040,000

4 Supply of crane LSM 180,000

5 Transportation of pumps, pipes LSM 83,449,800

Valves,& crane

6 Installation of pumps, fittings pipes LSM 27,816,600

7 Supply of electric power substation LSM 70,906,445

8 Investment cost including VAT 849,280,571.80

9 15 years electric power supply 1,031,428,836

Running +VAT

10 15 years operation& maintenance 771,576,854.25


cost+VAT

11 total 2,652,286,262.05

Source: Lower arjo Detail Electro mechanical BOQ preparation, OWWDSE, 2016

February,2017 OWWDSE Page 56


Water Abstractions Options MWI&E

Table : Cost of water abstraction by pumping system of civil work

NO Type of irrigation structures Unit QTY Estimated cost Remark

(birr)

1 Main canal excavation KM 64.3 438,539,151.6

And filling

2 escape NO 2 3,007,428.31

3 Cross drainage NO 35 106,784,290.78

4 Off take NO 33 6,895,878

5 Head regulators NO 5 5,509,008.16

6 Inverted siphon NO 8 107,536,947

7 Pump house LSM 290,600,000

8 Investment cost including 1,102,703,609


VAT

9 Operational &maintenance 213,207,742.9

Running cost 15 years

10 Total Cost Birr 1,315,911,352

Therefore, based on the above detail calculation of water abstraction system with pumping
system considering both the electro mechanical , related canal, and structures cost considering
15 years operation and maintenance cost is estimated Eth birr 3,968,197,614.05

Based on the above different alternatives of water abstraction options by summarized the
different cost of expense estimated and evaluating others issues of merit and de-merits the best

February,2017 OWWDSE Page 57


Water Abstractions Options MWI&E

options will be determined to proceed the detail design. See the following summarized table18
and figure 6

cost in billion birr


4.5
3.968
4 3.7
3.5
3.032
3 2.707
2.5
2
1.5
1
0.5
0
extension upper arjo separate canal from diversion Puming system
dam weiir, gravity & lifted
canal

Figure : Water abstraction options with required cost.

February,2017 OWWDSE Page 58


Water Abstractions Options MWI&E

Table : Summary of options of water abstraction system for phase IIA

No Method of water Advantage Disadvantage Total COST


abstraction including 15 years
operation &
maintenance
estimated (birr)

1 Extension of left  No Additional cost for weir  Need revision of upper Arjo and 2,707,711,420.0
side of main canal and dam construction is left side of main canal capacity
from the upper required including structures.
Arjo- Dhidhessa  It has more head than the other  Total left main canal is very
project by option long beginning from head work
redesigning upper  The canal is far from Dhidhisa upto end of command area is
Arjo Canal river gorge so that no flood 191KM
problem from Dhidhisa river  Management is complicated as
 There is 38.1m3/sec no it is owned by sugar corporation
shortage of water. & community

February,2017 OWWDSE Page 59


Water Abstractions Options MWI&E

2 Constructing  No additional cost of dam and  The main canal crosses the 3,700,031,945
separate canal weir required upper Arjo lifted, gravity, and
from the dam  No shortage of water as (56- pressurised irrigation system
outlet 17.9)= 38.1m3/sec from the  It is very long canal more than
dam outlet extension
 It has better head , which no  Idle canal is very long which is
pumping and electric system more than 104km and
required gravity system is conveyance efficiency is low
possible to the whole
command area
 No revision and redesign of the
upper Arjo project required.

February,2017 OWWDSE Page 60


Water Abstractions Options MWI&E

No Method of water Advantage Disadvantage COST estimated (birr)


abstraction

3 Water  Length of canal is short  Diversion weir cost is required 3,031,969,454.51


abstraction  No shortage of water even  Pumping and electrical power
option using possible to use wama river in are required for about 7368.83ha
diversion weir the addition of Dhidhessa  Future operation system and
and canals  Still possible to use gravity power stability will be
system of 3957.9Ha complicated to the farmers.
 The diversion weir also
possible to use for the right
side of phase IIB
 Management is separate
between sugar corporation and
community no complication
 Redesign of upper arjo project
is not necessary
4 Diverting water  The length of the canal is short  The whole system is required 3,968,179,614.05
by pumping  No diversion weir cost pumping and it needs electric
system from  management is separate power
Dedesa river between sugar corporation and  Future operation system and
near the community power stability will be more

February,2017 OWWDSE Page 61


Water Abstractions Options MWI&E

command area  redesign of upper Arjo not complicated to the farmer


required
 No shortage of water possible
to use wama river

February,2017 OWWDSE Page 62


Water Abstractions Options MWI&E

3.6. Recommendation on Water Abstraction Options of Phase IIA


By evaluating different advantages and disadvantages of the above factors, like the future
management system, water availability , size of irrigable command area, requirement of redesign
,future operation, energy requirement and the least total cost required for investment and
operation and maintenance and running cost of infrastructures of the above water abstraction
options, constructing diversion weir and using both gravity and lifted system for phase IIA
project was selected as the best water abstraction system.

Even if the water abstraction system of extension of canal from the upper Arjo-Dhidhessa by
redesigning has shown less cost with Eth birr 324,258,034.53 than the selected option of
diversion weir , but , due to the fact that future management of the irrigation scheme is
difficult as the Upper Arjo-Dhidhessa run by sugar corporation and lower Arjo-dhidhessa
phase IIA project is run by the community. Additionaly the upper Arjo Dhidhessa main canal
construction was already started as per the previous design, hence the diversion weir option is
more advantageous than the extension option.

Therefore, the detail design of irrigation and drainage system for phase IIA project in the next
section will be carried out on the water abstraction system of constructing diversion weir and
using both gravity and lifted canal conveyance system.

February,2017 OWWDSE Page 63


Surveying Work MWI&E

4. SURVEYING WORK
As per our TOR topographic survey of the command area, head work site and main canal route
was done by the establishment of DGPS Control Points so that detailed topographic survey of the whole
command area data was collected.

LowerArjo- Dhidhessa Irrigation & drainage project is continuation of project from upper Arjo
Sugarcane irrigation project which was designed to be constructed across Dhidhessa River for
the development of 32,000 ha irrigation area for sugarcane and community purpose.The BM
which was adopted for the topographic survey were those established earlier in the upper Arjo
project area located at:- GPS-10, E = 540121.403, N = 917128.198 and GPS-10A=
E=540418.749, N=916990.399 are the main control points of the project..

Surveying was done using conventional ground survey methods and modern surveying
equipments including Total Stations, static Global Positioning System (GRX1 DGPS) and
Leveling instrument, to establish a series of ground control stations (reference beacons and
benchmarks) and to produce a Digital Terrain Model (DTM) of the project alignment. The work
was performed with: -

 Establishment of geodetic control points using Static Global Positioning System (GPS)
 Setting up of permanent beacons to serve as a reference system during construction
 Development of control traverse-line and geometric level-line.
 Detailed field survey using SOKIA Total Stations and digital Levels.

4.1 Methodology of Surveying


The work methodology was included the following tasks:
 Establishment of GPS Control Stations
 Bench Marks Set up;
 Control Traverse-line;
 Geometric Level-line;
 Detailed Field Survey
 Data Processing and CAD;
 Mapping as per the TOR or any other scale agreed with client;
 Field Verification;

February,2017 OWWDSE Page 64


Surveying Work MWI&E

 Diagrams and Monographs;


 Delivery and Report.
The co-ordinates of the survey points were tied to the Local Survey Grid by a traverse and all
levels are related to existing Local Benchmarks. The reliability of the Benchmarks is confirmed
in the field before they were used.
All benchmarks were referenced in the permanent posts and shown on the plans and profile
drawings. Lists of benchmarks are incorporated in this report on a separate sheet accompanied by
a photo and their descriptions.

4.1.1. Establishing of GPS Control Stations


In establishing GPS the following methods were used before taking detail data collection to prepare topo
data.

4.1.1.1. Available Map and Geodetic Data of the Project


Topographic Mapping 1:50,000 & 1:250,000 scales for the project area were collected.

The Co-ordinates System used for the project was the Ethiopian National Grid (Clarke 1880
Spheroid, U.T.M. Grid, Adindan Datum) and in order to tie the GPS network of the project to the
National Grid system.
GPS control points has been established by transferring from the given bench mark which are
listed on the TOR using static GPS.

4.1.1.2. Planning of GPS Observation


Prior to field GPS observation, selection of appropriate GPS observation positions that are as
much as possible free from any nearby obstructions which affects the quality of observation was
made. Timing of each GPS observation was carefully selected prior to commencement of
observation in order to acquire the required precision of field GPS observations, which obviously
depends on the availability of sufficient satellites at a particulate time in a day.

4.1.1.3. GPS Geodetic Control


GPS Control points were established, using Global Positioning System (GPS) receiver working
in a static mode. These GPS control points were placed in highly accessible site and protected
against impact to guaranty their stability & integrity.
The GPS observation was carried out with a set of three (3) units of GRX-1 GPS system device
using static mode with at least 6 satellites tracking per site, in order to determine 3-D WGS84 co-

February,2017 OWWDSE Page 65


Surveying Work MWI&E

ordinates to a desired accuracy. The base line measurement was processed and adjusted with an
observation of minimum of 30 min to 45 min.
The GPS network points were linked to the given two BMs and checking with National Grid
System and the WGS84 coordinates shall be converted in to UTM coordinates based on Clark
1880 (Modified) Spheroid Datum, Adinadan (3 oth Arc).
After having static GPS observation on the GPS primary control points for uniform time and
session, the data is downloaded, processed and adjusted using Spectrum Survey Office Software.
This process results each GPS bench marks to have a known coordinates which are tied to the
given BMs and National Grid system (NGS).
For determination of orthometric heights tied to the national grid system, direct levelling of
established points was conducted by automatic level instrument starting from the known
GPS_10A (1348.222m) to the other established GPS points and BMs
Clear and intelligible monograph of the vertex with a brief description of the location supported
with photographic evidence is attached in this report for further reference and restoration of the
same in the future as required.

4.1.2. Data Collection for Detail Surveying of Topographic Map Preparation


After determining horizontal control points and vertical control points for each bench mark the
next step was collecting topographic data to determine their coordinates (Easting, Northing &
Elevation) in reference with the pre-determined bench mark coordinates which were tied to NGS.
Data collection of the survey work was completed to 68 concrete BMs.

4.1.2.1. Traversing
Using the established GPS points, benchmarks were built at every inter-visible site and a traverse
was run from one GPS point and closed on the next GPS to be adjusted by the GPS Easting &
Northing value‟s in order to avoid propagation of cumulative errors.

4.1.2.2. Leveling of the control points


The ground survey data obtained using GPS station provides accurate data for the Easting &
Northing coordinates, whereas significant difference could be observed on the Elevation (Z) with
that obtained through direct levelling due to a mathematical model of the globe which is not
usually parallel with Gravimetric Geoids.
Hence, levelling work was undertaken by using automatic levelling instrument to determine the
elevation of each GPS points and bench marks to tie to the given BMs to a desired accuracy.

February,2017 OWWDSE Page 66


Surveying Work MWI&E

The process of levelling work involve taking back sights and fore sight on every bench marks
and turning points for a run and check back activities.After having the desired allowable range
for precision, each run and check back observations were adjusted and final vertical control
points which are tied with the given BMs were obtained.

4.1.3 Bench mark setup


Tied up with the GPS control points established in the boundary of command area and
measurement of inter visible control points and Bench Marks was conducted at 250m-1500m
intervals. The horizontal Angles were measured using SOKIA Total Station while the elevation
was measured using differential (direct) levelling.
With this regard, in number 260 Bench Marks has been established for the whole command area
and in order to avoid change of location of established points, it is placed by stone and concrete
monument.see the detail part of data collected at the end of the report at annex part.

4.2. Data Processing and CAD


Specific computer programs was used such as AutoCAD, Spectrum survey field, Terra-model,
and spectrum Solutions for transferring field data into computer, editing and processing of the
data. In addition to this, software modules that operate inside Auto CAD. Detail GPS data is
attached at the annex part. After data was processed 24,000ha of the command area topographic
data has been collected with all artificial and natural features and topo map was ready for design
and system layout.

February,2017 OWWDSE Page 67


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

5. DESIGN OF DIVERSION WEIR/HEADWORK AND


APPURTENANT STRUCTURES
A weir can be defined as a barrier with a crest to raise the water level in order to take it by
gravity to an area for irrigation development. A weir structure is generally constructed across the
river for:

 Diversion of water into the canals


 Raising of water level to feed canals
 Storing the excess flow received from upstream storage sites.
 Regulation of desired supplies
Headwork is defined as the work made from different construction material it can be earth,
masonry, concrete, reinforced concrete, gabion, wood, stone fill etc or the combination of these
materials going to be constructed at the head of the canal in order to divert the river water
towards the canal, so as to ensure a regulated continuous supply of silt free water with certain
minimum head into the canal known as diversion head work (Garg, 1965). ICID also defined
head work is a collection term for all weirs , diversion dam , head regulators, upstream and
downstream river training works and their related structures. These related structures required at
intake of main or principal canal to divert and control river flow and to regulate water supply
into intake canal.

5.1 Design Criteria for Diversion weir /headwork


Before designing of head work or diversion weir, setting design criteria is important for selection
of weir site and determination of weir body and appurtenant structure dimension.

5.1.1 Design Criteria for Selection of Diversion Weir Point.


The following criteria have been adhered to in selecting the diversion site.

 The diversion location is decided on considerations of suitability for weir proper, the
under sluices and the canal head regulators. An ideal location is that which satisfies the
requirements for all the three. For irrigation purposes, the head works are planned in such
a way that as much command area as possible command area can be irrigated by a
diversion structure of reasonable dimensions based on local site conditions.

February,2017 OWWDSE Page 68


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

 The combined cost of the construction of head works and the canal from the headwork to
the point where irrigation commences should be as small as is consistent with the
efficiency of the project. With regard to this point, all possible locations for diversion
have been studied starting from the nearest point to the command areas, and going
upstream until the requirement was met.
These studies have helped in establishing a firm knowledge on the topography and
geological situation of the lower valley of the Dhidheesa River.
 Serious consideration should be given to the impact of back water due to water surface
rising on the area upstream of the weirs.
 As far as possible, the river reach should, be straight so that velocities may be uniform
and the sectional area of the river fairly constant. The banks should preferably be high,
well defined and non erodible. These requirements will obviate oblique approach as well
as non uniform distribution of flow on to the weir. In the case of a meandering river, the
diversion structure should be located at the nodal point. The following are the main
features considered in the head work design
 The alignment of the diversion structure is required to be placed at right angle to the
direction of flow of water. This is a criterion which is adhered to because a skew weir has
tendency to produce current parallel to the axis of the weir which will cause disaster on
erodible foundation.
 A narrow, straight and well-defined river section with defined bank is ideal location for a
diversion structure. With regard to this criterion, the surveyed topography map has been
studied in detail and the best location has been selected for the axis.
 The water to be raised by the weir should be able to command the proposed irrigable area
without excessive canal excavation. In this regard the best possibility shall been given
attention to make the best use of the available situation.
 Availability of construction material near the proposed weir site
 Arrangement of cofferdams and diversion channel during construction
 .The under sluices should be located in the deep channel in order to ensure adequate
supply to the canal head at all times. When canals take off from both banks, a site with
deep channels on both the banks and low water in the central portion is the most suitable.

February,2017 OWWDSE Page 69


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

 While deciding on the choice of suitable site, due consideration has been given for easy
accessibility and economic transportation of materials to the site of work.

5.1.2. Criteria for Selection of type of Diversion Weir structures


A diversion Structure is required for diverting the water from the river into the Canal system.
This can be a Dam with storage reservoir, a Weir/Barrage type diversion structure or river intake
type of diversion structure.

The choice of a suitable type depends on various factors such as topographical condition of the
diversion site and command area, foundation and geological condition, hydrology,
morphological condition of the river etc.Broadly there are three types of head works as under:

a) Storage with a dam which may be an earthen or concrete/ masonry dam.


b) Weir type, which may again be a weir or a barrage, and
c) River intake type diversion structure.

5.1.3. Design criteria for Various Components of Diversion Weir Structures


A weir can be defined as a barrier with a crest to raise the water level in order to take it by
gravity to an area for irrigation development.

5.1.4. Methodology for Design of Diversion Weir Structures


The design of the diversion structure is carried out in two parts i.e., hydraulic design and
structural design. In the hydraulic design, overall dimensions and profiles of the main structure
and a few of the components are worked out, so that satisfactory hydraulic performance of the
structure can be ensured.

In the structural design, the various component of the diversion structure (Weir) shall be
designed. In both the cases, the diversion structure has to be properly designed for both the
surface and subsurface flow conditions.

The surface design includes the fixing up of waterway, top profile of various structures, energy
dissipation arrangements, protection works, scour depths, length & protection of divide walls,
levels and protection of guide bunds, afflux bunds etc. The sub-surface design will include
fixing of the depth and section of cut-offs, uplift pressure calculations, exit gradient etc.

The basic parameters which were considered and selected before taking up detailed hydraulic
designs were the following;

February,2017 OWWDSE Page 70


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

vii) Design flood discharge


viii) Afflux
ix) Pond level
x) Crest level and profiles
xi) Rating curve & downstream retrogression of water levels.
xii) Safety against Sub-surface Flow & Uplift

5.1.4.1 Design Flood Discharge


The occurrence of a certain peak flood of given return period during the life time of a project is a
probability of a given flood that is required to be safely discharge from the project structure.

For the purpose of design of weir other than its free board, a design flood of 100 years frequency
is considered. The 100 years return period flood has been worked out by various hydrological
methods free board is to be checked using flood of 1000 year frequency.

The length of the waterway is equal to the width of the weir from abutment to abutment and it is
based on capacity to pass the design flood discharge.

5.1.4.2. Afflux
The width of the weir is governed by the value of afflux (at the design flood) to be permitted and
the proposed crest levels. It is also important for the design of downstream cistern, flood
protection and river training works, upstream and downstream loose protections and upstream
and downstream cut-offs.

The proposed weir is to be located in the lower reaches of the Dhidheesa River, where afflux
generally limited to about not more than 1m. Due to the limitation for the fixation of pond level
at elevation of bed level is 1265.0m and the available river width at weir site, the afflux has been
estimated as 1m (for design flood) above the crest level of the proposed weir.

The effect of afflux is evaluated in terms of required protection works in order to arrive at
economical solutions.

5.1.4.3. Pond Level


The pond level is the level of water which is maintained, immediately upstream of the weir to
facilitate withdrawal into the canals for irrigation water withdrawal or for any other purpose. The
pond level, in the under-sluice pocket, upstream of the canal head regulators is generally
obtained by adding the working head to the designed full supply level in the canal. The working

February,2017 OWWDSE Page 71


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

head includes the head required for passing the design discharge into the canal and the head
losses in the regulator.

In this project, pond level is uniquely decided by taking the impact of allowable river width,
afflux and back water into consideration. Therefore, the possible supply levels of the main canals
will be accordingly decided and estimated.

5.1.4..4. Crest Levels and profile


The floor level of the scouring sluice should be at lowest river bed level 1262.00m with slight
adjustment as required. The crest level of the scouring sluice should be 0.3 meter higher than it.
The crest level of weirs will be decided by taking allowable river width, afflux and and the like
into consideration.
As the weir is low in height, the advantages of ogee-shape profile are pointless because of
sediment. For this reason, broad crest concrete weir type with 1:3 slope for downstream face, 1:1
for upstream face is adopted.

5.1.4.5. Rating Curve & Downstream Retrogression of water levels


A stage discharge graph is required to be developed for the site of the hydraulic structure for
proper design of the structure. Progressive retrogression or degradation of the downstream river
bed and levels as a result of construction of a weir causes lowering of the downstream river
stages which has to be suitably provided for in the design of downstream stilling basins. At the
design flood, the reduction of gauges due to retrogression may be considered, if required which
is normally vary from 0.3 to 0.5 m depending upon whether the river is shallow or confined
during floods.

In the present study, as it is expected that the river bed is having rocky profile (after removing
some overburden), there is no river bed retrogression expected and will not be considered for the
design.

5.1.4.6. Safety against subsurface flow and uplift


In the case of alluvium river bed, the safety against piping shall be attained by providing
sufficient flow length in order to provide safe hydraulic gradient. The following measures shall
be taken and the values given below for safe hydraulic gradient, can serve as a guide line.

 Control of subsurface flow shall be established by provision for uplift pressures and
adhering to acceptable limits of exit gradient.

February,2017 OWWDSE Page 72


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

 Provision of upstream and downstream sheet piles / cutoff walls for limiting exit gradient
 Undertaking cement grouting measures to control the passage of water below the
foundation level of the weir structure.
 Provision of upstream and downstream seepage protection works by way of inverted
filter and launching apron as found appropriate.
The exit gradient at the end of the Impervious Floor is determined using accepted procedures
which make use of equations and curves plotted for the purpose. The factors of safety for exit
gradient for the following types of soils shall be considered for reference:
 For Shingle : 4 to 5,
 For Coarse Sand : 5 to 6,
 For Fine Sand: 6 to 7.

The safety against uplift will require the balancing of the uplift pressure by the weight of the
floor with. The following equation shall serve as a guideline.

h
T
(G  1)

Where, h = specific balanced hea

G= floor thickness and G is the specific gravity of the concrete floor material

For the this Project diversion structure, which is expected to be founded over Rocky River bed
profile, the value of safe exit gradient will be considered as 1/5.

5.1.5. Hydraulic Design of Weir


Broad crest weir is calculated by the following formulae.

The flow state through weir is considered for modular and unmodular flow, respectively.

When Upstream head (total head over the crest) = H1 and downstream head (total head over the
crest) =H2, it is for modular flow if H2/H1<0.75 and for unmodular flow if H2/H1>0.75.

Following formulae can be applied according to cases.

For modular flow

Q1 = CLHe3/2 modular flow;

Q1 = calculated discharge (m3/s)

February,2017 OWWDSE Page 73


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

L= length of the weir (m)

He = total head over the crest (m)

C = coefficient of discharge 1.7

For non-modular flow

C1L 2 g  H 2 - h a 2   C2 DL 2 gH
2 3 3
Q2 
3  

Where;

Q2 = calculated discharge (m3/s)

L =effective length of the pass (m)

H = difference of u/s and d/s water level (m)

ha =approach velocity head (m)

D =Downstream head (m) 6.12m

C1 = coefficient of discharge 0.577

C2 = coefficient of discharge 0.8

5.1.6. Forces Acting on the Weir Structure


 Static Forces

 Water pressure on the upstream face


 Water pressure on the downstream face
 Weight of water on raised crest
 Weight of raised crest, concrete structure gate, deck, piers, road etc

 Dynamic Forces

 This force is exerted by surface flow on superstructure.


 Erosive forces on the upstream side and downstream side of the weir, either by hi
 Velocity of water or by impact of water flowing over the raised crest sill.
 Force of impact of floating materials on upstream face or piers

February,2017 OWWDSE Page 74


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

 Substructure

 This force is exerted by subsurface flow on the foundation.


 The transporting erosive forces due to flow in the subsoil under the raised crest floor.
 The upward static pressure on raised crest floor exerted by sub soil flow-uplift pressure.

5.1.7. Design Criteria for Superstructure


 No tension in the masonry or contact plane between the raised crest and the foundation.
 No overturning of structure, factor of safety not less than 1.5.
 No slide on the joints with foundation or any horizontal plane above the base. Sliding
factor shall be less than 0.65.
 Toe and heel pressure on the foundation should not exceed prescribed limits.
 Piers, abutments, divide wall and gates should be safe under worst combination of
pressures exerted by static and dynamic forces.

5.1.8. Design Criteria for Substructure (floor and foundation)


 The downstream horizontal floor should be provided at a level such that within the range
of discharges, the jump always remains on the slopping glacis for the case where a
stilling basin is to be provided.
 Where a flip –bucket type of energy dissipation is required the downstream rock property
shall be evaluated for taking appropriate construction measures.
 For the case where a sloping glacis shall be provided, the main disturbance of the
hydraulic jump normally dies out at a distance equal to five times the length of hydraulic
jump. The length of horizontal floor should be nearly 5*(D2-D1). Where, D2 and D1 are
the depth of water after and before the formation of hydraulic jump at high flood design
discharge or pond level flow, whichever is critical.

5.1.8..1. Thickness of floor on the sloping glacis and on the d/s cistern
 Uplift pressures shall be worked out at all points of the toe of the weir and in the cistern
in two conditions:
 Maximum pond level in upstream side and minimum flow in downstream side. In this
situation, the uplift pressures shall be worked out on all points of d/s slope of the ogee
profile and in the cistern.

February,2017 OWWDSE Page 75


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

 Net uplift pressures at locations of hydraulic jump at variable discharges at different


points.
 The floor thickness at any point shall be found out from the maximum of the two uplift
pressures worked out as above divided by the submerged unit weight of floor material.
The uplift pressure on the floor is recommended to be worked out using Khosla‟s theory
and it will be revised as per type and joints existing in the rocky foundation.

5.1.9. Depth of Vertical Cutoffs/ Sheet Piles.


The cut off is required for the following functions:-

 To reduce loss of stored water through foundation and abutments.

 To prevent sub-surface erosion by piping.


The upstream and downstream cutoffs should generally be provided to cater for to 1.25 R and
1.50 R, respectively where, R is the depth of scour below the respective high flood levels. The
concentration factor shall be taken into account in fixing depth of cutoffs. These should be
suitably extended into the banks on both sides up to at least twice their depth from top of the
floors.

River scour is likely to occur in erodible soils, such as clay, silt, sand and shingle. In non-
cohesive soils, the depth of scour may be calculated from the Lacey‟s formula which is as
follows.

R = 0.473 (Q/f) (1/3) when looseness factor is more than 1, or

R = 1.35 (q2/f) (1/3) when looseness factor is less than 1

Where,

R = depth of scour below the highest flood level in m;

Q = high flood discharge in the river in m3/s;

f = silt factor which may be calculated by knowing the average particle size m,in
mm, of the soil from the relationship:

f = 1.76 √m

q = intensity of flood discharge in m3/s per m width. (M3/s)

February,2017 OWWDSE Page 76


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

The type of cut off shall be decided on the basis of detailed geotechnical investigation. However,
exact depth of the cut off can be decided only after the detailed geotechnical investigation.

5.1.10. Floor Length and Thickness of U/S and D/S Floor


 length

1 1 d
 Find out the value of from the equation = GE *( )
    H
Where,
H = maximum static head

d = depth of downstream sheet pile (in m) and GE is safe exist gradient of the order of
1
(assuming rocky profile of the river bed).
4

1
Depth of downstream sheet pile (in m) and GE is safe exist gradient of the order of
4
(assuming rocky profile of the river bed).

1
 Find out the value of α from Khosla‟s exit gradient curves for
 
 Total impervious floor length (u/s & d/s) shall work out to b = α*d
 Subtract glacis length; cistern length from b = α*d. The balance length shall be
upstream floor length.
If the total floor length worked out from b = α*d is excessive, provide deeper cut off wall on the
downstream side and work out new length a fresh so that upstream concrete floor length is
reasonable.
 thickness
 The subsoil hydraulic gradient line is well below the water level i.e. all the unbalanced
head acting on U/S floor is counter balanced by the height of water. Thus from
theoretical consideration, no floor thickness is required on U/S. However, minimum
prescribed thickness of 1.0m provided in the U/S floor.

5.1.11. Type of the Weir


The weir shape shall be of glacis type which represents the under nappies of a jet flowing over a
broad crested weir. Recommendations of the US Bureau of Reclamation hydraulic laboratories
shall be followed.

5.1.12. Length and Thickness of Upstream and Downstream Loose Aprons


For the case of a pervious foundation which requires protective measures, the following is the criteria
that are required to be fulfilled:-

 Downstream Apron

February,2017 OWWDSE Page 77


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

Inverted Filter: Just after the end of concrete floor, graded inverted filter of
length 1.5 to 2.0 D shall be provided, where, D is the depth of scour below bed.
Depth of inverted filter shall be kept equal to the depth of launching apron. It
shall consist of 0.5 to 1.5m deep concrete blocks with open joints laid on 0.5 to
0.6m graded filter material. The opening in concrete blocks shall be filled with
fine gravel. The filter shall be designed by Terzaghi‟s criteria.

The graded inverted filter should roughly conform to the following design criteria
D15 of Filter D15 of Filter
≥4≥
D15 of Foundation D85 of Foundation
D15 of Filter D15 of Filter
≥4≥
D15 of Foundation D85 of Foundation
Launching Apron:Launching apron in a length of 1.5D m & having thickness as that of
inverted filter shall be provided beyond the end of inverted filter.

 Upstream Apron: Just after the end of upstream concrete floor of the weir, concrete
blocks having 0.5 to 1.5 m depth laid on 0.6 m packed stones up to D distance shall be
provided, where, D is the scour depth below the river bed level.

5.1.13. Freeboard
Freeboard is the vertical distance between the crest of the embankment (without camber) and the
pond level. The free board shall be checked for 1 in 1000 years return period flood at the site of
diversion structure.

5.1.14. Water ways of the Weir


In deep and confined rivers with stable banks, the overall waterway (between abutments
including thickness of piers) should be approximately equal to the actual width of the river at the
design flood.

The design flood (Q m3/sec ) of 1 in 100 years return period flood routed through weir is taken
for designing the weir and for obtaining the required water way for the proposed weir. The
Lacey‟s waterway is given by the formula (in m.) W = 4.83*Q^0.5

 In plains, where, silt factor is less than 1.0, the waterway is generally provided 1.0 to 1.2
times of Lacey‟s waterway and where, the silt factor is between 1.0 to1.5, the waterway
is generally provided 0.6 to 1.0 times of Lacey‟s waterway.

February,2017 OWWDSE Page 78


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

 It is desirable to provide shorter waterway, which reduces the chances of shoaling in


upstream & downstream side of the weir.
 In boulder reach of the river waterways ranging from 0.25 to 0.90 of Lacey‟s water way
is generally provided.

 But, as per site condition and the requirement for keeping the stage of the river at a
comparatively low level, the water way has been recommended to be kept about 378 m
width (looseness factor =1.00).

5.1.15. Under Sluice Ways


A diversion structure (weir) normally requires deep pockets of under sluices portions in front of
the head regulator of off taking canals and long divide walls to separate the remaining river bays
portion from the under sluices portion. The arrangement is aimed at keeping the approach
channel to the canal head regulator comparatively clear of the silt and to minimize the effect of
main river current on the flow conditions in the regulator.

