Risk Assessment Example

This risk assessment document summarizes the hazards, risks, and controls associated with crane load testing. It identifies several high risks like failure of equipment, swing loads, and falling objects. Controls are outlined to reduce risks, such as applying loads slowly, using tag lines, erecting barriers and signs, and having a minimum two-person operation. With controls in place, most risks are reduced to medium or low levels. The assessment provides matrices to classify initial and residual risks and ensures all controls are documented for verification.

Uploaded by

David F Martinez
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
139 views3 pages

Risk Assessment Example

This risk assessment document summarizes the hazards, risks, and controls associated with crane load testing. It identifies several high risks like failure of equipment, swing loads, and falling objects. Controls are outlined to reduce risks, such as applying loads slowly, using tag lines, erecting barriers and signs, and having a minimum two-person operation. With controls in place, most risks are reduced to medium or low levels. The assessment provides matrices to classify initial and residual risks and ensures all controls are documented for verification.

Uploaded by

David F Martinez
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

CRANE LOAD TESTING RISK ASSESSMENT

Risk assessment number:- Location:- Date:-


Linked documentation :-
Overall category of risk LOW MEDIUM HIGH Reduced to low as reasonable practicable YES :-  No :-

No Controls in place with Controls in place


Hazard Description and Effect HS LH RR Controls Required HS LH RR
Failure of equipment being Test load to be applied slowly, do not stand
5 5 H 3 2 M
tested Death under load, radio contact with crane driver
Manual Handling / Back or hand Tag lines to be used, Cranes or Forklift shall be
5 4 H 3 1 L
injury used to move Weights
Designated area for testing using Barriers and
Crane Operations Death 3 4 M 3 1 L
signs
Designated Banks man/ slingers, Minimum 2
Swing Loads Death 5 3 H 3 1 L
man work party, Tag lines to be used
Underground Hazards i.e. Designated area to be assigned by site owner.
4 4 H 4 2 L
Electrical cables, sewage drains Used spreader pads
Falling Objects 4 4 H Warning Signs and Barriers to be erected 3 1 L
Weather, Strong Winds 5 3 H Adhere to Operators / Manufactures guidelines 3 1 L
Illumination, Darkness, Personal Area of test to be well illuminated prior to test
4 4 H 3 1 L
injury
Oil or Fuel leak, Environmental Drip trays to be used to contain oil / fuel
4 4 H 3 2 M
hazard
Load test operations 4 4 H Minimum two man operation 3 1 L
Crane Operations 4 4 H High visibility vests to be worn by all 3 1 L
Moving Test weights Hand / Designated person to be in charge of equipment
4 4 H 4 2 M
Back injury movements / minimum of 2 personnel
Hazard Initial Risk Controls Residual Risk
Hazard Description Hazard Likelihood Risk rating Controls required Hazard Severity Likelihood
Persons at risk Risk rating
and effect Severity (HS) (LH) (RR) (HS) (LH)
(RR)

Page 1 of 3
CRANE LOAD TESTING RISK ASSESSMENT

Describe all hazards, All personnel within From matrix From matrix Classify risk Describe fully all controls applicable for From matrix From matrix Classify risk
identified and their the work party, identify identify Rating from each hazard, if controls can be verified identify severity identify Rating from
effect for each task. Include people severity with severity with matrix for by documentation then it must be with controls in severity with matrix for
Additional hazards outside the work no control in no controls in each hazard available, All controls must be valid in place for each controls in each hazard
may be caused by party who may be place for each place for each that they reduce severity, likelihood or hazard place for each
interaction with affected hazard hazard Both hazard
other work

Risk Ratings (based on Likelihood and Severity)


Hazard Severity index
1 2 3 4 5 HIGH Control measure must be introduced to reduce the
degree of risk prior to the activity / process proceeding
5 5,1 5,2 5,3 5,4 5,5
4 4,1 4,2 4,3 4,4 4,5 MEDIUM Activity / process can continue, but additional controls
Likelihood 3 3,1 3,2 3,3 3,4 3,5 may need to be introduced to further reduce the risk
2 2,1 2,2 2,3 2,4 2,5 LOW Risk is being adequately controlled, but further controls
1 1,1 1,2 1.3 1,4 1,5 measures may further reduce the risk

Hazard severity index Likelihood index Environment index


NO Index description NO index description NO index description for effects on the environment
5 Death 5 Highly probable 5 Major Consequence
4 Major injury 4 Probable 4 High Consequence
3 Unfit for Normal duties for more than 3 days 3 Possible 3 Moderate Consequence
2 Unfit for Normal duties for less than 3 days 2 Unlikely 2 Limited Consequence
1 Minor injury 1 Highly unlikely 1 Minimal Consequence

Page 2 of 3
CRANE LOAD TESTING RISK ASSESSMENT

Senior Engineer name:- Signature:- Date:-

Team Tool box Talk


All team members must sign to show they know the risks and procedures for the task in hand
Name Signature Name Signature

Customer Review:-
Review completed
Review date Comments OR Actions
(print name, sign )

Page 3 of 3