Dy - CE Bridge
Dy - CE Bridge
▪ Trestles were made using CC cribs over the entire span. Ground was
consolidated and foundations were made with M25 grade concrete for trestles.
The center line of girder and location of trestles was marked on the ground.
CC crib trestles were erected. Foundations for pulling winches and restraining
winches were cast.
▪ 1+4 spans were erected on 52 kg rails fixed to gantry girder over the trestles.
The spans were erected away from railway line. The members were connected
with HSFG bolts. The alignment of girder and their verticality was checked.
The girders were connected with pulling and restraining winches.
▪ With the help of pulleys and winches, the OWG was moved over the rails
(with roller arrangement) under traffic and power block. OWG spans were
moved over the railway track and adequate space was made for fabrication of
the remaining span. 2 winches each of capacity 10 tonne were used to pull the
girder.
▪ The rails are welded to gantry girder (2 on each side) to facilitate movement
of girder in longitudinal direction. After this, rest of the span is erected on
trestles. It was connected to existing part using HSFG bolts.
▪ Girder is lowered on piers with the help of jacks. At ends, the cross girders are
jacked and 20mm thick wooden blocks are used to slowly lower the girder
over bearings. Here, Pot PTFE bearings will be used. The temporary staging
for girder is removed. After this, deck slab will be cast on the girder for
passage of road.
Date: 26.10.2021
Concerned Officials: Sh. R.K Srivastav, SSE/Bridgeline/HQ
• Learnt about the strengthening of OWG:
o Extensive corrosion in members of 14*45.72 mm span OWG of bridge no. 462
between Nipania and Dagori stations in Durg-Bilaspur section.
o Bottom gusset plate with vertical member were heavily corroded at multiple
locations. The reason for extensive corrosion can be attributed to discharge by trains
on the girders.
o For rehabilitation of the bridge, a speed restriction of 20 kmph was enforced. The
affected gusset plate and members were removed sequentially and replaced.
o The new members were sand blasted and metallized prior to riveting. The bottom
chord members were further strengthened by additional channels on inner side near
the supports.
o A protective metallic cover was wrapped around the girder for prevention against
corrosion in future.
o Initially, turn bolts were used to fix the members with gusset plate. They were then
replaced by rivets.
• Learnt about the procedure for replacement of bed blocks of bridge no. 209:
o Cracks were observed on bed blocks of bridge no. 209 on upline between
Vilayatkalan road and Rupaund stations. The bridge had a common pier for upline
and downline with isolated bed blocks on stone masonry piers.
o The existing bed block on pier was loosened. Track was opened over the bridge to
facilitate lifting by jack.
o The girder was lifted with the help of jacks to a height of 2feet. CC cribs were then
used to support the girder.
o CC crib staging was erected adjacent to the pier to move the existing bed block.
o New bed block was cast on the pier itself in between the two girders. The bed block
was made of M35 grade RCC and was designed at HQ (design cell).
o The new bed block was placed on rollers over NG rails to facilitate its movement to
the desired position. Once in position, the rails were released and bed blocks lowered.
o Bed block was grouted to the pier using epoxy grout. Finally, bearing was fixed to
bed block and girder was lowered.
o SECR has 60 track machines at present and further two machines are under
commissioning.
o The zone has POH capacity of 6/year and IOH capacity of 12/year.
o Track machine branch has 1002 total posts sanctioned as on date and 692 staff on roll
with 317 vacancies.
o In the year 2020-21, the progress of plain track tamping in SECR was 124% with
respect to the target given.
• Discussed about the planning of track machines:
o By Feb 5 of every year, Sr DEN (CO) of all the divisions send requirement of TM in
their division for a period of 18 months.
o The annual programme is then drafted by office of CE/TM for a period of 18 months
(firm programme for 12 months and tentative for 6 months thereafter). This helps the
divisions to finalize tenders for other support activities in time.
o Annual targets for track machine are finalized by railway board in consultation with
zonal railways. (Targets for SECR for the year 2021-22 are attached).
o Following factors are considered in deciding the targets (para 601 (5) of IRTMM):
▪ Track maintenance works due at beginning of year.
▪ Track renewal targets.
▪ Availability of machines on the railway sundering POH and IOH.
▪ Availability of traffic blocks.
▪ Progress per machine per month for past 3 years in the zone.
▪ Progress per machine per month for past 3 years in IR.
▪ Age of the machine.
• Observed the progress of track machines:
o The rated output of track machines has been specified in IRTMM along with
minimum period of block for efficient working of the machine:
▪ Tamping depth:
- The gap between top edge of tamping tool blade and bottom edge of
sleeper in closed position of the tamping tool should be adjusted to 15-
20mm. For this, initial depth is kept 15-20mm below rail head.
- Then, Tamping tool depth = sleeper depth at rail seat location + rail
height + rubber pad thickness = 172 + 210 + 6 = 388mm.
▪ Tamping vibration, amplitude and frequency:
Date: 04.11.2021
Holiday on the account of DIWALI.
Date 05.11.2021
Concerned official: Mr. Harish Kumar; SSE/TM/store
• Visit to satellite depot and track machine store:
o Track machine store:
▪ They store spares of machines, tools and plants and other consumables.
▪ The items are supplied from central store at Nagpur. Stock items include
blankets for staff, hydraulic/ engine sit, grease, gear ail etc.; for machines Non
stock items include valves, pumps etc.; of machines.
▪ These are not included in AMC as the cost involved in procurement through
OEM is much higher.
▪ Annual maintenance contract is done with OEM for maintenance of electric,
pneumatic and hydraulic systems of machines.
▪ Two types of registers are maintained at TM stores:
- Daily material transaction register: Details of daily receipts and issues
of materials are entered herein.
- Ledger: All the issues/receipts and the balances of items are recorded
in this register.
- The store records are being upgraded to user depot module (UDM).
- The daily material transaction register and ledger are maintained
online in this application.
- Material issue, receipt and balances are recorded and can be viewed by
anyone. Each material is assigned a unique number for easy
identification.
- This software is also used for proper organization of materials at the
store. The location of each material can be found out easily by entering
its number.
- A summary of materials available and their quantity for all the stores
can be seen. This will help in quick arrangement of materials required
on short notice.
o Satellite Depot:
▪ IOH of track machines is carried out at this depot. POH of track machines is
carried out at Nagpur depot.
▪ The satellite depot has a staff strength of 14 including 1 SSE, 1JE, 5 grade III
technician, 2 grade I technician and 5 assistants.
▪ The duty roster includes 21 days’ work and 7-day rest.
▪ IOH of UNIMAT 4S- 8414 was going on at the depot. As per schedule VI,
IOH is due after 2000 engine hours.
▪ However, for this machine IOH is being done after 7012 engine hours (new
machine; first IOH). IOH for UNIMAT is a long-drawn process which takes
up to 30 days.
▪ Satellite depot has three rate contracts for a period spanning 2 years (earlier 1
year). The contracts are for following works:
- Electrical and pneumatic.
- Hydraulic works.
- Other miscellaneous works.
▪ Machine maintenance and operation:
- The staff is responsible for operation and maintenance of machine in
TM siding as per schedule.
- 2 SSE are posted, one for tamping machines and other for non-tamping
machines.