The width of the under sluice portion was determined on the basis of the following
considerations:

 It should be capable of passing at least double the canal discharge to ensure good
scouring capacity.
 In general it should be capable of passing about 10 to 20 percent of the maximum flood
discharge at high floods. As supply volume is large in this project, the flood discharge of
under-sluice should be estimated accordingly estimated 50%.
 It should be wide enough to keep the approach velocities sufficiently lower than critical
velocities to ensure maximum settling of suspended silt load in the pocket.

5.1.16. Consideration for Width and Level of Crust and Upstream Floor
It would be desirable to keep the crest and upstream floor level in the pocket upstream of under
sluices at the normal low bed level of the deep current of the rivers, as far as practicable. In the
river bays portion, the upstream floor level should be fixed at the general river bed level at or
below the level of the crest.

February,2017 OWWDSE Page 79


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

For weirs, the head required to pass the design flood at the desired afflux directly determines the
crest level. The level of crest in this portion should be fixed by adjustment of the waterway. It
should, in any case, be kept higher than the under sluice crest level.

The under sluice crest level is kept as near to the bed level of deepest channel of river as far as
possible to facilitate de-silting in front of off take head works.

If crest levels are kept lower, this will permit higher discharges per meter and cause smaller
afflux. But, in that case the height of gates and u/s & d/s protection work will increase.

Thus on one hand we save on height of guide banks and marginal bunds but, on the other hand,
we spent more on gates & protections.

5.1.17. Application of Cement Grouting Technique


Because the weir height is considerable cement grouting technique is also foreseen either for
controlling flows below the structure or for strengthening any fractured subsurface foundation
layer. For the first case the preliminary assessment of the foundation layer is required by
performing water pressure tests to determine whether the loss of water is acceptable or not.

Concerning the bearing capacity of the subsurface layer, the need for any strengthening by
consolidation grouting shall be decided based on the findings of the geological and geotechnical
studies.

5.1.18. Foundation Treatment


Treatment of the foundation surface after attaining the excavated levels will follow. Methods of
treatment of fractured zones, seams and joints need the detailed procedures to be provided in the
geo-technical studies. Execution of the remedial measures shall require the follow up of an
experienced geotechnical engineer.

5.1.19. Wing walls and abutment


Wing walls and abutments of the weir structure shall be designed as retaining walls safe against
overturning, sliding & compression at critical sections. The inner side of these structures is
protected against erosion by providing appropriate cut offs in the same manner as upstream
downstream floors of the weir structure.

February,2017 OWWDSE Page 80


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

5.1.20. Divide Walls


Divide wall is normally provided up to the end of loose protection on downstream side in the
case of weirs on permeable foundation. However, in upstream side its length plays a very vital
role in controlling sediment entry into the off taking canals. In general, the distance between the
end point of divide wall on u/s side and intake end point of head regulators should be 1.5 times
of the difference between elevation of the bottom of channel for under sluice and design intake
level,

The top width is made 2 to 5.0 m depending on that whether, the fish ladder is incorporated
within the middle wall or not. It is aligned at right angle to the axis of weir, short of model study
which can result in curved alignment of the outer extremity for creating better flow conditions.
It is planned to be built in concrete and the top of divide wall shall be kept 1.00m higher than the
high flood level for Q100.

Divide walls beyond concrete floor shall be based on the top of closely spaced foundation wells.
In the case of permeable foundations, the nose and sides of divide wall shall be protected by
block protection and launching aprons as generally practiced for the case of concrete floors
ofweir on permeable foundations. The geological and geotechnical studies will be considered for
the detail design.

5.1.21. River Training Works


River training works for weirs are required to:

 prevent out flanking of the structure


 minimize cross flows through the weir, which may endanger the structure and protection
works
 prevent flooding of the riverine lands upstream of the weirs
 provide favorable curvature of flow at the head regulator from the point of sediment entry
into the canal, and
 Guide the river to flow axially through the weir over flow section.

A river generally flows in a wide alluvial belt and it becomes necessary to narrow down and
restrict its course through the weir constructed across it. The guide bunds are constructed to
arrest the meandering tendency, obliquity of flow and to maintain deep channels through the

February,2017 OWWDSE Page 81


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

under sluice bays adjacent to the canal off takes. Proper alignment of guide bunds is essential to
ensure satisfactory

5.1.22. Approach Embankments


While constructing barrage or weir, the natural water is restricted for economy as well as for
better flow conditions through the barrage or weir and the un bridged width is blocked by means
of embankments called approach embankments.

5.1.23. Design of Guide Banks


 Top Width
In order to permit the carriage of material and vehicles, the top width of the shank of
guide banks should be kept equal to 6 to 9 m at formation level. At the nose of the guide
bank, the width may be increased suitably to enable the vehicles to take turn and for
stacking stones.

 Free Board:
A free board of 1 m should be provided above the highest flood level for 1 in 500 floods
or above the affluxes water level in the rear portion of the guide bank, calculated after
adding velocity head to HFL, corresponding to 1 in 100 year flood at the upstream nose
of the guide bank, whichever is higher.

 Side Slopes
The side slopes of guide banks depend upon the nature of the river bed material of which
they are made of and the height. A slope of 2:1 may generally be found suitable.

 Size of Stone for Pitching


The size of stone required on the sloping surface to with stand erosive action of flow may
be worked out on the basis of the basis of velocity of flow. The minimum size of the
stone/boulder is 300 mm and no stone shall weigh less than 40 kg. If the required size
stones are not economically available, cement concrete blocks or smaller size stones in
Geo mesh boulder gabion may be used. On the rear side, turfing only may normally be
adequate.

February,2017 OWWDSE Page 82


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

 Thickness of Pitching:
The thickness of pitching should be kept equal to the size of stone but not less than 0.25
m. The thickness of pitching on the river side may be calculated by the formula.
t=0.06Q^1/2 where t is the thickness of stone pitching in meters and Q is the discharge in
cum/sec.

 Filters
o A graded filter, 20 to 30 cm in thickness, generally satisfying the criteria given
shall be provided.

 Launching Apron:
Whenever, a sloping face is protected by stone pitching against scour, the pitching is
extended beyond the toe of the bed called launching apron. The launching apron is
generally laid in a width equal to 1.5 times the depth of scour below the original bed.

Generally, a thickness of the launched apronshould be 1.9 t.

5.1.24. Planning of Layout of the Main Conveyance Systems (Canal Head


Works)
The basic functions of the canal head works are:-

 To regulates the supplies in the canal


 To controls the entry of sediment in the canal

5.1.24.1. Alignment of the off taking right and left canal Head regulators
The upstream abutment of the head regulator should be set back from the line at right angles to
the weir axis.

The head regulator is usually aligned at an angle of 900 to 1100 to the weir axis for minimizing
sediment entry into the canal. For the Low-arjodiversion weir the head regulator axis shall be
selected based on the surrounding topographical features.

5.1.24.2. Water Way off Head Regulators


 Keep waterway equal to the width of canal.
 In case when waterway works out to more than the width of canal, adjust crest level in such a way
that the water way becomes equal to the width of canal.
 In exceptional cases when waterway works out more than the width of canal flared out walls are
to the provided in downstream of regulator to join the canal width.

February,2017 OWWDSE Page 83


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

Waterway of canal head regulator shall be worked out with following formula in drowned condition.

Q=
2
3

C1L√2g H  ha   ha
3/ 2 3/ 2

+C2Ld√2g (H+ha)

Where: C1 andC2 are numerical coefficients having values 0.577 and 0.80
respectively

H= difference of u/s and d/s water level

ha= head due to velocity of approach

L= clear length of waterway

d= depth of downstream water level above the crest (sill)

5.1.25. Crust Level


In general the crest level of head regulator is kept at least 1.50 m above the crest level of under
sluice.

5.1.26. Approach Road and Bridges


The width of the approach road to the head work shall be 8 m (5.5 m clear road width with 1.25
m of shoulders on either side.

5.1.26.1. Bridge over the Weir


The bridge over the weir shall be designed operation and maintenance foot bridge with the
following dimensions:-

 Clear bridge width between curbs= 1.7 m


 Bridge shall be in R.C.C. to be supported on RCC beams resting on piers and
abutments in under sluice portions. Steel handrails shall be provided on both the sides
of the bridge
In weir portion the bridge of truss style of for increasing the span of bridge should be designed

5.1.27. Gate Operating Platforms

The gate operation platforms are planned to be adjacent but, separate from the bridge. A tentative
width is adopted to facilitate stop log placement and removal and gate operation space. Final
dimensions shall be adopted in consultation with the electro mechanical designer. The following
tentative dimensions shall serve as guide lines:

Accordingly the gate operation platforms shall be of 5.0 m width for all cases as specified
below:-

February,2017 OWWDSE Page 84


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

i. Right and left bank under sluice gate operation platform


ii. Right and left bank canal head regulating platform

5.1.28. Piers
Piers shall be constructed monolithic with the raft foundation. The width of pier shall be
determined by consideration of following forces:

(1) Weight of pier


(2) Weight of roadway with live load
(3) Horizontal force transmitted from gates impounding water
(4) Seismic Load shall be considered
The worst condition will be when there is no live load on the bridge deck and regulatory gates
are completely closed with water level up to full supply level with no water on d/s side. No
tension is allowed in any section of pier.

A minimum of 1.2 m wide conc. pier with C-25 cement concrete cap may be adopted.

Piers shall have at least one groove for stop-logs besides suitable groove for gates.

 Pier width
 The pier width supporting the bridge deck over the weir shall be equal to the width of the
bridge deck plus the curbs and the cable ducts. The pier width for the undersluice portion
and for off-taking canals will be kept the gate operation platform and bridge.
 The top of pier under road slab shall be lower and under gate operating platform shall
normally be high, which depends on the height of gates.

 Pier thickness
 For the piers supporting the bridge deck over weir potion the thickness is 0.90mFor the
piers supporting the bridge deck and gate operating platform for the main canals head
regulator and for the under sluice portion, the thickness of the piers will be 1.2 to 2.0 m,
as found appropriate

5.1.29. Abutments
 Keep top width of abutment not less than 0.8m out of which 0.50m will be bearing
for the R.C. slab. The bottom width shall be kept not less than 2.0m.

February,2017 OWWDSE Page 85


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

 The abutment shall have its front face vertical to facilitate the working of gates and
rear face sloping.
 The base of abutment shall be at least 1.5m below ground level. The section of
abutment shall be checked for stability considering its self-load, live load and dead
load transmitted by road slab, side thrust due to earth retained and surcharge due to
live loads etc
 Seismic load will also be considered.

5.2. Design of Detail Diversion Weir and Appurtenant Structures


The main objective of constructing diversion weir for phase IIA project along Dhidhessa river as
it was discussed with the above water abstraction system water will be diverted to the left and
right side of main canal intake in order to irrigate the command area available at phase IIA and
phase IIB (Beneshangul area) for a total estimated about net area 17,101.58ha and gross
30,000ha respectively.

5.2.1 Selection of Diversion Weir Points of Lower Dhidhessa project

Based on the above design criteria point of selection of head work position has been done using
prepared detail topographic map of and discussion with local farmers and site visiting along
the river course of Dhidhessa and considering proposed irrigable areas available at the project of
phase IIA area and phase IIB at Benshangule Gumuze area which is 200km far. The best
possible sites of head work Lower Dhidhessa site for both phase IIA and phase IIB was selected.

From the above water abstraction system analysis of different options, the diversion weir point
below the main road of Nekemte-Bedele bridge has been selected as the best option. It is
located on the point 4.3km and 3.3km to the downstream from the new bridge crossing the
Dhedessa River on Nekamte-Bedelle road. Their coordinates are X=214497.7532
Y=965480.7351, X=214400.6990 Y=964560.0315, respectively. The span of river width is
estimated 100-150m length. The river bank is totally covered by forest to the left and right side
as you go further the elevation will increase.

February,2017 OWWDSE Page 86


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

Figure : photo of diversion weir site

5.2.3. The Foundation Condition of the Selected Head Work Site


According to geotechnical study report the headwork site is characterised by river deposits and
bed rock units. In general geo-technical report has the following discussion and findings.

The central River course is characterised by river deposit that is loss gray to dark gray
/variegated Sand Gravel Cobble and boulder. Thickness of the material as inferred from valley
cut section is estimated to be in the order of 4mts. This shall be confirmed upon drilling of
boreholes at the site of interest and it willbe considered during detail design.

Temporarily, foundation is recommended to be in bed rock units that is estimated to be at depth


in the order of 5mts.

The left and right abatements are characterised by river deposits of considerable thickness. As
inferred from the valley cut section thickness of the material is estimated to be in the order of
6mts. This requires confirmation upon drilling of boreholes. Such a material is loss to stiff grey
to dark gray Clay Silt Sand Gravel with cobble.

February,2017 OWWDSE Page 87


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

The unconsolidated soil overburden deposits / River deposit found at the headwork site is weak
and highly pervious. To this the need for conducting proper consolidation and provision of
impervious material with positive cut off extending towards the upstream is recommendable to
alleviate problem of excess leakage.

The Underlying bed rock material is grey coarse grained medium to closely jointed slightly
weathered GRANITE. The material is sound that can support the intended headwork structure.
Considering water tightness it is slight to fairly pervious. This shall be confirmed upon in - situ
testing / packer permeability test for proper evaluation and hence to forward pertinent design
parameters and recommend appropriate measures for consideration.

Foundation is recommended to be in the bed rock unit. This is estimated to be at depth in the
order of 7mts. It is recommended for provision of mason supporting structure to the abatements.

5.2.4. Estimation of design flood at selected weir site


Based on the hydrological report the weir site is located in a hydrologically similar regime with
that of the Arjo station (114001) at nearly 5 km distance downstream. Therefore, area
proportionality (catchment analogy) method was considered to be an appropriate method to
estimate the ungauged flow at the weir which was also recommended by Admasu (1989). The
design flood with diffrent retun period are prepared in the following table20

Table : flood design at weir project site

Time LT NRM EVI EXP GAM LN2 LOG LN3 PE3


2 576.06 640.19 490.96 560.98 619.23 593.74 640.19 640.18 619.23
5 743.80 857.39 668.82 797.50 848.72 823.06 837.48 871.27 848.72
10 792.90 971.04 786.58 976.42 981.31 976.43 952.88 1005.26 981.31
20 829.76 1064.86 899.53 1155.34 1097.54 1124.37 1059.22 1123.26 1097.54
25 839.96 1092.19 935.37 1212.94 1132.56 1171.53 1092.46 1158.95 1132.56
50 867.92 1170.43 1045.75 1391.86 1235.84 1317.79 1194.04 1264.57 1235.84
100 891.55 1240.79 1155.31 1570.78 1332.56 1464.85 1294.13 1364.05 1332.56
200 911.99 1305.18 1264.48 1749.69 1424.31 1613.77 1393.49 1458.99 1424.31
500 935.29 1383.21 1408.50 1986.21 1539.74 1814.64 1524.32 1579.27 1539.74
1000 950.71 1437.93 1517.35 2165.13 1623.52 1970.28 1623.10 1667.20 1623.52
2000 964.60 1489.62 1626.16 2344.05 1704.82 2129.51 1721.82 1753.04 1704.82
5000 981.00 1554.02 1769.97 2580.57 1809.11 2346.02 1852.26 1863.95 1809.11
10000 992.17 1600.19 1878.75 2759.49 1885.95 2514.68 1950.92 1946.25 1885.95
100000 1023.28 1741.05 2240.08 3353.84 2131.30 3107.91 2278.62 2212.51 2131.30
Source: climatologically and hydrological draft study report, OWWDSE,2016

February,2017 OWWDSE Page 88


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

Therefore, from the above design flood estimation table 20 the peak design discharge at the
selected weir site location with the assumption of with the dam availability at the upper Arjo
project is estimated as per the hydrological study conducted for 100 years return period is
1464.85m3/sec.

In summary, the design flood under the existence of dam (i.e. “With Dam Scenario”) is
algebraically summed up to yield a 1 in 100 years return period flood estimate of 1199.15

m3/s ≈1200 m3/s. However, this estimate still remains conservative as it overlooks the
sediment inflow from the adjoining catchments below the dam axis.

In summary, the design flood at the weir site considering the 1 in 100 years return period
for both the scenarios (i.e. without dam and with dam) can be taken as 1464 m3/s and
1200m3/sec respectively.

5.2.5. Determination of Diversion Weir and Appurtenant Structure


Hydraulically
The storage capacity of the headwork is smaller than 6,000 ham and the size of under-sluice path
is large because the delivery capacity is relatively big. Therefore, the headwork is of semi-
barrage type. Hence the value of 100 year return period is selected as the design flood discharge.
And the freeboard of both abutments shall be checked by 1,000 year return period value. Based
on the above hydraulic report, the value of 100 year return period taken for our design purpose
1200m3/s and that of 1,000 year period is 1970.28m3/s, respectively.

5.2.6. Design of Diversion Weir


Diversion weir was designed to raise the level of water in the river sufficiently to the desired
height for diverting the water in full or in part through regulators into the main supply canals for
the development of irrigated agriculture.

The weir was designed for both Hydraulic and structural aspects. The hydraulic condition under
which the weir is supposed to work was analyzed first.

February,2017 OWWDSE Page 89


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

All the forces acting on it was calculated based on the hydraulic design. The general arrangement
of the proposed weir and its main dimension was determined based on the results of hydraulic
analysis and then after the structural design was carried out.

5.2.7. River Back –Water Effect Evaluation and Weir Location Determination
At the stage of preliminary design, weir site was considered to be on the point 4.3km (Option 1)
and 3.3km (Option2) from the bridge on Nekamte-Bedelle road toward downstream. Serious
consideration of the impact of river back water by the weir is needed in the developed area
upward including the bridge. Therefore, firstly, flood water level according to design flood on
the point of the bridge was decided when there is not the weir. And then, reasonable weir
location was decided by calculating and comparing river back water effect caused by rising water
surface on each weir. 1 meter which is generally used was taken for the rising water (afflux) on
the weir location. Analysis of river back water was undertaken with Hec-ras and Eaglepoint
Software on the basis of EMA topographic map.

The analysis result is given in the following figure river back water HEC-ras, Eagle-point Software

February,2017 OWWDSE Page 90


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

Figure : water surface profile without weir

Figure : Water surface profile with weir at 4.3km (option1)

February,2017 OWWDSE Page 91


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

Figure ; water surface profile with weir at 3.3km (option2)

As shown in the figures above, increment of 1m of water level on each weir brings about water
level rising on the bridge point by 5cm increment in case of option 1 and 11cm in case of option
2. Now there is no place down the option 1 weir which guaranties diversion level and facilitates
its construction.

February,2017 OWWDSE Page 92


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

Figure : Photo of Bedele-Nekemte Road Bridge over Dedesa river

And on the location of option 1 and option2 the river bed level is different by almost 1m.
Therefore, the location of option 2 is very unfavorable in terms of work and safety of structures.
Additionally 1km of main canal length and appurtenant structures are needed.

5.2.8. Determination of Water tail curve.


Based on the weir site topographic map, River‟s cross-sectional and longitudinal profiles were
produced. Using these profiles the stage discharge curve was computed by HEC-ras Software
and plotted as shown below. It helps for knowing the tail water depth after construction of weir
and enables to decide the arrangement of the weir and protective structures.

February,2017 OWWDSE Page 93


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

Figure : tail Water curve

As per the above curve the tail water level according to design flood level is 1271.04m and tail water
depth is 1271.04-1265.0=6.04m on the location of the weir.

5.2.9. Types of Weir & selection


Various types‟ weirs are available. The most common type of weirs considered for construction
is Glacis type and Ogee weir. In general, the coefficient of discharge of Ogee weir is great, but
its impact is not expected due to upstream deposit in case of low weir. Because the geological
state of the proposed weir site foundation has deep bed rock and is permeable, so that Glacis type
weir section was selected.

Weirs can be constructed using deferent materials; the suitability of the each mater depends
largely on the shape of the weir. For selecting construction material, among others the following
factors are considered.

 Type of construction materials available at or near by construction site.


 The type and size of bed materials transported by the river during its high flood.
 The hydrological characteristics of the river.
 Availability of skilled and unskilled labor.
 The foundation condition of the weir site.

Considering the above points and other factors, concrete weir with plum concrete is adopted for
this study.

February,2017 OWWDSE Page 94


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

5.2.10. Shape of the Weir Crest


Weirs differ in type and shape, but designed and constructed to serve the same purposes. The
following points are considered to determine the type and shape of the weir suited to this specific
site.

 A weir with a shape that cannot easily be constructed by local manpower should not be
considered.
 The availability of the skilled manpower for implementing.
 The skill of the local builders, to perform as per design and specification.
 Taking into account the cited points and other factors, broad crest concrete weir type with
1:3 slope for downstream face,1;1 for upstream face is adopted.

5.2.11. Fixing Weir Crest Level


At the location of the selected weir site, the minimum river bed level is approximately 1262.00m
above mean sea level. The weir crest elevation is fixed with reference of this river bed elevation
considering the following factors.

 The crest level should be set at desired height or level to be able to obtain the required
driving head to safely deliver the designed discharge to main canal.
 The weir crest should be set to allow a safely passage of maximum flood discharge
within designed weir crest length.
 The bed level and crest level of the under sluice should be below sill level of canal
head regulator and nearly the river bed level
 The main canal at the head reach should not be too deep in order to avoid large
excavation work, to minimize construction cost and to reduce maintenance and side
slopes stability problems.

5.2.12. Design of under sluices


Theunder sluice helps to allow the removal of silt deposited near the head regulators. The
proposed headwork delivers to phase IIA (left side) 23m3/s of 69.13m3/s dropped from Arjo-
Dhidhessa Dam to the Dhidhessa River and phase IIB(right side) 46 m3/s. Therefore, the sizes of
the headwork regulators are relatively big. Accordingly, under-sluice paths take large proportion
in weir waterway. The above-said waterways of under-sluices are 10 m wide on the left side each
width has 5m and 20m the right side, discharging about 50% (730.12m3/s) of total design flood.

February,2017 OWWDSE Page 95


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

To avoid clogging by debris, the space of each under-sluice is determined to be 5m and four
under-sluices and two under-sluice are disposed on the right side and left side, respectively.

The waterways of under-sluices are separated by 2m-thick divide walls and the right-side under-
sluices pier is 2m-thick.

The bed level of under-sluices is the same as river bed level, ie, 1265.00m and their crest level is
1265.30m that is 0.3m higher than the bed level.

The crest levels of head regulators on both sides is decided to be 1266.80m that is 1.50m higher
than 1265.30m of the crest level of the sluices, in order to prevent sediment of waterways from
entering main canals.

5.2.13. Determination of Height of Weir


Height of weir was determined based on the following data.

 Minimum river bed level = 1265.00 masl.


 Afflux = 1.00 m.
 Weir crest elevation =1269.00 masl.
 Weir crest height, H = 1269 -1265.00 = 4 m above river bed level.
 Under sluice bed level = 1265.00 masl.
 Under sluice crest level = 1265.30 masl.

Figure : river cross-section of head work.

February,2017 OWWDSE Page 96


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

5.2.14. Crest Length of the Water Way.


The length of water way should be adequate to pass the design flood safely. For alluvial river it
is usually determined from the Lacey wetted perimeter (P).

The wetted perimeter (P) is given by

P  4.75 Q

Where, Q = design discharge (m3/s)

P = wetted perimeter

P = 4.75√1200= 164.54 m

Based on the site condition let us provide a water way equal to 86 m, in such that the space that
occupied by under sluice Piers and divide wall which passed the discharge approximately 50% of
the maximum flood which passes the entire waterway.

Assume the waterway as below

 Under sluice Portion


6 bays of 5 m each 30.00 m

4 Piers of each 2m = 8m

Divide walls of 2 m each = 4 m

Overall Waterway = 42 m

 Other Weir Portion


Clear width of weir portion = 56 m

2 Pier of 1 m each = 2.00 m

Over all Weir porition = 58.00 m

Hence, total overall waterway provided b/n abutments = 100 m

Clear Water way =86m

Looseness factor = Actual length/ theoretical length = 86/164.56 =0.522

Looseness factor = 0.52, its OK! (B/n 0.50-1.00)

February,2017 OWWDSE Page 97


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

5.2.15. Head over the Weir and Discharge.


Neglecting the pier and abutment contractions and assuming the weir to be broad crested:

Discharge intensity, q = Q/L= 1200/100 = 12 m3/s/m

Normal scour depth, R = 1.35(q2/f) 1/3 =1.35(12 2/1.75)1/3 = 5.87 m.

Regime velocity, v = q/R = 12 /5.87 =2.044 m/s

Velocity head, ha = v2/2g =2.044 2/2*9.81 = 0.21m.

Therefore,

Upstream HFL=Tail water level + Afflux=1271.04+1=1272.04 m

Upstream total energy level (TEL) = 1272.04+0.21 = 1272.25 m.

Downstream total energy level (TEL) = 1271.04+0.21 = 1271.25m

 Weir Portion Discharge.


Effective width of the weir portion.

Leffective  Lclear  nK p  Ka H e

Where n is the number of piers (= 4), kP is the pier coefficient (= 0.01 for semicircular piers), and
ka is the abutment coefficient (= 0.1 for 90° wing walls).

Where, He= u/s head- crest level= 1272.04- 1269= 3.04m

Downstream head D= 1271.04- 1269=2.04m

Therefore,

Leffctive = 56- 2*(4*0.01+0.10)*3.04

Leffective  55.15 m,

Let‟s check whether the flow is free (modular) or submerged (non-modular).

For the flow to be modular, i.e. not affected by submergence, the ratio H2/H1, where H1 and H2
are the upstream and downstream heads above the weir crest, is less than 0.75 (BSI, 1969; Bos,
1976):

Upstream head (total head over the crest) , H1 = 1272.04m – 1269m = 3.04 m, and

Downstream head, H2 = 1271.04m - 1269 = 2.04 m.

Therefore, the submergence ratio,

February,2017 OWWDSE Page 98


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

H2/H1 = 2.04 / 3.04 = 0.67 (< 0.75).

Hence the flow is modular, and the weir discharges the design flow with the desired upstream.

The discharge through the weir

Q1 = CLHe3/2 modular flow;

Where;

Q1 = calculated discharge (m3/s)

L= length of the weir (m)

He = total head over the crest (m)

C = coefficient of discharge 1.7

So, Q1 = 1.7 x 55.15 x 3.25 3/2 = 550 m3/s

 Under sluice Portion Discharge, Q2


Effective width of the under sluice portion

Leffective  Lclear  nK p  2Ka He

Where n is the number of piers (= 4), kP is the pier coefficient (= 0.01 for semicircular piers),
and ka is the abutment coefficient (= 0.1 for 90° wing walls).

Therefore,

Leffective = 30-(4*0.01+2*0.1)*1

Leffective  29.76 m,

Let‟s check whether the flow is free (modular) or submerged (non-modular).

Upstream head over the crest, H1 = 1272.04 – 1265.30 = 6.74m, and

Downstream head over the crest, H2 = 1271.04m – 1265.30 = 5.74 m.

Therefore, the submergence ratio,

H2/H1 = 5.74 / 6.74 = 0.851 (> 0.75).

Hence the flow is non-modular, and the weir discharges the design flow with the desired
upstream and downstream water levels.

February,2017 OWWDSE Page 99


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

C1L 2 g  H 2 - h a 2   C2 DL 2 gH
2 3 3
Q2 
3  

Where;

Q2 = calculated discharge (m3/s)

L =effective length of the pass (m)= 28.38m

H = difference of u/s and d/s water level (m)=1m

ha =approach velocity head (m)=0.21

D =Downstream head (m) 5.74m

C1 = coefficient of discharge 0.577

C2 = coefficient of discharge 0.8

 0.577  31.5  2  9.8 1 2 - 0.22 2   0.8  6.12  31.5 2  9.8 1


2 3 3
Q
3  

2
Q= 3 ∗ 0.577 ∗ 29.76 ∗ 2 ∗ 9.81 (13/2 – 0.213/2) +0.80* 5.74*29.76* 2 ∗ 9.81 ∗ 1

= 651.13

discharge through weir and under-sluices

under sluice

Qtotal= Q1 + Q2 = 549.31+ 651.13=

= 1200.44 (m3/s)

As Qtotal=1200.44 m3/s is bigger than 1200m3/s of total design flood, the above-selected weir
dimensions are satisfied.

5.2.16. Determination of stilling basin weir portion


- With no retrogression and concentration

Discharge in Weir Q=550 m3/s

February,2017 OWWDSE Page 100


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

Total clear waterway L=55.15 m

Discharge per meter length q=9.97 m3/s /m

Head loss HL=1.00 m (Afflux)

From Blench Curve,

Critical Depth, Dc = (q2/g)1/3 Dc = (9.92/9.81)^1/3=2.16 m

HL/Dc = 0.46

Pre-jump depth corresponding to Ef1 D1 = 1.41 m (From Blench Curve).

Post jump depth corresponding to Ef2 D2 = 3.69 m (From Blench Curve)

Upstream specific energy level Ef1=5.06 m

Downstream specific energy level Ef2=4.06 m

Froude no., F = q / √ g x D13 F=2.63

Cistern level = D/S TEL - Ef2 = 1271.25-4.06

=1267.19 m

Because calculated cistern level is higher than river bed level; the cistern level is selected to be
lower than river bed level by D2/4, by taking work condition during non-flood period.

D2/4= 3.69/4 = 0.92 m

Provided Cistern Depth =1.0 m

Provided Cistern level =1265-1.00

=1264m

The length of the stilling basin is:-

L = 4*D2 = 4 x 3.69 = 14.76 m

Say L=14.8 m

Cistern length required for Fr< 4.5= 5(D2-D1)= 5*(3.69- 1.41= 11.4m

Consider L= 15m

February,2017 OWWDSE Page 101


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

5.2.17. Determination of retrogeration and concentration


Considering 20% concentration and 0.50m retrogression and discharge over the weir is
Q=660m3/sec.

Downstream depth is drop is 0.5m and the total clear water way is 55.15m and discharge per
meter length is q= 11.96m3/sec/m.

Upstream head , He= (q/c)2/3 =(3.67m,), and head loss is (3.67m+ 1m) - ( 0.102 from kohsla
+0.50m drop)

= 2.13m

New TElu/s= (q/c)2/3 +Weir crest level= 1272.67

New TEl d/s = TEld/s -0.50= 1270.54m

From blench curve Critical depth Dc= (q2/g)1/3 = Dc= 2.44m

Hl/dc= 0.87

Pre jump depth corresponding to Ef1= , D1= 1.10m

Post Jump depth corresponding to EF2, D2= 4.62m

Upstream specific energy level = Ef1= 7.10m

Downstream specific energy level= Ef2= 4.97m


q
Fraude No= F= = , f= 3.3
(𝑞∗𝐷1)^3

Δcystern level= D/s Tel-Ef2= 1265.79m and, Δ cistern depth will be equal to d/s bed level minus
cistern level or in case of d/s bed level is higher than calculated cistern level then the depth be
kept equal to FSD/4= 1.16m.

