Gantt Chart Format

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

PERCENT ACCOMPLISHED = 17.

62
LEGEND

MAY JUNE

ID TASK NAME
14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
DURATION

Feeder Lines for AVR, isolation/step-up


transformers and 5kw Transmitter panel
23 14

27 Feeder line for transmitter Panel 9

28 Feeder line for 2units 3TR ACU 8

29 Feederline for 2 units generator and MTS 8

30 Lighting Fixtures, switches convenience outlets 7

31 Fire Detection and Alarm System 7

32 Clearing and Cleaning for turnover 9

SUBJECT : LOCATION
BAR CHART PROPOSED SECOND FLOOR DTT ROOM EXPANSION MT. BANOY, BRGY TALUMPOK EAST, BATANGAS CITY, BATANGAS

PREPARED BY:

ENGR. ROMEL L. BURIO JR.


CIVIL ENGINEER
APOVIL CONSTRUCTION CORPORATION
GANTT CHART

75 days Construction Lead Time Mon, 4/12/2021


Date Mobilized Target Completion - June 25, 2021
1 Apr 12, 2021 Apr 19, 2021 Apr 26, 2021 May 3, 2021 May 10, 2021 May 17, 2021 May 24, 2021 May 31, 2021 Jun 7, 2021 Jun 14, 2021 Jun 21, 2021
Date Awarded : March 29, 2021 as per PO 7010024692 Week Shown
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

TASK PROGRESS START END M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

General Requirements

Mobilization 100% 4/12/21 4/15/21

Temporary Facilities 100% 4/14/21 4/16/21

Temporary Power (by GMA) 100% 4/14/21 4/16/21

Hauling & Delivery of Materials to site 100% 4/16/21 5/11/21

Task 5

Civil and Architectural Works

Building lay-out 100% 4/14/21 4/16/21

Excavation 100% 4/16/21 4/24/21

Backfilling 100% 4/22/21 4/27/21

Earthfilling 100% 4/24/21 4/30/21

Gravelfilling 100% 4/27/21 4/29/21

Soil Poisoning 100% 4/28/21 5/1/21

Rebar Works 100% 4/22/21 5/6/21

Form Works 75% 5/1/21 5/18/21

Concreting 65% 5/4/21 5/26/21

Masonry Works 74% 5/14/21 6/3/21

Floor Finishes 0% 5/30/21 6/4/21

Wall Finishes 0% 6/2/21 6/5/21

Ceiling finishes 0% 6/3/21 6/7/21

Carpentry Works 0% 6/6/21 6/13/21

Doors complete with accessories 15% 6/8/21 6/10/21

Windows 10% 6/10/21 6/12/21

Metal Works 20% 6/5/21 6/16/21

Waterproofing Works (Elastomeric) 0% 6/1/21 6/7/21

Plumbing Works 10% 5/21/21 6/13/21

Construction of New Reinforced Concrete Stair 78% 4/29/21 5/18/21

Electrical Works

Feeder Lines for AVR, isolation/step-up transformers and 5kw


0% 5/17/21 5/30/21
Transmitter panel

Feeder line for transmitter Panel 0% 5/26/21 6/3/21

Feeder line for 2units 3TR ACU 10% 6/1/21 6/8/21

Feederline for 2 units generator and MTS 0% 6/4/21 6/11/21

Lighting Fixtures, switches convenience outlets 10% 6/11/21 6/17/21

Fire Detection and Alarm System 0% 6/15/21 6/21/21

Clearing and Cleaning for turnover 0% 6/17/21 6/25/21

Page 2 of 2