Δprovided cistern depth = 1.20m and Δ provided cistern level= 1263.80m.

The length of stilling vasin L= 4*d2= 4*4.62= 18.49m, take 18.50m, agin with fraude nimber ,
cistern length required (for F<4.5)= 5*(D2-D1)= 17.6m then take 19m.

February,2017 OWWDSE Page 102


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

Figure : longitudinal section of designed diversion weir

February,2017 OWWDSE Page 103


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

5.2.17. Freeboard
Sufficient freeboard should be provided for u/s and d/s wing walls in order to protect the walls
and embankments from being overtopped by surges, splash and spray, and wave action setup by
the turbulence of hydraulic jump, and not to allow high flood water to bypass the diversion weir.

Table : freeboard depending design flood discharge

Design flood discharge Freeboard


No.
(Unit:m3/sec) (Unit in M)

1 Dh < 200 0.6

2 200 ≦ Dh < 500 0.8

3 500 ≦ Dh < 2,000 1.0

4 2,000 ≦ Dh < 5,000 1.2

5 5,000 ≦ Dh < 10,000 1.5

6 10,000 ≦ Dh < 2.0

Because design flood is 1200m3/s, freeboard is selected to be 1m.

Top elev. of the d/s retaining walls = d/s H.F.L +FB = 1271.04+1

=1272.04 m

Top elev. of u/s retaining walls and embankments = u/s HFL + FB = 1272.04+ 1= 1273.04

5.2.18. Top Width of Crest


Because of glasic type of profile will be provided with site river condition . The minumu top
width as per IS 6531-1944 is 2/3 He

He = U/S FSL - Crest Level = 1272.04-1269=3.04 m

∆ Min. top width of crest=2.02m

Provide top width of crest for accommodating Gates and Stop log = 3.00 m

February,2017 OWWDSE Page 104


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

5.2.19. Vertical Cut off


(i) Provide U/S Cut-off of 1.9 m depth below U/S bed level
=1.80 m

Bottom elevation of upstream pile=1263.20m

(ii) Provide D/S cut-off of 3.7 m depth for safe exit gradient
=3.70 m

Bottom elevation of downstream pile =1265-3.70=1261.30 m

5.2.20. Floor Length


From Khosla's theory, the exit gradient can be expressed by the relation as

Exit gradient = 1 / p x sqrt ( l ) X (H / d ) Where, GE ( Exit gradient ) = 1 / 5


d = Depth of d/s cutoff = 3.70 m

H = Maximum static head = U/S FSL - D/S cistern level


=7.25 m

Substituting the values 1 / 5 = 1 / p x sqrt ( l ) X (H / d )

or 1 / p x sqrt ( l ) = d / (5 x H) =0.102

From Khosla curve for 1 / p x sqrt ( l ) a =18.45

Floor length = ᾳ x d = 68.27 m

The Total length will be provided as below:-

(i) D/S Floor length =29.00 m

(ii) D/S Glacis length ( 3:1 slope) =15.60 m

(iii) Length for Gates & Crest =3.00 m

(iv) U/S Glacis length ( 1:1 slope) =4.00 m

(v) U/S floor length =17.00 m

(vi) Total length of floor =68.60 m

5.2.21. Pressure Variation Calculation


At U/S cut off wall

Total floor length (b) = 68.60 m

February,2017 OWWDSE Page 105


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

Depth of U/S cut off wall (d) = 1.80 m

From Khosla's equation

1/ ᾳ = d/b = 0.026

ᾳ = b/d = 38.111

l =  = (1 + √ (1 + 2))/2 = 19.562

fE = E = Cos-1((- 2)/)= 15

fD = D = Cos-1(( - 1)/)= 10

fC1 = C1 = 100 - E = 85

fD1 = D1 = 100 - D = = 90

Assuming floor thickness at U/S end as = 0.900 m

Correction for floor thickness at U/S end = (90 - 85) X 0.90 / 1.80 =2.50 %

fC1 (Corrected) = 85.00 + 2.50= 87.50%

 At D/S cut off wall

Total floor length (b) = 68.60 m

Depth of D/S curtain wall (d) =3.70 m

From Khosla's equation

1/ ᾳ = d/b =0.054

ᾳ = b/d =18.541

l =  = (1 + √ (1 + 2))/2 = 9.784

fE = E = Cos-1((- 2)/) = 21

fD = D = Cos-1(( - 1)/)= 

Assuming floor thickness at D/S end as = 0.900

Correction for floor thickness at D/S end = (21 - 15) X 1 / 3.70

=1.62%

fE (Corrected) = 21 - 1.62= 19.38 %

February,2017 OWWDSE Page 106


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

Pressure variation = (87.78 – 19.38) / 68.60 = 0.997%

5.2.22. Floor Thickness

(i) D/S FLOOR

Floor thickness from D/S face of D/S cut off wall at = 4m

r = 19.38 + 4 * 0.997= 23.37 %

Floor thickness = (r x H) / ((sp,gr.-1) X 100) = 0.75m, take sp.gravity 2.24tone/m3

Provide minimum as = 1.00 m

Floor thickness from D/s face of D/s cut off wall at 10m.

R= 19.38 + 10*0.997= 29.35%

Floor thickness = (r x H) / ((sp,gr.-1) X 100) = 0.95m let provide 1m thickness

Floor thickness from D/S face of D/S cut off wall at =20.00 m

19.38 + 20* X 0.997 =39.32 %

Floor thickness = (r x H) / ((sp.gr.-1) X 100) =1.27m

Provide minimum as =1.30 m

Floor thickness from d/s face of D/s cut off wall at 29m

R= 19.38 + 29*0.997= 48.29%

Floor thickness = (r x H) / ((sp.gr.-1) X 100) = 1.56m

Provide minimum as = 1.60m

Floor thickness of D/s glacis varies from 5m to 1.6m from crest to cistern.

(ii) U/S FLOOR

Provide thickness of upstream floor = 1.00 m

5.2.23. Protection Works Beyond Impervious


(i) Upstream protection:

Depth of scour R = 1.35 x (q2/f)1/3 = 5.86 m

Anticipated scour = 1.5 X R = 8.79m

February,2017 OWWDSE Page 107


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

Upstream scour level = 1272.25 – 8.79= 1263.25 m

Scour depth 'D' below u/s floor = 1265.00 – 1263.25=1.80 m

(a) Block protection:

Hence „D‟ = 1.80 cu.m/m

Block protection shall be provided minimum equal to 'D' in length & minimum 4 rows of blocks,

Provide 3 rows of 1.25m x 1.25 m x 0.60 m

Gravel apron in a length of = 3.81 m

No. of rows required across the bed width =68.80m

Provide the no. of rows across the bed width = 69 m

Gravel apron in a length= 1.80 / (0.60 + 0.60) =1.50 m

Rows of above blocks in a length of 1.80m

(b) Launching apron:

Quantity of launching apron should be 2.25 X D = 4.05 cu.m/m

Thickness of launching apron = 1.20 m

The length required = 2.25 x D / thickness = 3.38 m

Provide length of launching apron = 4.00m

(ii) Downstream protection:

Anticipated scour = 1.75 X R = 9.73m

Downstream scour level = 1272.25 – 9.73= 1261.31 m

Scour depth 'D' below u/s floor = 1265 – 1261.31= 3.70 m

(a) Block protection

Block protection shall be provided in a minimum length equal to '2D' which comes

Provide 5 rows of 1.25 m X 1.25 X 0.60 m C.C. blocks with 3 cm gap filled with 'bajri'
(Sand) over 0.60 m thick graded filter in a length of 6.37 m

(b) Inverted filter:

February,2017 OWWDSE Page 108


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

AS per Code of Practice, Just at the end of concrete floor on the downstream an inverted filter

1.5 to 2 D long (D being the depth of scour below bed), is provided below the concrete bloc

The length of the inverted filter should be equal to 1.5D = 5.55 m

Providing 1.25m x 1.25 m x 0.60 m CC blocks with 10cm gap filled with 'bajri' over 0.60 m.
0.60 m thick graded filter.

No of rows required = 5.55 /1.35 = 4.11 m

Hence, provide 4 rows of blocks in the direction of flow. Provide length of inverted filter in
the direction of flow = 5.3m

No. of rows required across the bed width =63.78 m

Provide the no. of rows across the bed width =64 N0.

(c) Launching apron:

Downstream of the inverted filter, loose apron 1.5 D in length consisting of either boulders of not
less than 40 kg or wire boulder crates should be provided so as to ensure a minimum thickness of
1 m in launched position. Thickness of launching apron (Sum of thickness of blocks & Filter)
= 1.20 m

Quantity of launching apron required = 2.25 X D = 8.33 cu.m/m

Length required = 8.83 / 1.20 = 6.94 m

Provide launching apron 1.20 m deep in a length of say 7m

Toe wall : also provide a0.90m thick and 1.2m deep masonry toe wall between the filiter and the
lounching apron.

Under sluce: Provide the crest of under sluce at 1265.50m near the canal head regulator which is
0.50m above the river bed level.

5.2.23. Stilling basin for under sluce portion


Discharge through under sluce (Q)=650.714m3/sec

Total clear water way L= 30m

Discharge per meter length q= 21.69m3/sec

Head bloss = 1.00m

From blench curve

February,2017 OWWDSE Page 109


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

Critical depth Dc= (q2/g)1/3 = and Dc= 3.63m, prejump depth Hl/Dc= 0.287

Corrospoding to Ef11 = D1= 2.11

Post jump depth corrospoding to Ef2 =D2= 5.76

Upstream specific energy level = Ef2= 6.49

Fraude No = f= q/ 𝑞 ∗ 𝐷1^3 = 2.26, but for afraude f=1.7-2.5, a series of small rollwrs develop
on the jump , but the downstream water surface remains smooth. The velocity through out is
fairly uniform and energy loss is low. This jump is called weak jump.

Δcistern level = D/s TEL-Ef2= 1264.77m.

The length of stilling basin is ,L= 4*d2= 4*5.76= 23.056m take 23.1m. Cistern length required
(fr<4.5)= 5*(D2-D1)= 18.26m say L= 24.00m. The total length of under sluce paths is minum
72.39m in case of left. This kind of stilling basin calculated. The calculated basin floor level is
1265.10m and basin length is 24m. Therfore, because of in undersluce itself the energy
dissipation is good enough and downstream weir portion stilling basin is applied here.

5.2.24. Design of Appurtenant Structures


All structures related to head work or diversion structures like foot Bridge and , head regulators
should be designed as appurtenant structures.

5.2.24.1 Design of Head Regulator


The axes of both head regulators are aligned to be 45o from the axis of the weir, so as to facilitate
intake of river water and their smooth linking to main canals.

Full supply level and crest level of both head regulators are designed to be 1269 m and 1267m,
respectively.

Head Regulators main canal 45o

Head Regulators full supply level 1269m and crest level 1267.00 m

 Design of Left Head Regulator

Designed Left Main Canal Data

Design discharge =23m3/s

U/s maxmum water level= 1272.04m

U/s FSL= 1269m

February,2017 OWWDSE Page 110


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

U/S bed level= 1267m

U/S FSD= 2.00m

D/s Bed barrel FSD = 2.10m

Rack loss = 0.05m

Working head = 0.20m

Freeboard = (FRB)= 1.00m

Gravitaional acceleration= 9.81m/sec2

Crest level of weir bay section : The crest level of weir bay section is generally kept about 1.0m
to 1.5m high than the crest level the under sluce.

Crest keight = 0.30m

Crest l;evel = U/s TEL-He =1267.30m

Upstream head , Hd= 1269- 1267.30m-0.05= 1.65m

Downstream head = D= 1268.75- 1267.30 =1.45m

Diffrence of U/s and D/s water level = H= 0.20m

H2/H1= 1.45/1.65 = 0.88 (check) , considering velocity head is 0, therefore use non moudular
formula.

q=Q/Le=2/3*C1*(2*9.8)^.5(H^(3/2)-ha^(3/2))+C2*D*(2*9.8*H)^.5= 2.45m, and


where, C1 and C2 numerical cofficent values are 0.577 and 0.8 respectively.

Effective length of crest = Q/q= 23/2.45= 9.38m

Actual length of crest La= Le +(0.05*(4bays-1) +2*0.1)H= 9.46m, considering numbers of bays
are 4 and thickness of piers are 1.2m. The width of bays are 9.46/4= 2.36m take 2.5m.Actual
length of crest Le= 4*Wbays +(No bays -1)*Thickness= 13.6m.

Top width of crest : It is sharp crested weir will be provided so as to have minimum possible
head loss . The minmum top width as per IS 6531 -1994 is 2/3 He, where

He= U/s FSL – crest level = 1.7m

Δmin top width of crest =1.1m

February,2017 OWWDSE Page 111


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

Provide top width of crest for accommodating gates and stoplogs =4.1m so that top width is
5.00m.

February,2017 OWWDSE Page 112


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

Operating Platform

U/S FSL

1269.00

D/S FSL 1268.75

U/S of Left Settling Basin


U/S BL CRL 1267.30
Inlet
1267.000 1 :1 3:1 Barrel BL 1266.65

1266.65 5:1

0.30 5.00 1.95 Vari. 0.00

Figure : Level and length of left D/S floor

February,2017 OWWDSE Page 113


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

Top width of crest

Level and D/s of length of floor

 Discharge in main canal = Q= 23m3/sec


 Total clear water way , L=9.46m
 Discharge per meter width ,q= 1.94m3/sec/m
 Head loss Hl, = 0.20m
 Critical depth , Dl =( q2 /g)1/3 , Dc= 0.73
 Z= Hl/Dl= z= 0.27
 Prejump depth corrospoding to Ef1=D1=0.44m
 Post Jump depth corrospoding to Ef2= D2= 1.34m
 Ef2= q2/(2*g*y2 2) + y2 + Ef2= 1.48m
 Ef1= Hl +Ef2 = Ef1 = 1.79m

Downstream floor level = D/s TEL- Ef2= 1267.27

ΔCistern length required = 5*(D2- D1)= 4.50.

Barrel bed level and length is 1265.80 and 37.07 respectively. Therefore separately the emergy
dispation is satisfacyory and separate stilling basin is no required.

 Design of Right Head Regulator


 Design discharge =46m3/s
 U/s maxmum water level= 1272.04m
 U/s FSL= 1269m
 U/S bed level= 1267m
 U/S FSD= 2.00m
 D/s Bed barrel FSD = 2.65m
 Rack loss = 0.05m
 Working head = 0.26m
 Freeboard = (FRB)= 1.00m
 Gravitaional acceleration= 9.81m/sec2
 Crest level of weir bay section : The crest level of weir bay section is generally kept
about 1.0m to 1.5m high than the crest level the under sluce.
 Crest height = 0.10m
 Crest level = U/s TEL-He =1267.10m
 Upstream head , Hd= 1269- 1267.30m-0.05= 1.85m

February,2017 OWWDSE Page 114


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

 Downstream head = D= 1268.75- 1267.30 =1.59m


 Diffrence of U/s and D/s water level = H= 0.26m
 H2/H1= 1.59/1.85 = 0.86 (check) , considering velocity head is 0, therefore use non
moudular formula.

q=Q/Le=2/3*C1*(2*9.8)^.5(H^(3/2)-ha^(3/2))+C2*D*(2*9.8*H)^.5= 3.10m, and


where, C1 and C2 numerical cofficent values are 0.577 and 0.8 respectively.

Effective length of crest Le, = Q/q= 46/3.10= 14.84m

Actual length of crest La= Le +(0.05*(6bays-1) +2*0.1)H= 14.84+(0.05(6-1)+2*0.1)*0.26=


14.97m, considering numbers of bays are 6 and thickness of piers are 1.2m. The width of
bays are 14.97/6= 2.49m take 2.5m.Actual length of crest Le= 6*Wbays +(No bays -
1)*Thickness= 6*2.5 +(6-1)*1.2= 21m.

Top width of crest : It is sharp crested weir will be provided so as to have minimum possible
head loss . The minmum top width as per IS 6531 -1994 is 2/3 He, where

He= U/s FSL – crest level = 1269-1267.10 = 1.9m

Δmin top width of crest = (2/3)*He =1.3m

Provide top width of crest for accommodating gates and stop logs =4.1m so that top width is
5.00m

February,2017 OWWDSE Page 115


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

Operating Platform

U/S FSL

1269.00

D/S FSL 1268.69

U/S of Left Settling Basin


U/S BL CRL 1267.10
Inlet
1267.000 1 :1 3:1 barrel BL #REF!

1266.04

0.10 5.00 3.18 Vari. 18.00

Figure : level and length of D/s right floor

February,2017 OWWDSE Page 116


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

Top width of crest

Level and D/s of length of floor

 Discharge in main canal = Q= 46m3/sec


 Total clear water way , L=14.97m
 Discharge per meter width ,q= 2.46m3/sec/m
 Head loss Hl, = 0.26 m
 Critical depth , Dl =( q2 /g)1/3 , Dc= 0.85
 Z= Hl/Dl= z= 0.31
 Prejump depth corrospoding to Ef1=D1=0.44m
 Post Jump depth corrospoding to Ef2= D2= 1.34m
 Ef2= q2/(2*g*y2 2) + y2 + Ef2= 1.48m
 Ef1= Hl +Ef2 = Ef1 = 1.79m

Downstream floor level = D/s TEL- Ef2= 1267.21

ΔCistern length required = 5*(D2- D1)= 4.50.

Barrel bed level and length is 1265.11 and 38.08 respectively. Therefore separately the emergy
dispation is satisfacyory and separate stilling basin is not required.

5.2.24.2 Design of Barrel


As the proposed headwork is located in a narrow place, head regulators and main canals are
designed to be connected by barrels.

A barrel is a kind of paved canal; its capacity is determined by hydraulic calculation method.

Headwork (narrow) head regulators main canals Barrels.

 Design of left main canal Left Barrel

Design Discharge = 23 m3/s

Number of Bays N=4

Manning‟s coefficient =0.025

Bed slop =1/7400

Bed width = 13.20

February,2017 OWWDSE Page 117


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

Side slope= 1.50

Depth of water =2.14m

Fb= freeboard= 0.75m

Velocity , V= 0.66m/sec

Headwork (narrow) head regulators main canals Barrels

Bay discharge of a bay=23/4 = 5.57 m3/s

Bed width of a bay=3.18 m

N= 0.014

Fb=0.70

Slope= 1/6000

The following table shows the hydraulic calculation according to above condition.

Left Barrel

Table : hydraulic calculation of left side barrel

HYDRAULIC CALCULATION OF LMC & BARREL(LEFT SIDE)

Expo Flow
Dis. Rou. F.S. Bed Side Flow Wetted Hyd. n Chezy veloc Dis.
Req. Coef. D F.B Slope width slope area perimeter radius ential coef. ity Des.
m3/s m m m m2 m m m0.5/s m/s m3/s
23.000 0.0250 2.14 0.75 7400.0 13.20 1.50 35.05 20.90 1.68 0.17 43.60 0.66 23.000
5.750 0.0140 2.10 0.70 6000.0 3.18 0.00 6.67 7.38 0.90 0.17 70.24 0.86 5.750

14.40

0.40 3.18 0.30 3.18 0.30 3.18 0.30 3.18 0.40


0.40
0.70

1268.75
FSL
3.20
2.80
2.10

0.30
1266.65 0.30
DBL
0.10 0.40

15.00

Figure : diagram showingLeft side barrel

February,2017 OWWDSE Page 118


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

Design data for right side canal frommain canal design

Design Discharge = 46m3/s

Number of Bays N=6

Manning‟s coefficient =0.018

Bed slop =1/10,000

Bed width= 19.20

Slope = 1:1.5

V= 0.9m/sec

Fb= 1m

Design of right side barrel

Bay discharge of a bay=46/6 = 7.667 m3/s

Bed width of a bay=3.25 m

Depth = 2.65

N= 0.014

D=2.10m

Fb= 0.70

The following table shows the hydraulic calculation according to above condition.

Table : hydraulic calculation of right side barrel

Dis. Rou. Bed Side Flow Wetted Hyd. Expon Chezy Flow
Req. Coef. F.S.D F.B Slope width slope area perimeter radius ential coef. velocity
m3/s m m m m2 m m m0.5/s m/s
46.000 0.0180 2.65 1.00 10000.0 19.20 0.00 50.87 24.50 2.08 0.17 62.75 0.90
7.667 0.0140 2.65 0.70 6500.0 3.25 0.00 8.61 8.55 1.01 0.17 71.51 0.89

February,2017 OWWDSE Page 119


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

21.80

0.40 3.25 0.30 3.25 0.30 3.25 0.30 3.25 0.30 3.25 0.30 3.25 0.40

0.40
0.70
1268.69
FSL

3.61
4.01

3.21
2.51
0.30
0.30 1266.04
DBL

0.10 0.40
22.40

Figure : Diagram showing right side barrel

February,2017 OWWDSE Page 120


Design of Diversion Weir, Headwork and Appurtenant Structures MWI&E

5.2.25. Design of Settling Basin.


Settling basin is used to settle and exclude sand which may flow into an intake facility under
certain river conditions and which may obstruct canals and degrade their functions. A settling
basin must be effective in exclusion of sand particles and have a proper hydraulic design for

design discharge and site conditions.

For example, an intake without a diversion dam or weir constructed at a steep-flow-section of a


river will require settling basin. A settling basin is also one of the most important facilities for a
weir which is installed on a mountain stream where the discharge and river bed changes. For
smooth operation of the canal system settling basin was incorporated in the head work design. To
decrease the load of silt in the canal system is very important sotht it also makes the irrigation
system is eacy in operation and maintenance furher cost will decrease.

In the case of lower Dhdhisa project for both of left and right side of canals settling basins were
design as per design discharge of canals. Settling basin is planned to be connected directly to the
barrel of each head regulators . The settling basin has two sedimentation ditch parts and the
emergency by passing canals. The sedimentation ditch compartments and emergency by passing
canals were designed with half of each disgned canal discharge. Itmeans 11.5m3/sec and
23m3/sec for left and right canal respectivelty.Sedimentation ditch parts consist of inlet,
transient, settling ditch and outlet flashing gate, whereas emergency bypassing canal is composed
of a regulator and pavement canal. Detail design will be presented in detail design report stage.

February,2017 OWWDSE Page 121


Design of the Irrigation and Drainage system MWI&E

6. DESIGN OF THE IRRIGATION AND DRAINAGE


SYSTEM
The proposed Lower Dhidhessa Irrigation Development Project command area is goining to be
irrigated by the Diversion weir which will be constructed on river Dhidhessa proposed at the
downstream of Arjo- Bedele Road bridge 4.3 km far. The available water in the Arjo- Dhidhessa
storage dam is sufficient for irrigating an area of 80000 ha based on the previous study. Upper
Arjo-Dhidesasa Sugarcane development Irrigation project is one of the projects presently being
under construction for an area of 32,000 Ha for sugarcane development.

The LowerArjo- Dhidhessa Irrigation and drainage Project is another project planned to study
using extra water stored at the dam by construction a diversion weir downstream of Arjo Bedele
Road so that a potential of gross 60,000 Ha of land cloud possibly be available for irrigation both
in Oromia and Benshangul Gumuz regional state.

The first Phase of the project (phase-IIA) which is found in Oromia Regional State accounts for
30,000ha, but after making detail investigation and taking topographic map of the area in phase
IIA project has a gross irrigable area of 30,426.50Ha and net area of 17,101.70Ha will be
develop.

6.1. Irrigation Efficiency (E)


As per the detail of agronomical study report the irrigation efficiency expresses the percentage
of the quantity of water used efficiently for the growth of the crop in the field to the quantity of
intake water from the water source. A part of the intake water is lost during transport through the
canals and in the fields by the evaporation, the infiltration and so on. The remaining part is stored
in the root zone and used by the crop. The irrigation efficiency is computed by the following
formula.

e = ec * ea / 100

Where

e : Irrigation efficiency (%)

ec : Conveyance efficiency (%)

ea : Field application efficiency (%)

February,2017 OWWDSE Page 122


Design of the Irrigation and Drainage system MWI&E

The conveyance efficiency is the ratio of the quantity of water supplied to the fields out of the
quantity of intake water from the water source. It represents the efficiency of water transport in
the canals. The conveyance efficiency mainly depends on the length, the soil type or
permeability of the canal banks and the condition of the canals. Assuming the soil type is
dominantly clay and canal condition is lined, the conveyance efficiency will be 95 % ( Guideline
for the field application efficiency is the ratio of the quantity of water used for the growth of the
crop out of the quantity of water supplied to the fields. It represents the efficiency of water
application in the field. The field application efficiency mainly depends on the irrigation method
and the level of farmer practice.

Field application efficiency assumed to be 60% since the method of irrigation to be used is
surface irrigation with furrow method (Guideline for Irrigation Master Plan Study Preparation on
Surface Water Resources, 2014)

Therefore, for this project, overall efficiency, E=0.95X0.6=0.57= therefore about 60%efficency
can be used.

Table : Efficiency of the irrigation system

NO Description Efficiency % Remark

1 Conveyance efficiency of MC, PC, 95%


SC, TC

2 Application & distribution efficiency 60%

3 Overall efficiency 0.57=0.60

In design of main canal of LMC, LGC and LLGC and all PC capacity will be design with 12
hours of water demand of 2.1lit/sec/ha and the rest SC and TC will be design on 1.995lit/sec/ha.

6.2 Design Criteria of Irrigation and Drainage System


A diversion weir is proposed at the downstream of Arjo- Bedele road for both command area
found in phase IIA and IIB. The estimation of canal capacity to meet water requirement for
proposed cropping pattern is the most important input for irrigation in project. Provided that in
the project for design of canal the cropping pattern is proposed in different phases, for design of

February,2017 OWWDSE Page 123


Design of the Irrigation and Drainage system MWI&E

canal the requirement of water is considered for the maximum water requirement. The duty
required per ha of land for irrigation is evaluated and taken as per sectorial report of Irrigation
and Drainage agronomical study. Canal is designed considering trapezoidal section with lined,
unlined or both depending on the geological investigation of the project area.

Many procedures have been developed over the years for the hydraulic design of open channels
Level of assumption implied while developing the given equations. Chezy equations are one of
the procedures that were developed by a French engineer in 1768 (Henderson, 1966). A more
practical procedure was presented in 1989by the Irish engineer Robert Manning (Chow, 1959).
The manning equation has proved to be very reliable in practice.

The following factors are also taken into account for design of canal section. For determination
of velocity in a canal, Manning's formula is considered, longitudinal slope shall be considered in
such a way that velocity in canal shall be non-scouring and non-silting, critical velocity.

Critical velocity ratio will be determined from velocity calculated from formulae. The discharge
in canal is worked out as by multiplying area of canal up to FSL and velocity calculated by
Manning's formulae.

6.2.1.Hydraulic Design of Irrigation Canals of lined and unlined canals


The success of the gravity irrigation system depends on the perfect design of the network of
canals. The canals may be excavated through the different types of soils such as alluvial, non-
alluvial, etc. The design considerations naturally vary according to the type of soil.

Open canals could be either lined or unlined. Lined canals are those channels whose side slopes
and their bottoms are covered with impervious materials to prevent excessive seepage and
growth of weeds in channels. The materials used for best lining of irrigation canals are concrete
and brick or stone masonry. Well mixed and well-made cement concrete lining and single layer
bricks or stones lay in cement or lime mortar provide virtually water proof channel lining.

Unlined canals are, however, earthen channels with no any lining materials both on their side
slopes and their bottoms. A large portion of the irrigation water harnessed at the source of water
supply is lost by seepage from unlined conveyance systems comprising of the main canals,
secondary canals, tertiary canals and field channels.

February,2017 OWWDSE Page 124


Design of the Irrigation and Drainage system MWI&E

Type of canal whether it is lined or unlined mainly governed with the permeability value of the
soil in which the canals are aligned. Lined canals are also selected in expansive soils depending
on the swelling pressure value of the soil. The design criteria for lined canal depend on type of
lining material. The lining material will be decided based on geological investigation of the
project area.

6.2.1.1. Hydraulic design of unlined canals.


Irrigation canals are designed to take adequate discharge safely to satisfy the crop water
requirement of a given crop. The design criteria include:
The design discharge should flow at non-silting and non-erosive velocities.
Side slopes should be flat enough not to cave in when saturated.
Longitudinal slopes should not be excess. Otherwise, velocity will be high which causes
scoring of the channel bottom and sides.

6.2.1.2. Canal Capacity Determination Criteria


The capacity of the canal should be sufficient to fulfill the maximum of the peak demand of all
the crops that are required to be irrigated at any one time amongst all season as the agronomist
determined cropping pattern in sectors study.

All types‟ canals capacity will determine using the following manning formula. MC, PC, SC, TC
and FC will be designed as the following criteria.

Area of cross-section of the canal is worked out by continuity equation

Q = A .V

Where,

Q is the design discharge and V is the velocity of flow.

Value of „V‟ is worked out by Manning's formula for assumed channel section
and bed slope.

Manning formula
1
V= 𝑛 * R2/3 * S1/2 (Kumar, 2005)
Where, V= velocity of flow in m/sec
R= Hydraulic mean depth in meters

February,2017 OWWDSE Page 125


Design of the Irrigation and Drainage system MWI&E

S= Bed slope of the channel


n = Rugosity coefficient
The values of n in both these equations depend upon a channel condition and also upon
discharge.
Capacity required for the canal to irrigate the command depends on the crop pattern, irrigation
intensity, rotation period, water required during critical period, transmission losses, etc. For
fixing the canal capacity, a design statement, or capacity statement should be separately
prepared, reach by reach. The section of a particular reach should be designed for the maximum
discharge in that reach. The points to consider in determining canal capacity are area to be
provided with irrigation facilities (net CCA or net irrigable area) and design duty.

Main, Primary, Secondary and tertiary canals sections are getting reduced from head to tail reach
with discharge getting reduced. The flow in the main, primary, secondary and tertiary canals will
be maintained continuous throughout the year except where no irrigation required during wet
season. As in case of surface irrigation method, water application is planned to be in rotation in
the field canal and farm units the capacities of field canals will be the same and kept its
dimension constant from head to tail reach. This is done to facilitate diversion of entire
discharge in one field canal at one time. This will help to achieve equitable distribution of
irrigation water and improve the quality of service of irrigation.

6.2.1.3. Determination of Velocity in Unlined Canal


The critical velocity in a channel as mean velocity (across the section) which will just keep the
channel free from silting or scouring and related to the depth of flow by the equation according
to Kennedy is the following (Kumer,2005).
Equation as:

Vo  0.546 D
0.64

Where,

VO = critical velocity in m/sec


D = the depth of water in meter.

The critical velocity ratio will be determined from the equation:

CVR  V
Vo

February,2017 OWWDSE Page 126


Design of the Irrigation and Drainage system MWI&E

Where, V = mean velocity as determined by manning‟s equation

The values of CVR will depend on type of silt. The value is nearest to 1. For channel carrying
appreciable bed and suspended loads, the value of CVR should be taken as 1.10 at the head and
0.85 towards the tail end.
Where VO= mean velocity, D= depth of water, and M = critical velocity ratio.
Table : Recommended value of CVR

NO Type of Silt Value of M

1 Silt river 0.70

2 Light sandy silt 1.0

3 Light sandy silt little coarser 1.1

4 Sandy loam silt 1.2

5 Debris of hard soil 1.30

The permissible velocity minimum and maximum: It may be noted that canal carrying water with
high velocity may scour the bed and the sides of the channel leading to collapse of the canal. On
the other hand weeds and plants grow in the channel when nutrients available in the water.
Therefore the minimum permissible velocity should not allow the growth of vegetation such as
weed, grass as well you should not be permitting the settlement of suspended material (non-
silting velocity). Minimum permissible velocity refers to the smallest velocity which will prevent
sedimentation and vegetative growth. An average velocity of (0.4-0.9) and for small canal it can
be used upto 0.27m/sec that will prevent sedimentation when the silt load of the flow is low.
Maximum permissible velocity entirely depends on the material that is used and the bed slope of
the channel. Hence the following gives the maximum permissible velocity for some selected
material.
Table : Maximum permissible velocity and n values for different materials

No material V(m/sec) n

1 Fine sand 0.5 0.02

2 Vertical sandy loam 0.58 0.020

February,2017 OWWDSE Page 127


Design of the Irrigation and Drainage system MWI&E

No material V(m/sec) n

3 Silt loam 0.67 0.020

4 Firm loam 0.83 0.020

5 Stiff clay 1.25 0.025

6 Fine gravel 0.83 0.020

7 Coarse gravel 1.33 0.020

8 Gravel 1.2

9 Disintegrated rock 1.5

10 Hard roack 4.0

11 Brick masonry with cement pointing 2.5

12 Bric masonry with cement plaster 4.0

13 Concrete 6.0

13 Steel lining 10.0

Therefore the maxmum velocity for unlined canals of clay material of phase IIA project
0.9m/sec.In case phase IIA based geotechnical recommendation of the canal material for unlined
canal it is given clay material therefore, manning roughness coefficient was given for our design
0.025-0.03 value. Since phase IIA main canal passed through a type of sandy clay soil and the
critical velocity ratio is between the value is recommended about 0.7-1 for main canals.

6.2.1.4. Determination of Longitudinal Slope of the Canal Criteria


The longitudinal slope of the channel is influenced by topography, the head required to carry the
design flow, and the purpose of the channel. For example, in a hydraulic power canal, ahigh head
at the point of delivery, and minimum longitudinal channel slope should be used. The slopes
adopted in the irrigation channel should be as minimum as possible to achieve the highest
command. Generally, the slopes vary from 1:4000to 1:20,000in canal.

6.2.1.5. Side Slopes of the Canal Criteria


The side slopes of a channel depend primarily on the engineering properties of the material
through which the channel is excavated. From practical viewpoint, the side slopes should be

February,2017 OWWDSE Page 128


Design of the Irrigation and Drainage system MWI&E

suitable for preliminary purpose. However in deep cuts side slopes are often above the water
surface than they would be in an irrigation canal excavated in the same material. In many cases,
side slops are determined by the economics of construction. In this regard following observation
are made: a, In many unlined canals , the side slopes are usually 1.5:1; however side slops as
steep as 1:1 have been used when the channel runs through cohesive materials‟, in lined canals
the side slops are generally steeper than in unlined canal.
If concrete is the lining material, side slops greater than 1:1 usually require the use of forms and
with side slops greater than 0.75:1, the lining must be designed to withstand earth pressure. C,
side slops through cuts in rock can be vertical if this is desirable

Table : Suitable side slopes for channel built in various material (chow,1959)

No Material Side slops

1 Rock Nearly vertical

2 Muck and peat soil ¼ :1

3 Stiff clay or earth with concrete lining ½:1 to 1:1

4 Earth with stone lining or each for large canals 1:1

5 Firm clay or earth for small ditch 1 ½ :1

6 Loose , sandy earth 2:1

7 Sandy loam or porous clay 3:1

From the above both table for the canal with clay embankment material side slope of the canal of
phase IIA project is selected 1.5:1 for all large canals and 1:1 for some branch canals based on
the discharge.

6.2.1.6. Freeboard of the canal


The term freeboard refers to the vertical distance between the top of the channel and the design
flow at a normal depth. The purpose of freeboard is to prevent the overtopping of either the
lining or the top of the channel fluctuation in the water surface caused by
 Wind driven waves
 Tidal action
 Hydraulic jumps

February,2017 OWWDSE Page 129


Design of the Irrigation and Drainage system MWI&E

 Super elevation of the water surface as the flow goes round curves at high velocity
 The intercept of storm runoff by the channel
 The occurrence of greater than the design depths of flow caused by the canal
sedimentation
 Temporary mis-operation of the canal system
There is no universal accepted role of the determination of freeboard since waves, unsteady flow
condition, curves, etc .influence the freeboard. The freeboard varying from less than 5% to 30%
of the depth is commonly used in design
Table ; the Freeboard recommended by USBR for channel

NO Q (m3/Sec) Freeboard Fb (M)

1 < 0.75 0.45

2 0.75-1.5 0.60

3 1.5-85 0.75

4 >85 0.90

In general the normal freeboard is 15cm for small canals and may range upto 1m for large canals
and in the case phase IIA project the following freeboard was recommended in the design
considering the practical condition.

Table : discharge versus freeboard of main canals design of chewaka

NO Q (m3/Sec) Freeboard Fb (M)

1 26-8.5 0.75

2 8.34-7.69 0.70

3 5.92-3.92 0.60

4 3.9-2.76 0.55

5 < 2.69 0.50

6.2.1.7. Design of Channel Bed Width and Water Depth


Various methods of irrigation channel design are practiced to estimate the channel bed width and
water depth , applying a flow resistance equation that correlates the geometrical elements of the
channel cross-section , longitudinal bed slope and permits that reflect the resistance channel

February,2017 OWWDSE Page 130


Design of the Irrigation and Drainage system MWI&E

friction using the combination of the above mentioned hydraulic parameters canal cross-section
design are determined.

6.2.1.8. Design of Berm Width


Berms along earthen canal are usually provided to reduce bank loads which may cause sloughing
of earth into the canal section and to lower the elevation of the service road for easier
maintenance. The following practice is recommended:

a) When the full supply level is above ground level but the bed is below ground level, berm is
important.

In the case of Arjo-Dhidhessa phase IIA project when OGL is below the canal bed level and
water depth is below 3m the berm is not required but when OGL is above bed level and the
depth of water is above 3 m berm is required and usually its width is 2.5 m. And if the depth is
increasing due to higher OGL another berm width given as additional between 1-1.5 m.

6.2.1.9. Design of Canal Bank


The primary purpose of banks is to retain water. They can be used as a means of communication
and as inspection paths. They should wide enough, so that a minimum cover of 0.50 m is
available above the saturation line. For large canals usually give 1-1.5 m.

6.2.1.10. Curvature of the canal


The allowable curvature for unlined canals depends on the size or capacity, velocity, soil and
canal section. A small canal, 0.60m3 /s or less in capacity, flowing at low velocity 0.65 m/s or
less will require only a very small radius of curvature. A large canal, 70 m3/s or more in capacity
will require much larger radius regardless of the velocity. A suggested rule is that the radius of
the canal centre line should be from 3T to &T where T is the top width of the water surface (the
larger ratios for the larger capacities), depending upon the size or capacity of the canal, the soil
characteristics, and the velocity.
Table : General criteria of canal parameter for PC, SC, Tc, TD, CD,

Parameter Unit Qty Remark

Maximum velocity M/sec 0.6

Minimum Velocity M/Sec 0.27

February,2017 OWWDSE Page 131


Design of the Irrigation and Drainage system MWI&E

Manning roughness - 0.025-0.03


Coefficient

Minimum bottom Width M 0.3

Minimum Crust width M 0.65

Minimum Fb M 0.25

Maximum Attractive N/mm2 40


force

Head from MC to PC M 0.30-0.50

Head from MCtoSC M 0.20

Head from Sc to TC M 0.20-0.15

Head from TC to FC m 0.15

6.2.2. Design of lined canal section


Though lining material will be decided further the design criteria discussed is concrete lining
material. Concrete lined canals are usually designed with a ratio of base width to water depth of
from 1 to 2. Small canals normally have a ratio of nearly 1, while the ratio for large canals may
exceed 2. The steepest satisfactory side slopes for most large canals from both construction and
maintenance considerations are 1:1 to ½:1. However, from experience of other project a side
slope of 1.5:1 can be recommended uniformly. The velocity for lined canal ranges from 2m/s to
2.5m/s. see the above table 34. When the velocity exceeds 2.5m/s energy dissipation mechanisms
is required. Recommended values of Manning roughness coefficient for concrete lining type
ranges from 0.011-0.018. The lining thickness depends on the type of lining and size of the
canal. Accordingly, concrete canal needs a minimum lining thickness of 45mm.

6.2.3. Working Head in Gravity Irrigation System


While planning and designing for the layout of the canal system the fixation of full supply levels
(FSL) in different components of the canal system has to be provided with working head as
follows.

February,2017 OWWDSE Page 132


Design of the Irrigation and Drainage system MWI&E

Sufficient working head should be provided between the proposed FSL of different canals.
Hence, the canals can take water from one other under gravity. Accordingly, head from field
canal to field, from tertiary canal to field canal and from secondary canal to tertiary canal is
15cm while head from primary canal/ main canal to secondary canal is 30cm to 50cm. see the
above table 29

6.2.4. Design of Canal Structures Criteria


Many different types of canal structures are required in an irrigation and drainage system. In
order to convey effectively and efficiently, regulate, and measure the canal discharge and protect
the canal from runoff structures are very important. The canal structures can be dividing into
conveyance and regulating structures.

6.2.4.1. The hydraulic design of irrigation structures criteria


The hydraulic design aspect of all hydraulic structures will have two major sections; surface
hydraulic and sub surface hydraulic. In surface hydraulic head losses, depth of scour, alignment
and fluming have to be considered.
Head loss
In design hydraulic structures for surface flow, the design should predict the most reliable type
of flow profile in the vicinity of structures and shall select the appropriate type to fit within the
available head loss. There are different types head loss like head loss across flat gates, head loss
across box culvert, inlet loss, outlet loss, friction loss, and head loss due to trash ark, head loss
due to change flow, etc. Different formulas of head loss have to be considered according to the
type of structures.
Example
Head loss across the flat gates
Q= CdA(2gh)^0.5
Where Q= discharge inm3/sec
Cd= discharge coefficient=0.62
A= area of opening(m2)
G= acceleration due to gravity (m2)
H= Operating head (M)
Depth of scour

February,2017 OWWDSE Page 133


Design of the Irrigation and Drainage system MWI&E

The scour depends upon the type and size of bed material. the scour in alluvial sand deposit
material should be estimated by lacey‟s formula indicated as the following
R= 1.35 (q2/f)^1/3
Where, R= Normal scour depth in M below the maximum flood level
. q= design flood discharge per unit width in m3/sec at the point of consideration
F= Lacy „s silt factor corresponding to the bed material at sites given by
F= 1.76 (d)^1/2 , where d is the mean diameter of the soil particle in mm upto possible
scour depth.
Alignment and fluming: as much as possible the structure should be align at right angle to the
canals and generally there should be not any reduction in the cross sectional area or at the canal
structure. The structure should design to have free flow as it reduces head losses at the entry of
barrel and exit.
In sub surface hydraulics like piping, exit gradient, uplift will be considered during the structure
design and it should be safe against this problem.
The exit gradient is computed by the formula

GE = H/d *1/

Where GE = safe Exit gradient

H = Maximum static Head

= HFL - downstream floor level

d = depth of downstream cut off below downstream floor level

 = another variable defined as = 1+ (1+α2 )^0.5

α = b/d

b = Total floor length of the regulator

The following factors of safety as recommended by Is: 6531 - 1972 may be adopted for various
types of soils

Shingle 4 to 5

Coarse sand 5 to 6

February,2017 OWWDSE Page 134


Design of the Irrigation and Drainage system MWI&E

Fine Sand 6 to 7

Since GE , H and d are known, the value of factor 1/ can be computed from the formula.
Corresponding to this value of 1/, value of α should be read from Khosla's exit gradient
curves. Alternatively the value of α can also be computed from the formula ={1+ (1+α2
)^0.5}/2 .As the value of d is known ,length of impervious floor can be computed . Having
computed the minimum value of „b‟ the total length of floor is decided from the considerations
of over all layout of structure, e.g., for accommodating piers, etc. Value of exit gradient provided
is again read with the help of curve.

Out of the total floor length as obtained above , the downstream floor length may be provided
according to hydraulic considerations. The rest may be provided on the upstream side of the
crest. Providing minimum floor length downstream of the crest from hydraulic considerations
leads to economical design.

Hydraulic jump and energy dissipation


Hydraulic jump is the jump of water that takes place when super critical flow changes into sub
critical flow. In irrigation structures sometimes in some structures can be happen like on drop
and inclined structures. Fraud number gives (f) gives the intensity (strength) of the jump
expected
F=V/(gd)^0.5
Where, F- fraud number, V= velocity of flow, d= depth of flow
For flows on inclined drops the sequent depth (height of jump) can be estimated
Y1= Y1/2(1+8f2)0.5- 1)
Where, Y2= height of jump
Y1= depth of flow before jump
F= fraud number before jump
Based the above formula appropriate energy dissipation structures will be selected

6.2.4.2 The structural design consideration


All structures should be checked for the stability and stress condition. The major factors involved
are the loads, construction materials, and the required factor of safety to be adopted
All the construction materials like masonry, concrete, steel and timbers have to be properly
selected.

February,2017 OWWDSE Page 135


Design of the Irrigation and Drainage system MWI&E

All loads like self weight, earth pressure, water pressure, imposed live loads, imposed dead loads
will be considered.
Both structural and hydraulically design involve.
 The loads which the structure may carry from time to time.
 How these load arecombined together and interact.
 The material of which structure is made and their strength and behavior
under load.

6.2.4.3 Factor of safety and design parameters


The following table shows assumption made in the design of structures.
The factor of safety (the ratio between stabilizing to destabilizing should be at least 1.3 for long
term stability requirement of the structure.

Table : Unit weight of material

NO Dead loads Weight (KN/M3)


1 Water 10
2 Stone masonry 21
3 Brick masonry 21
4 Mass concrete 24
5 Reinforced concrete 25
6 steel 78.5
7 Dry back fill 16.0
8 Saturated back fill 20
9 Submerged back fill 10.2
10 Dry compacted back fill 18.5
11 Saturated compacted back fill 21.5
12 Submerged back fill 11.7

February,2017 OWWDSE Page 136


Design of the Irrigation and Drainage system MWI&E

Table : Internal angle of (ɸ) of the soil

Soil type (ɸ)


Gravel 40º-55º
Sandy gravel 35º-50º
Sandy loose 28º-34º
dense 34º-45º
Silt, silty sand loose 20º-22º
Silt, silty sand dense 25º-30º

Table : allowable bearing capacity

Soil type Allowable bearing pressure KN/m2


Soft clay and silts <80
Firm clay and firm sandy clay 100
Stiff clay and stiff sandy clays 200
Very stiff boulders clay 350
Loose well graded sands and gravel/sand 100
mixture
Compact well graded sands and gravel 200
Loose uniform sands <100
Compact uniform sands 150
Table : permissible concrete structure

oncrete Compressive Compressive Maximum Permissible Permissible stress in


stress Fcc stress Fcbc shear stress in bond bond for
(direct (bending) stress qc for deformed(average)
)(N/mm2) )(N/mm2) max( plan(average) (N/mm2)
N/MM2) (N/mm2)
grade mix
M10 1;3;6 2.5 3 - 0.4 0.56
M15 1;2;5 4.0 5 1.6 0.6 0.84
M20 1:1.5:3 5.0 7 1.8 0.8 1.12
M25 1:1:2 6.0 8.5 1.9 0/9 1.26

February,2017 OWWDSE Page 137


Design of the Irrigation and Drainage system MWI&E

Table : permissible Reinforcing steel stresses

Stress Condition Permissible stress (N/mm2)


Mild steel High yields strength
deformed bars
1 Tension Pst
1.1 Bars up to 25mm 140 230
1.2 Bars over 25mm 130 230
2 Compression in column
2.1 All Bars sizes 130 130
2.2 Stirrups reinforcement 140 175

Table : constant for design section

Grade of concrete Steel stresses


Pst= 140N/mm2 Pst= 230N/mm2
R J R J
M15 0.87 0.87 0.65 0.904
M20 1.21 0.87 0.91 0.904
M25 1.47 0..87 1.11 0.904
Note= R=A factor related to the concrete and steel permissible stress.
J= liver arm factor.
The allowable stress for cement masonry is 0.7N/mm2 and tensile stress is 0.
The hydraulic and structural analysis should be done for both regulating and conveyance
structures along the canals. As per the size of the canal structures detail data given by hydrologist
on the flood magnitude different years of return period will be considered. Internal and external
load will be considered. Based on geo-technical report the project area is not seismic area so that
for the canal structures it will not be considered.
It should be checked, against sliding, overturning, over stressing by giving enough safety factor.
In the canal structures design like cross drainage, flumes, siphon, foot bridge along the main
canals the following main parameters were considered. Drainage water discharge will be
considered as per the hydrologist recommendation. The bearing capacity of the foundation of the
soil also considered based on the geotechnical recommendation.

February,2017 OWWDSE Page 138


Design of the Irrigation and Drainage system MWI&E

All structures design of beam, slab, walls, abutment and foundation for allowable design criteria
should be checked.

6.2.4.4. On-Farm Structures


Canal structures in the farms for primary, secondary and tertiary canals like division box drop off
take, cross drainage, culvert siphon will be worked according the well known standard given in
the typical drawings prepared template. It will follow the same above principle of hydraulic and
structural analysis.

6.2.4.4.1 Proportional flow distribution

Flow of a canal can be distributed in to smaller branches using a variety of structures which have
been developed to suit a wide variety of conditions. The flow being diverted in to each branch is
usually defined as a proportion of the total flow. Thus, these flow distributing structures differ
from the flow regulating structures since the latter are designed to draw off any amount of
discharge irrespective of the flow in the parent channel. The flow distributing structures require
a control section in both the off-take channel and in the parent channel. Flow distributors of fixed
proportion type are generally used.

February,2017 OWWDSE Page 139


Design of the Irrigation and Drainage system MWI&E

Figure proportional off take with one off take on left side, one of take with right side , and off take on either
side

6.2.4.4.2 Drop structure


There are two main types of drops. They are vertical type drops and inclined drop type. In
selecting a type of drop most suitable for a particular site, the main consideration is the height of
the drop and the discharge passing over the drop or in other words the amount of energy to be
dissipated downstream of drop. The type which dissipates this energy most satisfactorily is to be
preferred.

In cases where full dissipation of energy does not take place on the masonry structure of the
drop, the issuing jet has still got higher bed velocity than what soil can with stand. In such cases
a baffle design, though costly in construction may prove economical in the long run, from the
maintenance point of view. Where bed material is hard enough to withstand scouring action of
the strong current, the type of design that is just enough to dissipate the surplus energy should be
adopted.

February,2017 OWWDSE Page 140


Design of the Irrigation and Drainage system MWI&E

Design of a drop envisages the following aspects:-

 It should be cheap in initial cost


 Recurring expenditure on maintenance and repairs should be minimum
 A limited amount of harmless scour may be tolerated
 The design should work under 10 percent retrogression, if it were to occur
 It should be capable of being used as a meter

6.2.5. Design of Night Storage Pond Criteria


The purpose of night storage ponds are to store water during night time from the canals pumped
by pump and to deliver to the canals through designed outlet structures to the distribution system
and farmer fields. The night storage ponds will be designed under left lifted blocks of NO 1, 5
and 6. The designed will be based on to serve the size of the command area on the maximum
crop water requirement. Based on the size of reservoir inlet, outlet structures and freeboard will
be considered. Relative bed level, full supply level of the canal, the field and night storage will
be considered.
In night storage pond design the following main parameters will be considered like the irrigation
water duty at the pond level 2.095lit/sec/ha at 12 hours and others factors.
To determine the pond size Phreatic line in the embankment of night storage pond should be
clearly determined and it gives a divide line between dry and submerged soil it does not cut the
downstream face of the embankment in homogeneous soil but in our design geo-membrane will
be considered and this will not be considered. Based on the type of embankment soil, and water
pressure stability of the embankment will be checked.

6.2.6. Design of the Drainage System


Irrigation and drainage for successful crop production is the development and maintenance of an
environment in the plant root zone in which, soil moisture (water), oxygen, and salt balance is
favorable for plant growth. The excess soil moisture (water logging condition) creates hindrance
for timely farm operations and affects crop growth because of deficient aeration.

Agricultural drainage criteria are therefore defined as criteria specifying the highest permissible
levels of the water table on or in the soil so that the agricultural benefits are not reduced by
problems of water logging.

February,2017 OWWDSE Page 141


Design of the Irrigation and Drainage system MWI&E

Drainage problems are occurred due to excessive precipitation, irrigation water, and excess water
for leaching salts.Adequate artificial drainage surface to maintain water and salt balance
favorable for optimum production is therefore essential.

As per recommendation given by soil survey and hydro-geologist for the problem of water
logging after irrigation can be avoided with simple surface drainage system. The previous studies
of the project area and experiences of other irrigation development of the same nature project are
considered mostly. As per the recommendation of phase IIA hydrological study, for the drainage
system reported that 4.24 li/sec/ha of duty has been determined 1 in 5 years of return period of
24 hours of storm rainfall. All the drainage canals like TD, SD, and CD will be designed with
drainage water duty of 4.6lit/sec/ha. To be in the safe side for Chewaka project 4.6lit/sec/ha duty
is considered in the design of the drainage duty. And as per recommendation given no sub
surface drainage system will be required.

The drainage canal design criteria are the same as with canal system water conveyance based on
the given duty.that is using continuity and manning formula. ID capacity should be design for
1in 10 years , structeres on ID it should design 1 in 25 years and 1 in 50 years of 24 hours
rainfall storm runoff are used based on the catchement size and structure size on the flood
magnitude given by hydrologist.As the size of the number of field drain increasing the TD, SD,
and CD of the canal dimensions are increasing.

All FD, TD, SD, and, CD, will be designed based on the size of the area in Ha serving. In case
of phase IIA field drain (FDs) collect water from the command area plots based on water duty
of 4.6lit/sec/ha at the end of the furrow then supply to tertiary drain (TD) and tertiary drains
collect water from FDs supply water to Secondary drain (SD) and all secondary drains supply to
collective drain (CD) or natural drain.

Table : Drainage system of water duty versus years of return period

36.6mm / (3*24*3600) *10000 = 4.237 L/s/ha 4.237 


Return Amount of disposal in days
Period 1 2 3 4 5 7
5 4.24 2.12 1.41 1.06 0.85 0.61
10 5.35 2.67 1.78 1.34 1.07 0.76
25 6.82 3.41 2.27 1.71 1.36 0.97

February,2017 OWWDSE Page 142


Design of the Irrigation and Drainage system MWI&E

50 7.96 3.98 2.65 1.99 1.59 1.14


100 9.11 4.55 3.04 2.28 1.82 1.30
Source: Climate and hydrological draft report of Chewaka project, OWWDSE, 2016

6.2.7. Design criteria for Road network system


In the project of Irrigation and drainage system road networks will be designed to facilitate all
the irrigation water management operation and agricultural activities including inputs and
outputs management.

Road network design will be considered all main, secondary, tertiary and field roads along main
canals, secondary, tertiary and field canals, collective, secondary and tertiary drain of the
irrigation and drainage system respectively. Gravel pavement are generally used for roads where
the design of traffic flow i.e the Annual Average Daily Traffic (AADT) is less than 200 based on
ERA‟s pavement design manual. The performance of the gravel surface mainly depends up on
material quality, location of the road and volume of traffic using the road. The detail road
network designed to should considered , land cover and land use, climate (rain fall and
temperature, geology, and topography condition.

6.2.8. Irrigation Methods in Water Distribution System criteria

There are three major types of irrigation methods. These are Surface irrigation, Sprinkler or
overhead irrigation, and Drip or trickle irrigation.Each method has certain limitations but most of
the methods can be adapted to a fairly wide range of conditions. In following section each
method will be described with advantage and disadvantage to select the best method for the
project.

6.2.8.1. Surface Irrigation system.

Surface Irrigation refers to direct irrigation water to irrigation fields by gravity allowing water to
over the soil surface from a supply of channel at the upper reach of a channel. It is the dominant
and widely practiced method of irrigation, which accounts for about 95% of irrigation system
worldwide has been used for 1000 years to irrigate a wide range of crops on different soil types.
This method practices in Ethiopia is considered as the most dominant irrigation methods being
used among subsistence farmers .and even state owned irrigated commercial farmers. The main
advantages are:

February,2017 OWWDSE Page 143


Design of the Irrigation and Drainage system MWI&E

 Well suited to economic condition of farmers.


 Efficiency of surface irrigation is in the hands of farmers
 The maintenance of the system is less problematic no especial material
required can be done locally by the farmers

The main disadvantages are compare to other irrigation system is results in higher water
looses.Under surface irrigation system there are various water distribution and application
methos can be used .

6.2.8.2. Sprinkler Irrigation system.

Sprinkler irrigation refers to the application of irrigation water under pressure in which water is
sprinkled into the form of spray or simulating artificial rain. This is achieved by distributing
water over head of perforated pipe lines to various types of sprinkler head or nozzles fitted to a
riser attached to the system or pipes laid on the ground and spray water from the above on the
crops. Nozzles are fixed type or rotating type. Sprinkler irrigation is used on approximately 5%
of the irrigation land throughout the world.

The main advantages are;

 The systems are good for water management practices


 It is independent on the variables soils, topography,
 Uniform distribution of water in the field with high water efficiency
except wind
 Accurate measurement of applied water
 Less interference with subsequent farming

The limitations are the following

 High capital investment for initial investment


 Operating cost is high due to cost of energy.
 It needs high technical person for operating and maintenance
 Clean water required in order to avoid clogging
 Sensitive to the wind it distort uniform distribution

February,2017 OWWDSE Page 144


Design of the Irrigation and Drainage system MWI&E

 Not suitable for rice


 Not suitable heavy clay soil

6.2.8.3. Drip Irrigation system.

Drip irrigation is sometimes called trickle irrigation , refers to the application of water in the soil
at slow rate just drip by drip but frequent and with precise condition through a small sized called
emitters located at or just above ground level (upto 300mm) and above ground level directly to
the soil surface to irrigate a limited area around each plant . The system suited of high
temperature and limited water resource of high water costs. This irrigation system is recently
developed in the last 30 years. The irrigation system is used over the world wide under 0.1%.

The main advantages are:

 More uniform distribution of water can be obtained


 More efficient of use of available water (90-95%)
 Reduced cost for fertilizer and other chemical application.
 Low labor operating required
 Low energy required as compared to sprinkler
 Possible utilization of saline water
 Possibility of using marginal land soils shallow depth

The main advantages are;

 Installation cost is high particularly for installation drip system


 Required more skilled labour in design and project management
 Possibility of clogging of emitters and laterals blockage

6.2.8.4 Selecting the best Irrigation method

There are a large number of considerations which must be taken in to account in the selection of
an irrigation system. i.e. each method is applicable to a particular set of conditions; none can be
used successfully under all conditions. Selection of irrigation methods is based on compatibility,
economic considerations, topographic limitations,soil characteristics, water supply, crop factors,
and external influences.

February,2017 OWWDSE Page 145


Design of the Irrigation and Drainage system MWI&E

Due to the topographic condition of the area considering most of the command area‟s slope is
high and undulating nature it seems overhead or sprinkler irrigation is better than surface and
drip irrigation system But, considering the above different advantages and disadvantages of
each system the sprinkler or overhead irrigation system will not be appropriate due to high
technical capacity requirement and the initial investment cost is high considering the irrigation
scheme of phase IIA project is intended to the farmers. And most of soil nature of the command
are is dominated by silt clay to clay soil nature and some crops like rice also common in the area.
Hence, surface irrigation sytem was considered for this particular project for the area both
under left gravity and lifted blocks of command area.

6.2.8.5 Surface Irrigation Methods of water distribution


Two general requirements are of prime importance to obtain high efficiency in surface methods
of irrigation; properly constructed water distribution system to provide adequate control of water
to the fields and proper land preparation to facilitate uniform distribution. In surface irrigation
water may be supplied to the crops with five methods in free flooding, border flooding, check
flooding, and basin flooding and furrow systems.

Free flooding: In this method ditches are excavated in the field and may be either in the contour,
or upward and downward slopes. Water from these ditches flow across the field. After the water
leaves the ditch no attempts is made to control the water. Wild flooding is most suitable for close
growing crops , pastures etc particularly where the land is steep.

Check flooding: Check flooding is similar to ordinary flooding except that of the water is
controlled by surrounding the area with low and flat levels. Levels are constructed along the
contour having a vertical interval

Border flooding: in this method the land is divided into a number strips separated by low levels
called borders. The land area confine in each strip of the order 10 m to 20 m in width and 100 m
to 400 m in length. This method is suitable for more permeable soils as well as less permeable
soil.

Basin flooding: This method is a special types of check flooding and is adopted for orchard trees
one or more trees are generally placed in the basin.

February,2017 OWWDSE Page 146


Design of the Irrigation and Drainage system MWI&E

Furrow irrigation method: In the above flooding methods water covers the entire surface whereas
in furrow methods water cover one-fifth to one –half of the land surface. Furrow is narrow field
ditch excavated between row of plants and carry irrigation water through them.

There are different factors to be taken in consideration in selecting appropriate irrigation


methods some the factors are listed as the following

 Types of crop grown


 Soil characteristics the land to be irrigated
 Topography of the land.
 Available source of water
 Amount of water applied during irrigation
 Depth of water table
 Length of run and time required for wetting
 Labor requirement and availability

As per the agronomist recommendation in phase IIA project there are 13 kinds of crops are
recommend. These crops recommended are banana, maize, rice, mango, groundnut, pepper,
soybean, sugarcane, tomato, onion, sesame, H. cabbage, pasture. Considering these crops two
methods of furrow and basin types are selected for water application of this project.

Furrow irrigation is used for all row crops except rice for all types of soil even if the labor
requirement is high.

Basin method also used for all types of crops including rice and the labor requirement is low but
not using for undulating topography nature but rice is grown by local farmers in most of flat area.
Therefore, farmers can use basin method for rice.

As mentioned above, the furrow method of irrigation shall be most widely used in the project
command area as it is most suitable method and easily applicable it will be explained as the
following.

 Furrow Irrigation

Furrow irrigation is the most widely used method worldwide for irrigating purpose. In furrow
irrigation, water no longer flows over the entire soil surface but is confined to small channels

February,2017 OWWDSE Page 147


Design of the Irrigation and Drainage system MWI&E

(furrows) between the crop rows. It is then gradually absorbed into the bottom and sides of the
furrow to wet the soil. Permit less evaporation.

Furrow Spacing

A furrow spacing of 1.2 m is used for sugarcane. This spacing is possible from the wetting
pattern of clay soil.

Furrow shape

Furrows are usually V-shaped. The width of furrow depends on stream size, soil and crop types.
In general, a top width of 300 mm and depth of 100 mm is practical.
Furrow length

Furrow length depends on several factors such as soil type, stream size, irrigation depth and
slope. From experience of different projects a furrow length of 200 m can be used. However, it
can be limited by size and shape of the field and ranges from 45m to 300m.
Table : suggested furrow length for different soil type

Slope Maximum Clay Loam Sand


(%) stream size
Average irrigation depth (mm)
(l/s)
75 150 75 100 150 50 75 100

0.05 3.0 300 400 120 270 400 60 90 150


0.1 3.0 340 440 180 340 440 90 120 190
0.2 2.5 370 470 220 370 470 120 190 250
0.3 2.0 400 500 280 400 500 150 220 280
0.5 1.2 400 500 280 370 470 120 190 250
1.0 0.6 280 400 250 300 370 90 150 190
1.5 0.5 250 340 220 280 340 80 120 190
2.0 0.3 220 270 180 250 300 60 90 150

(Source: Training Manual on Irrigation Planning and Design, Volume-II, Ministry of


Agriculture, Addis Ababa, January 1995)

The average depth of water applied during irrigation can be calculated from the following
relationship:
q * 360 * t
d =
w* L
Where; d: average depth of water applied, cm
q: stream size, l/s

February,2017 OWWDSE Page 148


Design of the Irrigation and Drainage system MWI&E

t: duration of irrigation (elapsed time), hours


w: furrow spacing, m
L: furrow length, m
Therefore, Table below shows values derived from the above relation:
Table : Average depth of water that can be applied on different slopes

Furrow length = 200m Furrow spacing = 1.0m


Slope (%) 0.5 1 1.5 1.8 2 2.2 2.5 2.75 3 3.25 3.5
qm (l/s) 1.2 0.60 0.40 0.33 0.30 0.27 0.24 0.22 0.20 0.18 0.17
d(cm) 51.84 25.9 17.3 14.4 13.0 11.8 10.4 9.4 8.6 8.0 7.4
Source: Upper Arjo Design and study document,OWWDSE,2014

Thus, for furrows adjacent to the natural drains having slope of 2 to 3% by reducing the stream
flow, the efficiency can be optimized. Furrow sizes and stream sizes can be easily selected in the
field accordingly for the given slopes.
Furrow stream size

The maximum non-erosive furrow stream size can be determined from equation:
Qm = 0.6lit/S
Where: Qm = maximum non-erosive stream, l/s

S = slope of furrow expressed as a per cent.

The stream size is usually between 0.2 and 5.0 l/s. The slope of furrow is usually level (0 - 1%).
A minimum furrow grade of 0.05% is needed to ensure surface drainage.

February,2017 OWWDSE Page 149


Design of the Irrigation and Drainage system MWI&E

Figure : photo of furrow system directly from the field canal

6.2.8.6. Supply system


Siphons can be used to take water from quaternary canal to furrow. They are good for water
management. Here, depending on the type of quaternary canal there can also be an orifice outlet
to the furrow and the detail design will be given. Siphon tubes can be used to take out water from
a quaternary canal and distribute in the field through furrows/corrugations or even to smaller
channels. These tubes are generally portable, made of aluminium, plastic or rubber. These are
usually shaped to fit into half cross section of the head/field canals (The normal diameter ranges
from 2.5 to 7.5cm). Practically all sizes from small to large sizes are available in various lengths.
Flow at the end of the farm is stopped down wards by a simple bag filled with soil or by
providing a gate in the cross wall. In case where hydro-flume is used for quaternary canal, there
is no need of using siphons.

February,2017 OWWDSE Page 150


Design of the Irrigation and Drainage system MWI&E

6.2.8.6.1. Equipment for Irrigating Straight Furrows

Flow monitoring devices are most essential to release desired flow rate in each straight furrow.

 Siphon Tubes has the following advantages


 Equalizers should be constructed to get at least 10 cm driving head
for the siphon tubes,
 Easy to operate during day time.
 Low Cost
 Measured quantity of water can be given at the desired frequency
 Irrigation efficiency (water application efficiency )would be 85-90%
Siphon tubes can also be used to take out water from a field channel or head ditch and irrigate
the fields. These tubes are generally portable, made of aluminium, plastic, or rubber. These are
usually shaped to fit into half cross section of the head/field canals. The normal diameter ranges
from 2.5 cm to 15 cm. Practically, all sizes from small to large are available in various lengths.
The smaller sizes are used with furrows corrugation and the larger sizes with borders. Siphon
tubes have very low initial cost, easy and quick in installation to irrigate a given area. Flow into
individual furrows or borders can be controlled effectively by using the number of tubes that will
divide the total head ditch flow into individual streams of the desired size. Many tubes may be
used in the fields with little cross slope in order to maintain a near constant operating head on
each tube.
The discharge of a siphon tube depends on:-
 The water head,
 The length & diameter of the tube,
 Head loss depending on the roughness of the inside surface and number &
degree of bends in the tube.

Figure : furrow method of irrigation using siphons

February,2017 OWWDSE Page 151


Design of the Irrigation and Drainage system MWI&E

Figure : method of siphon flow in furrow

6.2.9. Water application at the field


To calculate how much water can be stored in particular soil and made available for use by the
crop, it is necessary to consider the depth of soil from which plant roots can draw water this is
called root depth (D) when the soil is at field capacity, the plant can extract water slowly to
maintain the maximum rate of evapo-transpiration. This is the freely available soil moisture can
defined as the fraction ( P) to which the total available soil moisture can be depleted without
causing evapo-transpiration to drop.

𝑃.𝑠𝑎𝑚𝑚 /𝑚 ∗𝐷𝑚
Depth of application (dmm)= 𝐸𝑎 (𝑎𝑝𝑝𝑙𝑖𝑐𝑎𝑡𝑖𝑜𝑛 )

Where P.sa= readily available soil moisture. In mm/m for heavy textured soil the agronomies
study recommend 180mm/m

Ea = application efficiency= 60% for surface irrigation

February,2017 OWWDSE Page 152


Design of the Irrigation and Drainage system MWI&E

Dm= Rooting depth in meter

Kc= Crop coefficient

Etcrop mm/day= Kc*Etomm/day

NIRmm/day = ETcropmm/day- Re mm/day, where NIR= net irrigation requirement, ET crop =


evapo-transpiration of the crop and Re= effective rainfall.
𝑃.𝑆𝑎𝑚𝑚 /𝑚 ∗𝐷𝑚
I days (irrigation interval)= 𝑁𝐼𝑅𝑚𝑚 /𝑑𝑎𝑦

𝐴𝑟𝑒𝑎 𝑚2 ∗𝑑𝑒𝑝𝑡 ℎ 𝑜𝑓 𝑎𝑝𝑝𝑙𝑖𝑐𝑎𝑡𝑖𝑜𝑛


Qm3/sec = 𝐼𝑑𝑎𝑦𝑠 ∗𝑡𝑖𝑚𝑒 𝑜𝑓 𝑎𝑝𝑝𝑙𝑖𝑐𝑎𝑡𝑖𝑜𝑛

6.3. Design of Irrigation and Drainage System


In this part of irrigation and drainage system of design, brief description of hydrology,
agronomy, geo-technical, soil and others sectors study and general system layout of the
command area will be discussed before designing of all irrigation and drainage of canals and
structures required for the project as per design criteria given in the above section.

6.3.1. Description of phase IIAproject command area


Phase IIA command area is found 420 km far from Addisababa /finfine capital city of
Ethiopia/Oromiya it has allweather roads and out of which asphalt part is 390 km from Addis
ababa via to Nekemte and bend to the left side after Arjo Gudetu town on the way of Gimbe road
near Efreme Hotel. It has also 30km all weather gravel road after bending to the left side from
the asphalt road down to Efreme Hotel. The command area is bounded by Dabena River from the
west and north, and Chamen kebele from south and Dhidhessa River from the east and by
series of natural drainage channels, which join the main Dhidhessa river. The command area has
26 kebeles under Chewaka district, Illubabore zone of Oromia National Regional State. The area
is resident by the people came from East Harerge and west Haraerghe zone during the severe
draught happened in the year1997 in Ethiopia.

In the command area there are different crops of varieties are grown by the farmers from the
grain like maize, sorghum, soybean, rice, sesame and from vegetables and fruits tomato, onion,
head cabbage, beetroot , carrot and banana and papaya are the major. Based on the detail
agronomical study in the future irrigation scheme the proposed crops are maize, rice, sesame,
soybean, mango, banana, sugarcane, groundnut, pepper, tomato, onion, head cabbage and pasture
were recommended.

February,2017 OWWDSE Page 153


Design of the Irrigation and Drainage system MWI&E

Figure : photo of proposed command area of phase IIA /Chewaka

6.3.2. Geotechnical,hydrogeology , Hydrology, Soil and Land Suitability


Description of the Area
According to geotechnical report main cannel route is characterized by the bed rock unit and
unconsolidated soil overburden material. The soil overburden deposits along main canal route
are dominantly stiff to very stiff reddish brown to dark brown silty CLAY to Clayey SILT in
texture. Sand, gravel cobble and boulder are encountered commonly along stream beds and
banks.

The silty clay to clayey silt soil material is of poor hydraulic conductivity that would not cause
excess leakage. Consequently, lining is unlikely at such sites. However, at chain-ages
characterised by the fractured, highly weathered and decomposed bed rock units are pervious
that can cause excess leakage. As per the study 0-10km of canal route it has poor hydraulic
conductivity lining not required, from 10-46km fractured and weathered bed rock it is pervious
causes excess leakage it is recommended lining and from 56 to the end the canal route material is
reddish brown silt clay underlain by decomposed bed rock and it has poor hydraulic conductivity
lining is not required.Chain age along proposed main canal recommended for provision of
Lining is CH. 15 – 46 kms most drainage crossings sites are found being characterized by sound
bed rock unit.

In hydrological study of the project irrigation command area is dominantly characterized by


undulating land mass with small hills dispersed in the command area. The valley cuts and

February,2017 OWWDSE Page 154


Design of the Irrigation and Drainage system MWI&E

massive basement rock units charactering the site would enhance run off rather than infiltration
that would inhibit recharge to ground water. The contribution of groundwater recharge from the
application of irrigation would be very low. Another factor that can reduce the contribution of
irrigation application to groundwater recharge is the presence of several creeks that are
transversal to the trend of the command area. Its final recommendation is the expected Water
logging in the relative plain land characterized by silty clay soil of low hydraulic conductivity
can be prevented among others by providing an effective drainage system. Such drains could be
open or closed. Concerning the problem of salinity the high rate of precipitation (rainfall) in the
area can counteract the problem by leaching the highly soluble salts such as chlorides, sulphates
and carbonate salts.

Concerning the climate in the area, the average annual rainfall is estimated about 1564.56mm the
average monthly minimum temperature is 15.2Cand maximum temperature is 31.3C and its
average altitude above sea level is 1216 m. The command area has between the contour elevation
1310 and 1165 m from both lifted and gravity system.

The General topographic of the area is undulating with many drainage lines, gullies, outcropping
mountains, slanted lands, marshy areas, pasture areas, village settlers, small farm roads, rivers,
and plain farm lands. It has different slopes with 1% to 16%. , see the detail in the table38& 39

Therefore based on the above table 90% the command area of the soil is dominated by three
types of soil like Nitisols, Lixisols,and cambisols. This mean the command area of soil‟s
physical and chemical characteristics almost depends on these types of soil as per the study
conducted.

Table : type of Major soils of the command area

No Types of soil % of area Cumulative

1 Nitisols 53.67 53.67

2 Lixisols 26.57 80.24

3 Cambisols 11.14 91.38

4 Vertisols 3.513 94.89

February,2017 OWWDSE Page 155


Design of the Irrigation and Drainage system MWI&E

No Types of soil % of area Cumulative

5 Acrisols 0.568 95.461

6 Leptosols 0.105 95.566

7 Flovisols 0.05 95.616

Source: Detail soil survey study, Nov, 2015 by OWWDS

Therefore ,based on the soil and land suitability analysis for the types of crops recommended by
the agronomist from the total gross area on the average base 48.50% is highly suitable and
suitable, 30.37% is marginally suitable and the rest 21.13% is not currently suitable and
permanently not suitable in relation to surface irrigation. The evaluation of land suitability is
based on soil depth, slope, and nutrientcontent and other factors.

Concerning land and soil suitability of the project area for surface irrigation the above
recommendation of types of soil was given S1 is very suitable, S2 is moderately suitable and S3 is
marginally suitable for different types of crops. If we only consider S1 and S2 Chewaka
command area is in general recommended for surface irrigation 48.5% of the area is good for
surface irrigation for the types of crop recommended by agronomist without any further
treatment of the soil. The rest 30.37% of the area of the command area is required some
treatment like fertilizer, crop rotation, good quality of irrigation water and other inputs. Based on
the laboratory analysis the water is very suitable for irrigation. The farmers living at phase IIA
project area had already experienced using different inputs so that they can be used the
marginally suitable land for irrigation. 21.13% of the gross area is totally rejected from the
system of irrigation. In general the soil and land suitability study given the recommendation for
the surface irrigation system of the project area for imperfectly and poorly drained soil
construction of open surface drainage system and to use good quality of water are important.
Topography of the area for irrigation phase IIA area is very rugged, hilly, it has many streams,

February,2017 OWWDSE Page 156


Design of the Irrigation and Drainage system MWI&E

Table : Crop and land suitability for surface irrigation

Source: Land suitability study, draft feasibility report of lower Dhidhessa phase IIA project, OWWDSE,
2016

February,2017 OWWDSE Page 157


Design of the Irrigation and Drainage system MWI&E

Figure : map showing soil and land suitability for irrigation

Source: soil and land suitability draft feasibility lower Dhidhessa phase IIA report, OWWDSE,2016

The hydro geological investigation also recommended that the expected water logging in the
relative plain characterized by silty clay soil of low hydrological conductivity can be prevented
by open or closed drainage system.

6.3.3. General System Layout of Design


The total command area of the project lies inside the valley of the Dhidhessa River. The major
slope of the area is from west to east direction to the center of the River. The elevation in the
command area varies between El.1310 m to 1165 m.
The command area of size of a minimum block can range from 15 – 20 ha for mechanized
farming and 4-6ha maximum for farmers based. In phase IIA project case under the left gravity
block has both gravity and lifted blocks and each block has different size of command area. Field
canal block will have (6 ha maximum and 0.13 ha minimum in rear case) command area. But
most of the area of field canal block is 2 Ha. Based on the land holding system of the phase IIA
farmers and the given cropping pattern 0.30 ha is considered as one farm unit because about 11%
of the farmers have an area of less than 0.5 Ha.

February,2017 OWWDSE Page 158


Design of the Irrigation and Drainage system MWI&E

Table : Land holding ownership of the community of the command area

No Amount of land in hectare Respondent Percent

1 <0.5 100 10.7

2 0.51-1 186 20.0

3 1.1-2 523 56.1

4 2.1-3 92 9.9

5 >3.1 4 .4

6 Not Responded 27 3.0

Total 932 100.0

Source: OWWDSE Lower Dhidhessa phase IIA Socio economy Study Household Survey Result

6.3.3.1 System Layout of Gravity and lifted blocks


The topographic of the area for gravity block, out of 5891.12Ha , 0-2 % , 2-5%, 5-8%, 8-16%
and >16 % slopes have 2.21%, 15.97%, 25.89% 43.09% and 10.53% of area size respectively.
The other part of the command area has 0.05%, 1.58%, 0.03%, 0.05% areas covered by town,
village, grave and forest respectively The gross command area is in general having undulating
topography type In system layout design the maximum slope considered under irrigation is 11-
12% considering the past experience of local farmers living at Chewaka people can work
irrigation by constructing terrace. The area above 11-12 % slope of the command area was not
considered as suitable for surface irrigation system.
There are also some isolated hills rising above the average level of the plain and very marshy
areas which actually will be excluded from irrigation suitability except some pocket area can be
used during dry season. Therefore, from gravity block of the whole total gross area 5891.12 Ha,
in system layout the net irrigable area of 3957.86 ha was considered; see the following fig 24 and
table 42.

February,2017 OWWDSE Page 159


Design of the Irrigation and Drainage system MWI&E

Figure : map showing gravity block command area with slope class

Table : slope class and area size for gravity block

No Slope class Area (Ha) percentage Remark

1 0-2 130.74 2.21

2 2-5 946.64 15.97

3 5-8 1534.09 25.89

4 8-16 2553.05 43.09

5 >16 627.23 10.53

6 Town 3.79 0.05

7 Village 93.76 1.58

9 Grave 1.82 0.03

Total 5891.12

February,2017 OWWDSE Page 160


Design of the Irrigation and Drainage system MWI&E

In phase IIA irrigation and drainage system of the project based on the proposed water
abstraction system in the addition of gravity block, lifted blocks of area is considered to irrigate
the whole recommended area of the project. For lifted block out of 12000.45Ha , 0-2 % , 2-5%,
5-8%, 8-16% and >16 % slopes have the area size of 3.87%, 27.11%, 33.03% , 24.54% and
6.54 %. The other part of command area Have 1.56%, 3.11%, 0.05% and 0.25% has town,
village, grave and (rock surface) RS respectively out of 12000.45 Ha. The following table 41 and
fig 25 are showing the suitability of the command area in relation to slope and topographic
feature of the area.For upper lifted block out of 1620.49ha it has 0-2%,2-5%, 5-8%, 8-16%, and
>16% slopes have 0.35, 17.98, 27.64, 27.65, 4.96, % respectively, and the other area is covered
by grave and village.

In the case of phase IIA the system layout has done for the gross area of 13,620.94 ha and net
area is 7368.83ha.The maximum of the slopes of the area has been considered upto 11-12%.
Since, due to the lifted head of to be determined maximum 60-65m from the gravity elevation
to lifted system and considering the slope of canal the command area by gravity system with
maximum elevation is 1310 m , and above 1310 m is considered in upper lifted blocks of area.
. See table 46 and fig 25.

February,2017 OWWDSE Page 161


Design of the Irrigation and Drainage system MWI&E

Figure : map showing lifted block command area with slope class

Table : slope class and area for lifted block

No Slope class Area (Ha) lifted percentage Upper Remark


lifted(Ha)

1 0-2 520.76 3.82 8.48

2 2-5 3695.59 27.11 209.84

3 5-8 3966.09 33.03 478.37

4 8-16 2945.28 24.54 638.79

5 >16 784.68 6.54 146.61

6 Town 187.77 1.56 0.0

7 village 372.75 3.11 133.26

9 Grave 1.68 0.01 5.14

10 Rs 30.53 0.25 0.0

Total 12000.45 1620.49

Source: Draft report of system layout map phase IIA, OWWDSE, 2016

February,2017 OWWDSE Page 162


Design of the Irrigation and Drainage system MWI&E

The Left main canal (LMC) has divert water from diversion weir and travel for 46.6 km length
with the gravity system .Immediately after Left main canal end two canals Left gravity canal
(LGC) and Left lifted gravity canals (LLGC) will take water for 84.58km and 57.25 km to
irrigategravity and left lifted blocks respectively. Each system of command area divided into 8
and 6 blocks of command area respectively. Eight gravity blocks have the total net command
area of 3957.9 ha and six lifted blocks have the total net area is 7368.83ha.

The gravity system is supplied the command area using the gravity but the lifted system is using
the pump system, using electric energy. In gravity block water is conveyed by 57.25 km length
of canal (LGC ) off taking from LMC and supplying to two primary canals and many secondary
canals again these PCs and SCs supplying to many TCs to supply many field canals built by
farmers in order to distribute to the farmer fields to the crops by furrows.

In lifted blocks water is delivered by a pump from one station to the highest elevation to the
canal system and then using the gravity system through the canals and intake structures water is
distributed to the fields. In lifted system after the pumps are lifted the water to the gravity canal
which has 57.25 km length and this canal is supplying to 12 PCs, 17 SC and 2 TC canal lines
through off take structures. And these PSc, Scs and Tcs are supplying to different canals
according to the situation to the lower canals of SC, Tc and FC respectively. The lifted system
has night storages in some block No2, 5. & 6. The night storage store water during the night
and supply and empty during the day.

In the design of system layout of the canals all the left main canal, left gravity canal and left
lifted canal run along the contour this will avoid or minimize many drop structures. Most of all
primary canal and SC runs across the contours and TCs also run along the contour and this kind
of arrangement of layout is good for the minimize numbers of drop structures and this means
minimize the cost of the structure and for the whole project cost.

February,2017 OWWDSE Page 163


Design of the Irrigation and Drainage system MWI&E

Figure Command area with gravity and lifted blocks

February,2017 OWWDSE Page 164


Design of the Irrigation and Drainage system MWI&E

Table : Different blocks of net irrigable area under gravity and lifted system

NO Gravity Blocks Lifted Blocks Total

Number of Area Number of Area Number Area (Ha)


Block (Ha) Block (Ha) of Block
(upper lifted)

1 BG-1 443.35 BL-1 1339.60 LLUB-1 452.49

2 BG-2 765.9 BL-2 1122.96 LLUB-2 652.09

3 BG-3 544.99 BL-3 1043.39 -

4 BG-4 465.59 BL-4 874.12 -

5 BG-5 565.59 BL-5 793.95 -

6 BG-6 687.46 BL-6 1090.23 -

7 BG-7 416.54 - - -

8 BG-8 68.1 - - -

Total 3957.86 6264.25 1104.58 11,326.69

February,2017 OWWDSE Page 165


Design of the Irrigation and Drainage system MWI&E

6.3.3.2. Canal nomenclature


For irrigation and drainage design the proposed canals will have the following nomenclature:

Main canal – Left main canal (LMC) , run along the contour beginning from the diversion weir
end up upto the junction point of beginning gravity and lifted pump system and it has a total
length of 46.6 km.LMC.

 Left Gravity canal (LGC) and left lifted gravity canals(LLGC) -after the junction points
will run for 84.56 km and 57.25 km respectively.
 Primary canals – Left Gravity Primary canals (LGBPC), and left lifted primary canal
(LLBPC) are the canals take water from main canals run along the contour to supply
water to secondary canals and other types of canal. There is only one primary canal in
left gravity blocks. But, different primary canals under left lifted blocks are available.
 Secondary canals- There are two types of secondary canals on Left gravity blocks and left
lifted gravity blocks. Most of the secondary canals are running across the contour and
take water from main canals and primary canals to supply to tertiary canals and
sometimes field canals. The abbreviation LGB1SC1-4 means secondary canals four on
main canal one on left gravity block one.
 The secondary canals under LGB are serially numbered by assigning a number as
subscript for block number after the letter „SC‟ as LGB1SC1- 1, 2, 3,4……
 Tertiary canal- aligned along the contour which takes water from secondary canals and
sometimes from primary and main canals so that supply water through the off take or
turnout to field canals. For instance the abbreviation LGB1TC1-1-2: means Tertiary canal
two taking water from secondary canal one , secondary canal taking water from primary
canal one, under the command area of left gravity block one
 The tertiary canals are numbered according to their location on the respective secondary
and primary Canal.
 Under left gravity block one, primary canal NO1 , Secondary Canal No.1, tertiary canal
NO1, as LGB1TC1-1-1, LGB1TC-1-1-2, LGB1TC-1-1-3
 Under left gravity block one Secondary Canal No.2 as LGB1TC-2-1-1, LGB1TC-2-1-2,
LGB1TC2-1-3
 Tertiary canals also may take sometimes water from Primary Canal or main canal as the
layout situation allowed.

February,2017 OWWDSE Page 166


Design of the Irrigation and Drainage system MWI&E

 Field canal- aligned across the contour and take water from tertiary canals and supply
water to the field by furrow system.
 On left gravity block one field canal one off take from tertiary canal one which off take
from SC one which off takes from Primary canal one or main canal. The abbreviation is
LGB1FC 1-1-1-1
The nomenclature of drainage canals also the same principle of the above canal water for both
gravity block and lifted blocks of area.
 Under left gravity blocks one , secondary drain NO1, tertiary drain NO3, field drain
NO6 means LGB1-FD-0-1-3-6
 Under left Lifted gravity block one, secondary drain, No1, tertiary drtain No3, Field
drain 6 means LLB1-Fd-0-3-6

February,2017 OWWDSE Page 167


Design of the Irrigation and Drainage system MWI&E

Diversion weir
Arjo-Bedele Bridge

River Course Dhidhessa

LMC

Pump station

RMC LGC PhaseIIA


LLGC

LLGB

Pump station
(Belo+Diga)

Phase IIA LGB

NEKEMTE-_GINBI ROAD

Phase IIA legend

(Belo+Diga) LMC= Left Main Canal

Phase IIB LGC= Left Gravity Canal

Phase IIB Suge area LLGC= Left Lifted Gravity Canal

LGB= Left Gravity block

LLGB= Left Lifted Gravity Block

Phase IIB Shenkore area

: General scheme layout of phase IIA phase IIB project (not to scale)

February,2017 OWWDSE Page 168


Design of the Irrigation and Drainage system MWI&E

6.3.4. Water for the irrigation


The level of ground water and the quality of irrigation water has to be evaluated whether it is fit
or not fit for irrigation of the recommended crops. The productivity of lands gets affected when
the root zone of plants gets flooded with water and this become ill aerated. The supply of oxygen
gets cut off when the land becomes ill aerated. The normal cultivation operation such as tillage,
plugging etc cannot be easily carried out in wet soils and certain water logging grasses and
weeds etc can grow. Water logging also leads salinity.
But, based on the hydro-geological and geotechnical study the contribution of water recharge
from the application of irrigation would be very low. The contribution of irrigation application to
ground water recharge is due to the presence of several creeks that are transversal to the trend of
land are very low.

6.3.4.1 Water quality and water table


The depth of ground water in the area is below 5m during the dry season except in rainy season.
The expected water logging in relative plain land characterized by silty clay soil of hydraulic
conductivity can be prevented among by providing an effective drainage system. Based on the
report water sample has been tested by taking from Dhidhessa river and it was found that the
sodium absorption ratio (SAR) and EC value indicate that it can be classified an excellent
quality that can be used for irrigation.

6.3.4.2. The volume of Water Requirements for crops


As shown in water requirement analysis, the net water requirement of each crop is divided by the
overall efficiency 60% to obtain the gross water requirement. The project supply of lower Arjo
IIA irrigation project during full irrigation is indicated for 24 hour irrigation and becomes 1.05
L/s/ha.This can be determining at the outlet head or canal head regulator for calculating the
discharge capacity of the main off taking canal.

February,2017 OWWDSE Page 169


Design of the Irrigation and Drainage system MWI&E

Table : scheme supply for lower arjo phase IIA full irrigation

Ma
Jan Feb Mar Apr y Jun Jul Aug Sep Oct Nov Dec

Precipitation deficit

1. Banana 128.9 130.1 173.6 145.1 47.4 0 7.3 0 0 0 25.3 128.4

2. Maize 68.8 143.2 185.2 62.8 0 0 0 0 0 0 0 14.9

111.
3. Mango 115.7 111.1 138.3 113.7 26.4 0 0 0 0 37.6 8 89.9

4. Groundnut 76.4 136.9 179.2 80.6 0 0 0 0 0 0 0 28.1

5. Sweet Peppers 82.1 117.7 163.6 96.8 0 0 0 0 0 0 0 29.7

6. Soybean 11.7 94.5 180.9 76.4 0 0 0 0 0 0 0 0

111.
7. Sugarcane 52.2 81.8 162.2 153.5 54.7 0 0 0 1.2 50.4 8 89.8

8. Tomato 118.3 142.6 174 71.3 0 0 0 0 0 0 15.2 78.6

9. Rice 144.2 149.2 188.2 111.2 0 0 0 0 0 0 0 332.7

10. Sesame 68.4 125.4 162 65.5 0 0 0 0 0 0 0 17.4

105.
11. Pasture perennial 109.2 104.9 130.1 102.1 18.3 0 0 0 0 30.8 8 106.1

12. Onion 136.1 130.7 134.8 28.3 0 0 0 0 0 0 44.3 117.9

13. Cabbage Crucifers 113.7 126.2 159.9 80.1 0 0 0 0 0 0 73.3 93.4

Net scheme irr.req.

in mm/day 2.5 4 5.4 3.7 0.8 0 0 0 0 0.7 1.8 3

in mm/month 77.8 112.1 168.1 109.6 24.2 0 0.2 0 0.5 21.5 54.3 93.5

in l/s/h 0.29 0.46 0.63 0.42 0.09 0 0 0 0 0.08 0.21 0.35

Irrigated Area(% of
total area) 100 100 100 100 47 0 3 0 40 44 59 95

Irr.req. for actual


area((l/s/h) 0.29 0.46 0.63 0.42 0.19 0 0.03 0 0 0.18 0.35 0.37

Project efficency (60%)

Project supply in
L/S/ha(24hr) 0.48 0.77 1.05 0.70 0.32 0.00 0.05 0.0 0.00 0.30 0.58 0.62

12hr 0.97 1.53 2.10 1.40 0.63 0.00 0.10 0.00 0.00 0.60 1.17 1.23

February,2017 OWWDSE Page 170


Design of the Irrigation and Drainage system MWI&E

Source: Lowr Dhidhessa draft feasblity study agronomical report, , OWWDSE, 2016

The water requirement of crops means the total quantity of water which crops are required from
the time of crops sown to the time of harvest. The amount of water required from crops is
different depending upon the variation in climate, type of soils, method of cultivation and useful
rainfall etc.

The summation of the total water depth supplied during the base period of a crop, for its full
growth is the total quantity of water required by the crops for its full-fledged nourishment. The
duty of water is the relationship between the volume of water and the area of the crops it
matures.

In the case of Chewaka out of twelve months in a year, for nine months the agronomist
recommended that irrigation water is required. The duty of water for 13 crops, fruits, and
pastures required in the area were calculated. The demand of water volume required for each
months are different. Considering the current net irrigation area of 11326.70 ha designed in the
system layout if the framer will put 100% of command areaunder fully irrigation both in lifted
and gravity systems of irrigation blocks the following water required table 46 and has been
prepared.

Table : Annual water required for proposed crops

N Months Water Irrigation Total water Irrigation Water Remar


O duty(lit/se area (Ha) required area under required for k
c/ha) (Mm3) lifted (ha) lifted
block(MM3)
1 January 0.48 11,326.70 14.092 7368.83 9.168
2 February 0.77 11,326.70 22.606 7368.83 14.707
3 march 1.05 11,326.70 30.827 7368.84 20.055
4 April 0.7 11,326.70 20.551 7368.84 13.370
5 May 0.32 11,326.70 9.395 7368.83 6.112
6 June 0 11,326.70 0.000 7368.83 0.000
7 July 0.05 11,326.70 1.468 7368.83 0.955
8 August 0 11,326.70 0.000 7368.83 0.000
9 Septemb 0 11326.7 7368.83 0.000
er 0.000
10 October 0.3 11326.7 8.808 7368.83 5.730

February,2017 OWWDSE Page 171


Design of the Irrigation and Drainage system MWI&E

11 Novemb 0.58 11326.7 7368.83 11.078


er 17.028
12 Decemb 0.62 11326.7 7368.83 11.842
er 18.202
Total 142.977 93.017

Therefore, from the above table the total volume of requirement of water for phase IIA
command area is 142.977Million m3/year. Hence, the water stored at the dam is enough and
there will not be any shortage of water.

35 30.827
30
25 22.606
Water 20.551
18.202
17.028
requred 20
(MM3) 14.092
15
9.395 8.808
10
5 1.468
0 0 0
0

Figure :graph showing monthly water volume requred

In the water abstraction system of pumping system both the lifted and gravity blocks of
estimated net area of irrigation 11,326.70 ha will be irrigated using the lifted canal system by the
pump through the supply of electricity. Based on the water demand of every month and power of
electricity required power cost was calculated in the following table of table 47 for every
months.

Table : water required and electric city charge in pumping system

Duty Discharge Discharge Power


Month (l/s) Area (Ha) (M3) Cost (Birr)
Duty Discharge Discharge in
Month (lit/sec) Area (Ha) 10^6(M3) Power Cost in(birr)
Jan 0.48 11,326.70 14.092 6,530,175.70
Feb 0.77 11,326.70 22.606 10,475,490.20
Mar 1.05 11,326.70 30.827 14,284,759.30

February,2017 OWWDSE Page 172


Design of the Irrigation and Drainage system MWI&E

Duty Discharge Discharge Power


Month (l/s) Area (Ha) (M3) Cost (Birr)
Apr 0.7 11,326.70 20.551 9,523,172.90
May 0.32 11,326.70 9.395 4,353,450.50
Jun 0 11,326.70 0.000 0.0
Jul 0.05 11,326.70 1.468 680,226
Aug 0 11,326.70 0.000 0.0
Sep 0 11,326.70 0.000 0.0
Oct 0.3 11,326.70 8.808 4,081,359.80
Nov 0.58 11326.70 17.028 7,890,629.0
Dec 0.62 11,326.70 18.202 8,434,810.30
Total 14.092 66,254,074.20
Annual cost
required with VAT
annual 76,192,184.76
Total cost of 15
years +VAT 1,142,882,771.33

25
20.055

20

14.707
13.37
15
11.842
11.078
9.168 (water volume in Mm3)
10
6.112 5.73
5

0.955
0 0 0 0
june

Nov
Aug
Apr

oct
July

Dec
Feb
Mar

sep
Jan

may

Figure : Graph showing water required for lifted Irrigation block

February,2017 OWWDSE Page 173


Design of the Irrigation and Drainage system MWI&E

Table : Requirement of monthly water volume and electricity cost for lifted system

Monthly Required Discharge & Power


Duty Discharge in
dischar Million (M3) Power of
ge Discharge electricity charge
Month (lit/sec) Area (Ha0 in(M3) (birr)
Jan 0.48 7368.83 9,168,003.50 9.168 2,453,420.50
Feb 0.77 7368.83 14,707,005.70 14.707 3,935,695.40
Mar 1.05 7368.83 20,055,007.70 20.055 5,366,857.40
Apr 0.7 7368.83 13,370,05.20 13.370 3,577,904.90
May 0.32 7368.83 6,112,002.40 6.112 1,635,613.70
Jun 0 7368.83 0.0 0.000 0.00
Jul 0.05 7368.83 955,000.40 0.955 255,564.60
Aug 0 7368.83 0.0 0.000 0.0
Sep 0 7368.83 0.0 0.000 0.0
Oct 0.3 7368.83 5,730,002.20 5.730 1,533,387.80
Nov 0.58 7368.83 11,078,004.30 11.078 2,964,549.80
Dec 0.62 7368.83 11,842,004.6 11.42 3,169,001.50
93,017,035.8
Total 79,073,878.3 0 24,891,995.70
Total cost with VAT(Birr) 28,625,795.1
Total cost 15 years withVAT (Birr) 429,386,926.50

6.3.5. Design of water conveyance system


The entire water conveyance system for irrigation comprising of the main canals, primary canals,
secondary canals , tertiary canals , field canals and water courses/furrows have to be properly
designed. The design process comprises of finding out the longitudinal slope of the channel and
fixing the cross-section. The channels the surface may be made up of different construction
materials. In unlined channels those could be some passes through soil which are erodible due to
high water velocity, while some other may pass through stiff soil or rock which may be relatively
less permeableto erosion. Further the bank slope or canals would different for canals passing
through loose or stiff soils or rock.

The net irrigation command areas under the left gravity and lifted blocks have estimated 3957.86
ha and 7368.83 ha respectively. The discharge required of left main canal in order to supply both
left gravity and left lifted system including future water supply is 23m3/sec.

February,2017 OWWDSE Page 174


Design of the Irrigation and Drainage system MWI&E

6.3.5.1. Designing of Left Main Canal LMC, LGC &LLGC


Based on the above water duty from the agronomical study for maximum demand in the month
of March considering project efficiency of 60% for 12 hours of application at the beginning of
canal the discharge required at intake outlet is 2.10lit/sec/ha.
Based up on design criteria and the above recommendation of different sectors study the design
of main canal was done as the following.
Water discharge at outlet of left diversion weir = 23m3/sec
According to geo-technical study recommendation from 0-10 km no lining but it needs
compaction to reduce leakage and from10-46 it needs lining to reduce leakage. Manning formula
used. In choosing the type of lining two options with clay material embankment fill and concrete
lining has been compared and the list cost option of clay embankment fill was selected.
All the rest canals left gravity canal (LGC) and left lifted gravity canal (LLGC) design were done
with the same formula at a beginning discharge of 8.39m3/sec and 12.26m3/sec respectively. The
cross-section and dimension of canals were decreasing from head to tail.
Area of cross-section of the canal is worked out by continuity equation

Q = A .V

Where,

Q is the design discharge and V is the velocity of flow.

Value of „V‟ is worked out by Manning's formula for assumed channel section
and bed slope.

Manning formula
1
V= 𝑛 * R2/3 * S1/2 (Kumar, 2005) and Q= A*V

Where, V= velocity of flow in m/sec


R= Hydraulic mean depth in meters
S= Bed slope of the channel
n = Rugosity coefficient =0.025 from table for earth canal and 0.018
for lined
s= consider trapezoidal section of canal of unlined canal as per
design and rectangular for lined canal.

February,2017 OWWDSE Page 175


Design of the Irrigation and Drainage system MWI&E

For satisfactory and safe results when using Manning equation, it is important to select a
reasonable value for the Manning roughness coefficient 'N' which may hold for the whole of the
year. According to the design criterion of canal design for earthen section, value of 'N' 0.025 to
0.04is generally used for earth canals and 0.018 for lined canal. In some part of the canals due to
the pervious nature of the ground lined canals were designed and the canal shape is rectangular
type. Based on the above calculation formula the following dimension of canals of left main
canal, gravity and lifted canals are determined in the following table 50, 51, and 52.

Figure : layout of left main canal, gravity canal and lifted canal

February,2017 OWWDSE Page 176


Design of the Irrigation and Drainage system MWI&E

Table : Left main canal (LMC) designed dimension

Flow
Dis. Rou. F.S. Bed Side Bank Flow Wetted Hyd. Expon Chezy veloci
CH Req. Coef. D F.B Slope width slope width area perimeter radius entail coef. ty
m3/s m m m m m2 m m m0.5/s m/s
SOIL 23.000 0.0250 2.14 0.75 7400.0 13.20 1.50 2.50 35.12 20.92 1.68 0.17 43.61 0.66
LGB
1-
SC1 0.082 22.918 0.0250 2.13 0.75 7400.0 13.20 1.50 2.50 34.98 20.89 1.67 0.17 43.59 0.66
LGB
1-
SC2 0.211 22.707 0.0250 2.12 0.75 7400.0 13.20 1.50 2.50 34.75 20.85 1.67 0.17 43.55 0.65
MAS
CAN 23.000 0.0180 3.10 0.50 3000.0 5.64 0.00 2.50 17.50 11.84 1.48 0.17 59.29 1.32
FLU
ME 23.000 0.0156 2.48 0.50 5564.0 8.20 0.00 0.00 20.33 13.16 1.55 0.17 68.71 1.14

Table : Left gravity canal (L G C) designed dimension

Dis. Rou. Bed Side Bank Flow Wetted Hyd. Flow Dis.
CH Req. Coef. F.S.D F.B Slope width slope width area perimeter radius velocity Des.
m3/s m m m m m2 m m m/s m3/s
1407.7 8.390 0.0250 1.59 0.70 1:5000.0 6.15 1.50 2.00 13.57 11.89 1.14 0.62 8.390
2665.2 8.189 0.0250 1.59 0.70 1:5000.0 5.98 1.50 2.00 13.30 11.71 1.14 0.62 8.189
3861.6 8.007 0.0250 1.59 0.70 1:5000.0 5.82 1.50 2.00 13.05 11.56 1.13 0.61 8.007
11373.5 7.690 0.0250 1.59 0.70 1:5000.0 5.55 1.50 2.00 12.62 11.28 1.12 0.61 7.690
12971.9 5.925 0.0250 1.45 0.60 1:4200.0 4.47 1.50 2.00 9.64 9.70 0.99 0.61 5.925
14193.9 5.805 0.0250 1.45 0.60 1:4200.0 4.36 1.50 2.00 9.48 9.59 0.99 0.61 5.805
16660.7 5.656 0.0250 1.45 0.60 1:4200.0 4.22 1.50 2.00 9.28 9.45 0.98 0.61 5.656
16794.4 5.575 0.0250 1.45 0.60 1:4200.0 4.15 1.50 2.00 9.17 9.38 0.98 0.61 5.575
16808.7 5.508 0.0250 1.45 0.60 1:4000.0 3.96 1.50 2.00 8.90 9.19 0.97 0.62 5.508
17812.9 5.457 0.0250 1.45 0.60 1:4000.0 3.92 1.50 2.00 8.83 9.14 0.97 0.62 5.457

February,2017 OWWDSE Page 177


Design of the Irrigation and Drainage system MWI&E

19314.3 5.425 0.0250 1.45 0.60 1:4000.0 3.89 1.50 2.00 8.79 9.11 0.96 0.62 5.425
20143.9 5.413 0.0250 1.45 0.60 1:4000.0 3.88 1.50 2.00 8.77 9.10 0.96 0.62 5.413
20611.8 5.396 0.0250 1.45 0.60 1:4000.0 3.86 1.50 2.00 8.75 9.09 0.96 0.62 5.396
20776.8 5.279 0.0250 1.45 0.60 1:4000.0 3.75 1.50 2.00 8.59 8.98 0.96 0.61 5.279
22864.0 5.183 0.0250 1.45 0.60 1:4000.0 3.66 1.50 2.00 8.47 8.89 0.95 0.61 5.183
26389.8 5.174 0.0250 1.35 0.60 1:4000.0 4.32 1.50 2.00 8.57 9.19 0.93 0.60 5.174
26766.3 5.163 0.0250 1.35 0.60 1:4000.0 4.31 1.50 2.00 8.56 9.18 0.93 0.60 5.164
27190.3 5.126 0.0250 1.35 0.60 1:4000.0 4.28 1.50 2.00 8.51 9.14 0.93 0.60 5.127
27783.0 5.077 0.0250 1.35 0.60 1:4000.0 4.23 1.50 2.00 8.44 9.09 0.93 0.60 5.078
30019.3 5.058 0.0250 1.35 0.60 1:4000.0 4.21 1.50 2.00 8.41 9.07 0.93 0.60 5.059
30693.5 5.019 0.0250 1.35 0.60 1:4000.0 4.17 1.50 2.00 8.36 9.03 0.93 0.60 5.020
31199.2 4.973 0.0250 1.35 0.60 1:4000.0 4.12 1.50 2.00 8.30 8.99 0.92 0.60 4.974
31454.3 4.900 0.0250 1.35 0.60 1:4000.0 4.05 1.50 2.00 8.19 8.91 0.92 0.60 4.901
31602.2 4.879 0.0250 1.35 0.60 1:4000.0 4.02 1.50 2.00 8.17 8.89 0.92 0.60 4.880
33828.9 4.786 0.0250 1.35 0.60 1:3600.0 3.68 1.50 2.00 7.70 8.54 0.90 0.62 4.787
34965.5 4.769 0.0250 1.25 0.60 1:3600.0 4.36 1.50 2.00 7.80 8.87 0.88 0.61 4.769
35698.4 4.745 0.0250 1.25 0.60 1:3600.0 4.34 1.50 2.00 7.76 8.84 0.88 0.61 4.745
37309.2 4.686 0.0250 1.25 0.60 1:3600.0 4.27 1.50 2.00 7.68 8.78 0.88 0.61 4.686
37828.0 4.613 0.0250 1.25 0.60 1:3600.0 4.19 1.50 2.00 7.58 8.70 0.87 0.61 4.613
39131.4 4.287 0.0250 1.25 0.60 1:3600.0 3.83 1.50 2.00 7.14 8.34 0.86 0.60 4.287
39785.9 4.084 0.0250 1.25 0.60 1:3600.0 3.61 1.50 2.00 6.86 8.12 0.84 0.60 4.084
41973.1 3.975 0.0250 1.25 0.60 1:3600.0 3.49 1.50 2.00 6.71 8.00 0.84 0.59 3.975
44731.9 3.907 0.0250 1.15 0.55 1:3600.0 4.12 1.50 2.00 6.73 8.27 0.81 0.58 3.907
45975.2 3.837 0.0250 1.15 0.55 1:3600.0 4.04 1.50 2.00 6.63 8.18 0.81 0.58 3.837
47591.8 3.676 0.0250 1.15 0.55 1:3600.0 3.83 1.50 2.00 6.39 7.98 0.80 0.58 3.676
49992.9 3.511 0.0250 1.15 0.55 1:3600.0 3.63 1.50 2.00 6.15 7.77 0.79 0.57 3.511
51863.2 3.335 0.0250 1.15 0.55 1:3600.0 3.40 1.50 2.00 5.90 7.55 0.78 0.57 3.336
55940.1 3.181 0.0250 1.15 0.55 1:3600.0 3.21 1.50 2.00 5.67 7.36 0.77 0.56 3.182
56335.6 3.081 0.0250 1.15 0.55 1:3600.0 3.08 1.50 2.00 5.53 7.23 0.76 0.56 3.081
56879.8 2.916 0.0250 1.15 0.55 1:3600.0 2.87 1.50 2.00 5.28 7.02 0.75 0.55 2.916

February,2017 OWWDSE Page 178


Design of the Irrigation and Drainage system MWI&E

58046.1 2.762 0.0250 1.15 0.55 1:3600.0 2.67 1.50 2.00 5.06 6.82 0.74 0.55 2.762
64642.1 2.696 0.0250 1.05 0.50 1:3600.0 3.23 1.50 2.00 5.04 7.01 0.72 0.53 2.696
66139.9 2.575 0.0250 1.05 0.50 1:3800.0 3.15 1.50 2.00 4.96 6.94 0.72 0.52 2.576
67802.7 2.344 0.0250 1.05 0.50 1:3800.0 2.80 1.50 2.00 4.59 6.59 0.70 0.51 2.345
67859.0 2.135 0.0250 1.05 0.50 1:3800.0 2.48 1.50 2.00 4.26 6.27 0.68 0.50 2.135
67859.0 1.987 0.0250 1.05 0.50 1:3800.0 2.25 1.50 2.00 4.02 6.04 0.67 0.49 1.988
67930.2 1.929 0.0250 1.05 0.50 1:3800.0 2.16 1.50 2.00 3.92 5.95 0.66 0.49 1.929
67930.2 1.639 0.0250 1.05 0.50 1:3800.0 1.71 1.50 2.00 3.45 5.49 0.63 0.48 1.639
68787.8 1.461 0.0250 0.90 0.50 1:3800.0 2.22 1.50 2.00 3.21 5.46 0.59 0.46 1.461
70235.4 1.397 0.0250 0.90 0.50 1:3800.0 2.09 1.50 2.00 3.10 5.33 0.58 0.45 1.397
70361.3 1.228 0.0250 0.86 0.50 1:3800.0 1.99 1.50 2.00 2.81 5.08 0.55 0.44 1.228
70766.2 1.168 0.0250 0.86 0.50 1:3800.0 1.86 1.50 2.00 2.70 4.95 0.54 0.43 1.168
71753.7 1.140 0.0250 0.86 0.50 1:3800.0 1.80 1.50 2.00 2.65 4.89 0.54 0.43 1.140
73801.7 1.104 0.0250 0.84 0.50 1:3800.0 1.80 1.50 2.00 2.58 4.84 0.53 0.43 1.104
74799.6 1.065 0.0250 0.83 0.50 1:3800.0 1.80 1.50 2.00 2.52 4.78 0.53 0.42 1.065
74860.8 0.945 0.0250 0.78 0.50 1:3800.0 1.80 1.50 2.00 2.31 4.60 0.50 0.41 0.945
75508.5 0.702 0.0250 0.67 0.50 1:3800.0 1.80 1.50 2.00 1.86 4.20 0.44 0.38 0.702
77397.0 0.639 0.0250 0.63 0.50 1:3800.0 1.80 1.50 2.00 1.74 4.08 0.43 0.37 0.640
78088.0 0.621 0.0250 0.53 0.50 1:3800.0 2.55 1.50 2.00 1.77 4.46 0.40 0.35 0.621
79154.6 0.577 0.0250 0.53 0.50 1:3800.0 2.34 1.50 2.00 1.66 4.25 0.39 0.35 0.577
80838.4 0.478 0.0250 0.53 0.50 1:3800.0 1.88 1.50 2.00 1.42 3.79 0.37 0.34 0.478
82139.7 0.317 0.0250 0.53 0.50 1:3800.0 1.12 1.50 2.00 1.01 3.03 0.33 0.31 0.318
82234.6 0.269 0.0250 0.53 0.50 1:3800.0 0.88 1.50 2.00 0.89 2.79 0.32 0.30 0.269
82577.2 0.247 0.0250 0.53 0.50 1:3800.0 0.77 1.50 2.00 0.83 2.69 0.31 0.30 0.247
83593.1 0.203 0.0250 0.49 0.50 1:3800.0 0.74 1.50 2.00 0.72 2.50 0.29 0.28 0.203
84066.6 0.159 0.0250 0.48 0.50 1:3800.0 0.52 1.50 0.90 0.60 2.25 0.26 0.27 0.159
84093.9 0.137 0.0250 0.43 0.50 1:3800.0 0.60 1.50 2.00 0.53 2.15 0.25 0.26 0.137
84580.7 0.115 0.0250 0.43 0.50 1:3800.0 0.44 1.50 2.00 0.47 1.99 0.23 0.25 0.115

February,2017 OWWDSE Page 179


Design of the Irrigation and Drainage system MWI&E

Table : Left lifted gravity canal Designed dimension

February,2017 OWWDSE Page 180


Design of the Irrigation and Drainage system MWI&E

Based on the above designed dimension of left main canal (LMC) left Gravity canal (LGC) and
left lifted gravity canal (LLGC) were designed according to the discharge of maximum crop of
water required of peak requirement. All the hydraulic characteristics of its depth, width,
velocity, freeboard are different and its‟ discharge is also decreasing from upstream to
downstream or to the end of the canal for LGC and LLGC. This is due to the fact that the
discharge is supplying different main and branch canals. There are six scenarios of typical canal
dimensions cross-section in relation of berm , side slope of the canals and other dimensions
based on the natural situations of features of the main canal passing through the ground , that is
whether the canal is passing through under deep cut, cliff area, and more sloppy, and level area
were determined.

February,2017 OWWDSE Page 181


Design of the Irrigation and Drainage system MWI&E

February,2017 OWWDSE Page 182


Design of the Irrigation and Drainage system MWI&E

February,2017 OWWDSE Page 183


Design of the Irrigation and Drainage system MWI&E

Figure : six types of canal cross-section of main canal.

6.3.5.2 .Design of PC, SC, TC of the irrigation canal


Based on the above design criteria for canal design on velocity, freeboard, side slope ,
longitudinal slope, bed width , depth are determined using manning equation formula and
continuity equation. All the farm works of the irrigation system were designed for both gravity
block and lifted block In the project under gravity and lifted block have PC, SC, and TC have
different lengths.

Primary canals:The purposes of primary canals are to off take water directly from main canal by
off take structures to convey water to supply secondary and tertiary canals. The total length of
PC under gravity , lifted, and upper lifted block have 6.5 km , 57 km, and 0 respectively.
Primary canals sections are getting reduced from head to tail reach with discharge getting
reduced. The flow in the primary canals will be maintained continuous throughout the year. As
in case of surface irrigation method, water In both Gravity and lifted block canals run across the
contour. The discharge capacity is based on the irrigable area serving under many numbers of
secondary canals and Tc canals and maximum water duty 2.1lit/sec.The flow in the primary
canals will be maintained continuous during application time of 12-14 hours.
Secondary canals: The main functions of secondary canals are to convey and carry water by off
taking water from main canal at different station to supply many tertiary canals off taking from
it. It was designed across the contour and the ridge part of the command area Based on the size
of the command area serving by tertiary canals under sub section of secondary it has different
dimension and capacity. Design of Secondary canals mainly comprises of two parts, (i)

February,2017 OWWDSE Page 184


Design of the Irrigation and Drainage system MWI&E

estimation of total area that can be irrigated by the respective secondary canals and discharge of
water required to irrigate this area with the given irrigation hours. The discharge duty is
1.996lit/sec/ha. The total length of secondary canals under gravity , lifted and upper lifted blocks
have 49 km , 72 km, and 6 km respectively. The flow in the secondary canals will be
maintained continuous during application time of 12-14 hours.
Tertiary canals:The main functions of tertiary canals are used to transport water by off taking
water from secondary canals to the field canals where water distributed to the farm. But
sometimes it will offtaking water from main canals based on the situation of layout. The
discharge capacity of the canal of water required to irrigate this area with the given irrigation
hours. The discharge duty was 1.996lit/sec/ha.The flow in the tertiary canals will be maintained
continuous during application time of 12 -14 hours. The total lengths of tertiary canals under
gravity and lifted block have 197 km , 286, and 56 km respectively.Detail design will be
presented during detail design reporting.
Table : Summary of canal length designed for farm work

No Description Unit Canal length Canal Canal Total


under gravity length length
block under under
lifted upper
block lifted
block
1 PC km 6.5 57 - 63.5
2 SC km 49 72 6 127
3 TC km 197 286 56 539

6.3.5.3 Design of irrigation canal structure on LMC, LGC, and LLGC


As per the design criteria on canal structures there are different type of structures were designed
on the above major canals. The types of structures and their functions are listed as the
following.

Off take structures : The off taking structures were designed on main canal, secondary canal,
primary canals , tertiary canals considering the required head so that water can be easily flow

February,2017 OWWDSE Page 185


Design of the Irrigation and Drainage system MWI&E

from the parent canals to the off taking canals with gravity. All hydraulic and structural
calculations were considered.

Head regulators:The discharge of irrigation water passing from the parent canal of main canal to
the off taking canal like primary canal, secondary canals and tertiary canal can be regulated by
head regulators. The head regulators provided at the head of the canals and control the supply
entering the canal.
Inverted Siphon:Inverted siphon are used to convey canal water by gravity under roads, various
types of drainage channel and depression.
Aqueduct/flume Structure:The purpose of flume structures is to convey water on the river course
and some drainage when the topographic features in such a way that the level of the drainage
crossing is deeper than the bed level of the canal.
Cross Drainage: In more or less flat type of lands across the canals small cross drainage canals
need to cross all types of canals MC, PC, SC and TC . The bed levels of these channels are
neither deep for an aqueduct or flume nor high is enough for a super passage and the channel not
wide enough
Foot Bridge:The main purpose of Foot Bridge is to carry the canal water safely under the road
crossing so that farmers and their livestock can easily cross over the canal water safely
Escape:The main purpose of escape is to discharge or release the surplus water from the canal
when the canal is flowing continuously. It is a safety valve for the canal system. It can serve
protection of the canal against possible damage empting the canal and properly release the water
to the river course or nearby drainage system.
Drop structure: The function of drop structure is to convey water from the higher elevation to a
lower elevation to dissipate the excess energy resulting from this drop. The water must therefore
be conveyed with a drop structure designed to safely dissipate the excess energy.
In the above all structures all hydraulic and detail structural calculation with safety factors were
considered.All head loss, cutoff depth, hydraulic jupm calculation protection work were
considered.Detail design of all structures will be presented in the future during detail design
reporting time.

February,2017 OWWDSE Page 186


Design of the Irrigation and Drainage system MWI&E

Table : Canal Structures on LMC, LGC, & LLGC

NO Type of LMC LGC LLGC


structures unit Qty unit Qty Unit Qty
1 Off take NO 2 NO 64 NO 31
2 Head regulator NO 1 NO 7 NO 5
3 Inverted siphon NO 4 - - NO 8
4 Aqueduct/Flume NO 7 - -
5 Cross drainage NO 60 NO 33 NO 35
6 Foot bridge NO 6 NO 7 NO 6
7 Escapes NO 2 NO 2 NO 2
8 Drop structures NO NO 12 - -

6.3.5.4. Design of farm structures


All farm structures on the irrigation scheme and canals like off take, drop, division box, and
box culvert and siphon are very important to regulate, convey and distribute the water for the
irrigation. They were designed based on the template prepared. The detail inlet outlet transition,
cut off, head losses were considered. These structures were designed on the farm work canals
like on PC, SC, and TC especially they are important to distribute the water on the field of the
farmers.

Table :farm structures on gravity canals of PC,SC&TC

NO Type of Unit QTY Total


structures On PC On SC On TC On FC
1 Drop (0.5-2)m NO 13 1525 492 - 2030
2 Culvert NO 5 339 1814 - 2158
3 Division Box NO - 53 - - 53
4 offtake NO 2 78 358 1554 1992

Table : farm structures on lifted gravity canals of PC, SC, &TC

NO Type of Unit QTY Total


structures On PC On SC On TC On FC
1 Drop (0.5-2)m NO 224 981 622 - 1827
2 Culvert NO 132 269 1872 - 2273
3 Division Box NO 16 28 - - 44
4 offtake NO 17 66 314 2171 2568
5 Inv siphon No - 1 - - 1
6 N.S.P NO 1 16 4 - 21

February,2017 OWWDSE Page 187


Design of the Irrigation and Drainage system MWI&E

Table : farm structures on upper lifted gravity of PC, SC, and TC

NO Type of Unit QTY Total


structures On PC On SC On TC On FC
1 Drop (0.5-2)m NO - 7 47 - 54
2 Culvert NO - 14 138 - 152
3 Division Box NO - 2 - - 2
4 offtake NO - 2 14 129 145
6 N.S.P NO - 2 4 - 6

6.3.6 Design of drainage system.


The drainage system of any irrigation project is very important for the whole project
effectiveness and to meet the main objective of crop productivity of the agriculture. If it is
properly managed introduction of irrigation increases the amount of deep percolation causing
arise in water table level so that the root systems will not survive for long below a water table.
The loose of water occur from the main irrigation canal, from branch canals, from field
distribution canals and from the field itself. In lower Arjo-Dhidhessa project based on soil and
land suitability study most of the command area soil dominated by sandy clay loam, clay, sandy
clay and loam type soilhydraulic conductivity that would not cause excess leakage and the left
main canal also fill with good clay material and hydro geological study also shows recommend
the expected Water logging in the relative plain land characterized by silty clay soil of low
hydraulic conductivity can be prevented by providing an effective drainage system. Such drains
could be open or closed. In the case of Phase IIA open drainage system was designed.

6.3.6.1 Drainage Design of Canal System


The excess water arising either from irrigation or excessive rainfall over the irrigated land will be
collected by a network of field drain each serving an area of maximum 6ha land and the field
canal built by the farmers as per the design criteria 1 in 5 years return period of 4.6lit/sec ha. As
the size of the number of field drain increasing the TD, SD, and CD of the canal dimensions are
increasing. Interceptor design will run parallel to LMC and LGC and LLGC collect the flood
coming from outside and its‟ the command area and upstream of main canals catchment.

The design discharge duty for this is the same as 4.6lit/sec /ha and the catchment size is
determined as based on the given hydrologist detail calculation. All the drainage canal capacity
determination is based on manning formula and continuity equation as the given design criteria
for canals.Detail design will be presented in the future on detail design reporting time.

February,2017 OWWDSE Page 188


Design of the Irrigation and Drainage system MWI&E

Table : Summary of drainage canals for farm work, LMC, LGC& LLGC

No Description Unit For both Canal Canal length Canal length


system length under lifted under upper
under block lifted block
gravity
block
1 CD km 24.6 9.2 15.4
2 SD km 41.7 26.8 14.9
3 TD km 356.20 142.6 180.8 32.80

6.3.6.2. Structures design on drainage canals


Different types of structures are required on the drainage system of the canals like on the water
conveyance system of the canals. The main types of structures are drop, out fall, and cross
drainage, foot Bridge/crossing culvert. The main functions are discussed on the canal delivery
system of structures except outfall. Out fall structures are designed in the drainage system to
regulate water and convey water safely from FD to TD or from TD to SD and SD to CD. Based
on the relative bed level it may combine with drop height and it has inlet and out let transition.
Detail design will be presented in detail design reporting.

Table : Farm structures on drainage canals of gravity block

NO Type of Unit QTY Total


structures On CD On SD On TD
1 Drop (0.5-2)m NO 267 840 684 1791
2 R.Culvert NO 116 141 817 1074
3 Drain out fall NO 94 245 1217 1556

Table : farm structures on drainage canals of lifted block

NO Type of Unit QTY Total


structures On CD On SD On TD
1 Drop (0.5-2)m NO 102 292 643 1037
2 R.Culvert NO 61 35 901 997
3 Drain out fall NO 75 25 727 827

February,2017 OWWDSE Page 189


Design of the Irrigation and Drainage system MWI&E

Table : farm structures on drainage canals of upper lifted block

NO Type of Unit QTY Total


structures On CD On SD On TD
1 Drop (0.5-2)m NO - - 12 12
2 R.Culvert NO - - 93 93
3 Drain out fall NO - - 154 154

6.3.7. Road network design


In the project of Irrigation and drainage system road networks were designed to facilitate all the
irrigation water management operation and agricultural activities including inputs and outputs
management. All the agricultural machineries like tractor, vehicles, agricultural harvesting and
equipments and other inputs of agricultural crops have to be contentiously transported in the
irrigation system to the market access. Detail design will be presented in detail design reporting.

The design of road network of Phase IIA project divided into four main divisions. These roads
are main road run along LMC,LGC, LLGC , secondary road run along PC, SC , SD and CD
tertiary road along TC and TD and field roads run along FC which is built by the community.
Detail design report will be presented during detail design reporting.

Table : Road network designed in irrigation and drainage system

NO Name of Unit Gravity Lifted Upper Total Width


Road lifted
1 Road along LMCR km 46.6 7
2 Road along LGC and km 84.56 57.25 141.82 7
LLGC (RLGC,RLLGC)
4 Road along Primary km 4.784 20.793 25.577 4
canal (RPC)
5 Road along Secondary km 53.548 80.973 134.521 4
canal (SCR)
6 Road along Tertiary km 222.12 297.17 519.29 4
canal (TCR)
7 Road along CD (RCD) km 1.1 2.480 3.58 4
8 Road along SD (RSD) km 18.454 7.060 25.514 4
9 Road along TD(RTD) km 11.12 19.83 75.53 106.48 4
Total 395.68 485.556 1003.38

February,2017 OWWDSE Page 190


Design of the Irrigation and Drainage system MWI&E

6.3.7.1. Design of structures on road network.


Just like canals and drainage system, structures on the road system are very important. These
structures are mainly road crossing culvert, bridge, ford . As per the geology, geo-technical,
topography condition, and hydrology of peak flood determination the structures should be
designed. All hydraulically and structural analysis with required safety factor should be done.
Design of detail structeres will be presented in the future in detail designing report.

6.3.8. Design of water distribution system


Water should be distributed in the irrigation system as per the above design criteria of detail
system layout and the surface system of irrigation method. . The above water conveyance system
of from the diversion weir water is conveyed by LMC for a length of 46.6km by the gravity
system from the diversion Intake outlet of left side. The head work head regulators has proper
discharge measuring structures and the exact water required as per the crop water requirement of
water discharge is released. These water discharges have two off takes before joining of LGC
and LLGC which is supplying some plot of area. The LGC has different off take structures
supplying PC, SC, and TC according to the situation. And The LLGC has received water from
the pumping system and running by the gravity system for a length of 57.25km. On this canal
different off taking structures arranged to supply different PS, SC, and TC. With the same
principle of gravity system the FSL on between every parent and off taking canals have head
difference as per the design criteria so that water can easily flow up to distribution point. The
different off take structures were designed and arranged to take water according to the size of
area of farm and water duty calculated. Where night storages are available water is travelled
from MC to NSP and NSP supply to SC,PC and TC

6.3.8.1. The Sizing of irrigation farm unit


The sizing of the field unit is based on the stream size that an individual farmer can manage and
from a consideration of individual crop water requirements and current land holding of most
farmers. The designed field canal block has in a range between 0.13ha to 6Ha . Based on the
socio-economic study 11 % of the farmers have a land holding between less than 0.5Ha, so that
the minimum size of one farm unit is 0.30ha and this field size is taken as being of a manageable
size. The field canal must be sized to meet the peak requirement for the crop with the highest
demand. The theoretical maximum irrigation intervals is divided on the basis of the consumptive

February,2017 OWWDSE Page 191


Design of the Irrigation and Drainage system MWI&E

use, rooting depth and soil moisture holding capacity and represent the period required to despite
the soil moisture reserve.

6.3.8.2. Water distribution system design in the farm


Considering the above table of the irrigation interval depth of water application six critical main
crop of shortest interval of each crops are rice, pepper, tomato, onion, G nut , H.cabbage and we
have an average of 5.83days of average interval. Taking the minimum of irrigation to be on
the safe side average interval of days are 5 days. Hence in the system layout designed the
maximum field canals block is 6ha and one farm unit is 0.3ha based on the land holding of
farmer .This means in one field canal block maximum we have 20 farm units. Since in large
scale project the system is during the application time of the day time run MC, PC, SC and TC
and FC run continuously but there is rotation between farm units. In MC at lifted block it will
run for 24 hours due to night storage. In one day for this maximum field canal block of 6ha it is
possible to irrigate upto 4 farm units or1.2ha because the water discharge available
1.995lit/sec*6Ha= 11.97lt/sec which can be mange by the farmers.

Table ; Irrigation interval and depth of application for full irrigation

Source : draft final feasibility report of agronomy of PhaseIIA project ,OWWDSE,2016

Using the formula of depth of application

𝑃.𝑠𝑎𝑚𝑚 /𝑚 ∗𝐷𝑚
Depth of application (dmm)= 𝐸𝑎 (𝑎𝑝𝑝𝑙𝑖𝑐𝑎𝑡𝑖𝑜𝑛 )

February,2017 OWWDSE Page 192


Design of the Irrigation and Drainage system MWI&E

Where P.sa= readily available soil moisture. In mm/m for heavy textured soil the agronomies
study recommend 130mm/m

Ea = application efficiency= 60

Dm= Rooting depth in meter

Table : Different crops and irrigation depth of application in 5 days interval

irrigation
depth per irrigation
Types of Irrigation interval irrigation required
crops grown interval required required /day depth/5day
banana 9 93.6 10.40 52
Maize 13 136.5 10.50 52.5
Rice 2 26 13.00 65
pepper 6 57.2 9.53 47.67
soyabean 14 143 10.21 51.07
Tomato 8 87 10.88 54.38
Seasome 15 143 9.53 47.67
onion 6 54.6 9.10 45.50
sugercane 21 211 10.40 50.24
mango 32 260 8.13 40.63
Groundnut 8 83.2 10.40 52
H. cabbage 5 48.75 9.75 48.75
pasture 12 86.67 7.38 36.11
Average 49.50

From the above table the average depth of water required for the minimum 5 days interval for all
crops except rice it is 49.5mm. Considering 12 hours Ethiopian farmer application during the
maximum requirement it is possible to apply within one day for 4 farm unit or 1.2 ha because
the interval is 5 days where the maximum block has 6 Ha. This means it is possible to irrigate
within one day 4 farm unit or 1.2Ha

Discharge= depth *Area of plot/3600* Time of application

Discharge= 1.995*6= 11.97lit/sec

Depth of application in 5 days = 49.5mm

Area of plot considering 5 days interval= 1.2Ha or 4 farm units

February,2017 OWWDSE Page 193


Design of the Irrigation and Drainage system MWI&E

Time required in hours = Depth*Area plot /Discharge *3600

0.0495*1.2 *10,000/0.01197*3600 = 13.78 hours= 14 hours.

Therefore, it required 14 hours of water application.

This means the system should run for 14 hours instead of 12 hours otherwise the plot of area
should decrease but the interval of the minimum is 5 days and which is impossible to decrease
the plot area. This will happen in the month March but there will not have a problem in the rest
months so that it is better extend upto 14 hours in the month of March.

The application of water to the field as per the design criteria for most of the crops were
recommended furrow type and only for rice it should use Basin methods.

February,2017 OWWDSE Page 194


Design of Electromechanical System MWI&E

7. DESIGN OF ELECTRO MECHANICAL SYSTEM


In LowerArjo- Dhidhssa irrigation phase IIA project there are two types of conveyance system
used for the command area irrigation systems. The conveyance systems used will be the gravity
and lifted gravity canal system as based on the proposed water abstraction system. Out of
10,222.12 Ha , 3957.9 Ha and 6264.25 Ha will be used gravity canal and lifted gravity canal
system respectively. Therefore, the lifted gravity canal system required the design of detail
electromechanically system. Additionally all the head work and appurtenant structures needs the
design of mechanical system. In the following section design criteria and design of the
electromechanical system of the lifted irrigation system will be discussed.

7.1 Design Criteria of Electromechanical System


Providing an outline of the design criteria to be followed during the design of a system helps a
great deal in clarifying the details of the design process and the results obtained. In the following
some basic design concepts related to the design of the Electro-Mechanical system and
associated design criteria are described. The criteria are compiled from previous project
documents (mainly the design criteria prepared for the 25 projects), manufacturer catalogues, and
hydraulic & water supply reference books.

7.1.1. Design life time


Each element of irrigation and water supply system has an expected life time. This varies
depending on whether it is civil works or mechanical and electrical works, and the purpose for
which the works are to be utilized.

The design life is an important aspect of any financial / economic comparison of options as
recurrent replacement costs has to be included.

The proposed design life for major components of a pumping system is set out in Table 59.

February,2017 OWWDSE Page 195


Design of Electromechanical System MWI&E

Table : design of life for major components

Mechanical and
Item Civil (Years) Electrical (Years)
Pumping Stations 50 15
Service Reservoirs – Concrete 50 15
Service Reservoirs – Steel 20 15
Ductile Iron Pipes 40 -
Steel Pipes 40 -
UPVC Pipes 25 -
Pipeline Fittings - 25
Buildings 50 -

7.1.2 Pumping Cost


The need for minimizing the pumping costs is central to the long term viability of the system.
Recurrent electric expenditure is a significant element of the system operating costs and hence
consideration is to be given to the following:

 Reducing frictional head losses by employing larger diameter pipes


 Designing for pump units with high efficiency
 Accurately calculating the system operation point and specifying Limits for the deviation
of pump duty points from the system operation point.

Inefficiencies arising from overdesigning (i.e., choosing a pump that will, for a given head,
deliver more water than is needed) are common. The result of “conservative” design is often a
system that operates inefficiently because it is capable of delivering more water than is ever
required.

Such systems are wasteful in terms of both initial investment and continuing operating cost. To
avoid this pitfall, the design must consider pump characteristics and system head curves
carefully. In this regard the efficiency of both the pump and the driver should be considered.
Pumps with fairly steep characteristic curves are usually preferred since their capacity to deliver
water is relatively unaffected by changes in head. As pumps, water lines, valves, etc., age, head

February,2017 OWWDSE Page 196


Design of Electromechanical System MWI&E

losses will tend to increase. This can significantly affect flow rates if both the pump
characteristic and system head curves are fairly flat.

7.1.3 Simplicity of Operation and Maintenance


All aspects of the proposed system will be designed, wherever it is appropriate, in order to ensure
that the operational and maintenance requirements are kept to a minimum.

The above philosophy will generally result in manually operated control systems being installed
rather than automatic systems. The level of technology utilized should be appropriate to the
maintenance capabilities of the operating staff and should not be reliant on outside assistance.
Where appropriate, the systems to be installed should be familiar to the operating staff.

7.1.4 Standardization
It is considered important to have standardization of equipment, both in terms of types of
equipment to be employed and in their sizing. This will simplify operation and maintenance
activities. Steelwork, including ladders, stairs, walkways and handrails shall be locally
manufactured.

7.1.5 Hydraulic Design


The hydraulic analysis of a water transmission system usually involves the use of the Hazen-
Williams or Darcy-Weisbach equations to determine frictional head losses in the various pipes
and appurtenances for various design flow rates. This information can be combined with
topographical data to estimate operating pressures at various locations within the system.

A commonly used form of the Hazen-Williams equation is

H =10.675*L*(Q^1.852)/(C^1.852) *(D^4.87)

Where

Q = the flow rate in meter cube per second

C = a coefficient depending on the smoothness of the interior of the pipe

D = the diameter of the pipe in meters

L = the length of the pipe in meter

H = the frictional head loss in the pipe in meter

February,2017 OWWDSE Page 197


Design of Electromechanical System MWI&E

The C factor, or coefficient, used in the Hazen-Williams equation reflects the relative
smoothness of the inside surface of the pipe under consideration. Typical values range from
about 100 for 20-year-old cast iron, to about 130 for asbestos-cement, to 140 or more for plastic
pipe. Various manufacturers‟ catalogues recommend a C value in the range of 130 mm. therefore
this value can be employed for the design of pumping lines.

Frictional head losses associated with pipe bends, elbows, tees, valves, hydrants, and other
distribution system fittings and appurtenances are classified as Minor losses. For long pipelines,
these losses are generally negligible. However, in pumping stations, where equipment is
concentrated or piping layouts are complex, they can be substantial. The following formula is
employed to calculate the head loss.

Hf = Fc*V^2/2g

Where

Hf = friction loss in fittings & valves in meter/sec

V = velocity of water in meter /sec

Fc = friction coefficient for fittings & valves

g = acceleration due to gravity in meter/sec^2

The friction coefficient depends on the type of fitting and valve employed and construction
features of the item. The values for the specific items used in the design shall be referenced from
design standards and hydraulic text books.

In the pumping station flow velocities should not exceed 1.5 m/s in suction pipe lines and 2.8
m/s in discharge lines. In short transmission pipe lines velocities in the range of 1.6 m/s to 2.2
m/s are recommended.

7.1.6. Pump Station


Pump stations should protect pumps and other equipment from weather and vandalism. Adequate
interior drainage should be provided as well as ventilation to prevent the overheating of
equipment during warm weather. Pumping stations should be large enough to allow free access
to all equipment and to facilitate maintenance work. Repairs that are technically quite simple can
be made very complex by poor placement of pipes and equipment and insufficient room to
maneuver. It is good practice to design pipe layouts and equipment and valve placement with this

February,2017 OWWDSE Page 198


Design of Electromechanical System MWI&E

in mind. Another good approach is to assume that sooner or later every piece of equipment, pipe,
or fitting will fail, and then consider what will have to be done to make the necessary repair or
exchange. Special attention should be given to ensuring that crane ways, are provided to allow
for removal and replacement of heavy items such as pumps, and motors.

Pumps will be designed at a capacity of 110% to 125 % of the design capacity to provide for
leakage in the transmission pipeline. Provision will not be made for any future expansion. Where
more than one operating pumps are required, an additional pump will be installed as a stand-by
unit to maintain the station capacity during maintenance/repair operations.

A pumping system should be capable of delivering the maximum instantaneous design flow.
Absolute maximum allowable pressures are dictated by the pressure ratings of the pipes and
appurtenances used and regulatory requirements. However, system pressures should be kept as
low as is commensurate with the needs. Unnecessarily high pressures are wasteful in terms of the
extra costs of the equipment and energy required to produce them, and the increased volume of
water lost to leakage.

The design should ensure that pumps will operate under a negative suction head. Each pump
should have a gate valve upstream and downstream for maintenance purposes together with a
non-return valve, air relief valve and a pressure gauge downstream. Pump protection devices will
be specified to prevent damages to pumps caused by no water or closed delivery valves. Motors
have to be protected against phase failure as well as too low or high voltage.

Where multiple pumps are used, each one should have its own intake, or the multiple intakes
should be carefully designed to ensure that all pumps have essentially the same inlet conditions.
Care must be exercised to make sure that the pumps always draw water, not an air/water mixture,
or air alone. The specific locations of check valves and other appurtenances will depend on the
inlet conditions, type of storage and piping layout.

7.1.7 Selection of Pumps


It is not possible to select the best pump for a given application until the expected operating
conditions are fairly well defined. The following specific information must be available:

 Minimum safe rate at which water can be supplied to the pump.


 Average and maximum rates at which water must be delivered by the pump

February,2017 OWWDSE Page 199


Design of Electromechanical System MWI&E

 Minimum available net positive suction head (this requires knowledge of the maximum
lift required and all head losses on the intake side of the pump).
 The range of discharge heads the pump must work against (this requires knowledge of the
system head/flow characteristics, which include the effects of all head losses on the
discharge side of the pump).
 Availability of suitable electric power at the site.
 Expected level of operation and maintenance capability (i.e., operator time per day, skill
level of operator, availability of maintenance and repair support).
 Desired placement of pump (e.g., indoors, outdoors, submerged, in a dry well).
 Design period.

Once these and perhaps other site-specific factors are known, it is possible to consult
manufacturers‟ literature and consider the available pumps. A major portion of this process
involves consideration of trade-offs among the reliability, first cost, and operation and
maintenance cost of various pumps having suitable flow/head/efficiency characteristics.

While several kinds of pumps are available, centrifugal pumps are almost always chosen for
deep well or surface-supplied water systems. In the latter case, either horizontal or vertical
pumps may be used. The choice depends largely on the type of intake and storage systems used
and the desired placement of the pump.

Regardless of project size, economic considerations are important in pump selection. However, a
premium should be put on minimizing operational difficulty and expense. Therefore, it is usually
best to use a pump and control system that is simple, rugged, and reliable even though less
expensive (first cost) options may be available. Whenever feasible, pumps and drivers should be
selected that will operate near their peak efficiencies under the actual operating conditions that
are expected. Maximizing the efficiency of pumps and drivers (subject to the constraints of
operational ease and reliability) will tend to reduce operating costs without reducing
dependability significantly, when compared to overdesigned facilities.

The suction conditions available for the pump should be determined for all pumping conditions.
A diagram should be prepared showing the NPSHA for the entire range of pumping conditions.
In all cases the NPSHA should be greater than the NPSHR for the selected pump over the entire
range of required pump operation.

February,2017 OWWDSE Page 200


Design of Electromechanical System MWI&E

The highest efficiency that is commercially attainable should be specified for whatever type of
pump is selected. This will not only control operating costs but will normally improve the
operation of the pump through less vibration, cavitations, and maintenance requirements.

7.1.8. Emergency Operation


The need for an emergency generator will depend on the specific project requirements. As a
general rule, some type of emergency operating capability should be maintained. The relative
importance of such a capability is, of course, a function of the local situation (i.e., type of
scheme, storage capacity, and the ramifications of interrupted service). The most common
method employed is to provide emergency electrical power by a diesel fuel powered generator.
As a general standard, stand-by generation capacity with sufficient power for pump station
output of 50% of design capacity is recommended.

7.1.9. Water Hammer


When the velocity of flow in a pipe changes suddenly, surge pressures are generated as some, or
all, of the kinetic energy of the fluid is converted to potential energy and stored temporarily via
elastic deformation of the system. As the system “rebounds,” and the fluid returns to its original
pressure, the stored potential energy is converted to kinetic energy and a surge pressure wave
moves through the system. Ultimately, the excess energy associated with the wave is dissipated
through frictional losses. This phenomenon, generally known as “water hammer,” occurs most
commonly when pumps are started and stopped or when valves are opened or closed suddenly.
The excess and vacuum pressures associated with water hammer can be significant under some
circumstances.

The magnitude of the maximum potential water hammer pressure surge is a function of fluid
velocity and the pipe material. Some allowance for surge pressure is built into the pressure
ratings of commonly used pipe materials. When it is anticipated that water hammer may be a
problem analysis of hydraulic transients to estimate surge pressures is required. The
requirements for water hammer protection shall be determined on a case by case basis during the
design phase. If it is determined that protection is necessary, the protection method shall be
incorporated into the design.

Based on the analysis results, consideration should be given to the use of slow-operating control
valves, safety valves, surge tanks, air chambers, and special pump control systems.

February,2017 OWWDSE Page 201


Design of Electromechanical System MWI&E

7.1.10. Miscellaneous
 Fuel tanks
The design should specify day tanks to be supplied integral with the generator set. Employment
of a gravity system for the supply of the day tank from the storage tank is preferred. This will
entail locating the storage tank at a higher elevation and design of a ramp for unloading fuel into
the storage tank.

The overhead crane travel shall be coordinated with the equipment to be lifted, loaded, and
unloaded. The pump house building design shall include room for a vehicle to enter the facility
for loading and unloading pumping equipment. This shall be coordinated with the civil
engineering design.

 Gates
Slide gates are classified as either pressure-seating or pressure-unseating type and having either a
rising or a non-rising stem. In all cases, slide gates should be designed to provide positive seating
by means of suitable wedges. Slide gates provide a more positive means of sealing than any
other types of closure. In general, the use of pressure unseating gates should be avoided unless
the stem threads are exposed to fouling or abrasive materials, it would be difficult to maintain the
wedge. Rising-stem gates are preferred due to their easy maintenance and the locations of thread
engagement outside the corrosive area. Non-rising stems are to be used only if there is
insufficient head room for a rising stem. Slide gates are normally limited to a 3.0-meter (10-foot)
opening width. Gates used for pumping station service are usually of the flush bottom style. This
style gate permits station design without steps in the flow line. All slide gates should be mounted
on an "F" type wall thimble which is cast into the concrete wall. A flange back type gate is
recommended since they are the strongest.

 Trash Protection

Trash-racks are required to protect the pumps from debris which could clog or damage the
pumps. Accumulated debris in front of the racks should be removed to prevent structural damage
to the trash-racks or damage to the pumps due to restricted flow into the pump sump. Hand
raking and power raking are two methods used for removing trash from the rack.

Hand raking should be used when the amount of trash can be handled with manually raked
methods. The rake handle should be less than 6 meters but should reach the bottom of the rack

February,2017 OWWDSE Page 202


Design of Electromechanical System MWI&E

with the operator standing on the trash-rack platform. Hand railing should be provided for safe
hand raking operations.

 Equipment Handling

A station crane should be provided, for handling the major items of equipment. Small stations
may be built with removable ceiling hatches so that a mobile crane may be used when work is
required.

Bridge-type cranes are usually used, but a monorail type over the pumping units may be used if
that is the only requirement for the crane and it is capable of doing the job. Cranes of less than 3-
ton lifting capacity should be of the manual type. Cranes with capacities from 3-to 10-ton lifting
capacity may be equipped with a motorized hoist while still retaining manual travel
arrangements. Cranes over 10-ton capacity should be of the three-motor type, where all functions
of the crane are motorized. Hoist and travel speeds can be kept to a minimum since the crane will
be used only for major maintenance. The high position of the crane hook should be at such an
elevation to permit removal of the pump. Allowance should be made for use of slings and lifting
beams plus some free space.

 Ventilation

The ventilation system shall be designed in a manner to optimize the airflow across the motors. It
shall avoid intake or exhaust openings over electrical equipment. Intake or exhaust openings
shall not be installed on the roof.

The fresh air inlet areas should be a minimum of twice the outlet area to prevent high losses. The
operating area is ventilated to remove any gases and to remove excess heat buildup caused by the
operation of the electrical and mechanical equipment. The system design is based on the amount
of air to be removed in order to have an inside temperature not greater than 40 degrees C. The
design should consider outside maximum temperatures occurring coincident with operation.

 Sump dewatering

Provisions should be provided to dewater the sumps between pumping periods for inspection and
to perform maintenance and repairs. The dewatering may be accomplished by means of one or
more sump pumps. The sump pumps should be of the submersible motor/non-clog pump type.

February,2017 OWWDSE Page 203


Design of Electromechanical System MWI&E

Dewatering sumps are normally located outside the main pump sumps to avoid disturbing flow
patterns to the main pumps. Any interconnecting piping should be kept to a minimum and should
be installed so that it may be unclogged.

In the design of pumping and accessory equipment, ratings that are specific to particular
manufacturers shall not be employed.

7.1.11. Electrical System


The design investigations should disclose the location of the nearest EEPCO facilities which may
be involved in the supply of power to the pumping station, voltage regulation, starting current
limitations and power factor restrictions.

Costs which must be considered for the electrical design include line construction, substation
installation, motors, controls, conduit/ cable sizes, and floor space required.

7.1.11.1. Motors
Constant-speed motors of either the squirrel-cage induction or synchronous type are the preferred
drives for pumps installed in pumping stations. Both squirrel-cage and synchronous motors are
available in speed ranges and sizes that embrace most requirements. All motors should be
designed for full-voltage starting, even if incoming power limitations indicate that some form of
reduced-voltage starting is required.

There are three basic variables that classify motor performance types. These are:

 Starting torque.
 Starting current.
 Slip.

Motors can have high or low starting torques, starting currents, and slip. However, these six
variables are not produced in every combination. For example, high resistance rotors produce
higher values of starting torque than low resistance rotors. But high resistance in the rotor also
produces a "high slip" motor. A high slip motor, by definition, has higher slip losses, hence
lower efficiency, than an equivalent low slip motor.

Squirrel-cage induction motors have very simple construction, with no electrical connections to
the rotor, and hence they possess a very high degree of reliability. However, the squirrel-cage
rotor does not rotate as fast as the revolving magnetic field setup by the stator winding. This

February,2017 OWWDSE Page 204


Design of Electromechanical System MWI&E

difference in speed is called "slip." Because of this inherent feature, squirrel-cage motors are not
as efficient as synchronous motors, whose rotors rotate in synchronization with the magnetic
field. In general, their usage is preferred for pump drive requirements less than 375 kW (500
HP).

The synchronous motor starts and accelerates its load utilizing the induction principles common
to a squirrel-cage motor. However, as the rotor approaches synchronous speed (approximately 95
to 97 percent of synchronous speed), a second set of windings located on the rotor is energized
with direct current. These field coil windings are responsible for providing the additional torque
necessary to "pull" the rotor into synchronism with the revolving magnetic field established by
the stator windings. The time at which direct current is applied to the field coil windings is
critical and usually takes place when the rotor is revolving at approximately 95 to 97 percent of
synchronous speed. Synchronous motors are preferred as pump drives in the large capacity, low
rpm mixed flow-or propeller-type pumps. In general, their usage should be limited to pumps of
at least 375 kW (500 HP) and above, and at speeds of 500 rpm and below.

Most motor Specifications limit the locked rotor current to 600 percent of rated (full-load)
current. However, EEPCO requirements specify reduced-voltage starting, to reduce starting
current for motors above 7.5kw. Reduced-voltage starters of the autotransformer type or star-
delta starters should generally be used. Caution must be exercised in the application of reduced
voltage starting, however, since the motor torque is reduced as the square of the impressed
voltage. Connections should be made at the lowest tap that will give the required starting torque.

Solid state motor starters employing phase-controlled thyristors are an option to reduce inrush
currents for 400-volt motor applications. However, the reliability, price, availability of qualified
maintenance personnel, and space considerations should all be studied carefully before electing
to use solid state starters.

Duty Cycle Care should be taken in the selection of the number and size of pumps to avoid
excessive duty cycles. Mechanical stresses to the motor bracing and rotor configuration as well
as rotor heating are problems with frequently started motors. The number of starts permissible
for an induction motor should conform to the limitations given, by the motor manufacturer
concerning the frequency of starting requirements. Economic comparisons of different pumping

February,2017 OWWDSE Page 205


Design of Electromechanical System MWI&E

configurations should include the reduction in motor life as a function of increased motor starting
frequency.

The motor must be designed with sufficient torque to start the pump to which it is connected
under the maximum conditions specified, but in no case should the starting torque of the motor
be less than 60 percent of full load.

For squirrel-cage induction motors, the design should be checked to ensure that the motor has
sufficient starting torque to accelerate the load over the complete starting cycle. Breakdown
torque should not be less than 200 percent of full load unless reduced voltage starting is
employed. Then the breakdown torque must be reduced to 150 percent of full load.

7.1.11.2. Disconnecting Device


The main pumping station disconnecting device should be located within the station as part of
the EEPCO/standby generator changeover panel.

The main for the changeover panel could be a molded case circuit breaker, power air or vacuum
circuit breaker, or a quick-make, quick-break fusible interrupter switch.

Below 600 volts, circuit breakers and fuses are generally available in all continuous current
ratings and interrupter ratings likely to be encountered.

Some general advantages and disadvantages of a fusible interrupter switch include:

Advantages

 Simple and foolproof


 Constant characteristics
 Initial economy
 No maintenance

Disadvantages

 Self-destructive
 Requires spares
 Nonadjustable
 No remote control

Some general advantages and disadvantages of a circuit breaker include:

Advantages

February,2017 OWWDSE Page 206


Design of Electromechanical System MWI&E

 Remote control
 Multipole
 Smaller, convenient
 Resettable
 Adjustable

Disadvantages

 Periodic maintenance
 Higher initial cost

7.1.11.3. Control panels


In general, motor control centers are preferred over "metal enclosed low-voltage power circuit
breaker switchgear" for control of motors 400 volts and below in pumping station design. While
metal-enclosed switchgear is a high quality product, its application is found more in feeder
protection and starting and stopping of infrequently cycled motors and generators. Another
consideration in the choice between the two is the relative cost. Metal-clad switchgear is
approximately three times as expensive as an equivalent line-up of motor controllers.

Experience has shown that frequent operation of power circuit breakers requires additional
maintenance of the various mechanical linkages that comprise the operating mechanisms. Since
maintenance of pumping station equipment is usually a local responsibility, every effort should
be made to reduce system maintenance and optimize station reliability. Magnetic starters provide
a simple, reliable, and less expensive alternative to the usage of power circuit breakers.
Combination magnetic starters are available in either the circuit breaker or fusible type.

Controls, alarms, and devices to indicate system status should be grouped on a control console so
that one operator can conveniently initiate control sequences and observe the system response
Care should be taken to include a monitoring capability for all essential pumping system
parameters. Some alarms that may be required include motor and pump bearing temperatures,
motor winding temperature, motor trip and lockout relays, motor or gear cooling water failure,
excessive pump discharge piping pressures or flow rates, lubrication system failures, abnormal
water levels, etc. A graphic display is an effective means of grouping alarm and status
information.

February,2017 OWWDSE Page 207


Design of Electromechanical System MWI&E

7.1.11.4. Motor protection


Protection of the motor is provided by thermal overload relays, which are normally built into the
starter itself. The bi-metallic type relay has two advantages not found in the fusible-alloy type: it
can reset itself automatically and can compensate for varying ambient-temperature conditions if
the motor is located in a constant temperature and the starter is not. The heaters must be sized to
accept the starting current of the motor for the expected starting time without causing the
contactor to open. To achieve this with a variety of connected loads, conventional starters are
available with a range of standard heaters, which can be selected according to the application.

Each motor controller enclosure is divided into a high-and low voltage section. The high-voltage
section contains the magnetic contactor and its protective fuses. The low voltage section contains
the controls and protective relaying. Contingent upon motor size and relaying requirements, one,
two, or three starters can be located in one vertical section. Power for control relays is usually
220 volts but may be 48-, 125-, or 250-volt DC.

The contactor itself is not capable of interrupting a short circuit and must be protected by silver-
sand type current limiting fuses. One limitation of such fuses is that, should a short-circuit occur
on one phase only, only that fuse will blow, and the motor will continue to operate on the single
phase between the remaining two lines. This can be avoided by the addition of suitable relaying.
The contactor may also incorporate a trip mechanism that is actuated by the blown fuse itself.
Either protective relaying or a mechanical trip mechanism should be provided.

For motors rated below 375 kW (500 HP), protection against loss of voltage or low voltage is
generally provided by the three-phase time-delay under-voltage relay. This would, In addition
provide protection against phase sequence reversal should it occur between the source and the
motor‟s associated switchgear. For short-circuit, stalled-rotor, and running overload protection; a
relay which has a thermally operated time-over current characteristic is used. It is generally to be
preferred for this application over an inverse time-over-current relay Sensitive and fast ground-
fault protection is provided by instantaneous ground-sensor equipment.

The running overload protection device operates from a resistance temperature detector
embedded in the machine stator winding. It is to be preferred over the stator-current-operated
device, since it responds to actual motor temperature. An additional relay is required to provide
protection against stalled rotor conditions since the resistance-temperature detector used with the

February,2017 OWWDSE Page 208


Design of Electromechanical System MWI&E

running overload protection device will not respond immediately to fast changes in the stator
conductor temperature as would be the case under stalled conditions.

7.1.11.5. Water Level Sensors


variety of sensors are available for use in sensing water levels, including float-actuated mercury
switches, float-actuated angle encoders, bubbler systems, bulb-type floats, etc. The use of float-
actuated mercury switches is discouraged due to environmental concerns. A comparison should
be made of the particular pumping station requirements in relation to the various level sensor
capabilities before deciding upon the system to be employed.

7.1.11.5. Station Wiring


The reliability of the entire electrical installation will be only as good as that of the wiring by
which the various items of power supply, power distribution, control and utilization equipment
are interconnected. Selection of proper materials and methods of construction for the wiring
system are therefore a matter of prime importance. The following basic principles should be
observed in design of pump station wiring systems.

For the mechanical protection of wiring and for the safety of operating personnel, all station
wiring should be enclosed. Rigid galvanized steel conduit is the most commonly used material
for raceways and is suitable for all locations where wiring is required within a pumping station.
If it is necessary to run conduits exposed below the operating floor, consideration should be
given to polyvinyl chloride (PVC) coated rigid galvanized steel or PVC conduit.

Conductors wire and cable for pumping stations should be furnished with moisture-and heat-
resisting insulation. Sizes of conductors should be in accordance with the standards for motor
feeders and branch circuits.

7.1.11.6. Surge Protection


Special care should be taken to reduce the magnitude of Lightning-induced voltage surges to
avoid major damage to the electrical equipment contained within. A relatively small investment
can greatly reduce the voltage stresses imposed on rotating machinery and switchgear by
lightning-induced surges.

There are two transient elements of a voltage surge that require different protective equipment.
The protection of the major insulation to ground is accomplished by station surge arresters which

February,2017 OWWDSE Page 209


Design of Electromechanical System MWI&E

limit the amplitude or reflections of the applied impulse waves within the motor windings. The
protection of turn insulation by reducing the steepness of wave fronts applied to or reflected
within the motor windings is accomplished by protective capacitors.

7.1.11.7. Auxiliary Power Distribution


Auxiliary loads of 400 volts and below are most conveniently distributed by means of a power
panel(s) either mounted in a vertical section of the motor control center or in a strategic location
along a station wall. This power panel(s) should be fed from a circuit breaker or fusible
disconnect switch in the motor control center.

In general, 400 / 230-volt, three-phase, four-wire systems are recommended for lighting loads. A
minimum of 20-percent spare circuits should be provided for future expansion. Operating floor
lights, floodlights, and other lights that may be used for considerable periods of time should
usually be of the high-pressure sodium-type due to their efficiency. Following are typical light
levels for various pumping station areas:

Location LUX

Operating Floor 325

Control Room 540

Sump/Catwalk 215

Roadway 10

7.2. Design of the elector mechanical system


Based on the above design criteria the following pump and other electromechanically part had
designed. Horizontal centrifugal pump will be used and installed at lower level than wet-well
water level.

In the following the detail design and calculations of the major components of the
electromechanical system are set out in detail.
Table : Design Data for electro mechanical part

Channel full supply level, masl 1255.13

Pump Station Ground level, masl 1258.18

NSR inlet level, masl 1316.25

February,2017 OWWDSE Page 210


Design of Electromechanical System MWI&E

Static Head, m 61.12

Pumping Time, hr 20

Required discharge from Pump Station, l/s 12,201

Design discharge from Pump Station, m3/s =12.201*1.1=13.4

Length of rising main pipe from pump station to NSR, m 670

Required number of rising main lines 2

7.2.1..Intake channel and well


A manual gate and stop log system will be designed at the inlet to the channel, which supplies
the wet well at PS, as part of the civil works design. A trash rack will be built at the end of
channel.

7.2.2. Wet well


The open roof type wet-well will have a minimum chamber height which is the sum of the bottom
clearance height between the suction pipes and the chamber floor plus the height between suction
pipe and canal water level plus freeboard allowance which would ensure that the top of the wet-
well is above the canal bank level to avoid any overflow problems.

ha = bottom clearance = D/2+1 (Considering of the quality of canal water)


Where D is the suction pipe diameter=0.7 m
ha = 0.7/2+1 = 1.35 m
hx = level difference between suction pipe and water level = D/2+1.5=1.85 m
hc = freeboard allowance= 1.3 m
Therefore, minimum height of the wet-well is
H= ha + hx + hc = 1.35+1.85+1.3 =4.5 m
Wet-well top level = 1255.13+1.3 = 1256.43 masl
The length of the wet-well is governed by the pumping arrangement selected and is 104 meter. An
internal width of 5 meter is selected to provide sufficient access for installation and cleaning.

February,2017 OWWDSE Page 211


Design of Electromechanical System MWI&E

7.2.3 Trash rack


Three trash racks at canal will be installed and the dimensions of a trash rack are a width of 2
meters and a height of 2 meters. The spacing between the bars is limited to 8 cm.

7.2.4. Sliding Gate


A sliding type manually operated gates will be installed at the inlet of the wet-well to isolate the
channel during maintenance operations in the wet-well. Three canals are in the inlet and service
gate and emergency gate will be installed in a canal. Total six gates will be a pressure sitting type
with a rectangular opening of 2*2 meters.

7.2.5. Selection of Pipe Sizes


For the design of suction and discharge piping and the rising main pipeline from PS to NSR, flow
velocity limits described in the design criteria section were adopted. The following formula is
used for calculating pipe sizes.

V = 1.274*Q / D2

𝟏. 𝟐𝟕𝟒 ∗ 𝐐
𝐃=
𝐕

Where
V = velocity of water in pipe in m/sec
Q = station design discharge in m3/sec
D = diameter of selected pipe in meters
The calculations were made for the selected pumping arrangements of 24+4(two groups, 12+2 in
one group). Rising main choice is to employ twin transmission lines from PS to NSR. The results
and the selected diameter of the pipes are shown in below table. The pipes are seized, based on the
selection of commercially available pipes with the minimum diameter but satisfying the suction
and discharge velocity limits.

As per the calculation, pipe diameters of 700mm, 500mm and 2000mm are the minimum
diameters satisfying the velocity limits for the suction, independent discharge and
manifolddischarge systems respectively. For the PS-NSR twin rising main pipe diameter of 2000
mm satisfies the velocity criteria.

February,2017 OWWDSE Page 212


Design of Electromechanical System MWI&E

For upper lifted block of 1104.58ha the pumnp was designed and the total number of pump is nine
and it required 982kw power.

Table : left side pump station piping calculation

Frequency 50hz
Discharge (m3/hr) 48,240.0
Discharge (l/s) 13,400.0
Wet well water level (masl) 1255.13
Discharge reservoir level (masl) 1316.25
Static head (m) 61.12
No of duty pumps 24
No of standby pumps 4
Total No of pumps 28
Single pump discharge (m3/hr) 2016
Single pump discharge (l/s) 560
Rising main pipe length (m) 670
Manifold pipe length (m) 104
Independent suction pipe length (m) 4
Independent discharge pipe length (m) 6
No of rising main pipes 2
Allowable velocity (m/s), suction side, independent 1.50
Allowable velocity (m/s), discharge side, independent 2.8
Allowable velocity (m/s), manifold 2.2
Allowable velocity (m/s), rising main, twin 2.2
Independent suction pipe dia (m) 0.689
Independent discharge pipe dia (m) 0.5
Manifold pipe dia (m) 1.971
Alternative – rising main dia (m), twin 1.971

Actual independent suction pipe dia (mm) 700


Actual independent discharge pipe dia (mm) 500
Actual manifold pipe dia (mm) 2000
Actual rising main dia (mm), twin 2000

Actual velocity (m/s), suction side, independent 1.453


Actual velocity (m/s), discharge side, independent 2.5
Actual velocity (m/s), manifold 2.14
Actual velocity (m/s), rising main, twin 2.14

February,2017 OWWDSE Page 213


Design of Electromechanical System MWI&E

7.2.6. Selection of Pumps


The first step in the selection is calculation of the system head, to identify system operation points,
followed by pump selection calculations. Next Surge analysis is performed with the parameters of
the selected pumps.

7.2.7. System head


The system head calculations were made for the selected pump layouts, employing the pipe sizes
calculated above. The hazen-williams formula described in the design criteria is employed for the
calculations. In order to identify the maximum NPSH requirements, the system heads were also
calculated for situations where only one or several pumps are operating.

In this project, to identify the NPSH is not needed because pump level is lower than supply water
level.
The following K factors were adopted for the calculation of head losses in fittings and valves.
Table ; Left Side pump station , valve factor k

Type of fitting/valve K factor

Reducer in pump independent suction 0.5

Gate valve in pump independent suction 0.4

Enlarger in pump independent discharge 0.3

22.5° Bend in pump independent discharge 0.1

Gate valve in pump independent discharge 0.4

Check valve in pump independent discharge 1.5

Tees in manifold 0.7

Butterfly valve in rising main pipe 0.5

45° Bends in rising main pipe 0.2

90° Bends in rising main pipe 0.8

90° Bends in NSR inlet 0.8

The results of the detail calculations for head loss in valves, fittings and lines are shown in
Table : Head loss in valve, fittings and lines

February,2017 OWWDSE Page 214


Design of Electromechanical System MWI&E

ITEM VALUE

Reducer in pump independent suction 0.1 m

Gate valve in pump independent suction 1.28 m

Enlarger in pump independent discharge 0.199 m

22.5° Bend in pump independent discharge 0.664 m

Gate valve in pump independent discharge 0.166 m

Check valve in pump independent discharge 0.623 m

Tees in manifold 0.291 m

Butterfly valve in rising main pipe 0.123 m

Two 45° Bends in rising main pipe 0.099 m

Three 90° Bends in rising main pipe 0.593 m

Two 90° Bends in NSR inlet 0.395 m

Headloss in rising main pipe 3.648 m

Total head loss (m) 8.181 m

Static head (m) 61.12 m

Actual pumping head is calculated as following.


Pumping head = static head +total head loss =
= 61.12 + 8.181 = 69.3 m
Table : Required data to select pump

ITEM VALUE

Required design discharge at PS (m3/s) 13.4

Number of working pumps 24

Number of standby pump 4

Required discharge at a pump (m3/s) 0.56

Working head of pump (m) 69.3

Required efficient More than 0.75

February,2017 OWWDSE Page 215


Design of Electromechanical System MWI&E

Based on the above results, pump model are selected from manufacturer catalogues. The detail
data of the pumps are shown in the following tables and charts.

Table : Model Pump Data

ITEM VALUE

Type of Pump Horizontal Surface Centrifugal Pump

Head, H (m) 70

Discharge, Q (m3/hr) / q (m3/s) 2016 / 0.56

Rotation (rpm) 1470

Output Dia (inch / mm) 10 / 250

Input Dia (inch / mm) 12 / 300

Weight (kg) 658

The hydraulic coverage of selected pump is shown at below figure.

February,2017 OWWDSE Page 216


Design of Electromechanical System MWI&E

Figure Graph showing head versus capacity of pump

7.2.8. Calculation For Electric Power for LLMC discharge


Required electric power at PS is calculated as following
P∗Q
N = 1.1 ∗ 102∗η
1η2

Where N: required power for pumping(Kw)

P = 69.3m : system head (m)

Q = 13400 ℓ/s : discharge at PS (ℓ/s)

η1 = 0.75 : efficient of pump

η2 = 0.85 : efficient of electric motor


69.3∗13400
N = 1.1 ∗ = 15,709 KW
102∗0.75∗0.85

February,2017 OWWDSE Page 217


Design of Electromechanical System MWI&E

7.2.9 Calculation for electric power of LLUB1

Required electric power at PS(A) is calculated as following


P∗Q
N = 1.1 ∗ 102∗ η 1 η 2

Where N: required power for pumping(Kw)

P = 22.07m : system head (m)

Q = 315 ℓ/s : discharge at PS (ℓ/s)

η1 = 0.7 : efficient of pump

η2 = 0.7: efficient of electric motor


22.07∗315
N = 1.1 ∗ = 139 KW
102∗0.7∗0.7

The capacity of a electric motor is calculated as following.

N1 = N / number of working pumps = 139 /2= 69.5 KW

Therefore the adopted capacity of Electric motor is 75 KW.

7.2.10 Calculated for electric power of LLUB2


Required electric power at PS(A) is calculated as following
P∗Q
N = 1.1 ∗ 102∗ η 1 η 2

Where N: required power for pumping(Kw)

P = 25.3m : system head (m)

Q = 211 ℓ/s : discharge at PS (ℓ/s)

η1 = 0.7 : efficient of pump

η2 = 0.7: efficient of electric motor


25.3∗211
N = 1.1 ∗ = 106.8 KW
102∗0.7∗0.7

The capacity of a electric motor is calculated as following.

N1 = N / number of working pumps = 106.8 /2= 53.4 KW

Therefore the adopted capacity of Electric motor is 55KW.

February,2017 OWWDSE Page 218


Design of Electromechanical System MWI&E

Required electric power at PS(B) is calculated as following


P∗Q
N = 1.1 ∗ 102∗ η 1 η 2

Where N: required power for pumping(Kw)

P = 50.8m : system head (m)

Q = 323 ℓ/s : discharge at PS (ℓ/s)

η1 = 0.7 : efficient of pump

η2 = 0.7 : efficient of electric motor


50.8∗323
N = 1.1 ∗ = 328.3 KW
102∗0.7∗0.7

The capacity of a electric motor is calculated as following.

N1 = N / number of working pumps = 328.3 /2 = 164 KW

Therefore the adopted capacity of Electric motor is 170KW.

Required electric power at PS(C) is calculated as following


P∗Q
N = 1.1 ∗ 102∗ η 1 η 2

Where N: required power for pumping(Kw)

P = 75.4 m : system head (m)

Q = 204 ℓ/s : discharge at PS (ℓ/s)

η1 = 0.7 : efficient of pump

η2 = 0.7: efficient of electric motor


75.4∗204
N = 1.1 ∗ = 307.7 KW
102∗0.7∗0.7

The capacity of a electric motor is calculated as following.

N1 = N / number of working pumps = 307.7 /2= 154 KW

Therefore the adopted capacity of Electric motor is160 KW.

Required electric power at PS(D) is calculated as following

February,2017 OWWDSE Page 219


Design of Electromechanical System MWI&E

P∗Q
N = 1.1 ∗ 102∗ η 1 η 2

Where N: required power for pumping(Kw)

P = 97.8m : system head (m)

Q = 171 ℓ/s : discharge at PS (ℓ/s)

η1 = 0.7 : efficient of pump

η2 = 0.7 : efficient of electric motor


97.8∗171
N = 1.1 ∗ = 334.6 KW
102∗0.7∗0.7

The capacity of a electric motor is calculated as following.

N1 = N / number of working pumps = 334.6 /1 =335 KW

Therefore the adopted capacity of Electric motor is 345KW.

February,2017 OWWDSE Page 220


Cost Estimations MWI&E

8. COST ESTIMATION OF PHASE IIA PROJECT


It is very important to estimate the total cost required for the implementation of the whole project
though it is not detail at this draft feasibility report stage. Since major work areas are identified
like the water abstraction system, the diversion head work and its‟ major quantity of work, the
three big main canals like left main canal, gravity canal and lifted canal with numbers of
structures like (inverted siphons, flume, Cross regulators, escape), the major electro-mechanical
works like number of pumps, diameter and length of pipes including the electrical consumption
are known.

All the irrigation development of under gravity and lifted canals of 11,326.70ha from the system
layout the canals like primary canal (PC), SC, TC, TD, CD, SD length and the discharge
capacity required and related dimensions are known. The numbers of structures along these
canals like culvert, off takes, drops, escapes, division box, and outfalls were also known
therefore the cost can be estimated as the following tables after preparing unit rate considering
the local labour cost and the price of inputs material.

February,2017 OWWDSE Page 221


Cost Estimations MWI&E

Table Cost estimation of Head work, main canals and related structures

N Description Unit Qty Gravity block Lifted Block Upper lifted Total birr
O (the Block
whole Qty Amount (birr) Qty Amount(birr) qty Amount
)
1 Diversion head NO 0.5 - - - - 132,645,793.80
work &
appurtenant
structure
2 Left main canal km 46.6 - - - - 606,692,766.60
and related
structure cost
3 Left gravity canal km 84.56 84.5 233,953,388.90 - - 233,953,388.90
and related 6
structure of t cost
4 Left Lifted Gravity km 57.25 - - 57.2 445,204,277.8 445,204,277.80
canal and related 5
structure cost
5 Electro- NO LSM - - - 273,262,628.3 273,262,628.33
Mechanical cost 3
LLMC
6 Electro- LSM - 63,429,01 63,429,012

February,2017 OWWDSE Page 222


Cost Estimations MWI&E

Mechanical cost 2
for ULLC
Total cost 1,755,187,867.4
VAT 15% 263,278,180.11
Total cost 2,018,466,047.5
including VAT

Table : Cost estimation of farm work canals and related structure phase IIA project

N Description Un Gravi Lifted Block Upper Total birr


O it ty lifted
block
Qty Amount (birr) Qty Amount(birr) Qt amount
y
1 All primary canals km 6.526 6,224,992.21 56.656 59,945,519.86 66,170,512.07
cost
2 All structures on km 6.526 281,575.51 56.656 14,029,068.76 14,310,644.27
PC cost
3 All Secondary km 48.76 25,924,234.55 71.66 47,035,587.93 6 14,339,755 87,299577.48
canal cost
4 All structures on km 48.76 84,765,458.98 71.66 141,977,157.63 6 13,681,723 240,424,339.61
SC cost

February,2017 OWWDSE Page 223


Cost Estimations MWI&E

5 All tertiary Canal km 197.4 69,072,634.06 285.95 90,768,726.38 56 18,760,895 178,602,255.44


cost 8
6 All Structures on km 197.4 22,339,282.14 285.95 36,961,920.51 56 31,270,955 90,572,157.65
TC 8
7 All structure on FC km 4,731,798.40 10,090,949.34 252,827.79 15,075,575.53
canal
Sub total 213,339,975.85 400,808,930.41 78,306,156 692,455,062.05

Add VAT 15% 32,000,996.377 60,121,339.56 11745923.37 103,868,259.35


Total cost 245,340,972.23 460,930,269.97 90,052,079.97 796,323,321.36
including VAT

February,2017 OWWDSE Page 224


Cost Estimations MWI&E

Table : Cost estimation of farm work drainage canals and related structures

N Description Unit Gravity block Lifted Block Upper lifted Total birr
O Qty Amount (birr) Qty Amount(birr) Qty Amount

1 All tertiary Drain km 142.63 11,708,024.56 180.844 31,063,305.78 32.80 6,275,625.79 49,046,956.13
canal(TD) earth work
2 All structure on TD NO 142.63 14,641,749.77 180.844 20,760,045.80 32.80 3,711,799.41 39,113,594.98
canal
3 All secondary Drain km 26.721 15,748,385.03 14.87 12,523,954.36 28,272,339.39
canal (SD) earth
work
4 All structure on SD NO 26.721 58,910,286.09 14.87 39,396,890.27 98,307,176.36
5 All collective Drain km 9.223 5,345,450.66 15.377 5,244,501.96 10,589,952.62
canal(CD) earth work
6 All structure on CD NO 9.223 6,895,222.50 15.377 5,706,861.96 12,602,084.46
canal
Total 113,249,118.6 114,695,560.13 9,987,425.20 237,932,103.94
1
Add15% VAT 16,987,367.79 17,204,334.01 1,498,113.78 35,689,815.591
Total cost including 130,236,486.4 131,899,894.15 11,485,538.9 273,621,919.531
VAT 0

February,2017 OWWDSE Page 225


Cost Estimations MWI&E

Table : Cost estimation of road network and related structures of phase IIA project

Description unit Qty Gravity block Lifted Block Total (birr)


all Qty Amount (birr) Qty Amount(birr)
NO
1 main road along km 46.6 - - - - - -
LMC
1.1 Clearance km 46.6 - - - - - 2,687,703.16
1.2 Drainage system km 46.6 - - - - - 34,718,258.13
1.3 Earth work km 46.6 - - - - - 108,956,701.25
1.4 Subase , course and km 46.60 - - - - - 12,815,557.17
& gravel
1.4 Ancillary work km 46.6 - - - - - 2,552,519.87
Subtotal - - - - - - 161,730,739.58
2 Road along LGC km 84.57 - - - - -
2.1 Clearance km 84.57 84.57 3,274,719.64 - - - 3,274,719.64
2.2 Drainage work km 84.57 84.57 14,452,776.91 - - - 14,452,776.91
2.3 Earth work km 84.57 84.57 165,350,535.61 - - - 165,350,535.61
2.4 Sub base course & km 84.57 84.57 14,452,776.91 14,452,776.91
gravel
2.4 Ancillary work km 84.57 84.57 1,629,208.67 - - - 1,629,208.67
Subtotal - - - 199,540,518.67 - - 199,540,518.67

February,2017 OWWDSE Page 226


Cost Estimations MWI&E

3 Road along LLGC km 57.25 - - 57.25 - - -


3.1 Clearance km 57.25 - - 57.25 - 2,764,738.51 2,764,738.51
3.2 Drainage work km 57.25 - - 57.25 - 20,231,290.48 20,231,290.48
3.3 Earth work km 57.25 - - 57.25 - 112,741,667.93 112,741,667.93
3.4 Subase course & km 57.25 - - 57.25 - 13,622,341.22 13,622,341.32
gravel
3.5 Ancillary work km 57.25 - - 57 - 2,139,531.20 2,139,531.20
Subtotal - - - 199,540,518.67 - - 151,132,245.78 151,132,245.78
Total main roads 199,540,518.67 151,132,245.78 512,403,504.03
Farm road
4 All roads along PC km 4.78 188,524.57 20.793 2,387,914.08 2,576,438.65
5 All road along SC km 53.55 4,331,634.68 88.033 6,833,697.99 11,165,332.67
6 All roads along Tc km 222.1 11,207,257.87 297.17 24,344,754.55 35,552,012.42
3
7 All road along CD km 1.1 295,111.32 2.480 336,985.99 632,097.31
8 All road along SD km 18.45 10,033,784.83 7.060 3,812,838.23 13,846,623.06
9 All road along TD km 11.12 1,895,396.50 19.83 7,602,823.08 9,498,219.58
Subtotal FR 27,951,709.77 45,319,013.92 73,270,723.69
Total road 227,492,228.44 196,451,259.70 585,674,227.72
15% VAT 34,123,834.266 29,467,688.955 87,851,134.158
Total cost inc VAT 261,616,062.70 225,918,948.65 673,525,361.878

February,2017 OWWDSE Page 227


Cost Estimations MWI&E

Table : Cost summary of head work, gravity and lifted blocks of irrigation and drainage phase IIA project

N Description Unit Qty Gravity block Lifted Block Upper li block Total birr
O (the Qty Amount (birr) Qty Amount(birr) q
whole t
) y
1 Diversion head work NO 0.5 132,645,793.80
2 Left main canal &structure km 46.6 606,692,766.60
3 LGC&LLGC including km 84.5 233,953,388.9 57.25 445,204,277.80 679,157,666.7
structure 8
4 Electro-mechanical work NO LSM 273,262,628.33 63,429,012 336,691,640.33
5
6 All farm work Canal and 213,339,975.85 400,808,930.41 78,306,156 692,455,062.05
related structures
7 All Farm work Drainage 113,249,118.61 114,695,560.13 9,987,425.20 237,932,103.9
canal and related structure
6 Road along LMC km 46.6 161,730,739.5
7 Road along LGC,LLGC& km 84.57 199,540,518.67 57.25 151,132,245.78 350,672,764.4
farm road
Total cost 760, 083,002.03 1,385,103,642.45 151,722,593. 3,197,978,537.28
20
ADD VAT15% 114,012,450.30 207,765,546.36 22,758,388.9 479,696,780.59
Total inc VAT 874,095,452.33 1,592,869,188.82 174,480,982. 3,677,675,318.87
2

February,2017 OWWDSE Page 228


Cost Estimations MWI&E

Table : Cost summary of gravity, lifted, head work and LMC Of phase IIA versus area of project

No Description Unit Qty Amount (birr) Remark


1 Diversion weir NO 0.50 132,645,793.80 50%
2 Left Main Canal , road , and KM 46.6 768,423,506.10
structure
3 All Gravity block of Ha 3957.87 760,083,002.03
irrigation and drainage system
cost
4 All Lifted block of all Ha 6264.25 1,385,103,642.45
irrigation and drainage system
cost
5 All upper lifted block ha 1104 151,722,593.20
irrigation and drainage system
Total cost 3,197,978,537.58
Add 15% VAT 479,696,780.64
3,677,675,318.22

February,2017 OWWDSE Page 229


References MWI&E

9. LIST OF REFERENCES
A.JAisenberg, R.Bhayes, HJWarner, Bl Winjeff and RB young. 1978. Design of Small canal
Structures United State Department of Interior bureau of Reclamation A water Resource
technical publication. Denver, Colorado, USA.

Cheng, Y. M., Lansivaara, T. and Wei, W. B. (2007) Two-dimensional slope stability analysis by
limit equilibrium and strength reduction methods. Journal of Computers and Geo-techniques,
Vol. 34, pp.137-150

Concert Engineering and consulting Enterprise in association with continental consultant, 2002 ,
design guide line on Irrigation structures , FDRE,MWR, Addis Ababa, Ethiopia

Concert Engineering and consulting Enterprise in association with continental consultant, 2002
, design guide line on Irrigation system , FDRE,MWR, Addis Ababa, Ethiopia

Duncan, J.M. (1996) State of art: limit equilibrium and finite element analysis of slopes, ASCE,
Journal of Geotechnical Engineering, 122(7); 577-596.

Griffiths, D. V. and Lane, P. A. (1999) Slope stability analysis by finite elements. Journal of
Geo-technique, 49(3): 387-403.

Irrigation Engineering and hydraulic Structures, Sanatoche, Kumer Garg, 2005.Newdelhi, India

Krahn, J. (2004) Stability modeling with SLOPE/W: An engineering methodology. Alberta:


Geo-Slope/W International Ltd.

Kutzner, C. (1997) Earth and Rock fill Dams: Principles of Design and Construction, A. A.
Balkema,

Netherlands.

Ministry of Water Irrigation and Energy with, OWWDSE, 2014. Arjo Dedesa Sugar
development Irrigation engineering report , Addis Ababa, Ethiopia.

Novak, P., Moffat, A.I.B., Nalluri, C. and Narayanan R. (2001) Hydraulic Structures Fourth
Edition, Taylor & Francis Group, London.

Ratnayaka, D.D., Brandt, M.J. and Johnson, M. (2009) Twort's Water Supply 6th Edition,
Butterworth-Heinemann: Elsevier.

USACE (2003) Engineering and Design: Slope Stability, Department of the Army, U.S. Army
Corps of Engineers, Washington DC, United States of America.

February,2017 OWWDSE Page 230


References MWI&E

USACE (2004) General Design and Construction Considerations for Earth and Rock-Fill Dams,
Department of The Army, U.S. Army Corps of Engineers, Washington DC, United States of
America.

Zienkiewicz, O. C., Humpheson, C. and Lewis, R. W. (1975) Associated and non-associated


visco-plasticity and plasticity in soil mechanics. Geo-technique 1975; 25(4): 671–89

February,2017 OWWDSE Page 231


Annexes MWI&E

10. ANNEXES
Annex-1 Detail GPS data

February,2017 OWWDSE Page 232


Annexes MWI&E

February,2017 OWWDSE Page 233


Annexes MWI&E

February,2017 OWWDSE Page 234


Annexes MWI&E

February,2017 OWWDSE Page 235


Annexes MWI&E

February,2017 OWWDSE Page 236


Annexes MWI&E

February,2017 OWWDSE Page 237


Annexes MWI&E

February,2017 OWWDSE Page 238


Annexes MWI&E

February,2017 OWWDSE Page 239


Annexes MWI&E

February,2017 OWWDSE Page 240


February,2017 OWWDSE Page 241

You might also like